Date : 71– 03 - 1074

Ref. : LY-BK- 61-R7

To.: M/S. EGEC

Attn. : Eng. Mohamed Awad Gaballah

Subject : Quotation for GRP water tank.

We are pleased to quote you the following:


ITEM Tank Size Qty Unit (SR) Amount ( SR) Remarks
GRP Water 701 Cu m -6*6*3 (H) 4 49’500 SR 349’000 SR Non-
Tank Heat
Insulated

GRP Water 701 Cu m- 6*6*3 (H) 4 809’500 SR 939’000 SR With


Tank Heat
Insulated

Accessories & Specifications:

7-Internal A’ssy bolts are S.S Grade 376 .

1-External A’ssy bolts :dacro

3-Internal ladder GRP.

4-Extrnal Ladder – HDG .

5-Opens for(Inlet , Outlet, Overflow, Drain, Air vent) as for the site requirements .

6-Manhole : 7- lockable.

1- Brand Product , South Korea.


Warranty:

Tanks are warranted for 70- years under condition of applying the product
instruction and maintenance manual .

Validity :

This offer is valid for one – Month.

Installation:

We will send Technician for installation , but at site cliect have to arrange enough
labourers, scafolding, access ladder and other power tools.

Exclusions:

7-All civil works on site ( concrete foundations) .

1-Full accomodation for supervisors .

3-All pipe connections,float control switches , Fittings( if any flanges), water for
testing and any cost for third party testing or inspection.

4-Unloading and shifting of material at the installation location .

5-Power required for the installation tools .

Payment :

- 00 % in advance with LPO.


- 70% on complete installation.
Delivery & Intallation :

- Delivery in 6 - 1 weeks from tha date of LPO and advance payment.


- Installation and testing( Leakage) in 4-week from the readiness of site.

Note :

- The clint is responsible for securing the proper store for the material of tank
untill the sites get ready and it will be transported to the installation site by
the clint means.
- This price consider one shipment for No.4 tank .
- Load bearing factor of safety of soil conditions at site to be taken care by the
owner.
- Owner to ensure that the structural elements that carry the tank is suitable
and safe In terms of design.
- Not Discharge the tank after filling only the time necessary maintenance
work, according to his operating and maintenance instructions.