MAIN CONTRACTOR

DOCUMENT TITLE
CALCULATION
SHEET CACULATION FOR GCS
WALL FORMWORK

Issue date Project No.


Doc. No
19/05/2024 WALLS

DESIGN LOADINGS
23/. Designer to explain, why pouring rate of 1.5m is
considered in concrete pressure calculation? Please ensure
calculations are perform to ACI standard.
Do concrete mix properties are known? Has concrete mix
been approved?

03-230000-4800000866-GCS-CON-CAL-000001 Rev.01 Page 12 of 50


MAIN CONTRACTOR
DOCUMENT TITLE
CALCULATION
SHEET CACULATION FOR GCS
WALL FORMWORK

Issue date Project No.


Doc. No
19/05/2024 WALLS

CHECK ELEMENTS

spans and distances between beams at The biggest panel 2.7 x 1.2 m

03-230000-4800000866-GCS-CON-CAL-000001 Rev.01 Page 13 of 50