Professional Documents
Culture Documents
Week8 Moodle
Week8 Moodle
2
Application time!
3
Seek Feedback
4
Learning Objectives
5
1.
RISK
MANAGEMENT
PROCESSES 2.
(ISO31000)
3.
4.
5.
6
7
8
9
10
1st Month
2nd Month
3rd Month
4th Month
5th Month
6th Month
11
→ Site Reports
12
13
1st Month
2nd Month
3rd Month
4th Month
5th Month
6th Month
14
Short discussion
• Think about measuring schedule variance based on progress reports and the
planned cost of activities. How will you implement this in your project?
Discuss with your classmates please.
15
Another
Example
Analysis at the
end of period #1
Analysis at the
end of period #2
Analysis at the
end of period #3
16
17
→ Invoices, Payment requests,…
18
1st Month
2nd Month
3rd Month
4th Month
5th Month
6th Month
19
20
1st Month
2nd Month
3rd Month
4th Month
5th Month
6th Month
21
Analysis at the
end of period #1
Analysis at the
end of period #2
Analysis at the
end of period #3
22
23
24
25
26
Project Earned Value Analysis - Assignment Report
• Consider a date for Earned Value Analysis (e.g. end of 6th weeks/months…)
• Assume Progress percentages (field reports) and Actual costs (invoices)
• Table and graph for PV, EV, AC
• Calculate deviations from planned objectives (SV, CV, SPI, CPI)
• Interpretation of results (schedule delays, cost overruns,…)
27
Quiz question 1
Using the following information, what will be the CV and SV at the end of week 4?
Response: CV = 295,
End of week 4
SV = 295
0
28
Quiz question 2
Using the following information, what will be the CV and SV at the end of week 8?
Response: CV = 397,
End of week 8
SV = 397
29
Quiz question 3
Using the following information, what will be the SPI and CPI at the end of week 8?
30
1.
RISK
MANAGEMENT
PROCESSES 2.
(ISO31000)
3.
4.
5.
31
Thank you