FACULTY OF PLANTATION & AGROTECHNOLOGY

PROG./COURSE CODE : AT110/AGR242


COURSE : GENERAL FIELD MAINTAINANCE

TOPIC: LINEAR MEASUREMENT BY METRIC CHAIN


FIELDWORK NO. 4
G. LEADER NAME MUHAMMAD AZRI BIN ZAINUDDIN
MATRIC. NO. 2020476314
GROUP (COURSE) RAT1104F

NO. NAME MATRIC NUM.


1. AKIF HISHAM BIN AZRIL HISHAM 2020610502
2. MUHAMMAD HAMINUR HADI BIN ABD NASIR 2020845288
5. 3. MUHAMMAD AFIQ DANISH BIN ABD HAMID 2020871282
6. 4. MUHAMMAD AZRI BIN ZAINUDDIN 2020476314

CHECK LIST FOR REPORT SUBMISSION & CONTENT TICK PAGE NO.
(√)
1. Report Cover 1
2. Introduction
3. Objectives
4. Learning outcomes
7. 5. Procedure
8. 6. Results (Field book, calculation and GRAPH or others)
7. Plotting (Use Graph Paper with Scale)
8. Conclusion
9. Discussion and recommendations of the field works and result
10. References
11. Appendixes: Others - Photographs, Tables & Sketches with
captions

1
INTRODUCTION

OBJECTIVES

LEARNING OUTCOMES

Students should be able to:

1. Setting the equipment.


2. Take readings of back sight, middle sight, and fore sight.
3. Make the appropriate booking.
4. Calculate the decreased level of all the points that have been taken.
5. Make a correction to the lower level.
6. Using a suitable scale, draw a longitudinal profile and cross section.

EQUIPMENTS

Auto Level

Tape

Ranging Poles

2
Arrow

Levelling Staff

Staff Bubble

Levelling Tripod

PROCEDURES
3
Leveling on a Longitudinal Scale (50m length)

1. Select the level to be set up at the assumed Benchmark 100m (BM 100M)
peg point at CH 0m.
2. Make a temporary modification to the level after setting it up.
3. Take the reading with the staff at the benchmark. This is a back sight reading.
4. Make a note of the reading in the supplied form.
5. Place a 5m spacing between the first staff and ranging poles.
6. Take the second staff's reading and mark it as the intermediate sight.
7. Place the third staff position at a distance of 5m from the second staff. The
reading on the field sheet should be considered intermediate sight.
8. Steps 5–7 should be repeated until the staff can no longer be read. The staff's
most recent reading before the level is changed is recorded in the column as
foresight. The staff in charge of foresight. The level must not move until the
(becoming) back sight (after moving the level) reading is taken (before moving
the level).
9. Make a temporary modification by moving the level to a new suitable point.
10. Perform a back sight reading.
11. Steps 5 to 10 should be repeated until the job is finished.
12. Calculate all of the staff positions' rise and fall, as well as their reduced level.
13. Draw the road's longitudinal profile. Plot a Longitudinal Cross Section for
Road making on GRAPH PAPER.