EFF/24-25/CUS/OUT/MAY/097 27-05-2024

To
The Sr Dste/GNT,
South Central Railway.

Sub: Safety Point Alarm units not working in GNT division -Reg...
Ref Letter no: GNT/SG/10 Dated 26.03.2024

Dear Sir,

With reference to the above cited it is to bring to your kind notice that, we had analysis completed
as your given SPAU failures in all stations in Guntur Division, also we are start update & modified logics
from this week, All stations will be completed by 15th -JUN-2024.
Attached sheet for planning

SL no Station Remarks from Site Our Remarks & Plan Planned Date
1 CBM Abnormal indications appearing New SPAU logics to be download 03/06/2024
Warning indication appearing
2 SAB with in 2 min New SPAU logics to be download 04/06/2024
3 JBK Abnormal indications appearing New SPAU logics to be download 05/06/2024
Warning indication appearing
4 MUK with in 2 min New SPAU logics to be download 06/06/2024
Warning indication appearing
5 VKN with in 2 min New SPAU logics to be download 07/06/2024
Warning indication appearing
6 NRT with in 2 min New SPAU logics to be download 08/06/2024
7 SDV Not working Old Model 09/06/2024
8 GID Not working Old Model 10/06/2024
New Logics preparing with front
9 PGRN Abnormal indications appearing end at site planed 29/05/2024
New Logics preparing with front
10 RPCA Abnormal indications appearing end at site planed 29/05/2024
New Logics preparing with front
11 NLPI Abnormal indications appearing end at site planed 29/05/2024

Thanking you,
For Efftronics Systems Pvt.ltd.

Manager –Customer support,


(K Rama Rao)
Mobile no: 7660001578.