Technical Manual

7” Casing Circulator
Drill Collar Sub Assembly
700-CE-17B

CE.04.C
Revision C
Revision Issue Date: April 6, 2010

The information and/or data in this publication is supplied solely for informational
purposes and TAM International makes no guarantees or warranties, either expressed or
implied, with respect to its accuracy, completeness or use.

TAM INTERNATIONAL CE.04.C Page 1 of 11


Table of Contents

Section 1
Description - Not Provided

Section 2
Assembly Drawing, Parts List 3

Section 3
Assembly Procedure 5
Testing Procedure 10

Section 4
Disassembly and Inspection Procedure 11

Warning
Use of TAM International equipment contrary to manufacturer’s
specification may result in property damage, serious injury, or fatality.

Revision Notice

Revision C Added disclaimer


Change page 8 – Fig 1502 Hammer Union verification.

TAM INTERNATIONAL CE.04.C Page 2 of 11


Section 3
Assembly Procedure

Critical Factors & Safety Notes

l
Assure that the latest Revision Level Assembly Drawing is utilized.

Read entire manual before proceeding.

Install all “O” Rings and Lubricate with NC111.

Apply API pipe dope to all threads.

1. Place COLLAR (700-CE-123) in vise.

2. Apply Teflon tape on the 3/8” NPT Pipe Plug.

3. Install the 3/8” NPT Pipe Plug into the top end of the COLLAR.

COLLAR

3/8” NPT
PLUG

TAM INTERNATIONAL CE.04.C Page 5 of 11


4. Make up the QUICK DISCONNECT NIPPLE (SST-N3M) into the RING
WELD, using Teflon tape on the threads.

QUICK
CONNECT
NIPPLE

RING
WELD

5. Slide the RING WELD (700-CE-111) over the top end of the COLLAR until it
shoulders out and is over the “O” RINGS.

If Non Top Drive Assembly is required, go to step 10

TAM INTERNATIONAL CE.04.C Page 6 of 11


6. Install the TOP SUB (700-CE-121) onto the top of the COLLAR. Torque to
3,500 ft-lbs.

TOP
SUB

7. Make up Set Screw into relief groove to prevent thread back off.

8. Install TUBE A into the bottom of the COLLAR. Torque tight.

TUBE A

COLLAR

9. Proceed to TEST SECTION.

TAM INTERNATIONAL CE.04.C Page 7 of 11


FOR NON TOP DRIVE APPLICATIONS, INSTALL COLUMN SUB ASSEMBLY
700-NT-90

10. Make up COUPLING (700-NT-80) onto WELD ASSEMBLY (700-NT-69) and


torque to 3,000 ft-lbs.

WELD
ASSEMBLY

COUPLING

Critical Factors & Safety Notes

All 2” 1502 hammer union connections must be verified with FMC’s Go/No-Go
Gauge (PIN P511389). The following statement must be included on shipping
paperwork:
“Supplier has verified through use of FMC’s Go/No-Go Gauge (PIN P511389) that
all external 2” hammer unions are 1502.
Sign __________________________ Date _____________________”

11. Make up COUPLING/WELD ASSEMBLY onto top of COLLAR with 3,500 ft-
lbs torque.

TAM INTERNATIONAL CE.04.C Page 8 of 11


12. Make up SET SCREW to lock threads from backing off.

13. Make up NUT (700-NT-31) onto SUB (700-NT-36), hand tight.

NUT SUB

14. Make up NUT/SUB onto WELD ASSEMBLY with 3,500 ft-lbs torque.

WELD
ASSEMBLY

NUT/SUB

TAM INTERNATIONAL CE.04.C Page 9 of 11


Section 3
Testing Procedure

THIS COMPONENT IS TESTED AS PART OF THE FINAL


ASSEMBLY AFTER INFLATION MODULE HAS BEEN
ADDED

TAM INTERNATIONAL CE.04.C Page 10 of 11


Section 4
Disassembly & Inspection Procedure

1. Clamp COLLAR in vise.

2. Remove TUBE A from lower end of COLLAR.

3. Remove Set Screw from TOP SUB (or COLUMN SUB ASSEMBLY) attached to
COLLAR.

4. Remove TOP SUB or COLUMN SUB ASSEMBLY from COLLAR.

5. Slide RING WELD off COLLAR.

6. Remove and discard all “O” RINGS.

7. Inspect seal surfaces and threads for damage.

8. Reassembly as per Section 3.