Manual Llenado Rápido CCP TAM
7” Casing Circulator
Drill Collar Sub Assembly
700-CE-17B
CE.04.C
Revision C
Revision Issue Date: April 6, 2010
The information and/or data in this publication is supplied solely for informational
purposes and TAM International makes no guarantees or warranties, either expressed or
implied, with respect to its accuracy, completeness or use.
Section 1
Description - Not Provided
Section 2
Assembly Drawing, Parts List 3
Section 3
Assembly Procedure 5
Testing Procedure 10
Section 4
Disassembly and Inspection Procedure 11
Warning
Use of TAM International equipment contrary to manufacturer’s
specification may result in property damage, serious injury, or fatality.
Revision Notice
l
Assure that the latest Revision Level Assembly Drawing is utilized.
3. Install the 3/8” NPT Pipe Plug into the top end of the COLLAR.
COLLAR
3/8” NPT
PLUG
QUICK
CONNECT
NIPPLE
RING
WELD
5. Slide the RING WELD (700-CE-111) over the top end of the COLLAR until it
shoulders out and is over the “O” RINGS.
TOP
SUB
7. Make up Set Screw into relief groove to prevent thread back off.
TUBE A
COLLAR
WELD
ASSEMBLY
COUPLING
All 2” 1502 hammer union connections must be verified with FMC’s Go/No-Go
Gauge (PIN P511389). The following statement must be included on shipping
paperwork:
“Supplier has verified through use of FMC’s Go/No-Go Gauge (PIN P511389) that
all external 2” hammer unions are 1502.
Sign __________________________ Date _____________________”
11. Make up COUPLING/WELD ASSEMBLY onto top of COLLAR with 3,500 ft-
lbs torque.
NUT SUB
14. Make up NUT/SUB onto WELD ASSEMBLY with 3,500 ft-lbs torque.
WELD
ASSEMBLY
NUT/SUB
3. Remove Set Screw from TOP SUB (or COLUMN SUB ASSEMBLY) attached to
COLLAR.