PERMANENT

MODULAR
CONSTRUCTION
REPORT

MOD U L A R BUI L D I NG I NS T IT UT E ’ S
Key Findings and Best Practices for Successful Modular Projects
About the Modular Building THANK YOU TO OUR 2023
Institute— The Voice of Commercial MBI CORPORATE SPONSORS
Modular Construction™
The Modular Building Institute (MBI) is
the only international nonprofit trade PLATINUM
association serving the commercial
modular construction industry. For 40
years, MBI has promoted the advan-
tages of modular construction while
advocating for the removal of barriers GOLD
that limit growth opportunities.
Through its long-standing relation-
ships with member companies,
policymakers, developers, architects,
and contractors, MBI has become the
industry’s go-to resource for reliable
information for the commercial
modular construction industry. SILVER

HISTORY
Founded in 1983 to serve the global
modular construction industry, today
MBI has more than 500 member
companies, including manufacturers,
contractors, relocatable building fleet
owners, architects, developers, and
material and service providers.
BRONZE
MISSION
As the Voice of Commercial Modular
Construction, MBI’s mission is to
expand the use of offsite and modular
construction through innovative
construction practices, outreach and
education to the construction commu-
nity and customers, and recognition
of high-quality modular designs
and facilities.
Image courtesy of
DJR Architecture.

IFC About the Modular 16 Quality Control 26 Industry


Building Institute and Assurance Production Data
History Design Approval by Project Analysis
the End-user and
Mission Projects by Market
Regulating Authorities

4 Executive Summary Fabrication of Module 30 Financial Data


Components in a
Revenue and PERMANENT
Controlled Factory
6 Overview of the Environment Market Share MODULAR
Modular Industry
Assembly of Modular
CONSTRUCTION
8 About Permanent Units Onsite to Form 33 Frequently Asked REPORT
the Finished Building, Questions
Modular Construction
and Approval by
Construction Local Authorities 36 Definitions
Key Advantages
Design Considerations: 19 Environmental Impact
Best Practices Making the Case
for Architects for Modular
New Contract Eases Waste Reduction
Use for Prefab and
Lower Carbon
Modular Buildings
Footprint

12 Cost Savings Relocate, Renovate,


and Certainty and Repurpose
Case Studies Greater Energy
Demonstrating Efficiency/Tighter
Cost Savings Building Envelope
Schedule Savings
and Certainty 23 Worker Safety and
Quality of Life Issues
Cover Image: Alvera Apartments. Built by RISE Modular.
Winner, Permanent Multifamily Over 10,000 Sq. Ft.

The images in this report represent some of the winners of the Modular Building Institute’s 2023 Awards of Distinction.
To see the complete list of winners and learn more about each project, visit. modular.org/awards.
EXECUTIVE
SUMMARY
The permanent modular construction modular industry. This figure does For the third year in a row, the multi-
(PMC) industry topped $12 billion in not include modular factories that family sector was the largest market
North America in 2022, accounting for generate no revenue from the com- for the modular industry, accounting
6.03 percent of all new construction mercial sector (i.e., revenue derived for about one-third of all factory
starts. This continued market share exclusively from the single-family output. Other key markets include
growth is impressive, considering it modular home and/or manufactured office and administrative, institution-
has nearly tripled since 2015, when housing sectors). al and assembly, and education.
market share was 2.14 percent.
In 2022, 24 modular manufacturers Using these averages provided by
The reasons for continued growth reported total production of 8,123,554 the MBI survey and manufacturers’
are numerous, including cost and square feet, for an average of 338,481 input of data, it is possible to
schedule predictability and savings, square feet each. MBI estimates the estimate certain information
environmental advantages, and projects utilizing modular construction about the industry as a whole.
worker safety, all of which are detailed accounted for approximately 6.14 While the calculated information is
in this report. percent of the total square footage for reliable only to the extent the data
new construction in 2022. provided by industry participants is
MBI gathers data from this report accurate, MBI’s data comes directly
from two primary sources: MBI also analyzed 62 modular from its modular manufacturer
1. Direct financial and production projects completed in 2022. The members and represents the most
data from modular manufacturers average size for projects completed comprehensive and accurate
2. Project data from case studies was 24,057 square feet, consisting of industry information available in
submitted to the Modular an average of 37 modules each. The North America.
Building Institute (MBI) average time to complete each project
from approval to occupancy was just
MBI estimates that there are 255 309 days, while the average total cost
modular manufacturing companies in of these projects was $6,708,142,
North America generating some por- for an average cost per square foot
tion of revenue from the commercial of $278.84.

4 PERMANENT MODULAR INDUSTRY


Adquisición de Centros
Modulares de Salud.
Built by ECOSAN S.A.
Winner, Permanent Healthcare
Over 10,000 Sq. Ft.

ANNUAL REPORT 2023 5


OVERVIEW
OF THE
MODULAR
INDUSTRY
The modular construction industry is regulated at
the state and local levels by building-code adminis-
trators and authorities having jurisdiction. As with
site-built structures, a building constructed using the
modular process must meet the local codes where
the building will be placed. Unlike federal manufac-
tured housing products built in accordance with U.S.
Department of Housing and Urban Development
standards, there is no specific “modular building
code,” nor are there exceptions for a building
constructed utilizing the modular construction
process—it is simply a more efficient process to
construct building components at an offsite facility,
then transport and assemble those components at
the final building site.

Modular construction can be used for a variety of


purposes, including residential, commercial, and
industrial applications. MBI represents the commer-
cial sector of the industry.

6 PERMANENT MODULAR INDUSTRY


Commercial modular buildings are Permanent modular construction
nonresidential, factory-built build- (PMC) is an innovative, sustain-
ing components and structures able delivery method utilizing
designed to meet all applicable offsite, lean manufacturing
building codes. Commonly, these techniques to prefabricate single-
buildings are constructed in accor- or multistory whole building
dance with the International Build- solutions in deliverable volumetric
ing Code (IBC) in the United States, module sections. Manufactured
the National Building Code in in safe, controlled settings, PMC
Canada, or a local version modeled buildings can be constructed of
after these codes. In this context, wood, steel, or concrete. PMC
prefabricated mechanical, electri- modules can be integrated into
Carter Credit Union. cal, or plumbing (MEP) systems are site-built projects or stand alone
Built by Black Diamond Group. not included for industry revenue as a turnkey solution, and can be
Honorable Mention, Permanent Retail and production figures. delivered with MEP, fixtures, and
Under 10,000 Sq. Ft.
interior finishes in less time, and
The commercial modular building with less waste and higher quality
industry is composed of two distinct control than projects utilizing only
divisions, both represented by MBI. traditional site construction.

Relocatable buildings, as de- PMC buildings are subject to the same


fined in the IBC, are partially or building codes and requirements
completely assembled buildings as site-built structures, depreciate
designed and constructed to in much the same manner, and are
be reused multiple times and classified as real property. This
transported to different building segment of the industry provides
sites. This segment of the construction-related services for the
industry maintains fleets of successful design, manufacturing,
relocatable buildings offered for delivery, installation, and finish-out of
sale or lease to customers. commercial and multifamily buildings.

ANNUAL REPORT 2023 7


ABOUT
PERMANENT project data to calculate average
square footage of buildings by

MODULAR
market type, average days to
complete by market type, modular
project costs, and total project costs.

CONSTRUCTION Construct Connect Insight—MBI


uses this database to determine
the baseline for new construction
starts in key markets and to measure
overall industry market share.
Numerous industries, including remain in one location for the duration
schools, banks, restaurants, hospitals, of their useful life (hence the term Publicly available data such
hotels, medical clinics, and housing “permanent”). Permanent modular as news stories, public filings
developers, regularly use PMC. The buildings may be wood-frame, steel, or (in the U.S. and Canada), and
industry categories that utilize our concrete and can have as many stories corporate websites.
services most frequently (as mea- as applicable building codes allow.
sured by the North American Industry Every effort has been made to ensure
Classification System), include: MBI obtained industry information the accuracy and reliability of this data,
for this report from multiple and in some cases, MBI’s best esti-
236116 New Multi-family sources, including: mates are used. MBI is confident that
Sydney International Speedway.
Housing Construction this report represents the most com-
Built by Fleetwood Australia.
236220 Commercial and MBI member surveys—Each year, prehensive and accurate information Winner, Permanent Special
Institutional Building MBI asks all member companies available on the commercial modular Application Over 10,000 Sq. Ft.
for data regarding their annual construction industry in North America.
Construction revenues, sources of revenue,
The term “modular” describes a markets served, production, Key Advantages
construction method or process in capacity, and total employees. • Cost Savings and Certainty
which individual modules stand alone • Schedule Savings and Certainty
or are assembled to make up larger MBI’s project database—Through • Quality Control
structures. Unlike relocatable buildings, the annual Awards of Distinction • Reduced Environmental Impact
PMC structures are intended to contest, MBI gathers specific • Improved Worker Safety

8 PERMANENT MODULAR INDUSTRY


ANNUAL REPORT 2023 9
Design Considerations: Best Practices for Architects

Design for Modular Manufacturing • Three-dimensional modules have • Restroom areas should be
nominal widths that are typically 8, designed so that a module
In 2019, MBI worked with the American
10, 12, 14, and 16 feet, with 12 and “marriage line” does not split
Institute of Architects to help develop a new
14 feet being the most common. the space.
guideline called the “Modular and Off-Site
Framing dimensions are typically 2 • Multiple roof-framing styles are
Construction Guide.” This guide, which
inches less than nominal size. available. Some can be completed
serves as a primer on the modular approach
for architects, includes: • Module lengths are up to 70 feet, in the factory, while others
usually in 2-foot increments. may require the installation of
• Value and opportunities of
• Module heights vary from trusses onsite.
modular design,
approximately 11 feet, 6 inches to 13 • Modular buildings can be
• Pitfalls designers should be wary of, and
feet, not including the height of the configured using modules of
• Case studies that exemplify successes unit’s transport trailer or frame. various lengths and widths.
and obstacles.
• Wood-frame construction is the • Design elements (e.g., paint
• The document can be downloaded most common type of construction; color) need to be decided
for free at: https://www.aia.org/ however, manufacturers also build earlier in the process, since the
resources/6119840-modular-and-off- with steel and concrete and can offsite construction process
site-construction-guide. meet the requirements for Type I, begins earlier and is completed
Type II, and Type III construction. more quickly.
The Architect’s Role
• Multistory modular buildings can
In general, the architect’s role in a be built up to the maximum stories
construction project is critical to its allowed by code. While most modular
overall success. The decision to utilize buildings contain one to four stories,
modular construction should be made a growing number of projects have
prior to design and should factor in the exceeded 10 stories in recent years,
following considerations: including a 32-story project in
Brooklyn, NY.

10 PERMANENT MODULAR INDUSTRY


New Contract Eases Use for Prefab and Modular Buildings

The ConsensusDocs Coalition has just published the industry’s first standard contract document to address one
of the most important and growing trends in the design and construction industry: prefabricated construction.
ConsensusDocs has been working with industry leaders for two years to offer a standard prefabricated
construction contract document. MBI recently joined the ConsensusDocs Council as a result of the successful
work conducted by the working group. The new ConsensusDocs 753 Standard Prefabricated Construction
Contract addresses the most common use case scenario of prefabricated construction, in which a constructor,
general contractor, design-builder, or construction manager contracts with a prefabricator to fabricate a
component offsite and later install that component on a project worksite.

While prefabricated construction or modular buildings have been around for decades, important contractual
and legal issues have remained unaddressed in most construction contracts. Finally, with the leadership of
ConsensusDocs, there is now an off-the-shelf solution that defines important new industry definitions and
scenarios that are unique to prefabricated construction. Importantly, using a typical construction subcontract or
purchase order for prefabricated construction can be costly and carry significant risks.

“As someone who often represents general contractors and prefabricators, I have written several custom
agreements to address the unique risks presented by modular building and prefabricated construction generally,”
comments Ron Ciotti, a partner at Hinkley Allen and chair of the ConsensusDocs Prefab Working Group. “The
new ConsensusDocs prefabricated construction contract provides some desperately needed understanding of
risk allocation, with prefabricated construction revolutionizing the way construction will occur in a postpandemic
construction world.”

Brian Perlberg, ConsensusDocs executive director and senior counsel, comments: “This is one of the most
anticipated contracts in the history of ConsensusDocs because there is a glaring need to address the growing trend
of prefabricated construction or modular building, and current contracting practices simply do not cut it.”

ANNUAL REPORT 2023 11


COST
SAVINGS
AND
CERTAINTY
Dodge Data & Analytics’ Prefabrication and Modular
Construction 2020 Smart Market Report captured
the impact of modular construction on project
budget performance. Prefabricated Modular FLETC. Built by Sustainable Modular Management, Inc.
Honorable Mention, Permanent Hotel Over 10,000 Sq. Ft.
According to the report, 91 percent of all general
contractors reported modular construction as having
a favorable impact on project budget performance,
with 48 percent indicating that costs decreased
by more than 10 percent. More than two-thirds
of respondents (68 percent) cited better than a 5
percent positive budget impact.

Beyond cost savings, cost predictability is increas-


ingly cited as a benefit of modular construction. Due
to the method’s shortened construction schedule;
upfront materials purchases; and steady, reliable
labor, modular projects provide a hedge against
construction market uncertainty.

12 PERMANENT MODULAR INDUSTRY


Hospitality Industry Embraces to “heads in beds” much sooner than high opportunity for savings, while
Modular Construction, Due to Shorter with conventional construction. significant savings are currently
Schedule, Quicker Occupancy, and harder to achieve with structures
Accelerated Return on Investment. Capital Projects and Infrastructure such as high-end apartments and
Modular Construction: From office buildings.
Prior to the COVID-19 pandemic, many Projects to Products—McKinsey
hotel brands were investing heavily & Company, 2019 Building Affordability by Building
in modular construction. As of late Affordably: Exploring the Benefits,
2019, Marriott International had built Savings in construction costs come Barriers, and Breakthroughs Needed to
50 hotels featuring prefabricated from several different areas. First, Scale Offsite Multifamily Construction—
guest rooms or bathrooms—including the integrated processes involved Terner Center, March 2017
a 354-key hotel in Hawthorn, CA, for in modular construction remove the
which the method saved a year in con- need for subcontractors and the The benefits of modular construction,
struction time, according to Jennifer margins they include in their quotes. detailed in this report, include reduc-
Abuzeid, senior director, global design Next, the primary trade-offs are be- tions in construction costs of at least
strategies for Marriott. tween savings in onsite labor against 20 percent, shortening of construction
potentially higher costs for materials times by up to 40 percent, and minimi-
Some of the direct cost-saving and the increase in logistics costs. zation of impacts on neighborhoods
benefits of modular cited by the Modular projects also tend to have surrounding construction sites.
hospitality sector include consistent higher upfront design costs against Evidence from developers suggests
product quality, elimination of change lower costs for rework and redesign. that offsite construction, as it is
orders, and reduction of punch lists currently practiced, can save up to 20
and job site waste. The key factor Given these trade-offs, the projects percent on the cost of construction for
for using modular, however, is the most likely to deliver the greatest a three- or four-story wood-frame mul-
shortened construction schedule cost savings are those that have the tifamily apartment building, translating
and quicker occupancy. Marriott highest proportion of labor-intensive to significant savings for consumers.
estimated that modular production activities and the greatest levels These savings are achieved primarily
and assembly shaved anywhere from of repeatability. Therefore, student in reductions in labor time and costs,
three months to eight months off of accommodations, hotels and af- economies of scale in material use,
a hotel’s construction time, leading fordable housing, for instance, offer and procurement savings.

ANNUAL REPORT 2023 13


$400
Case Study—How Moving to Modular
$350
Made a Project Possible
$300
Cost Per Square Foot

$250
Type: Modular Multifamily
$200 Location: St. Paul, MN
$150
Project Type: Market-Rate

$100 Barriers to Onsite Construction: Moving to Modular Construction:


$500
Budget: Proforma did not work. Construction Duration: 12 months
Schedule was 18-24 months Number of Modules: 155
$0 conventionally. Number of Units: 193
Offsite Onsite
Construction Type • Tight urban site: Cranes and Project Status: Completed 2021
scaffolding would have been Results/Benefits:
Soft General & Subcontractor Profit & Overhead • Modular construction
incredibly challenging.
Materials Podium/Site maximized the site to achieve
Labor General Contractor Install • Logistics: There was no area the unit count and make the
near the site for staging or project happen.
Source: Galante C., Draper-Zivetz S., Stein A. Building Affordability by Building Affordably: Exploring the
Benefits, Barriers, and Breakthroughs Needed to Scale Off-Site Multifamily Construction. (2017) Terner material storage. • The timeline was reduced from
Center for Housing Innovation, University of California, Berkeley.
• Quality: Onsite construction 24 months to 14 months.
would have required sheer walls • Modular methods worked with
and gypcrete. a tight site, so the developer did
Because the offsite construction pool can complete work offsite that
not have to invest in multiple
process is more controlled, labor would require costly subcontractor • Modular construction offered
staging sites.
and production efficiencies can be labor onsite. higher acoustical and thermal
• Neighborhood impact was
achieved. The production environment insulation ratings.
lessened, with a 22-day mod-
is enclosed, meaning all equipment The efficiency of material supply set, fewer workers onsite,
and workers are in the same place chains also greatly influences the cost less traffic, and a significantly
(rather than moving to, from, and of construction. In offsite methods, shorter construction timeline.
within a construction site) and are because many design components • The quality of the project
less vulnerable to weather-related and materials are standardized across was improved—units
delays or impediments. projects, orders can be placed with have better acoustic and
greater consistency and at higher thermal insulation.
Further, much of the work in offsite volumes, driving down costs in both • Modular construction
construction is done via assembly respects. Purchasing also originates maintained the high aesthetic
lines and automation, maximizing with the manufacturer rather than of the original design.
production efficiency and requiring with subcontractors, meaning that
fewer specialized skills. A less material suppliers aren’t working
skilled and less expensive labor with middlemen, and therefore

14 PERMANENT MODULAR INDUSTRY


subcontractor overhead and profit are Broad Sustainable Buildings (BSB) have, in contrast, established a
substantially reduced or eliminated. reports higher savings. In its T30 solid track record of accelerating
high-rise, BSB saw around 30 percent project timelines by 20-50 percent.
Case Studies Demonstrating savings, at $93 per square foot,
Cost Savings compared to $130 per square foot for Construction of modular building
Source: WSP—Modular Construction for the average traditionally constructed components occurs simultaneous-
Affordable Housing (February 2018) Chinese high-rise. ly with site work, allowing projects
to be completed in less time than
Holliday Development’s 5830 Third St. Schedule Savings and Certainty with traditional construction.
in San Francisco, containing 136 units, Lowney Architects priced a project According to the 2019 McKinsey & Additionally, 60-90 percent of
was the largest factory-built housing in 2017 for a 96-unit supportive Company report “Modular Construc- construction is completed inside
project at the time of its completion housing project in San Francisco. The tion: From Projects to Products,” a factory, mitigating the risk of
in 2016. Holliday demonstrated firm asked for a site-built price and overruns of 25-50 percent of projected weather delays. Buildings are
a 20 percent cost savings over a factory-built price, and the factory construction duration are common. occupied sooner, creating a faster
conventional construction. price was 15 percent less. However, recent modular projects return on investment.

MODULAR CONSTRUCTION SCHEDULE


DESIGN PERMITS & SITE/LOT DEVELOPMENT INSTALL &
ENGINEERING APPROVALS & FOUNDATION SITE RESTORATION TIME SAVINGS!
Simultaneous site development and
BUILDING CONSTRUCTION AT PLANT
home construction at the plant
reduces the schedule by 30% to 50%

SITE BUILT CONSTRUCTION SCHEDULE


DESIGN PERMITS & SITE/LOT DEVELOPMENT BUILDING SITE
ENGINEERING APPROVALS & FOUNDATION CONSTRUCTION RESTORATION

ANNUAL REPORT 2023 15


QUALITY
CONTROL AND
ASSURANCE
The North American modular industry approved to build in a jurisdiction,
is currently made up of more than a modular building project includes
250 regional manufacturers building four stages:
everything from construction-site • Design approval by the end-user
offices to single-family homes and and regulating authorities.
hotels. The industry is regulated • Fabrication of module
primarily at the state/provincial level components in a controlled Because most elements of the building, authority having jurisdiction, construc-
through administrative agencies that factory environment. including electrical and plumbing, are tion documents and other documenta-
implement and enforce the rules • Transportation of modules to the completed and considered closed tion will bear the signature and seal of
for building in that jurisdiction. The final building destination. construction (i.e., concealed behind the registered design professional.
administrative rules of each agency • Assembly of modular units to the drywall when leaving the factory),
provide for quality control, quality form a finished building, and inspection protocols must be clear, Fabrication of Module Components in
assurance, safety standards, and approval by local authorities. concise, and coordinated among state a Controlled Factory Environment
inspection procedures for industri- and local authorities. Once the plans are approved, the build-
alized building construction, design, Design Approval by the End-User ing components can be fabricated.
and manufacture. The purpose of and Regulating Authorities A design package consisting of One of the key advantages of modular
these rules is to provide minimum Buildings constructed using the the aggregate of all plans, designs, construction is that building modules
requirements to safeguard public modular process must comply with specifications, and documentation is can be inspected by the staff quality
health, safety, and general welfare, all applicable building code require- submitted by the manufacturer to the assurance/quality control manager
and to address societal and industry ments, including wind, snow, and design-review agency for compliance at each station (framing, electrical,
challenges for the inspection and seismic conditions, where the building review, including the compliance con- plumbing, drywall, etc.), with any
regulatory compliance of offsite con- will ultimately be located—not at the trol manual and the onsite construction mistakes corrected before the modules
struction. Once a factory has been fabrication location. documentation. Where required by the arrive onsite.

16 PERMANENT MODULAR INDUSTRY


In-plant inspections are conducted
by a third-party inspection agency on Sierra Preparatory Academy.
Built by Silver Creek Industries, LLC.
behalf of a state agency to verify that
Winner, Permanent Education
construction is in compliance with the Under 10,000 Sq. Ft.
approved construction documents.
The inspection agency inspects each
modular or panelized unit in a phase
of construction for compliance.
Attached to each modular component
is a data plate containing identifying
information, providing the local code
official with all pertinent information in
an easily accessible location.

An agency decal (insignia, label)


issued by the authority having juris-
diction is also permanently attached

ANNUAL REPORT 2023 17


to the modular component, indicating Onsite inspections of components construction in which a constructor,
that it has been constructed to meet verify that the installation is general contractor, design-builder, or
or exceed the applicable building compliant with the approved man- construction manager contracts with
code requirements. ufacturer’s installation instructions, a prefabricator to fabricate a compo-
and that connections performed nent offsite that is later installed on a
These steps are necessary so that the onsite are compliant with approved project worksite.
local code official has assurance that construction documents.
the building has been inspected and While prefabricated construction or
will meet all local requirements, thus It is of critical importance to the modular buildings have been around
avoiding destructive inspections of success of any project utilizing for decades, important contractual
the component onsite. modular construction to have a clear and legal issues have remained
scoping document spelling out roles unaddressed in most construction
Assembly of Modular Units Onsite and responsibilities at each point contracts. Importantly, using a typical
to Form the Finished Building, and in the process. For instance, who is construction subcontract or purchase
Approval by Local Authorities liable for any damage to the module order for prefabricated construction can
Once the modules are delivered to the in the factory, during transport, and be costly and carry significant risks.
final site (often by third-party transpor- once onsite? Who will be responsible
tation companies), other site-related for the onsite storage of the modules
requirements are subject to approval prior to assembly? Will the factory or
at the local level. These requirements the general contractor be responsible
may include land use and zoning; for assembling the modules?
local fire zones; site development;
and building setback, side, and rear MBI worked with the ConsensusDocs
yard requirements. Other require- Coalition to publish the industry’s
ments could include property line first standard contract document
requirements, subdivision regulations, for prefabricated construction.
subdivision control, review and regu- The ConsensusDocs 753 Standard
lation of architectural and aesthetic Prefabricated Construction Contract
requirements, foundation design, addresses the most common use
utility, and module connections. case scenario of prefabricated

18 PERMANENT MODULAR INDUSTRY


ENVIRONMENTAL
IMPACT
Making the Case for Modular Waste Reduction Quantifying Advantages of Modular Qualitative comparisons asserting
According to a March 2022 article by The U.S. Environmental Protection Construction: Waste Generation— that prefabrication reduces waste
McKinsey & Company, the world will Agency considers construction waste Loizos Loizou; Khalegh Barati; have also been verified. For quanti-
see a once-in-a-lifetime wave of capital and debris to be one of the largest Xuesong Shen, ORCID; and Binghao tative comparisons, the results show
spending on physical assets through contributors to landfills annually. Li, School of Civil and Environmental greater waste reductions than most
2027. This surge of investment— While construction demolition of exist- Engineering, University of New previous studies. Quale et al., Jaillon et
amounting to roughly $130 trillion —will ing structures represents about 90 South Wales, Sydney, NSW 2052, al. Kim, Jaillon and Poon, and Hosseini
flood into projects to decarbonize percent of this type of landfill waste, Australia, November 2021 et al. showed waste reductions of 20.1
and renew critical infrastructure. new construction activity accounts for This paper focuses on modular percent, 52 percent, 60 percent, 65
Notably, 93 percent of chief executive 57 million tons of such waste. construction as an offsite production percent, and 92 percent, respectively.
officers say sustainability issues are But it does not have to be that way. system and proposes a framework to
important for the future success of Several studies have been conducted compare and quantify differences in Onsite Versus Offsite: Comparing
their business, and 54 percent expect and reports produced globally on the waste generation between modular Environmental Impacts—Quale et al.
sustainability to be embedded within impact modular and prefabrication and conventional, in-situ construction The University of Virginia conducted
the core business strategies of most have on overall waste reduction. methods. The framework relies on a a study (Quale et al.) using life-cycle
companies within the next decade. According to the groundbreaking comprehensive literature review to assessment to quantify the environmen-
“Prefabrication and Modular Con- estimate the waste rates of building tal impacts of constructing a typical
From a sustainable and strategic struction 2020” report by Dodge Data materials, which are then applied to residential home using two methods,
perspective, modular construction has and Analytics, 86 percent of architect, realistic case studies to determine based on data from several modular
the potential to dramatically change contractor, and developer respondents the differences in waste generation. construction companies and conven-
how we build in four key areas: said that utilizing modular construc- Overall, modular construction reduces tional homebuilders. The study, peer-re-
• Significant waste reduction tion had a medium, high, or very high the overall weight of waste by up to viewed and published in the Journal
• Lower carbon footprint impact on reducing waste generated 83.2 percent for the cases considered. of Industrial Ecology, included impacts
• Relocate, renovate, and repurpose by construction activities. This corresponds to a 47.9 percent from material production and transport,
• Greater energy efficiency/tighter In terms of academic research, the decrease in the cost of waste for offsite and onsite energy use, worker
building envelope results are also undeniable. large structures. transport, and waste management.

ANNUAL REPORT 2023 19


Oak Ridge National Laboratory.
Built by Satellite Shelters, Inc.
Honorable Mention, Permanent
Office Over 10,000 Sq. Ft.

20 PERMANENT MODULAR INDUSTRY