CALCULATION PE FILM

PE FILM (2 LAYER)
KT&G PROJECT
REV.0 2024.05.28

DESCRIPTION MARKING SPECIFICATION CALCULATION REMARK


QTY
WIDTH LENGTH SET
BUIDING
1. UTILITY 1 (PE FILM (2 LAYER)
PC1 0.90 0.90 14.00 11.34
PC2 2.25 2.25 23.00 116.44
PE FILM (2 LAYER)
PC3 2.25 2.25 12.00 60.75
PC4 2.25 2.25 15.00 75.94
Sub Total 264.47 m2

2. UTILITY 2 (PE FILM (2 LAYER)


PC1 0.90 0.90 18.00 14.58
PC2 2.25 2.25 17.00 86.06
PC3 PE FILM (2 LAYER) 2.25 2.25 16.00 81.00
PC4 2.25 2.25 2.00 10.13
PC6 2.25 3.60 1.00 8.10
Sub Total 199.87 m2

3. ADMIN (PE FILM (2 LAYER)


PC1 0.90 0.90 32.00 25.92
PC2 2.25 2.25 18.00 91.13
PE FILM (2 LAYER)
PC3 2.25 2.25 7.00 35.44
DP 1.50 1.50 35.00 78.75
Sub Total 231.23 m2

TOTAL ALL 695.57 m2


ADD.3% 717.00 m2
1 ROLL = 25 MTR 31.87 ROLL
PASIR PASANG
PASIR PASANG
KT&G PROJECT
REV.0 2024.05.28

DESCRIPTION MARKING SPECIFICATION CALCULATION REMARK


QTY
WIDTH LENGTH HEIGHT SET
BUILDING
1. UTILITY 1 (PASIR PASANG)
PC1 1.50 1.50 0.10 72.00 16.20
PC2 1.50 2.25 0.10 6.00 2.03
PASIR PASANG
PC3 0.90 0.90 0.10 21.00 1.70
PC4 0.90 2.25 0.10 11.00 2.23
Sub Total 22.15 m3

2. UTILITY 2 (PASIR PASANG)


PC1 1.50 1.50 0.10 63.00 14.18
PC2 1.50 2.25 0.10 6.00 2.03
PC3 PASIR PASANG 0.90 0.90 0.10 17.00 1.38
PC4 0.90 2.25 0.10 12.00 2.43
PC6 2.07 2.25 0.10 21.00 9.78
Sub Total 29.79 m3

3. ADMIN (PASIR PASANG)


PC1 1.50 1.50 0.10 69.00 15.53
PC2 1.50 2.25 0.10 4.00 1.35
PASIR PASANG
PC3 0.90 0.90 0.10 18.00 1.46
DP 0.90 2.25 0.10 17.00 3.44
Sub Total 21.78 m3

TOTAL ALL 73.72 m3


ADD.10% 76.00 m3