Download as pdf or txt
Download as pdf or txt
You are on page 1of 94

MDV3 Project Management Plan

Project Management Plan


for the
Magical Devices Version 3 (MDV3)
Project

20YY-MM-DD

Prepared by:
Charles Wallace, Project Manager

Authorized by:
Lucy Pevensie, President Magical Devices, Project Sponsor

This document provides a realistic example, for a significant size project to show all the moving
parts, of the kind of professional Project Management Plan that provides the gate to execution. It
provides the level of definition the Sponsor needs to make any final trade-offs (e.g. more funding
to compress schedule, or less scope to reduce budget), and the information the Project Manager
needs to successfully monitor and control the project once underway. Experience has shown that
the PM planning best practices will produce a plan with a schedule and budget accuracy within
+/- 10%, which is what the Sponsor requires for approval with realistic expectations before
execution begins. This plan should focus on project planning, not detailed planning. It should
define all the work required during execution, including any detailed planning and design,
estimate the schedule and cost for all of this work, include it in the plan, and leave all further
work for the execution stage once the plan is approved.

For more information, refer to the Deeply Practical Project Management (DPPM)
reference book Amazon.com/dp/1548650463/ or online course at DeeplyPracticalPM.com

In particular see the chapter “Planning”.

The entire Magical Devices Version 3 project is available from DeeplyPracticalPM.com


or with the online course.

Also see the document Project Planning With MS Office, bundled with the MDV3 project,
for description of how the various elements of this plan were created.

Completion of the online course will also give you a Practical Project Manager (PPM) certificate.

© 2023-03-05 William Stewart

DeeplyPracticalPM.com
MDV3 Project Management Plan

Contents

1. Executive Summary .................................................................................................... 1


1.1 Need ...............................................................................................................1
1.2 Sponsor ..........................................................................................................1
1.3 Customer ........................................................................................................1
1.4 Business Case ..................................................................................................3
1.4.1 Options ...............................................................................................3
1.4.2 Assumptions ........................................................................................3
1.4.3 Benefits ...............................................................................................4
1.4.4 Costs ..................................................................................................4
1.4.5 Analysis...............................................................................................5

2. Scope ....................................................................................................................... 6
2.1 Objective.........................................................................................................6
2.2 Requirements ..................................................................................................7
2.3 Solution ..........................................................................................................7
2.4 Work Breakdown Structure ................................................................................8
2.4.1 Full WBS............................................................................................ 10
2.4.2 Business Process ................................................................................ 11
2.4.3 System.............................................................................................. 12
2.4.4 Hardware........................................................................................... 13
2.4.5 Software............................................................................................ 14
2.4.6 Security............................................................................................. 15
2.4.7 Facility .............................................................................................. 16
2.4.8 Quality Assurance ............................................................................... 17
2.4.9 Implementation .................................................................................. 18
2.4.10 Training............................................................................................. 19
2.4.11 Support ............................................................................................. 20
2.4.12 Project Management ........................................................................... 21
2.5 Scope Verification ........................................................................................... 22

DeeplyPracticalPM.com Page i/iv


MDV3 Project Management Plan

3. Schedule ................................................................................................................. 23
3.1 Precedence Diagram ....................................................................................... 24
3.2 Gantt Schedule .............................................................................................. 25
3.3 Critical Path ................................................................................................... 29
3.4 Milestones ..................................................................................................... 31

4. Budget .................................................................................................................... 33
4.1 Deliverable Costs............................................................................................ 33
4.2 Resource Costs .............................................................................................. 35
4.3 Cost Curve .................................................................................................... 36

5. Risks ...................................................................................................................... 37
5.1 Risk Management Process ............................................................................... 37
5.2 Risk Register.................................................................................................. 38

6. Issues ..................................................................................................................... 46

7. Stakeholders ........................................................................................................... 47

8. Resources ............................................................................................................... 49
8.1 Project Team ................................................................................................. 49
8.2 Resource Loading ........................................................................................... 52
8.3 Critical Resources ........................................................................................... 52
8.3.1 Software Engineers ............................................................................. 52
8.3.2 Magic Dust ......................................................................................... 53

9. Communications ...................................................................................................... 54
9.1 Weekly Issue Status Meetings .......................................................................... 54
9.2 Monthly Project Review Meetings ...................................................................... 54
9.3 Change Control Board Meetings........................................................................ 55
9.4 Monthly Company Updates .............................................................................. 55
9.5 Mayor Of Oakville Updates ............................................................................... 55
9.6 Executive Director Magical Management Institute Updates ................................... 55
9.7 Facility Opening Press Conference .................................................................... 56

10. Quality .................................................................................................................... 57


10.1 Peer Reviews ................................................................................................. 57
10.1.1 Informal Peer Reviews......................................................................... 57
10.1.2 Formal Peer Reviews ........................................................................... 58
10.2 User Reviews ................................................................................................. 59

11. Procurement ............................................................................................................ 61

DeeplyPracticalPM.com Page ii/iv


MDV3 Project Management Plan

11.1 Facility .......................................................................................................... 61


11.2 Building Material............................................................................................. 61
11.3 Hardware Equipment ...................................................................................... 62
11.4 Magic Dust .................................................................................................... 62
11.5 Management Station & Control Station Hardware ............................................... 62
11.6 Management Station Software ......................................................................... 62
11.7 Control Station Software ................................................................................. 62

12. Change Control Process............................................................................................. 63

Appendix A - Requirements ............................................................................................... 65

Appendix B - Work Breakdown Structure Dictionary.............................................................. 70

Appendix C - Project Issues List Format .............................................................................. 86

Appendix D - Monthly Project Report Format ....................................................................... 87

Appendix E - User Review Template.................................................................................... 88

Appendix F - Change Request Form .................................................................................... 89

List of Figures

Figure 1 – Top-Level Facility Diagram ................................................................................... 8


Figure 2 - Work Breakdown Structure (Full) ......................................................................... 10
Figure 3 - Work Breakdown Structure (Top-Level) ................................................................ 10
Figure 4 - Business Process Work ....................................................................................... 11
Figure 5 - System Work .................................................................................................... 12
Figure 6 - Hardware Work ................................................................................................. 13
Figure 7 - Software Work .................................................................................................. 14
Figure 8 - Security Work ................................................................................................... 15
Figure 9 - Facility Work ..................................................................................................... 16
Figure 10 - Quality Assurance Work .................................................................................... 17
Figure 11 - Implementation Work....................................................................................... 18
Figure 12 - Training Work.................................................................................................. 19
Figure 13 - Support Work .................................................................................................. 20
Figure 14 - Project Management Work ................................................................................ 21
Figure 15 - Precedence Diagram ........................................................................................ 24
Figure 16 - Gantt Schedule (Full) ....................................................................................... 26
Figure 17 - Gantt Schedule (Summary Tasks) ...................................................................... 27
Figure 18 - Gantt Schedule (Calendar Order) ....................................................................... 28
Figure 19 – Gantt Schedule (Critical Path) ........................................................................... 29
Figure 20 - Gantt Schedule (Milestones).............................................................................. 31
Figure 21 - Cumulative Cost Curve ..................................................................................... 36
Figure 22 - Project Organization ......................................................................................... 49
Figure 23 - Resource Loading............................................................................................. 52

DeeplyPracticalPM.com Page iii/iv


MDV3 Project Management Plan

List of Tables

Table 1 - Project Benefits .................................................................................................... 4


Table 2 - Project Costs ........................................................................................................ 5
Table 3 - Project BCR and ROI ............................................................................................. 5
Table 4 - Critical Path Deliverables ..................................................................................... 30
Table 5 - Project Milestones ............................................................................................... 32
Table 6 – Major Deliverable Costs....................................................................................... 34
Table 7 – Resource Costs By Type ...................................................................................... 36
Table 8 - Risk Register ...................................................................................................... 45
Table 9 - Stakeholder Register ........................................................................................... 48
Table 10 - Project Roles & Responsibilities ........................................................................... 51
Table 11 - User Review Lead / Participation ......................................................................... 59

DeeplyPracticalPM.com Page iv/iv


MDV3 Project Management Plan

1. Executive Summary

This document provides the project management plan for the Magical Devices Version 3 (MDV3)
project, a major upgrade of the company manufacturing capability to help ensure Magical Devices
continued success. It documents the planning baselines for scope, schedule, budget, and risks,
and provides additional information to assist the Project Manager and team in successful
execution of the effort.

See the DPPM section “Overview: Strategic Plan”.

This project supports the following objective from the Magical Devices Strategic Plan: “Magical
Devices shall ensure we have sufficient manufacturing capacity to produce the most advanced
magical devices with the highest quality at the lowest cost to meet projected market demand for
the next ten years”.

This is a living document, and shall be updated by the Project Manager as needed throughout the
course of the project.

1.1 Need

The project has been initiated to respond to the following need. Magical Devices version 2 have
been selling well for the past several years with excellent results. However, recent innovations in
the field of magic, together with the results from our research and development projects, indicate
it is possible to increase the effectiveness of the devices by at least 60%. At the same time,
advances in magic manufacturing equipment and processes indicate that next generation devices
could be produced at a cost at least 30% lower than with our current facility.

In addition, user demand for the version 2 devices has been growing at a rate of 20% a year.
Projections show that, even with the retrofits currently planned, the existing manufacturing
facility will reach production capacity within 36 months.

Therefore, Magical Devices have identified an opportunity to build a new manufacturing facility
capable of producing a more effective suite of magical devices that will generate even greater
market demand, produced at a lower cost, and with capacity that combined with our existing
facility will be able to meet anticipated demand for at least the following ten years.

1.2 Sponsor

See the DPPM section “Initiation: The Sponsor & Customer”.

Lucy Pevensie, President of Magical Devices, is the sponsor of this project, responsible for the
project budget, and the authority for approval of this project plan and any changes during
execution.

1.3 Customer

See the DPPM section “Initiation: The Sponsor & Customer”.

Three customer groups have been identified representing the end-users of the project, who
participated in definition of the project scope, and will be responsible for sign-off of the
requirements and acceptance of the final deliverables:

DeeplyPracticalPM.com Page 1/94


MDV3 Project Management Plan

 Ava Lee, VP of Customer Satisfaction. Represents the consumer end-users of the magic
devices, and is responsible for ensuring the functional requirements for version 3 of the
magical devices are correctly and completely defined, coordination of related user reviews
as the project progresses, and acceptance of the final device configuration.

 Ezekiel Rawlins, Magical Devices VP Manufacturing. Represents the production end-users


of the project, and is responsible for ensuring the requirements for the production lines are
correctly and completely defined, coordination of related user reviews as the project
progresses, and acceptance of the final equipment and production line configuration.

 Dave Robicheaux, Magical Devices Director of Facilities & Operations. Represents the
facility and operations end-users of the project, and is responsible for ensuring the
requirements for the facility are correctly and completely defined, coordination of related
user reviews as the project progresses, and acceptance of the facility configuration and
support programs.

DeeplyPracticalPM.com Page 2/94


MDV3 Project Management Plan

1.4 Business Case

See the DPPM section “Initiation: The Business Case”.

The business case analysis from initiation has been revised to reflect the results of project
planning. In summary, the planning stage analysis indicates the ROI turns positive in year 2, and
is more than 600% in year 5. This indicates the project will provide much more benefit than it
costs, and so it has been prioritized for investment by the Magical Devices Board of Directors and
approved for proceeding to execution by the Project Sponsor.

More information on the options considered, assumptions, constraints, costs, benefits, and
analysis can be found in the following sections.

1.4.1 Options

Three options were examined:

(a) Upgrade the current manufacturing facility. This option was not chosen because the costs
were estimated to be prohibitive, it would interrupt current production, and it would not be
possible to build the capacity for expected growth in the market in the current space.

(b) Outsource production to third party providers. This option was not selected because there
is currently no critical mass of suppliers producing magical devices enabling competitive
outsourcing, and it was judged to not be possible with an outsourced model to innovate
enhancements as quickly as required to stay competitive in the new and rapidly changing
magical devices segment.

(c) Build a new manufacturing facility. This option was selected since it would not interrupt
current production, it would allow the most rapid in-house innovation to respond to market
input as version 4 and later devices are developed, and it provided the greatest five year
economic benefit.

1.4.2 Assumptions

The business case is based on the following assumptions:

 The feasibility study and pilot projects conducted by the Research and Development
department indicates it is possible to build version 3 magical devices with an at least 60%
increase in effectiveness over version 2.

 The marketing study and analysis conducted by the Business Development department
indicates that version 3 magical devices with 60% greater effectiveness will generate a
doubling of current year over year growth in market demand to 40%.

 The research and pilot projects conducted by the manufacturing department indicate
updated processes and equipment can reduce the production cost (manufacturing and
operating) per device by at least 30%.

 Marketing costs of $20 per unit and revenue of $100 per unit will not change.

 The costs for developing the new facility will be 15% greater per square meter than
experienced for the build of the version 2 facility. A new facility of size 5,000 square

DeeplyPracticalPM.com Page 3/94


MDV3 Project Management Plan

meters will be needed to meet the anticipated growth in demand over the next five years.

 The costs for the hardware, software, project personnel, and project management costs
will be 50% greater than experienced for build of the version 2 facility.

 This project does not need to consider decommissioning and sell-off of the version 2
equipment. It is assumed the current facility will be kept in operation for manufacture of
version 2 devices for the secondary market for at least two years following open of the
version 3 facility, following which a separate project will address retrofit of the version 2
facility to meet the additional demand for version 3 devices in years six through ten.

1.4.3 Benefits

The benefits of the project are defined by the additional profit to be obtained from the new
facility, calculated as the difference between the profits from the version 3 facility and the profits
from continued use of the version 2 facility. The following table estimates the production level,
production costs, marketing costs, revenue, and profit for the current manufacturing facility, the
new manufacturing facility, and the difference over five years.

Year 1 2 3 4 5 Total
1. Current Manufacturing Facility
Production (M) @ growth of 20% 0.7 0.84 1.01 1.01 1.01 4.56
Cost (M) @ $60 / unit $42 $50 $60 $60 $60 $274
Marketing costs (M) @ $20 / unit $14 $17 $20 $20 $20 $91
Revenue @ $100 / unit $70 $84 $101 $101 $101 $456
Profit (M) $14 $17 $20 $20 $20 $91
2. New manufacturing facility
Production (M) @ growth of 40% 1. 1.4 1.96 2.74 3.84 10.95
Cost (M) @ $42 / unit $42 $59 $82 $115 $161 $460
Marketing costs (M) @ $20 / unit $20 $28 $39 $55 $77 $219
Revenue @ $100 / unit $100 $140 $196 $274 $384 $1,095
Profit (M) $38 $53 $74 $104 $146 $416
3. Difference
Production (M) 0.3 0.56 0.95 1.74 2.83 6.38
Cost (M) $0 $8 $22 $55 $101 $186
Marketing costs (M) $6 $11 $19 $35 $57 $128
Revenue $30 $56 $95 $174 $283 $638
Profit (M) $24 $36 $54 $84 $126 $325

Table 1 - Project Benefits

1.4.4 Costs

Compared to the initiation stage business case estimate, the planning estimate has lower costs
for the facility, building materials, production equipment, management station hardware, control
station software, project personnel, and project management personnel. It has higher costs for
the control station hardware, management station software, magic dust, and risk budget. There
is a new cost in planning for a security consultant to mitigate the security certification risk as
described in the risk management plan. Overall, the planning estimate costs are approximately
6% lower than estimated during initiation.

The following table summarizes the costs to build the new facility based on the plan described in

DeeplyPracticalPM.com Page 4/94


MDV3 Project Management Plan

this document.

1. Facility Procurement
Number of square meters of factory space 5000
Cost per square meter of factory space $1,850
Total $9,250,000
2. Building Material
All facility internal materials $565,000
Total $565,000
3. Hardware Procurement
Number of production lines 3
Hardware cost per production line $3,000,000
Management station $100,000
Control station $200,000
Magic dust $777,000
Total $10,477,000
4. Software Procurement
Number of production lines 3
Cost per production line $1,100,000
Management station $200,000
Control station $300,000
Total $4,400,000
5. Project Personnel
Project leads $3,283,000
Project team $9,680,000
Security consultant $66,400
Total $13,029,400
6. Project Management
Project management team $1,695,960
Risk budget $5,050,000
Total $6,745,960
Total Project Costs $44,467,360

Table 2 - Project Costs

1.4.5 Analysis

The expected additional profit was compared to the project costs, and the benefit / cost ratio
(BCR) and return on investment (ROI) calculated over five years, as shown in the table below.

Year 1 2 3 4 5
Cumulative additional profit (M) $24 $60 $115 $199 $325
Benefit / Cost Ratio (BCR) 0.54 1.36 2.58 4.47 7.3
Return on investment (ROI) -46% 36% 158% 347% 630%

Table 3 - Project BCR and ROI

This analysis shows the project provides much more benefit than it costs, and so it has been
prioritized for investment by the Magical Devices Board of Directors and approved for proceeding
to execution by the Project Sponsor.

DeeplyPracticalPM.com Page 5/94


MDV3 Project Management Plan

2. Scope

This section describes the MDV3 project scope, including the project objective, assumptions,
constraints, requirements, and the work breakdown structure defining all the deliverables to be
produced during the project execution and closing. It also describes the process to be used for
scope verification.

All planning of the project schedule, budget, and risks described in the remainder of this
document is based on this scope definition.

The current status of the scope progress shall be reported each month to the Sponsor, Customer,
and other relevant Stakeholders at the Monthly Project Review described in Section 9.2 – Monthly
Project Review Meetings.

Any changes to the project scope once this plan is approved and baselined must go through the
formal change control process described in Section 12 – Change Control Process.

2.1 Objective

See the DPPM section “Initiation: The First Level Scope”.

The MDV3 project objective is:

 Develop a manufacturing facility capable of producing a version 3 release of Magical


Devices with 60% greater effectiveness, at 30% less cost, able to meet demand growing
by 40% a year for the next five years, by the end of fiscal year 20YY.

The project assumptions are:

 The site acquired last year adjacent to our current facility has sufficient space, power,
water, and other resources required for development of the new facility.

 Office staff shall remain in the current facility, and the two facilities shall be connected by
an enclosed walkway.

 This project does not need to consider staffing requirements since the Magical Devices
human resources department will provide all required personnel as part of their existing
growth plans.

The project constraints are:

 The budget for this project must not exceed the planned budget of $ $44,467,360.

 The total schedule for the project must not exceed the planned schedule of 32 months.

 Pilot operation of the first production line must begin within 25 months from project start.

 The manufacturing system must fully comply with all requirements of the Magical
Management Institute (MMI) industry standard Secure Magical Device Manufacturing
(MMI-321123-G).

DeeplyPracticalPM.com Page 6/94


MDV3 Project Management Plan

2.2 Requirements

See the DPPM section “Planning: Requirements”.

The MDV3 project requirements provide the scope detail required to build the Magical Devices
Version 3 facility to achieve the project objective. The requirements identify what the project
needs to meet the objective, not how it will be done. The “how” will be defined during project
execution as the detailed requirements and design deliverables are developed.

Requirements have been identified in the areas of functionality, facility, equipment, management
station, control station, supportability, regulatory, capacity, availability, environmental, security,
training, marketing, and procurement. A complete requirements listing can be found in Appendix
A, along with the owner of the requirement and preliminary deliverable and test case allocations
to be refined as the design and test planning is progressed during execution.

The requirements were gathered and baselined by the Magical Devices business analysts, based
on experience with build of the Magical Devices Version 2 facility, extensive interviewing with the
customer user groups, and research of relevant industry standards. The requirements have gone
through multiple rounds of review to ensure they are complete, consistent, and testable, and
have been signed off by the respective owners.

2.3 Solution

See the DPPM section “Planning: Solution”.

The solution to be developed to meet the project objective is a new manufacturing facility that
meets all the project requirements and uses the most modern and efficient production methods,
new business processes, the most recent equipment hardware, and enhanced software capable of
producing version 3 magical devices implementing the features made possible by the innovations
developed by our research and development lab.

A top-level facility diagram is provided below, showing the planned orientation of the production
lines, control stations, management station, material staging, shipping line, equipment spares
locker, tools cabinet, and loading dock.

DeeplyPracticalPM.com Page 7/94


MDV3 Project Management Plan

Figure 1 – Top-Level Facility Diagram

This solution definition was developed at a sufficient level of detail that the planning team was
able to prepare a project plan with a schedule and budget at a level of accuracy estimated to be
+/- 10% for Sponsor review and approval for proceeding to execution.1 The additional definition
detail sufficient to build the complete solution will be developed during project execution with
production of the system architecture, hardware design, software design, and facility design
deliverables.

2.4 Work Breakdown Structure

See the DPPM section “Planning: Deliverables”.

The MDV3 work breakdown structure (WBS) provides the formal baseline of the full scope of the
project. The Project Manager and Leads conducted several iterations of planning to prepare the
WBS. The WBS documents all of the project deliverables, and captures all the work to be
performed during the project.

The WBS is shown in the following sections. More information can also be found in the WBS
dictionary in Appendix B, providing a description, owner, and cost account for each deliverable,
and in the attached document “MDV3 WBS Dictionary”.

The deliverables in the work breakdown structure can also be found flowcharted they will be done

1
(Note: In a project of this size, it would not be unusual to include additional diagrams in this
section, for example showing more top-level detail for the architecture of the production lines,
management stations, and control stations, perhaps even a top-level software architecture.)

DeeplyPracticalPM.com Page 8/94


MDV3 Project Management Plan

in precedence order in Section 3.1 – Precedence Diagram, and as scheduled across the calendar
in Section 3.2 – Gantt Schedule.

DeeplyPracticalPM.com Page 9/94


MDV3 Project Management Plan

2.4.1 Full WBS

The full MDV3 work breakdown structure is provided below, showing all the deliverables to be prepared during the project. This
diagram can be zoomed in for greater visibility in this Project Management Plan document Microsoft Word soft-copy. The full
sized diagram can also be found in the attached documents “MDV3 Work Breakdown Structure” in PowerPoint, and “MDV3 Work
Breakdown Structure - PDF” in PDF format.
Magical Devices
V3 (MDV3)

Bus ine ss Sys te m Hard ware Softw are Secur ity Facility Quality Im plemen tation T rainin g Su pp or t Pro je ct
Proce ss A ss uran ce Man ag ement

Bu sine ss Bus ine ss System Sys te m Sys te m Hard ware Hard ware Hard ware Hardw are So ftware Software Softw are Softw are Secur ity Facilitie s Facilitie s Facilitie s Hard ware So ftware System System Se curity Se cu rity Facilities Im p lem entation Im plem en tation Im plemen tation Im plementation Train in g T rainin g T rainin g Sup po rt Su pp or t Pro ject
Pro ce ss Proce ss Gap An alys is Arch ite ctu re Te st Plan ning Build Plan ning Des ign T es t Plann ing Bu ild Plan nin g De sign Te st Plan ning Build Secu rity Des ign T es t Plann ing Plan nin g De sign Build Te st Te st T es t Certification T es t Ce rtificatio n Insp ectio n Plann ing Ph ase 1 Ph as e 2 Phas e 3 Plan nin g Material Ph as es Plann ing Pack age Ph ase Su pp ort Man ag ement Proje ct Closure Ris k Bu dge t
As-IS T o-Be Activitie s

Busin ess Bu sin ess Gap Analysis Syste m System Test System Hardw are Hardw ar e Har dware Hard ware Software So ftware So ftware Software Se cu rity Secu rity Facilities Facilities Facilitie s Hardw ar e Softw are Sys te m System Secur ity Security Facilitie s Im plementation Phase 1 Phase 2 Ph ase 3 T raining Tr ain ing Phas e 1 Su ppo rt Sup po rt Ph ase 1 Proje ct Pro ject Closu re
Proce sses Pr ocesses Draft A rchitecture Plan Bu ild 1 De taile d De sig n Te st Plan Pr ocurem ent Detaile d Des ig n T es t Plan Procu rement De tailed Te st Plan Detaile d Des ig n Procu rement Build 1 Sp rint 1 Build 1 Ce rtificatio n Te st Certification Ins pe ctio n Plan Pilo t Pilo t Pilot Detaile d Mate rial Train ing De tailed Packag e Sup po rt M anagem en t Readin ess Ris k Buffe r
As -Is Dr aft To -Be Draft Draft Req uirem en ts Draft 1 Re qu irements Draft 1 Req uiremen ts Re qu irements Draft 1 T es t T es t Te st Final Fin al Build 1 Dr aft 1 Req uirem en ts Draft 1 Requ iremen ts Draft 1 T ransition Office Review

Busin ess Bu sin ess Gap Analysis Syste m System Test System Hardw are Hardw ar e Hardw are Test Hard ware Software So ftware Software Test Software Se cu rity Secur ity T est Facilities Facilities Facilitie s Hardw ar e Softw are Sys te m Facilitie s Im plementation Phase 1 Phase 2 Ph ase 3 T raining Tr ain ing Phas e 2 Su ppo rt Sup po rt Ph ase 2 Kick-off Final
Proce sses Pr ocesses Final A rchitecture Pro ce du res Bu ild 2 De ve lop ment De sig n Pr oced ures Build 1 Develo pm ent Des ig n Proce du res Sprin t 1 Architecture Pro ced ures Bu ild Plan Des ig n Bu ild 1 Build 2 Sp rint 2 Build 2 Ins pe ctio n Plan Rollo ut Rollo ut Rollou t Plan Mate rial Train ing Plan Packag e Sup po rt Me eting Procu rements
As -Is Final T o-Be Final Final Draft 1 Plan Draft 2 Dr aft 1 Plan Draft 2 Draft 1 Draft Draft 2 T es t T es t Te st Build 2 Dr aft 2 Draft 2 Draft 2 T ransition Clos ure

System Test System Hardw ar e Hardw are Test Hard ware So ftware Software Test Software Secur ity T est Facilities Facilitie s Hardw ar e Softw are Facilitie s Im plementation Tr ain ing Phas e 3 Sup po rt Ph ase 3 L es sons
Pro ce du res Bu ild Final De sig n Pr oced ures Build 2 Des ig n Proce du res Sprin t 2 Pro ced ures Des ig n Bu ild 2 Build 3 Sp rint 3 Ins pe ctio n Plan Mate rial Train ing Packag e Sup po rt Le arned
Draft 2 Final Dr aft 2 Fin al Draft 2 Final Draft 3 T es t T es t Build 3 Dr aft 3 Draft 3 Draft 3 T ransition Rep or t

System Test Hardw are Test Software Test Facilities Softw are Facilitie s Im plementation Tr ain ing Sup po rt
Pro ce du res Pr oced ures Hard ware Proce du res Software Des ig n Facilitie s Sp rint 4 Ins pe ctio n Plan Mate rial Packag e Pr oject
Fin al Final Build 3 Fin al Sprin t 3 Fin al Bu ild 3 T es t Build 4 Dr aft 4 Final Final Fin al Rep ort

Softw are Facilitie s Im plementation


Hard ware Software Facilitie s Sp rint 5 Ins pe ctio n Plan
Build Fin al Sprin t 4 Bu ild 4 T es t Build 5 Final

Facilitie s Facilitie s Im plementation


Software Ins pe ction Re adin ess
Sprin t 5 Bu ild 5 Build 6 Re view

Facilitie s Facilitie s
Software Ins pe ction
Final Bu ild 6 Build 7

Facilitie s
Bu ild 7

Facilitie s
Bu ild Final

Figure 2 - Work Breakdown Structure (Full)

In order to ensure the work outputs have the highest quality and will be fit for purpose to meet the stakeholder expectations,
almost all of the work has been planned along agile principles, and so produced in more than one draft or sprint or version.
Reviews are conducted as part of the work of each deliverable, and by formal test or inspection events between the iterations, to
identify any issues or deficiencies well before completion of the work, and ensure the final deliverable satisfies all of the project
requirements and will fully meet the stakeholder needs.

A summary of the top two levels of the work breakdown structure can be found below. More information on the deliverables and
work in each area can be found in the following sections.

Magical Devices
V3 (MDV3)

Bus ine ss Quality Project


Sys te m Hardw are Softw are Security Facility Im plementation Training Support
Proces s As surance Management

Figure 3 - Work Breakdown Structure (Top-Level)

DeeplyPracticalPM.com Page 10/94


MDV3 Project Management Plan

2.4.2 Business Process

The business process work to be performed during the MDV3 project will develop the baselines for
the as-is business processes, the to-be business processes, and then perform a gap analysis to
determine what work is needed to implement the to-be processes.

The business process deliverables are shown in the WBS extract shown below. More information
on each deliverable can be found in the WBS Dictionary in Appendix B.

Business
Process

Business Business
Process Process Gap Analysis
As-IS To-Be

Business Business
Gap Analysis
Processes Processes
As-Is Draft To-Be Draft Draft

Business Business
Gap Analysis
Processes Processes
As-Is Final To-Be Final Final

Figure 4 - Business Process Work

DeeplyPracticalPM.com Page 11/89


MDV3 Project Management Plan

2.4.3 System

The system work to be performed during the MDV3 project will develop the top-level system
architecture, the system test plan and system test procedures, and build the integrated hardware
and software system that will produce the Magical Devices Version 3.

The system deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

System

System System System


Architecture Test Planning Build

System
System Test System
Architecture
Draft Plan Build 1

System System Test


System
Architecture Procedures
Final Draft 1 Build 2

System Test
System
Procedures
Draft 2 Build Final

System Test
Procedures
Final

Figure 5 - System Work

DeeplyPracticalPM.com Page 12/89


MDV3 Project Management Plan

2.4.4 Hardware

The hardware work to be performed during the MDV3 project will refine the hardware detailed
requirements, document a hardware development plan, prepare the hardware design, develop the
system test plan and test procedures to be used for validation, and build the production lines of
hardware equipment to produce the Magical Devices Version 3.

The hardware deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

Hardw are

Hardw are Hardw are Hardw are Hardw are


Planning Design Test Planning Build

Hardw are Hardw are


Hardw are Hardw are
Detailed Design
Requirements Draft 1 Test Plan Procurement

Hardw are Hardw are Hardw are Test


Hardw are
Development Design Procedures
Plan Draft 2 Draft 1 Build 1

Hardw are Hardw are Test


Hardw are
Design Procedures
Final Draft 2 Build 2

Hardw are Test


Hardw are
Procedures
Final Build 3

Hardw are
Build Final

Figure 6 - Hardware Work

As the system architecture and the hardware design are finalized, the “Hardware Procurement”
deliverable will be refined into greater detail to break out the individual elements of equipment
required for staging, piece build, assembly, finishing, QA, management stations, control stations,
and magic dust.

DeeplyPracticalPM.com Page 13/89


MDV3 Project Management Plan

2.4.5 Software

The software work to be performed during the MDV3 project will refine the software detailed
requirements, document a software development plan, prepare the software design, develop the
software test plan and test procedures to be used for validation, and build the software to
produce the Magical Devices Version 3.

The software deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

Softw are

Softw are Softw are Softw are Softw are


Planning Design Test Planning Build

Softw are Softw are


Softw are Softw are
Detailed Design
Requirements Draft 1 Test Plan Procurement

Softw are Softw are Softw are Test


Softw are
Development Design Procedures
Plan Draft 2 Draft 1 Sprint 1

Softw are Softw are Test


Softw are
Design Procedures
Final Draft 2 Sprint 2

Softw are Test


Softw are
Procedures
Final Sprint 3

Softw are
Sprint 4

Softw are
Sprint 5

Softw are
Final

Figure 7 - Software Work

As the system architecture and the software design are finalized, the “Software Procurement”
deliverable will be refined into greater detail to break out the individual elements of procured
software required for the production equipment, management stations, and control stations.

DeeplyPracticalPM.com Page 14/89


MDV3 Project Management Plan

2.4.6 Security

The security work to be performed during the MDV3 project will refine the security detailed
requirements, develop the security architecture, and develop the security test plan and test
procedures to be used for validation and certification of the secure system.

The security deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

Security

Security
Security Design
Test Planning

Security
Security
Detailed
Requirements Test Plan

Security Test
Security
Procedures
Architecture Draft

Security Test
Procedures
Final

Figure 8 - Security Work

DeeplyPracticalPM.com Page 15/89


MDV3 Project Management Plan

2.4.7 Facility

The facility work to be performed during the MDV3 project will refine the facility detailed
requirements, document a facility build plan, prepare the facility design, and build the internal
elements of the facility to produce the Magical Devices Version 3. The external elements of the
building itself will be constructed by the building contractor selected during the design process.

The facility deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B. As the facilities design is
completed, the “Facilities Procurement” deliverable will be refined to break out the individual
elements of building material required to complete the facilities build.

Facility

Facilities Facilities Facilities


Planning Design Build

Facilities Facilities
Facilities
Detailed Design
Requirements Draft 1 Procurement

Facilities
Facilities Facilities
Design
Build Plan Draft 2 Build 1

Facilities
Facilities
Design
Draft 3 Build 2

Facilities
Facilities
Design
Final Build 3

Facilities
Build 4

Facilities
Build 5

Facilities
Build 6

Facilities
Build 7

Facilities
Build Final

Figure 9 - Facility Work

DeeplyPracticalPM.com Page 16/89


MDV3 Project Management Plan

2.4.8 Quality Assurance

The quality assurance work to be performed during the MDV3 project will ensure the hardware,
software, system, security, and facility are fully tested and inspected to meet all the
requirements, are correctly configured, and will be of the highest quality and fit for purpose to
produce the Magical Devices Version 3.

The quality assurance deliverables are shown in the WBS extract shown below. More information
on each deliverable can be found in the WBS Dictionary in Appendix B.

Quality
Assurance

Hardw are Softw are System System Security Security Facilities


Test Test Test Certification Test Certification Inspection

Hardw are Softw are System System Security Facilities


Security
Build 1 Sprint 1 Build 1 Certification Certification Inspection
Test Test Test Final Test Final Build 1

Hardw are Softw are System Facilities


Build 2 Sprint 2 Build 2 Inspection
Test Test Test Build 2

Hardw are Softw are Facilities


Build 3 Sprint 3 Inspection
Test Test Build 3

Softw are Facilities


Sprint 4 Inspection
Test Build 4

Softw are Facilities


Sprint 5 Inspection
Test Build 5

Facilities
Inspection
Build 6

Facilities
Inspection
Build 7

Figure 10 - Quality Assurance Work

DeeplyPracticalPM.com Page 17/89


MDV3 Project Management Plan

2.4.9 Implementation

The implementation work to be performed during the MDV3 project will prepare and manage a
comprehensive implementation plan to ensure the success of a multi-phase pilot and rollout of
the production system to produce the Magical Devices Version 3.

The implementation deliverables are shown in the WBS extract shown below. More information
on each deliverable can be found in the WBS Dictionary in Appendix B.

Im plementation

Im plementation Im plementation Im plementation Im plementation


Planning Phase 1 Phase 2 Phase 3

Im plementation
Phase 1 Phase 2 Phase 3
Plan
Draft 1 Pilot Pilot Pilot

Im plementation
Phase 1 Phase 2 Phase 3
Plan
Draft 2 Rollout Rollout Rollout

Im plementation
Plan
Draft 3

Im plementation
Plan
Draft 4

Im plementation
Plan
Final

Im plementation
Readiness
Review

Figure 11 - Implementation Work

DeeplyPracticalPM.com Page 18/89


MDV3 Project Management Plan

2.4.10 Training

The training work to be performed during the MDV3 project will refine the training detailed
requirements, develop a training plan, prepare the material to train the users of the production
system, and train the teams.

The training deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

Training

Training Training
Training Phases
Planning Material

Training Training
Phase 1
Detailed Material
Requirements Draft 1 Training

Training
Training Phase 2
Material
Plan Draft 2 Training

Training
Phase 3
Material
Draft 3 Training

Training
Material
Final

Figure 12 - Training Work

DeeplyPracticalPM.com Page 19/89


MDV3 Project Management Plan

2.4.11 Support

The support work to be performed during the MDV3 project will refine the support detailed
requirements, develop a support plan, prepare the package of documentation and processes to
support the system and facilities, and transition support to the operations teams.

The support deliverables are shown in the WBS extract shown below. More information on each
deliverable can be found in the WBS Dictionary in Appendix B.

Support

Support Support
Phase Support
Planning Package

Support Support Phase 1


Detailed Package Support
Requirements Draft 1 Transition

Support Phase 2
Support
Package Support
Plan Draft 2 Transition

Support Phase 3
Package Support
Draft 3 Transition

Support
Package
Final

Figure 13 - Support Work

DeeplyPracticalPM.com Page 20/89


MDV3 Project Management Plan

2.4.12 Project Management

The project management work to be performed during the MDV3 project will establish the project
management office to manage the project as it progresses through execution and closing, hold a
kick-off meeting to coordinate all members of the project, manage the risk budget, and conduct
the activities required to successfully close out the project.

The project management deliverables are shown in the WBS extract shown below. More
information on each deliverable can be found in the WBS Dictionary in Appendix B.

Project
Management

Project
Management Project Closure Risk Budget
Activities

Project Project Closure


Management Readiness Risk Buffer
Office Review

Final
Kick-off
Procurements
Meeting Closure

Lessons
Learned
Report

Project
Final Report

Figure 14 - Project Management Work

DeeplyPracticalPM.com Page 21/89


MDV3 Project Management Plan

2.5 Scope Verification

All work that is delivered into the final product shall undergo verification by both the project
teams that produced the deliverables as well as independent verification by the Quality Assurance
organization to ensure they are compliant with all requirements and are fit for purpose – able to
fully meet the need for which they were intended.

Before each deliverable is completed, the project teams shall first conduct verification of their own
work to ensure it is defect free and meets all the project requirements before they pass it on for
Quality Assurance verification. The deliverable owners will not rely on the QA process to find
issues and defects.

Quality assurance shall then conduct formal verification to confirm the project outputs are
correctly built and configured. Any issues or deficiencies shall be documented and corrective
actions then defined by the deliverable owner. The corrections shall be implemented with all due
speed by the deliverable owners, and then the work re-verified by quality assurance. A
deliverable shall not pass verification until the quality assurance organization formally confirms all
issues have been addressed and the work is ready to passed on to the next step.

Verifications may be conducted through inspections, demonstrations, analyses, or tests as


appropriate. Verifications shall be conducted throughout the project as individual elements,
drafts, versions, increments, or sprints are completed to find issues and enable correction well
before the final deliverable is baselined.

Wherever possible, scenario based verification shall be used, where the verification event is
conducted in the context of an example of actual use of the deliverable to obtain the most
realistic verification it meets all the requirements and ensure it is clear that the work is fit for
purpose at the same time. The to-be business processes developed as part of the first steps of
the project will be the basis for these scenarios wherever applicable.

Where appropriate, thresholds for issues and defects shall be established to allow minor issues to
be corrected during the support phase while enabling the work to proceed to the next stage.
Where this approach is deemed appropriate, quality assurance shall work with the project team
and customer groups to establish criteria according to the following structure:

 There must be zero Category 1 issues – affecting core functionality.

 There must be less than N (e.g. 3) Category 2 issues – where a workaround acceptable to
the customer representative exists until the issue is corrected in a timely manner.

 There must be less than M (e.g. 5) Category 3 issues – minor usability not affecting use
that the customer representative agrees can addressed during support or the next phase
of the project.

Where the above thresholds are deemed useful for evaluation of deliverables they shall be agreed
and documented during test planning before the deliverable testing commences.

DeeplyPracticalPM.com Page 22/89


MDV3 Project Management Plan

3. Schedule

See the DPPM sections “Planning: Estimating” and “Planning: Schedule”.

This section documents the MDV3 schedule baseline, mapping the project work defined in the
work breakdown structure to the calendar in order to determine the project duration and the
critical path driving the end-date.

The schedule logic is provided in Section 3.1 – Precedence Diagram. The precedence diagram
mapped to the calendar showing when work will be done and providing the overall project
duration is provided in Section 3.2 – Gantt Schedule. The critical path driving the project
duration and end-date is provided in Section 3.3 – Critical Path. The major project milestones are
documented in Section 3.4 – Milestones.

The baseline schedule meets both of the schedule constraints specified in the initiation stage
project charter:

Charter Constraint Planning Baseline


The total schedule must not exceed 36 The planned schedule is less than 32
months months.
Pilot operation of the first production line The first production pilot begin at the end
must begin within 25 months from project of month 25.
start.

The above constraints have been included as milestones in the Gantt schedule shown in Section
3.4 - Milestones.

The current status of the schedule progress shall be reported each month to the Sponsor,
Customer, and other relevant Stakeholders at the Monthly Project Review described in Section 9.2
– Monthly Project Review Meetings. The schedule performance shall be reported using Earned
Value Management.

See the DPPM section “Monitoring & Control: Earned Value Management”.

Any changes to the project schedule once this plan is approved and baselined must go through
the formal change control process described in Section 12 – Change Control Process.

DeeplyPracticalPM.com Page 23/89


MDV3 Project Management Plan

3.1 Precedence Diagram

See the DPPM section “Planning: Logic”.

The MDV3 precedence diagram documents the execution logic of the project, flowcharting the deliverables to show the
dependencies between them and the order in which the project work will be carried out.

The Project Manager and Leads conducted several iterations of planning to baseline a complete and accurate precedence diagram
documenting the relationships between all of the project work. The full MDV3 precedence diagram is shown in the diagram
below, and can be zoomed in for greater visibility in this Project Management Plan document Microsoft Word soft-copy. The full
sized diagram can also be viewed or printed in full size A0 size paper from the attached documents “MDV3 Precedence Diagram”
in PowerPoint, and “MDV3 Precedence Diagram - PDF” in PDF format.

Secur ity Se curity Test Se cur ity Test


Se curity Se cur ity
Detaile d Proce dures Procedures
A rchitecture Te s t Plan
Requir emnts Dr aft Final

Software Software Softw are Software Software Software Software Software Software
Softw are Softw are Software Softw are Softw are Softw are Software Softw are
Detaile d De sign Des ign De sign Spr int 1 Spr int 2 Spr int 3 Spr int 4 Sprint 5
De v Plan Procurement Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Final
Requir emnts Draft 1 Draft 2 Final Te st Te st Te st Te st Tes t

Softw are Test Software Test Software Test


Software
Procedures Pr oce dures Procedures
Te s t Plan
Draft 1 Dr aft 2 Final

Sys tem Te st Syste m Test Sys te m Te st Sys tem Syste m


System Sys te m System Sys te m Se curity Se curity Syste m
Procedures Procedures Proce dures Build 1 Build 2
Tes t Plan Build 1 Build 2 Build Final Tes t Ce rtification Cer tification
Draft 1 Dr aft 2 Final Tes t Te st

Hardw are Hardware Har dw ar e


Hardware Tes t Te st Tes t
Te s t Plan Pr oce dures Procedures Pr ocedures
Dr aft 1 Draft 2 Final
Bus ine ss Busines s
Proces ses Proces ses
A s-Is Draft As-Is Final
Sys te m Sys tem Hardware Hardware Hardw are Hardware Hardwar e Hardwar e Hardw are
Kick off Gap Analys is Gap Analysis Har dw ar e Har dw ar e Hardware Hardware Hardware Hardware
S A rchitecture Architecture Detaile d Des ign De sign Des ign Build 1 Build 2 Build 3
Me eting Draft Final De v Plan Pr ocur ement Build 1 Build 2 Build 3 Final
Draft Final Requir emnts Draft 1 Dr aft 2 Final Te st Te st Tes t
Bus ine ss
Busines s
Proces ses
Proces ses
To-Be
To-Be Final
Draft
Facilities Facilities Facilitie s Facilities Facilitie s
Facilitie s Facilities Facilitie s Ins pe ction Facilitie s Ins pe ction Facilitie s Inspection Facilitie s Inspection Facilitie s Inspection Facilitie s Inspection Facilitie s Inspection Facilitie s
Detaile d De sign De sign Des ign De sign Build 5 Build 5 Build 7 Build 7
Build Plan Procurement Build 1 Build 1 Build 2 Build 2 Build 3 Build 3 Build 4 Build 4 Build 6 Build 6 Build Final
Requir emnts Draft 1 Dr aft 2 Draft 3 Final

Implement- Implement- Implement- Implement- Implement-


ation Plan ation Plan ation Plan ation Plan ation Plan
Draft 1 Dr aft 2 Draft 3 Draft 4 Final
Implement-
ation
Re adines s
Revie w
Training Training Training Training Training
Training
Detaile d M ate rial M ate rial M aterial M ate rial
Plan
Requir emnts Dr aft 1 Draft 2 Draft 3 Final

Support Support Support Support Support


Support
Detaile d Pack age Pack age Pack age Pack age
Plan
Requir emnts Dr aft 1 Draft 2 Draft 3 Final

Phasee 1
Phas Phas e 1 Phase 1 Phas e 1
Ris k Buffer
Training
Training Pilot Rollout Support

Pr oje ct
Final Les sons Le ssons
Phas e 2 Phase 2 Phas e 2 Phase 2 Clos ure Project
Procuremnts Le arned Learned F
Tr aining Pilot Rollout Support Re adines s Final Repor t
Closure Me eting Re port
Revie w

Phase 3 Phas e 3 Phase 3 Phas e 3


Training Pilot Rollout Support

Figure 15 - Precedence Diagram

This precedence diagram provides the logical structure of the project work that is then mapped to the calendar as shown in the
Gantt Schedule in the following section.

DeeplyPracticalPM.com Page 24/89


MDV3 Project Management Plan

3.2 Gantt Schedule

See the DPPM section “Planning: The Gantt Chart”.

The Project Leads prepared detailed activity breakdowns for all of their deliverables to obtain
duration estimates for all the elements of work. The precedence diagram structure and these
estimates were then loaded into Microsoft Project to obtain a Gantt schedule showing the
mapping of the project work to the calendar, including calculation of the critical path driving the
project end-date. This Gantt schedule provides the formal MDV3 schedule baseline.

The following pages provide three views of the project Gantt schedule:

 Full Schedule. This view shows the full Gantt schedule with the work listed in the order it
was entered according to the structure of the Work Breakdown Structure, including the
summary tasks identifying the functional areas by WBS header. The critical path is
highlighted in red. You can also view or print this graphic in PDF format on full size A0
size paper in the attached file “MDV3 Gantt Schedule (Full) - PDF”.

 Summary Tasks. This view shows the Gantt schedule summary tasks at the level of the
WBS headers, showing the broad calendar ranges in which the work is being done. You
can also view or print this graphic in PDF format on full size A0 size paper in the attached
file “MDV3 Gantt Schedule (Summary Tasks) - PDF”.

 Calendar Order. This view shows the lowest level deliverables by themselves without the
summary task WBS headers, listed in order of finish date, showing all the work of the
project in the calendar order in which it is planned to be completed. The critical path is
highlighted in red. You can also view or print this graphic in PDF format on full size A0
size paper in the attached file “MDV3 Gantt Schedule (Calendar Order) - PDF”.

These graphics can be zoomed in for greater visibility in this Project Management Plan document
Microsoft Word soft-copy. The full Gantt schedule including all of the resource allocations and
other relevant information can also be found in the attached Microsoft Project file “MDV3 Gantt
Schedule”.

DeeplyPracticalPM.com Page 25/89


MDV3 Project Management Plan
ID WBS-ID Deliv erable Duration Start Finish Float ' 50 Jan '50 Feb ' 50 Mar ' 50 Apr ' 50 May '50 Jun '50 Jul '50 Aug '50 Sep '50 Oct ' 50 No v ' 50 Dec ' 51 Jan '51 Feb ' 51 Mar '51 Apr ' 51 May '51 Jun '51 Jul '51 Aug ' 51 Sep '51 Oct ' 51 No v ' 51 Dec '52 Jan '52 Feb '52 Mar '52 Apr '52 May '52 Jun '52 Jul ' 52 Aug '52 Sep
27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
1 MDV3 Magical Devic es V3 Project 674 days 2050-01-03 2052-08-01 0 days
2 BPR1 Business Proc ess 60 days 2050-01-04 2050-03-28 0 days
3 BPRA1 Business Process As-IS 15 days 2050-01-04 2050-01-24 15 days
4 BPRA1.1 Business Processes As-Is Draft 10 days 2050-01-04 2050-01-17 15 days
5 BPRA1.2 Business Processes As-Is Final 5 days 2050-01-18 2050-01-24 15 days
6 BPRT1 Business Process To-Be 30 days 2050-01-04 2050-02-14 0 days
7 BPRT1.1 Business Processes To-Be Draft 20 days 2050-01-04 2050-01-31 0 days
8 BPRT1.2 Business Processes To-Be Final 10 days 2050-02-01 2050-02-14 0 days
9 GAN1 Gap Analysis 30 days 2050-02-15 2050-03-28 0 days
10 GAN1.1 Gap Analysis Draft 20 days 2050-02-15 2050-03-14 0 days
11 GAN1.2 Gap Analysis Final 10 days 2050-03-15 2050-03-28 0 days
12 SYS1 System 370 days 2050-03-29 2051-08-28 0 days
13 SYA1 System Arc hitecture 30 days 2050-03-29 2050-05-09 0 days
14 SYA1.1 System Architecture Draft 20 days 2050-03-29 2050-04-25 0 days
15 SYA1.2 System Architecture Final 10 days 2050-04-26 2050-05-09 0 days
16 SYTP1 System Test Planning 115 days 2050-05-10 2050-10-17 55 days
17 SYTP1.1 System Test Plan 10 days 2050-05-10 2050-05-23 55 days
18 SYTP1.2 System Test Procedures Draft 1 20 days 2050-08-30 2050-09-26 160 days
19 SYTP1.3 System Test Procedures Draft 2 10 days 2050-09-27 2050-10-10 160 days
20 SYTP1.4 System Test Procedures Final 5 days 2050-10-11 2050-10-17 160 days
21 SYB1 System Bu ild 65 days 2051-05-30 2051-08-28 0 days
22 SYB1.1 System B uild 1 20 days 2051-05-30 2051-06-26 0 days
23 SYB1.2 System B uild 2 20 days 2051-07-11 2051-08-07 0 days
24 SYB1.3 System B uild Final 10 days 2051-08-15 2051-08-28 0 days
25 HW1 Hardware 220 days 2050-05-10 2051-03-13 55 days
26 HWP1 Hardware Plan ning 30 days 2050-05-10 2050-06-20 75 days
27 HWP1.1 Hardware Detailed Requirements 20 days 2050-05-10 2050-06-06 75 days
28 HWP1.2 Hardware Develop ment Plan 10 days 2050-06-07 2050-06-20 75 days
29 HWD1 Hardware Design 35 days 2050-07-19 2050-09-05 55 days
30 HWD1.1 Hardware Design Draft 1 20 days 2050-07-19 2050-08-15 55 days
31 HWD1.2 Hardware Design Draft 2 10 days 2050-08-16 2050-08-29 55 days
32 HWD1.3 Hardware Design Final 5 days 2050-08-30 2050-09-05 55 days
33 HWTP1 Hardware Test Plan ning 65 days 2050-06-21 2050-09-19 175 days
34 HWTP1.1 Hardware Test Plan 5 days 2050-06-21 2050-06-27 195 days
35 HWTP1.2 Hardware Test Procedures Draft 1 10 days 2050-08-16 2050-08-29 160 days
36 HWTP1.3 Hardware Test Procedures Draft 2 10 days 2050-08-30 2050-09-12 170 days
37 HWTP1.4 Hardware Test Procedures Final 5 days 2050-09-13 2050-09-19 175 days
38 HWB1 Hardware Build 135 days 2050-09-06 2051-03-13 55 days
39 HWB1.1 Hardware Procurement 20 days 2050-09-06 2050-10-03 55 days
40 HWB1.2 Hardware Build 1 30 days 2050-10-04 2050-11-14 55 days
41 HWB1.3 Hardware Build 2 25 days 2050-11-29 2051-01-02 55 days
42 HWB1.4 Hardware Build 3 20 days 2051-01-17 2051-02-13 55 days
43 HWB1.5 Hardware Build Final 10 days 2051-02-28 2051-03-13 55 days
44 SW1 Software 275 days 2050-05-10 2051-05-29 0 days
45 SWP1 Software Planning 30 days 2050-05-10 2050-06-20 0 days
46 SWP1.1 Software Detailed Requirements 20 days 2050-05-10 2050-06-06 0 days
47 SWP1.2 Software Development Plan 10 days 2050-06-07 2050-06-20 0 days
48 SWD1 Software Design 50 days 2050-06-21 2050-08-29 0 days
49 SWD1.1 Software Design Draft 1 20 days 2050-06-21 2050-07-18 0 days
50 SWD1.2 Software Design Draft 2 20 days 2050-07-19 2050-08-15 0 days
51 SWD1.3 Software Design Final 10 days 2050-08-16 2050-08-29 0 days
52 SWTP1 Software Test Planning 70 days 2050-06-21 2050-09-26 20 days
53 SWTP1.1 Software Test Plan 5 days 2050-06-21 2050-06-27 35 days
54 SWTP1.2 Software Test Procedures Draft 1 20 days 2050-07-19 2050-08-15 20 days
55 SWTP1.3 Software Test Procedures Draft 2 20 days 2050-08-16 2050-09-12 20 days
56 SWTP1.4 Software Test Procedures Final 10 days 2050-09-13 2050-09-26 20 days
57 SWB 1 Software Bu ild 195 days 2050-08-30 2051-05-29 0 days
58 SWB 1.1 Software Procurem ent 10 days 2050-08-30 2050-09-12 0 days
59 SWB 1.2 Software Sprint 1 30 days 2050-09-13 2050-10-24 0 days
60 SWB 1.3 Software Sprint 2 30 days 2050-11-01 2050-12-12 0 days
61 SWB 1.4 Software Sprint 3 30 days 2050-12-20 2051-01-30 0 days
62 SWB 1.5 Software Sprint 4 30 days 2051-02-07 2051-03-20 0 days
63 SWB 1.6 Software Sprint 5 30 days 2051-03-28 2051-05-08 0 days
64 SWB 1.7 Software Final 10 days 2051-05-16 2051-05-29 0 days
65 SEC1 Security 125 days 2050-05-10 2050-10-31 5 days
66 SECD1 Security Design 25 days 2050-05-10 2050-06-13 5 days
67 SECD1.1 Security Detailed Requirements 10 days 2050-05-10 2050-05-23 5 days
68 SECD1.2 Security Architecture 15 days 2050-05-24 2050-06-13 5 days
69 SECTP1 Security Test Planning 100 days 2050-06-14 2050-10-31 215 days
70 SECTP1.1 Security Test Plan 5 days 2050-06-14 2050-06-20 280 days
71 SECTP1.2 Security Test Procedures Draft 1 20 days 2050-09-06 2050-10-03 225 days
72 SECTP1.3 Security Test Procedures Final 10 days 2050-10-18 2050-10-31 215 days
73 FAC1 Facility 380 days 2050-05-10 2051-10-23 5 days
74 FACP1 Facilities Plann in g 40 days 2050-05-10 2050-07-04 120 days
75 FACP1.1 Facilities Detailed Requirements 20 days 2050-05-10 2050-06-06 120 days
76 FACP1.2 Facilities Build Plan 20 days 2050-06-07 2050-07-04 120 days
77 FACD1 Facilities Design 70 days 2050-07-05 2050-10-10 110 days
78 FACD1.1 Facilities Design Draft 1 20 days 2050-07-05 2050-08-01 120 days
79 FACD1.2 Facilities Design Draft 2 20 days 2050-08-16 2050-09-12 110 days
80 FACD1.3 Facilities Design Draft 3 10 days 2050-09-13 2050-09-26 110 days
81 FACD1.4 Facilities Design Final 10 days 2050-09-27 2050-10-10 110 days
82 FACB1 Facilities Build 270 days 2050-10-11 2051-10-23 5 days
83 FACB1.1 Facilities Procurem ent 20 days 2050-10-11 2050-11-07 110 days
84 FACB1.2 Facilities Build 1 20 days 2050-11-15 2050-12-12 105 days
85 FACB1.3 Facilities Build 2 20 days 2051-01-03 2051-01-30 95 days
86 FACB1.4 Facilities Build 3 20 days 2051-02-14 2051-03-13 90 days
87 FACB1.5 Facilities Build 4 10 days 2051-05-30 2051-06-12 40 days
88 FACB1.6 Facilities Build 5 10 days 2051-06-27 2051-07-10 35 days
89 FACB1.7 Facilities Build 6 10 days 2051-08-08 2051-08-21 20 days
90 FACB1.8 Facilities Build 7 10 days 2051-08-29 2051-09-11 20 days
91 FACB1.9 Facilities Build Final 10 days 2051-10-10 2051-10-23 5 days
92 QA1 Quality Assurance 250 days 2050-10-25 2051-10-09 0 days
93 QAHW1 Hardware Test 75 days 2050-11-15 2051-02-27 55 days
94 QAHW1.1 Hardware Build 1 Test 10 days 2050-11-15 2050-11-28 55 days
95 QAHW1.2 Hardware Build 2 Test 10 days 2051-01-03 2051-01-16 55 days
96 QAHW1.3 Hardware Build 3 Test 10 days 2051-02-14 2051-02-27 55 days
97 QASW1 Software Test 145 days 2050-10-25 2051-05-15 0 days
98 QASW1.1 Software Sprint 1 Test 5 days 2050-10-25 2050-10-31 0 days
99 QASW1.2 Software Sprint 2 Test 5 days 2050-12-13 2050-12-19 0 days
100 QASW1.3 Software Sprint 3 Test 5 days 2051-01-31 2051-02-06 0 days
101 QASW1.4 Software Sprint 4 Test 5 days 2051-03-21 2051-03-27 0 days
102 QASW1.5 Software Sprint 5 Test 5 days 2051-05-09 2051-05-15 0 days
103 QASY1 System Test 35 days 2051-06-27 2051-08-14 0 days
104 QASY1.1 System B uild 1 Test 10 days 2051-06-27 2051-07-10 0 days
105 QASY1.2 System B uild 2 Test 5 days 2051-08-08 2051-08-14 0 days
106 QASC1 Security Test 10 days 2051-08-29 2051-09-11 0 days
107 QASC1.1 Security Test 10 days 2051-08-29 2051-09-11 0 days
108 QASE1 Security Certification 10 days 2051-09-12 2051-09-25 0 days
109 QASE1.1 Security Certification Final 10 days 2051-09-12 2051-09-25 0 days
110 QASEC1 System Certific ation 10 days 2051-09-26 2051-10-09 0 days
111 QASEC1.2 System C ertification Final 10 days 2051-09-26 2051-10-09 0 days
112 FACI1 Facilities In spectio n 200 days 2050-12-13 2051-09-18 20 days
113 FACI1.1 Inspection Build 1 5 days 2050-12-13 2050-12-19 105 days
114 FACI1.2 Inspection Build 2 5 days 2051-01-31 2051-02-06 95 days
115 FACI1.3 Inspection Build 3 5 days 2051-03-14 2051-03-20 90 days
116 FACI1.4 Inspection Build 4 5 days 2051-06-13 2051-06-19 40 days
117 FACI1.5 Inspection Build 5 5 days 2051-07-11 2051-07-17 35 days
118 FACI1.6 Inspection Build 6 5 days 2051-08-22 2051-08-28 20 days
119 FACI1.7 Inspection Build 7 5 days 2051-09-12 2051-09-18 20 days
120 IMP1 Implementation 541 days 2050-05-10 2052-06-04 0 days
121 IMPP1 Implemen tation Plan ning 390 days 2050-05-10 2051-11-06 0 days
122 IMPP1.1 Implementation Plan Draft 1 20 days 2050-05-10 2050-06-06 295 days
123 IMPP1.2 Implementation Plan Draft 2 20 days 2050-09-06 2050-10-03 230 days
124 IMPP1.3 Implementation Plan Draft 3 20 days 2051-05-30 2051-06-26 60 days
125 IMPP1.4 Implementation Plan Draft 4 20 days 2051-08-29 2051-09-25 15 days
126 IMPP1.5 Implementation Plan Final 10 days 2051-10-10 2051-10-23 5 days
127 IMPP1.6 Implementation Readiness R eview 5 days 2051-10-31 2051-11-06 0 days
128 IMPH1 Implemen tation Phase 1 50 days 2052-01-31 2052-04-09 0 days
129 IMPH1.1 Phase 1 Pilot 20 days 2052-01-31 2052-02-27 0 days
130 IMPH1.2 Phase 1 Rollout 30 days 2052-02-28 2052-04-09 20 days
131 IMPH2 Implemen tation Phase 2 50 days 2052-02-28 2052-05-07 0 days
132 IMPH2.1 Phase 2 Pilot 20 days 2052-02-28 2052-03-26 0 days
133 IMPH2.2 Phase 2 Rollout 30 days 2052-03-27 2052-05-07 10 days
134 IMPH3 Implemen tation Phase 3 50 days 2052-03-27 2052-06-04 0 days
135 IMPH3.1 Phase 3 Pilot 20 days 2052-03-27 2052-04-23 0 days
136 IMPH3.2 Phase 3 Rollout 30 days 2052-04-24 2052-06-04 0 days
137 TR1 Training 471 days 2050-05-10 2052-02-27 20 days
138 TRP1 Training Planning 15 days 2050-05-10 2050-05-30 270 days
139 TRP1.1 Training Detailed Requirements 5 days 2050-05-10 2050-05-16 270 days
140 TRP1.2 Training Plan 10 days 2050-05-17 2050-05-30 270 days
141 TRM1 Training Material 295 days 2050-09-06 2051-10-23 5 days
142 TRM1.1 Training Material Draft 1 30 days 2050-09-06 2050-10-17 200 days
143 TRM1.2 Training Material Draft 2 30 days 2051-05-30 2051-07-10 40 days
144 TRM1.3 Training Material Draft 3 30 days 2051-08-29 2051-10-09 5 days
145 TRM1.4 Training Material Final 10 days 2051-10-10 2051-10-23 5 days
146 TRPH1 Training Phases 30 days 2052-01-17 2052-02-27 0 days
147 TRPH1.1 Phase 1 Training 10 days 2052-01-17 2052-01-30 0 days
148 TRPH1.2 Phase 2 Training 10 days 2052-01-31 2052-02-13 10 days
149 TRPH1.3 Phase 3 Training 10 days 2052-02-14 2052-02-27 20 days
150 SU1 Sup port 561 days 2050-05-10 2052-07-02 0 days
151 SUP1 Supp ort Plan ning 20 days 2050-05-10 2050-06-06 265 days
152 SUP1.1 Support Detailed R equirements 10 days 2050-05-10 2050-05-23 265 days
153 SUP1.2 Support Plan 10 days 2050-05-24 2050-06-06 265 days
154 SUPA1 Supp ort Package 300 days 2050-09-06 2051-10-30 0 days
155 SUPA1.1 Support Package Draft 1 30 days 2050-09-06 2050-10-17 200 days
156 SUPA1.2 Support Package Draft 2 30 days 2051-05-30 2051-07-10 40 days
157 SUPA1.3 Support Package Draft 3 25 days 2051-08-29 2051-10-02 5 days
158 SUPA1.4 Support Package Final 15 days 2051-10-10 2051-10-30 0 days
159 SUPS1 Ph ase Support 60 days 2052-04-10 2052-07-02 0 days
160 SUPS1.1 Phase 1 Support Transition 40 days 2052-04-10 2052-06-04 20 days
161 SUPS1.2 Phase 2 Support Transition 30 days 2052-05-08 2052-06-18 10 days
162 SUPS1.3 Phase 3 Support Transition 20 days 2052-06-05 2052-07-02 0 days
163 PM1 Project Management 674 days 2050-01-03 2052-08-01 0 days
164 PMA1 Project Management Activities 673 days 2050-01-03 2052-07-31 0 days
165 PMA1.1 Project Management Office 673 days 2050-01-03 2052-07-31 1 day
166 PMA1.2 Kick-off Meeting 1 day 2050-01-03 2050-01-03 0 days
167 PMRB1 Risk Bud get 51 days 2051-11-07 2052-01-16 0 days
168 PMRB1.1 Risk B uffer 51 days 2051-11-07 2052-01-16 0 days
169 PMC1 Project Clo sure 22 days 2052-07-03 2052-08-01 0 days
170 PMC1.1 Project Closure Readiness Review 1 day 2052-07-03 2052-07-03 0 days
171 PMC1.2 Final Procurements C losure 5 days 2052-07-04 2052-07-10 0 days
172 PMC1.3 Lessons Learned Meeting 1 day 2052-07-11 2052-07-11 0 days
173 PMC1.4 Lessons Learned Report 5 days 2052-07-12 2052-07-18 0 days
174 PMC1.5 Project Final R eport 10 days 2052-07-19 2052-08-01 0 days

Figure 16 - Gantt Schedule (Full)

DeeplyPracticalPM.com Page 26/89


MDV3 Project Management Plan

ID WBS-I D Deliverable Dur ation Start Finish Float '50 Jan ' 50 Feb ' 50 Mar '5 0 Apr '50 May ' 50 Jun '5 0 Ju l '50 Aug '50 Sep ' 50 O ct '5 0 N ov '50 Dec ' 51 Jan ' 51 Feb '5 1 M ar '5 1 Apr ' 51 May ' 51 Jun '51 Ju l '51 Aug '51 Sep '5 1 O ct '51 N ov ' 51 Dec ' 52 Jan ' 52 Feb ' 52 Mar ' 52 Ap r '52 May '52 Jun '5 2 J ul '52 Aug '52 Sep
27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
1 MDV3 Magical Devices V3 Project 674 days 2050-01-03 2052-08-01 0 days
2 BPR1 Business Process 60 days 2050-01-04 2050-03-28 0 days
3 BPRA1 Business Process As-IS 15 days 2050-01-04 2050-01-24 15 days
6 BPRT1 Business Process To-Be 30 days 2050-01-04 2050-02-14 0 days
9 GAN1 Gap Analysis 30 days 2050-02-15 2050-03-28 0 days
12 SYS1 System 370 days 2050-03-29 2051-08-28 0 days
13 SYA1 System Architecture 30 days 2050-03-29 2050-05-09 0 days
16 SYTP1 System Test Planning 115 days 2050-05-10 2050-10-17 55 days
21 SYB1 System Build 65 days 2051-05-30 2051-08-28 0 days
25 HW1 H ardware 220 days 2050-05-10 2051-03-13 55 days
26 HWP1 Hardware Planning 30 days 2050-05-10 2050-06-20 75 days
29 HWD1 Hardware Design 35 days 2050-07-19 2050-09-05 55 days
33 HWTP1 Hardware Test Planning 65 days 2050-06-21 2050-09-19 175 days
38 HWB1 Hardware Build 135 days 2050-09-06 2051-03-13 55 days
44 SW1 Software 275 days 2050-05-10 2051-05-29 0 days
45 SWP 1 Software Planning 30 days 2050-05-10 2050-06-20 0 days
48 SWD1 Software Design 50 days 2050-06-21 2050-08-29 0 days
52 SWTP 1 Software Test Planning 70 days 2050-06-21 2050-09-26 20 days
57 SWB1 Software Build 195 days 2050-08-30 2051-05-29 0 days
65 SEC1 Security 125 days 2050-05-10 2050-10-31 5 days
66 SECD1 Security D esign 25 days 2050-05-10 2050-06-13 5 days
69 SECTP 1 Security T est Planning 100 days 2050-06-14 2050-10-31 215 days
73 FAC1 Facility 380 days 2050-05-10 2051-10-23 5 days
74 FACP 1 Facilities Planning 40 days 2050-05-10 2050-07-04 120 days
77 FACD1 Facilities Design 70 days 2050-07-05 2050-10-10 110 days
82 FACB1 Facilities Build 270 days 2050-10-11 2051-10-23 5 days
92 QA1 Quality Assurance 250 days 2050-10-25 2051-10-09 0 days
93 QAHW1 Hardware Test 75 days 2050-11-15 2051-02-27 55 days
97 QASW1 Software Test 145 days 2050-10-25 2051-05-15 0 days
103 QASY1 System Test 35 days 2051-06-27 2051-08-14 0 days
106 QASC1 Security T est 10 days 2051-08-29 2051-09-11 0 days
108 QASE1 Security Certification 10 days 2051-09-12 2051-09-25 0 days
110 QASEC1 System Certification 10 days 2051-09-26 2051-10-09 0 days
112 FACI1 Facilities Inspection 200 days 2050-12-13 2051-09-18 20 days
120 IMP 1 I mplementation 541 days 2050-05-10 2052-06-04 0 days
121 IMP P1 Implementation Planning 390 days 2050-05-10 2051-11-06 0 days
128 IMP H1 Implementation Phase 1 50 days 2052-01-31 2052-04-09 0 days
131 IMP H2 Implementation Phase 2 50 days 2052-02-28 2052-05-07 0 days
134 IMP H3 Implementation Phase 3 50 days 2052-03-27 2052-06-04 0 days
137 TR1 Training 471 days 2050-05-10 2052-02-27 20 days
138 TRP1 Training Planning 15 days 2050-05-10 2050-05-30 270 days
141 TRM1 Training Material 295 days 2050-09-06 2051-10-23 5 days
146 TRPH1 Training Phases 30 days 2052-01-17 2052-02-27 0 days
150 SU1 Support 561 days 2050-05-10 2052-07-02 0 days
151 SUP 1 Support Planning 20 days 2050-05-10 2050-06-06 265 days
154 SUP A1 Support Package 300 days 2050-09-06 2051-10-30 0 days
159 SUP S1 Phase Support 60 days 2052-04-10 2052-07-02 0 days
163 PM1 Project Management 674 days 2050-01-03 2052-08-01 0 days
164 PMA1 Project Management Activities 673 days 2050-01-03 2052-07-31 0 days
167 PMRB1 Risk Budget 51 days 2051-11-07 2052-01-16 0 days
169 PMC1 Project Closure 22 days 2052-07-03 2052-08-01 0 days

Figure 17 - Gantt Schedule (Summary Tasks)

DeeplyPracticalPM.com Page 27/89


MDV3 Project Management Plan

ID WBS-I D Deliverable Dur ation Start Finish Float '50 Jan ' 50 Feb ' 50 Mar '5 0 Apr '50 May ' 50 Jun '5 0 Ju l '50 Aug '50 Sep ' 50 O ct '5 0 N ov '50 Dec ' 51 Jan ' 51 Feb '5 1 M ar '5 1 Apr ' 51 May ' 51 Jun '51 Ju l '51 Aug '51 Sep '5 1 O ct '51 N ov ' 51 Dec ' 52 Jan ' 52 Feb ' 52 Mar ' 52 Ap r '52 May '52 Jun '5 2 J ul '52 Aug '52 Sep
27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
166 PMA1. 2 Kick-off Meeting 1 day 2050-01-03 2050-01-03 0 days
4 BPRA1.1 Business Processes As-Is Draft 10 days 2050-01-04 2050-01-17 15 days
5 BPRA1.2 Business Processes As-Is Final 5 days 2050-01-18 2050-01-24 15 days
7 BPRT1. 1 Business Processes To-Be Draft 20 days 2050-01-04 2050-01-31 0 days
8 BPRT1. 2 Business Processes To-Be Final 10 days 2050-02-01 2050-02-14 0 days
10 GAN1.1 Gap Analysis Draft 20 days 2050-02-15 2050-03-14 0 days
11 GAN1.2 Gap Analysis Final 10 days 2050-03-15 2050-03-28 0 days
14 SYA1.1 System Architecture Draft 20 days 2050-03-29 2050-04-25 0 days
15 SYA1.2 System Architecture Final 10 days 2050-04-26 2050-05-09 0 days
139 TRP1.1 Training Detailed Requirements 5 days 2050-05-10 2050-05-16 270 days
17 SYTP1.1 System Test Plan 10 days 2050-05-10 2050-05-23 55 days
67 SECD1. 1 Security Detailed Requirements 10 days 2050-05-10 2050-05-23 5 days
152 SUP 1.1 Support Detailed Requirements 10 days 2050-05-10 2050-05-23 265 days
140 TRP1.2 Training P lan 10 days 2050-05-17 2050-05-30 270 days
27 HWP1.1 Hardware Detailed Requirements 20 days 2050-05-10 2050-06-06 75 days
46 SWP 1.1 Software Detailed Requirements 20 days 2050-05-10 2050-06-06 0 days
75 FACP 1.1 Facilities Detaile d Requirements 20 days 2050-05-10 2050-06-06 120 days
122 IMP P1.1 Implementation Plan Draft 1 20 days 2050-05-10 2050-06-06 295 days
153 SUP 1.2 Support Plan 10 days 2050-05-24 2050-06-06 265 days
68 SECD1. 2 Security Architecture 15 days 2050-05-24 2050-06-13 5 days
28 HWP1.2 Hardware Development P lan 10 days 2050-06-07 2050-06-20 75 days
47 SWP 1.2 Software Development P lan 10 days 2050-06-07 2050-06-20 0 days
70 SECTP 1.1 Security Test P lan 5 days 2050-06-14 2050-06-20 280 days
34 HWTP1.1 Hardware Test Plan 5 days 2050-06-21 2050-06-27 195 days
53 SWTP 1.1 Software Test Plan 5 days 2050-06-21 2050-06-27 35 days
76 FACP 1.2 Facilities Build Plan 20 days 2050-06-07 2050-07-04 120 days
49 SWD1. 1 Software Design Draft 1 20 days 2050-06-21 2050-07-18 0 days
78 FACD1.1 Facilities Design Draft 1 20 days 2050-07-05 2050-08-01 120 days
30 HWD1.1 Hardware Design Draft 1 20 days 2050-07-19 2050-08-15 55 days
50 SWD1. 2 Software Design Draft 2 20 days 2050-07-19 2050-08-15 0 days
54 SWTP 1.2 Software Test Procedures Draft 1 20 days 2050-07-19 2050-08-15 20 days
31 HWD1.2 Hardware Design Draft 2 10 days 2050-08-16 2050-08-29 55 days
35 HWTP1.2 Hardware Test Procedures Draft 1 10 days 2050-08-16 2050-08-29 160 days
51 SWD1. 3 Software Design Final 10 days 2050-08-16 2050-08-29 0 days
32 HWD1.3 Hardware Design Final 5 days 2050-08-30 2050-09-05 55 days
36 HWTP1.3 Hardware Test Procedures Draft 2 10 days 2050-08-30 2050-09-12 170 days
55 SWTP 1.3 Software Test Procedures Draft 2 20 days 2050-08-16 2050-09-12 20 days
58 SWB1.1 Software Procurement 10 days 2050-08-30 2050-09-12 0 days
79 FACD1.2 Facilities Design Draft 2 20 days 2050-08-16 2050-09-12 110 days
37 HWTP1.4 Hardware Test Procedures Final 5 days 2050-09-13 2050-09-19 175 days
18 SYTP1.2 System Test Procedures Draft 1 20 days 2050-08-30 2050-09-26 160 days
56 SWTP 1.4 Software Test Procedures Final 10 days 2050-09-13 2050-09-26 20 days
80 FACD1.3 Facilities Design Draft 3 10 days 2050-09-13 2050-09-26 110 days
39 HWB1.1 Hardware Procurement 20 days 2050-09-06 2050-10-03 55 days
71 SECTP 1.2 Security Test P rocedures Draft 1 20 days 2050-09-06 2050-10-03 225 days
123 IMP P1.2 Implementation Plan Draft 2 20 days 2050-09-06 2050-10-03 230 days
19 SYTP1.3 System Test Procedures Draft 2 10 days 2050-09-27 2050-10-10 160 days
81 FACD1.4 Facilities Design Final 10 days 2050-09-27 2050-10-10 110 days
20 SYTP1.4 System Test Procedures Final 5 days 2050-10-11 2050-10-17 160 days
142 TRM1.1 Training Material Draft 1 30 days 2050-09-06 2050-10-17 200 days
155 SUP A1 .1 Support Package Draft 1 30 days 2050-09-06 2050-10-17 200 days
59 SWB1.2 Software Sprint 1 30 days 2050-09-13 2050-10-24 0 days
72 SECTP 1.3 Security Test P rocedures Final 10 days 2050-10-18 2050-10-31 215 days
98 QASW1.1 Software Sprint 1 Test 5 days 2050-10-25 2050-10-31 0 days
83 FACB1.1 Facilities Procurement 20 days 2050-10-11 2050-11-07 110 days
40 HWB1.2 Hardware Build 1 30 days 2050-10-04 2050-11-14 55 days
94 QAHW1.1 Hardware Build 1 Tes t 10 days 2050-11-15 2050-11-28 55 days
60 SWB1.3 Software Sprint 2 30 days 2050-11-01 2050-12-12 0 days
84 FACB1.2 Facilities Build 1 20 days 2050-11-15 2050-12-12 105 days
99 QASW1.2 Software Sprint 2 Test 5 days 2050-12-13 2050-12-19 0 days
113 FACI1 .1 Inspection Build 1 5 days 2050-12-13 2050-12-19 105 days
41 HWB1.3 Hardware Build 2 25 days 2050-11-29 2051-01-02 55 days
95 QAHW1.2 Hardware Build 2 Tes t 10 days 2051-01-03 2051-01-16 55 days
61 SWB1.4 Software Sprint 3 30 days 2050-12-20 2051-01-30 0 days
85 FACB1.3 Facilities Build 2 20 days 2051-01-03 2051-01-30 95 days
100 QASW1.3 Software Sprint 3 Test 5 days 2051-01-31 2051-02-06 0 days
114 FACI1 .2 Inspection Build 2 5 days 2051-01-31 2051-02-06 95 days
42 HWB1.4 Hardware Build 3 20 days 2051-01-17 2051-02-13 55 days
96 QAHW1.3 Hardware Build 3 Tes t 10 days 2051-02-14 2051-02-27 55 days
43 HWB1.5 Hardware Build Final 10 days 2051-02-28 2051-03-13 55 days
86 FACB1.4 Facilities Build 3 20 days 2051-02-14 2051-03-13 90 days
62 SWB1.5 Software Sprint 4 30 days 2051-02-07 2051-03-20 0 days
115 FACI1 .3 Inspection Build 3 5 days 2051-03-14 2051-03-20 90 days
101 QASW1.4 Software Sprint 4 Test 5 days 2051-03-21 2051-03-27 0 days
63 SWB1.6 Software Sprint 5 30 days 2051-03-28 2051-05-08 0 days
102 QASW1.5 Software Sprint 5 Test 5 days 2051-05-09 2051-05-15 0 days
64 SWB1.7 Software Final 10 days 2051-05-16 2051-05-29 0 days
87 FACB1.5 Facilities Build 4 10 days 2051-05-30 2051-06-12 40 days
116 FACI1 .4 Inspection Build 4 5 days 2051-06-13 2051-06-19 40 days
22 SYB1 .1 System Build 1 20 days 2051-05-30 2051-06-26 0 days
124 IMP P1.3 Implementation Plan Draft 3 20 days 2051-05-30 2051-06-26 60 days
88 FACB1.6 Facilities Build 5 10 days 2051-06-27 2051-07-10 35 days
104 QASY1.1 System Build 1 Test 10 days 2051-06-27 2051-07-10 0 days
143 TRM1.2 Training Material Draft 2 30 days 2051-05-30 2051-07-10 40 days
156 SUP A1 .2 Support Package Draft 2 30 days 2051-05-30 2051-07-10 40 days
117 FACI1 .5 Inspection Build 5 5 days 2051-07-11 2051-07-17 35 days
23 SYB1 .2 System Build 2 20 days 2051-07-11 2051-08-07 0 days
105 QASY1.2 System Build 2 Test 5 days 2051-08-08 2051-08-14 0 days
89 FACB1.7 Facilities Build 6 10 days 2051-08-08 2051-08-21 20 days
24 SYB1 .3 System Build Final 10 days 2051-08-15 2051-08-28 0 days
118 FACI1 .6 Inspection Build 6 5 days 2051-08-22 2051-08-28 20 days
90 FACB1.8 Facilities Build 7 10 days 2051-08-29 2051-09-11 20 days
107 QASC1.1 Security Test 10 days 2051-08-29 2051-09-11 0 days
119 FACI1 .7 Inspection Build 7 5 days 2051-09-12 2051-09-18 20 days
109 QASE1.1 Security Certification Final 10 days 2051-09-12 2051-09-25 0 days
125 IMP P1.4 Implementation Plan Draft 4 20 days 2051-08-29 2051-09-25 15 days
157 SUP A1 .3 Support Package Draft 3 25 days 2051-08-29 2051-10-02 5 days
111 QASEC1.2 System Certification Final 10 days 2051-09-26 2051-10-09 0 days
144 TRM1.3 Training Material Draft 3 30 days 2051-08-29 2051-10-09 5 days
91 FACB1.9 Facilities Build Final 10 days 2051-10-10 2051-10-23 5 days
126 IMP P1.5 Implementation Plan Final 10 days 2051-10-10 2051-10-23 5 days
145 TRM1.4 Training Material Final 10 days 2051-10-10 2051-10-23 5 days
158 SUP A1 .4 Support Package Final 15 days 2051-10-10 2051-10-30 0 days
127 IMP P1.6 Implementation Readines s Review 5 days 2051-10-31 2051-11-06 0 days
168 PMRB1.1 Risk Buffer 51 days 2051-11-07 2052-01-16 0 days
147 TRPH1.1 Phase 1 Training 10 days 2052-01-17 2052-01-30 0 days
148 TRPH1.2 Phase 2 Training 10 days 2052-01-31 2052-02-13 10 days
129 IMP H1.1 Phase 1 Pilot 20 days 2052-01-31 2052-02-27 0 days
149 TRPH1.3 Phase 3 Training 10 days 2052-02-14 2052-02-27 20 days
132 IMP H2.1 Phase 2 Pilot 20 days 2052-02-28 2052-03-26 0 days
130 IMP H1.2 Phase 1 Rollout 30 days 2052-02-28 2052-04-09 20 days
135 IMP H3.1 Phase 3 Pilot 20 days 2052-03-27 2052-04-23 0 days
133 IMP H2.2 Phase 2 Rollout 30 days 2052-03-27 2052-05-07 10 days
136 IMP H3.2 Phase 3 Rollout 30 days 2052-04-24 2052-06-04 0 days
160 SUP S1. 1 Phase 1 Support Transition 40 days 2052-04-10 2052-06-04 20 days
161 SUP S1. 2 Phase 2 Support Transition 30 days 2052-05-08 2052-06-18 10 days
162 SUP S1. 3 Phase 3 Support Transition 20 days 2052-06-05 2052-07-02 0 days
170 PMC1.1 Project Clos ure Readiness Review 1 day 2052-07-03 2052-07-03 0 days
171 PMC1.2 Final P rocureme nts Closure 5 days 2052-07-04 2052-07-10 0 days
172 PMC1.3 Less ons Learned Meeting 1 day 2052-07-11 2052-07-11 0 days
173 PMC1.4 Less ons Learned Report 5 days 2052-07-12 2052-07-18 0 days
165 PMA1.1 Project Management Office 673 days 2050-01-03 2052-07-31 1 day
174 PMC1.5 Project Final Report 10 days 2052-07-19 2052-08-01 0 days

Figure 18 - Gantt Schedule (Calendar Order)

DeeplyPracticalPM.com Page 28/89


MDV3 Project Management Plan

3.3 Critical Path

See the DPPM section “Planning: The Critical Path”.

A subset of the MDV3 Gantt schedule showing just the deliverables on the project critical path is shown below, listed in order of
finish date, showing the work driving the project duration and end-date in the calendar order in which it is planned to be
completed.
ID WBS-I D Deliverable Dur ation Start Finish Float '50 Jan ' 50 Feb ' 50 Mar '5 0 Apr '50 May ' 50 Jun '5 0 Ju l '50 Aug '50 Sep ' 50 O ct '5 0 N ov '50 Dec ' 51 Jan ' 51 Feb '5 1 M ar '5 1 Apr ' 51 May ' 51 Jun '51 Ju l '51 Aug '51 Sep '5 1 O ct '51 N ov ' 51 Dec ' 52 Jan ' 52 Feb ' 52 Mar ' 52 Ap r '52 May '52 Jun '5 2 J ul '52 Aug '52 Sep
27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
166 PMA1. 2 Kick-off Meeting 1 day 2050-01-03 2050-01-03 0 days
7 BPRT1. 1 Business Processes To-Be Draft 20 days 2050-01-04 2050-01-31 0 days
8 BPRT1. 2 Business Processes To-Be Final 10 days 2050-02-01 2050-02-14 0 days
10 GAN1.1 Gap Analysis Draft 20 days 2050-02-15 2050-03-14 0 days
11 GAN1.2 Gap Analysis Final 10 days 2050-03-15 2050-03-28 0 days
14 SYA1.1 System Architecture Draft 20 days 2050-03-29 2050-04-25 0 days
15 SYA1.2 System Architecture Final 10 days 2050-04-26 2050-05-09 0 days
46 SWP 1.1 Software Detailed Requirements 20 days 2050-05-10 2050-06-06 0 days
47 SWP 1.2 Software Development P lan 10 days 2050-06-07 2050-06-20 0 days
49 SWD1. 1 Software Design Draft 1 20 days 2050-06-21 2050-07-18 0 days
50 SWD1. 2 Software Design Draft 2 20 days 2050-07-19 2050-08-15 0 days
51 SWD1. 3 Software Design Final 10 days 2050-08-16 2050-08-29 0 days
58 SWB1.1 Software Procurement 10 days 2050-08-30 2050-09-12 0 days
59 SWB1.2 Software Sprint 1 30 days 2050-09-13 2050-10-24 0 days
98 QASW1.1 Software Sprint 1 Test 5 days 2050-10-25 2050-10-31 0 days
60 SWB1.3 Software Sprint 2 30 days 2050-11-01 2050-12-12 0 days
99 QASW1.2 Software Sprint 2 Test 5 days 2050-12-13 2050-12-19 0 days
61 SWB1.4 Software Sprint 3 30 days 2050-12-20 2051-01-30 0 days
100 QASW1.3 Software Sprint 3 Test 5 days 2051-01-31 2051-02-06 0 days
62 SWB1.5 Software Sprint 4 30 days 2051-02-07 2051-03-20 0 days
101 QASW1.4 Software Sprint 4 Test 5 days 2051-03-21 2051-03-27 0 days
63 SWB1.6 Software Sprint 5 30 days 2051-03-28 2051-05-08 0 days
102 QASW1.5 Software Sprint 5 Test 5 days 2051-05-09 2051-05-15 0 days
64 SWB1.7 Software Final 10 days 2051-05-16 2051-05-29 0 days
22 SYB1 .1 System Build 1 20 days 2051-05-30 2051-06-26 0 days
104 QASY1.1 System Build 1 Test 10 days 2051-06-27 2051-07-10 0 days
23 SYB1 .2 System Build 2 20 days 2051-07-11 2051-08-07 0 days
105 QASY1.2 System Build 2 Test 5 days 2051-08-08 2051-08-14 0 days
24 SYB1 .3 System Build Final 10 days 2051-08-15 2051-08-28 0 days
107 QASC1.1 Security Test 10 days 2051-08-29 2051-09-11 0 days
109 QASE1.1 Security Certification Final 10 days 2051-09-12 2051-09-25 0 days
111 QASEC1.2 System Certification Final 10 days 2051-09-26 2051-10-09 0 days
158 SUP A1 .4 Support Package Final 15 days 2051-10-10 2051-10-30 0 days
127 IMP P1.6 Implementation Readines s Review 5 days 2051-10-31 2051-11-06 0 days
168 PMRB1.1 Risk Buffer 51 days 2051-11-07 2052-01-16 0 days
147 TRPH1.1 Phase 1 Training 10 days 2052-01-17 2052-01-30 0 days
129 IMP H1.1 Phase 1 Pilot 20 days 2052-01-31 2052-02-27 0 days
132 IMP H2.1 Phase 2 Pilot 20 days 2052-02-28 2052-03-26 0 days
135 IMP H3.1 Phase 3 Pilot 20 days 2052-03-27 2052-04-23 0 days
136 IMP H3.2 Phase 3 Rollout 30 days 2052-04-24 2052-06-04 0 days
162 SUP S1. 3 Phase 3 Support Transition 20 days 2052-06-05 2052-07-02 0 days
170 PMC1.1 Project Clos ure Readiness Review 1 day 2052-07-03 2052-07-03 0 days
171 PMC1.2 Final P rocureme nts Closure 5 days 2052-07-04 2052-07-10 0 days
172 PMC1.3 Less ons Learned Meeting 1 day 2052-07-11 2052-07-11 0 days
173 PMC1.4 Less ons Learned Report 5 days 2052-07-12 2052-07-18 0 days
174 PMC1.5 Project Final Report 10 days 2052-07-19 2052-08-01 0 days

Figure 19 – Gantt Schedule (Critical Path)

Performance of this work on schedule is essential to avoid any delays to the overall project, and shall be a particular focus of the
Project Manager and Project leads. Resources shall be moved from non-critical path work to deliverables on the critical path
wherever practical if the critical path work requires additional resources to maintain the schedule performance.

The figure above can be zoomed in for greater visibility in this Project Management Plan document Microsoft Word soft-copy.
You can also view or print this graphic in PDF format on full size A0 size paper in the attached file “MDV3 Gantt Schedule (Critical
Path) - PDF”.

DeeplyPracticalPM.com Page 29/89


MDV3 Project Management Plan

A listing of the work on the critical path can also be found in the table below, sorted into calendar
order by start date, showing the work in the order it is planned to be completed.

WBS-ID Deliverable Duration Start Finish


PMA1.2 Kick-off Meeting 1 day 2050-01-03 2050-01-03
BPRT1.1 Business Processes To-Be Draft 20 days 2050-01-04 2050-01-31
BPRT1.2 Business Processes To-Be Final 10 days 2050-02-01 2050-02-14
GAN1.1 Gap Analysis Draft 20 days 2050-02-15 2050-03-14
GAN1.2 Gap Analysis Final 10 days 2050-03-15 2050-03-28
SYA1.1 System Architecture Draft 20 days 2050-03-29 2050-04-25
SYA1.2 System Architecture Final 10 days 2050-04-26 2050-05-09
SWP1.1 Software Detailed Requirements 20 days 2050-05-10 2050-06-06
SWP1.2 Software Development Plan 10 days 2050-06-07 2050-06-20
SWD1.1 Software Design Draft 1 20 days 2050-06-21 2050-07-18
SWD1.2 Software Design Draft 2 20 days 2050-07-19 2050-08-15
SWD1.3 Software Design Final 10 days 2050-08-16 2050-08-29
SWB1.1 Software Procurement 10 days 2050-08-30 2050-09-12
SWB1.2 Software Sprint 1 30 days 2050-09-13 2050-10-24
QASW1.1 Software Sprint 1 Test 5 days 2050-10-25 2050-10-31
SWB1.3 Software Sprint 2 30 days 2050-11-01 2050-12-12
QASW1.2 Software Sprint 2 Test 5 days 2050-12-13 2050-12-19
SWB1.4 Software Sprint 3 30 days 2050-12-20 2051-01-30
QASW1.3 Software Sprint 3 Test 5 days 2051-01-31 2051-02-06
SWB1.5 Software Sprint 4 30 days 2051-02-07 2051-03-20
QASW1.4 Software Sprint 4 Test 5 days 2051-03-21 2051-03-27
SWB1.6 Software Sprint 5 30 days 2051-03-28 2051-05-08
QASW1.5 Software Sprint 5 Test 5 days 2051-05-09 2051-05-15
SWB1.7 Software Final 10 days 2051-05-16 2051-05-29
SYB1.1 System Build 1 20 days 2051-05-30 2051-06-26
QASY1.1 System Build 1 Test 10 days 2051-06-27 2051-07-10
SYB1.2 System Build 2 20 days 2051-07-11 2051-08-07
QASY1.2 System Build 2 Test 5 days 2051-08-08 2051-08-14
SYB1.3 System Build Final 10 days 2051-08-15 2051-08-28
QASC1.1 Security Test 10 days 2051-08-29 2051-09-11
QASE1.1 Security Certification Final 10 days 2051-09-12 2051-09-25
QASEC1.2 System Certification Final 10 days 2051-09-26 2051-10-09
SUPA1.4 Support Package Final 15 days 2051-10-10 2051-10-30
IMPP1.6 Implementation Readiness Review 5 days 2051-10-31 2051-11-06
PMRB1.1 Risk Buffer 51 days 2051-11-07 2052-01-16
TRPH1.1 Phase 1 Training 10 days 2052-01-17 2052-01-30
IMPH1.1 Phase 1 Pilot 20 days 2052-01-31 2052-02-27
IMPH2.1 Phase 2 Pilot 20 days 2052-02-28 2052-03-26
IMPH3.1 Phase 3 Pilot 20 days 2052-03-27 2052-04-23
IMPH3.2 Phase 3 Rollout 30 days 2052-04-24 2052-06-04
SUPS1.3 Phase 3 Support Transition 20 days 2052-06-05 2052-07-02
PMC1.1 Project Closure Readiness Review 1 day 2052-07-03 2052-07-03
PMC1.2 Final Procurements Closure 5 days 2052-07-04 2052-07-10
PMC1.3 Lessons Learned Meeting 1 day 2052-07-11 2052-07-11
PMC1.4 Lessons Learned Report 5 days 2052-07-12 2052-07-18
PMC1.5 Project Final Report 10 days 2052-07-19 2052-08-01
Table 4 - Critical Path Deliverables

DeeplyPracticalPM.com Page 30/89


MDV3 Project Management Plan

3.4 Milestones

See the DPPM section “Planning: The Schedule Milestones”.

The MDV3 project milestones mark events where important elements of work are completed that significantly move the project
forward. The status of progress towards the milestones will be presented at each Project Monthly Review, and will be a
particular focus of management attention.

Two milestones were defined by the Sponsor in the Initiation Project Charter:

 Total schedule of less than 36 months. The schedule achieves this, totalling less than 32 months in duration.

 Start of first pilot by end of month 25. The schedule achieves this, starting the first pilot by the end of month 25, marked
in the Gantt chart by the start of milestone “Implementation Phase 1”.

The rest of the project milestones were selected by the planning team to indicate the most significant points of achievement as
the project progresses.

A Gantt schedule showing the project milestones as they fall across the calendar is shown in the following figure. This graphic
can be zoomed in for greater visibility in this Project Management Plan document Microsoft Word soft-copy. You can also view or
print this graphic in PDF format on full size A0 size paper in the attached file “MDV3 Gantt Schedule (Milestones) - PDF”.
ID WBS-ID Deliverable Duration Start Finish Float ' 50 Jan '50 Feb '50 Mar '50 Apr ' 50 May '50 Jun ' 50 Jul ' 50 Aug '50 Sep ' 50 Oct ' 50 Nov '5 0 D ec ' 51 J an ' 51 Feb ' 51 Mar '51 Apr ' 51 May ' 51 Jun ' 51 J ul ' 51 Au g ' 51 Sep '5 1 Oct ' 51 Nov '5 1 De c ' 52 J an ' 52 Fe b '52 Mar '52 Apr ' 52 May '52 Jun ' 52 Jul '52 Aug '52 Sep
27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
1 MDV3 Magical Devices V3 Project 674 days
Mon 50-01-03Thu 52-08-01 0 days
2 BPR1 Business Process 60 daysTue 50-01-0Mon
4 50-03-28 0 days
12 SYS1 System 370 daysTue 50-03-2Mon
9 51-08-28 0 days
13 SYA1 System Architecture 30 daysTue 50-03-2Mon
9 50-05-09 0 days
21 SYB1 System Build 65 daysTue 51-05-3Mon
0 51-08-28 0 days
25 HW1 Hardware 220 daysTue 50-05-1Mon
0 51-03-13 55 days
38 HWB1 Hardware Build 135 daysTue 50-09-0Mon
6 51-03-13 55 days
44 SW1 Software 275 daysTue 50-05-1Mon
0 51-05-29 0 days
48 SWD1 Software Design 50 daysTue 50-06-2Mon
1 50-08-29 0 days
57 SWB1 Software Build 195 daysTue 50-08-3Mon
0 51-05-29 0 days
65 SEC1 Security 125 daysTue 50-05-1Mon
0 50-10-31 5 days
66 SECD1 Security Design 25 daysTue 50-05-1Mon
0 50-06-13 5 days
69 SECTP1 Security Test Planning 100 daysTue 50-06-1Mon
4 50-10-31 215 days
73 FAC1 Facility 380 daysTue 50-05-1Mon
0 51-10-23 5 days
77 FACD1 Facilities Design 70 daysTue 50-07-0Mon
5 50-10-10 110 days
82 FACB1 Facilities Build 270 daysTue 50-10-1Mon
1 51-10-23 5 days
92 QA1 Quality Assurance 250 daysTue 50-10-2Mon
5 51-10-09 0 days
93 QAHW1 Hardware Test 75 daysTue 50-11-1Mon
5 51-02-27 55 days
97 QASW1 Software Test 145 daysTue 50-10-2Mon
5 51-05-15 0 days
103 QASY1 System Test 35 daysTue 51-06-2Mon
7 51-08-14 0 days
108 QASE1 Security Certification 10 daysTue 51-09-1Mon
2 51-09-25 0 days
110 QASEC1 System Certification 10 daysTue 51-09-2Mon
6 51-10-09 0 days
112 FACI1 Facilities Inspection 200 daysTue 50-12-1Mon
3 51-09-18 20 days
120 IMP1 Imple mentation 541 daysTue 50-05-1 0Tue 52-06-04 0 days
128 IMPH1 Implementation Phase 1 50 days
Wed 52-01-31Tue 52-04-09 0 days
131 IMPH2 Implementation Phase 2 50 days
Wed 52-02-28Tue 52-05-07 0 days
134 IMPH3 Implementation Phase 3 50 days
Wed 52-03-27Tue 52-06-04 0 days
150 SU1 Support 561 daysTue 50-05-1 0Tue 52-07-02 0 days
154 SUPA1 Support Package 300 daysTue 50-09-0Mon
6 51-10-30 0 days
159 SUPS1 Phase Support 60 days
Wed 52-04-10Tue 52-07-02 0 days
163 PM1 Project Management 674 days
Mon 50-01-03Thu 52-08-01 0 days
169 PMC1 Project Closure 22 days
Wed 52-07-03Thu 52-08-01 0 days

Figure 20 - Gantt Schedule (Milestones)

DeeplyPracticalPM.com Page 31/89


MDV3 Project Management Plan

A listing of the major project milestones and their end dates can also be found in the table below.

WBS-ID Deliverable Finish


SYA1 System Architecture Mon 50-05-09
SECD1 Security Design Mon 50-06-13
SWD1 Software Design Mon 50-08-29
FACD1 Facilities Design Mon 50-10-10
SECTP1 Security Test Planning Mon 50-10-31
QAHW1 Hardware Test Mon 51-02-27
HWB1 Hardware Build Mon 51-03-13
QASW1 Software Test Mon 51-05-15
SWB1 Software Build Mon 51-05-29
QASY1 System Test Mon 51-08-14
SYB1 System Build Mon 51-08-28
FACI1 Facilities Inspection Mon 51-09-18
QASE1 Security Certification Mon 51-09-25
QASEC1 System Certification Mon 51-10-09
FACB1 Facilities Build Mon 51-10-23
SUPA1 Support Package Mon 51-10-30
IMPH1 Implementation Phase 1 Tue 52-04-09
IMPH2 Implementation Phase 2 Tue 52-05-07
IMPH3 Implementation Phase 3 Tue 52-06-04
SUPS1 Phase Support Tue 52-07-02
PMC1 Project Closure Thu 52-08-01

Table 5 - Project Milestones

DeeplyPracticalPM.com Page 32/89


MDV3 Project Management Plan

4. Budget

See the DPPM sections “Planning: Estimating” and “Planning: Cost”.

This section documents the baseline MDV3 budget, describing all the costs planned to be
expended over the course of the project.

The total planned cost of the project is $44,467,360. Additional information is provided in the
following sections, including a breakdown of the cost per major deliverable, a summary of the
resource costs by type, and a cost curve graphing the planned spending across time.

The baseline budget meets the financial constraint specified in the initiation project charter:

Charter Constraint Planning Baseline


The budget for this project must not The planned budget of $44,467,360 is
exceed the business case estimate of approximately 6% less than the charter
$47,464,650. constraint.

The current status of the budget progress shall be reported each month to the Sponsor,
Customer, and other relevant Stakeholders at the Monthly Project Review described in Section 9.2
– Monthly Project Review Meetings. The cost performance shall be reported using Earned Value
Management metrics.

See the DPPM section “Monitoring & Control: Earned Value Management”.

Any changes to the project budget once this plan is approved and baselined must go through the
formal change control process described in Section 12 – Change Control Process.

4.1 Deliverable Costs

The Project Leads prepared a detailed activity breakdown for each of their deliverables including
all resources, material, and services required to produce the deliverables in order to obtain
complete cost estimates for all the elements of work.

A breakdown of the project cost at the deliverable summary level is provided in the table below.
Additional information on the costs of the lowest level deliverables can be found in the cost
column of the Microsoft Project file “MDV3 Gantt Schedule” and “MDV3 Gantt Schedule (Full) -
PDF”. Cost accounts to be used for tracking all cost expenditure for each deliverable were
assigned by the finance department, and can be found in the cost account column of the WBS
Dictionary in Appendix B.

WBS-ID Deliverable Cost


MDV3 Magical Devices V3 Project $44,467,360
BPR1 Business Process $324,000
BPRA1 Business Process As-IS $26,400
BPRT1 Business Process To-Be $105,600
GAN1 Gap Analysis $132,000
SYS1 System $978,000
SYA1 System Architecture $105,600
SYTP1 System Test Planning $140,800
SYB1 System Build $361,600
HW1 Hardware $11,143,100

DeeplyPracticalPM.com Page 33/89


MDV3 Project Management Plan

WBS-ID Deliverable Cost


HWP1 Hardware Planning $105,600
HWD1 Hardware Design $154,000
HWTP1 Hardware Test Planning $96,800
HWB1 Hardware Build $10,566,700
SW1 Software $7,103,800
SWP1 Software Planning $105,600
SWD1 Software Design $352,000
SWTP1 Software Test Planning $272,800
SWB1 Software Build $6,098,400
SEC1 Security $360,200
SECD1 Security Design $103,200
SECTP1 Security Test Planning $132,000
FAC1 Facility $11,444,600
FACP1 Facilities Planning $123,200
FACD1 Facilities Design $316,800
FACB1 Facilities Build $10,624,600
QA1 Quality Assurance $758,000
QAHW1 Hardware Test $105,600
QASW1 Software Test $132,000
QASY1 System Test $52,800
QASC1 Security Test $51,200
QASE1 Security Certification $25,600
QASEC1 System Certification $17,600
FACI1 Facilities Inspection $123,200
IMP1 Implementation $2,591,400
IMPP1 Implementation Planning $334,400
IMPH1 Implementation Phase 1 $572,000
IMPH2 Implementation Phase 2 $572,000
IMPH3 Implementation Phase 3 $572,000
TR1 Training $845,000
TRP1 Training Planning $30,800
TRM1 Training Material $264,000
TRPH1 Training Phases $79,200
SU1 Support $1,599,400
SUP1 Support Planning $52,800
SUPA1 Support Package $352,000
SUPS1 Phase Support $633,600
PM1 Project Management $7,319,860
PMA1 Project Management Activities $2,249,860
PMRB1 Risk Budget $5,050,000
PMC1 Project Closure $20,000

Table 6 – Major Deliverable Costs

DeeplyPracticalPM.com Page 34/89


MDV3 Project Management Plan

4.2 Resource Costs

A listing of the costs of the resources used by the MDV3 project is provided in the table below,
including summaries of the cost by major resource type. The rate for personnel resources is the
full loaded mid-point for each labour classification, including all indirect and overhead costs.

Name Work Standard Cost


Rate
Group: 1.1-Material-Facility $9,250,000
Facility Build Contract 1 Contract $9,250,000 $9,250,000
Group: 1.2-Material-Building $565,000
Building Material Other 1 Various $100,000 $100,000
Building Material Production 3 Line $100,000 $300,000
Building Material Shipping 1 Each $40,000 $40,000
Building Material Staging 1 Each $50,000 $50,000
Building Material Stations 1 Each $75,000 $75,000
Group: 1.3-Material-Hardware $9,700,000
Control Station HW 3 Each $200,000 $600,000
Equipment-Assembly 3 Each $600,000 $1,800,000
Equipment-Finishing 3 Each $600,000 $1,800,000
Equipment-Piece Build 3 Each $600,000 $1,800,000
Equipment-QA 3 Each $600,000 $1,800,000
Equipment-Staging 3 Each $600,000 $1,800,000
Management Station HW 1 Each $100,000 $100,000
Group: 1.4-Material-Software $4,400,000
Control Station SW 3 Each $300,000 $900,000
Management Station SW 1 Each $200,000 $200,000
Production Software 3 Line $1,100,000 $3,300,000
Group: 1.5-Material-Magic Dust $777,000
Magic Dust 1,000 gram $777 $777,000
Group: 2.1-Project Leads 26,264 hrs $3,283,000
Andre Young 1,784 hrs $125/hr $223,000
Byomkesh Bakshi 2,224 hrs $125/hr $278,000
Cathy Kerr 1,024 hrs $125/hr $128,000
Heidi Geis 4,352 hrs $125/hr $544,000
Henry Kiku 4,512 hrs $125/hr $564,000
Irwin Fletcher 3,064 hrs $125/hr $383,000
Jean Cunliffe 3,792 hrs $125/hr $474,000
Kong Qiu 504 hrs $125/hr $63,000
Mary Sperling 2,984 hrs $125/hr $373,000
Son Goku 2,024 hrs $125/hr $253,000
Group: 2.2-Project Team 88,000 hrs $9,680,000
Business-Process-Team 2,400 hrs $110/hr $264,000
Facilities-Team 11,360 hrs $110/hr $1,249,600
Hardware-Team 9,000 hrs $110/hr $990,000
Implementation-Team 18,640 hrs $110/hr $2,050,400
QA-Team 4,400 hrs $110/hr $484,000
Security-Team 1,840 hrs $110/hr $202,400
Software-Team 22,080 hrs $110/hr $2,428,800
Support-Team 9,440 hrs $110/hr $1,038,400

DeeplyPracticalPM.com Page 35/89


MDV3 Project Management Plan

Name Work Standard Cost


Rate
System-Team 5,440 hrs $110/hr $598,400
Training-Team 3,400 hrs $110/hr $374,000
Group: 2.3-Consultant 332 hrs $66,400
Security Certification Consultant 332 hrs $200/hr $66,400
Group: 3.1-Project Management 13,460 hrs $1,695,960
Ellie Arroway 5,384 hrs $110/hr $592,240
Charles Wallace 5,384 hrs $150/hr $807,600
Jonathan Livingston 2,692 hrs $110/hr $296,120
Group: 3.2-Risk Budget $5,050,000
Risk Budget $5,050,000

Table 7 – Resource Costs By Type

4.3 Cost Curve

See the DPPM section “Planning: The Project Cost Baseline”.

A time-phased summary of the planned project budget expenditure across the calendar is
provided below.

Cumulative Cost
$50,000,000

$45,000,000

$40,000,000

$35,000,000

$30,000,000

$25,000,000

$20,000,000

$15,000,000

$10,000,000

$5,000,000

$0
'50 Jul

'51 Jul

'52 Jul
'50 Feb

'51 Feb

'52 Feb
'50 Jun

'51 Jun

'52 Jun
'50 May

'50 Nov

'51 May

'51 Nov

'52 May
'50 Sep

'51 Sep
'50 Mar

'51 Mar

'52 Mar
'50 Dec

'51 Dec
'50 Jan

'51 Jan

'52 Jan
'50 Aug

'51 Aug

'52 Aug
'50 Apr

'50 Oct

'51 Apr

'51 Oct

'52 Apr

Cumulative Cost

Figure 21 - Cumulative Cost Curve

The large jumps starting in 2050 September are caused by the initiation of procurement of the
hardware, software, and facility build. When these contracts are finalized during project
execution, it is expected that the hardware and facility procurements will be negotiated with the
suppliers to include time phased milestone payment plans based on progress of delivery, and so
will end up spreading these expenditures more evenly across time.

DeeplyPracticalPM.com Page 36/89


MDV3 Project Management Plan

5. Risks

See the DPPM section “Planning: Risk”.

Also see the associated document “MDV3 Risk Register”.

This section describes the MDV3 risk management process, and provides a copy of the baseline
risk register. The total planned risk budget is 50.5 days and $5,050,000, and has been included
in the baseline project budget and schedule.

5.1 Risk Management Process

The risk register and associated risk budget was prepared by the Project Manager and Project
leads and refined in an iterative process through project planning. Risks were identified by
consideration of all the risks on our standard Risk Checklist, reference to the risk planning and
lessons learned of the build of the Magical Devices Version 2 facility, and consultation with the
project team. Risks were quantified, response plans prepared to avoid or mitigate the risks to the
greatest extent possible, backup plans prepared to deal with the event the risk occurred anyway,
and a final quantified risk budget baselined.

The probability and time estimates for the risks were developed by the project team considering
previous experience and using Delphi estimation. The dollar estimates were developed with a
cost impact analysis as a function of the estimated delay time and considering any other relevant
costs, with delays calculated at $100K a day to including consideration of profit loss if the start of
production is delayed.

The MDV3 Project Manager has accountability for management of the risk budget and successful
performance of the project. Ownership of individual risks has been allocated to the level closest
and best able to manage the risk. The risk register shall be reviewed at the end of each weekly
status meeting. The risk triggers shall be monitored by the risk owners, and action taken
proactively to avoid or mitigate the risks everywhere possible. Risk response plans shall be
refined and improved throughout the project as required. Funds shall be withdrawn from the risk
budget to fund proactive measures to provide the greatest possible risk avoidance or mitigation at
the earliest possible point possible. If it becomes apparent a risk cannot be avoided, the backup
plans shall be activated.

The Project Manager is the authorized signing authority for drawdown on the risk dollar budget.
To obtain funds from the budget the Project Manager shall submit a completed Risk Budget
Drawdown Justification form (RBDJ-14e) to the MDV3 financial controller, fully documenting the
status of the planned risk for which the funds are being accessed, or the reason they are needed
for an unforeseen risk, the alternatives to drawdown of the risk budget that were considered and
deemed unsuitable, and the justification for the amount being withdrawn. Amounts requested in
excess of 10% of the original risk budget baseline shall also require authorization by the Magical
Devices VP Finance.

The risk time buffer has been scheduled according to the principles of critical chain management,
in a single consolidated buffer before the critical customer event whose planned date should be
most protected, which was determined to be directly before the start of the pilot rollout of the
first production line.

The current status of the risk budget shall be reported each month to the Sponsor, Customer, and
other relevant Stakeholders at the Monthly Project Review described in Section 9.2 – Monthly

DeeplyPracticalPM.com Page 37/89


MDV3 Project Management Plan

Project Review Meetings.

Any increases to the risk budget once this plan is approved and baselined must go through the
formal change control process described in Section 12 – Change Control Process.

5.2 Risk Register

The MDV3 project risk register showing the known project risks, estimated schedule and cost
impacts, owner, trigger, response plans, and backup plan can be found in the following pages.
The total planned risk budget of 50.5 days and $5,050,000 is provided in the last row of the risk
register, summing up the amounts estimated to be required for all of the individual risks.

The full risk register can also be found in the attached document “MDV3 Risk Register”. The full
risk register also provides additional information on the quantification assessment before the risk
response planning was applied.

DeeplyPracticalPM.com Page 38/89


MDV3 Project Management Plan

Risk T Px
Risk Statement P% (d) $K T P x $K Owner Trigger Response Plan Backup Plan
Software If the 30% 30 $3,000 9 $900 Byomkesh Status • The software • Increase the
Development software Bakshi, burndown development team software
Issues development Software charts of early incorporated all development
effort is not Lead sprints the lessons of the team by
accurately indicate the Magical Devices dedicating the
planned, planned Version 2 project research and
estimated, schedule is to prepare development
and not realistic estimates personnel to
sufficiently achievable. and plans for the project
staffed, the Version 3. until
software • The version 3 complete.
development software is • Review the
schedule will building on the software
extend, near feature scope to see if
increasing the complete there is any
project prototypes non-essential
schedule and developed by the second
budget. R&D projects over priority scope
the couple years. that can be
• Detailed removed from
software the project or
requirements are implemented
documented and in a later
development follow-on
planning is project.
conducted before
design begins.
• Several
iterations of
design are
conducted before
build commences.
• Five sprints are
planned, each
incorporating
testing and
documentation, in
addition to
separate QA test
cycles.

DeeplyPracticalPM.com Page 39/89


MDV3 Project Management Plan
Magic Dust If there is not 20% 40 $4,000 8 $800 Andre Suppliers • An advance Three backup
Availability sufficient Young, cannot order for 70% of suppliers have
magic dust Hardware commit to the amount of been
available to Lead delivery dates magic dust identified, and
complete when anticipated to be sufficient
integration of ordering. required shall be research done
the made with our to
equipment, standard suppliers preliminarily
the hardware on the first day of qualify them
builds will not execution of the as potential
be able to project. candidates
proceed, • The remainder should our
increasing the shall be ordered regular
project as the first step in suppliers be
schedule and hardware unable to
budget. procurement. fulfill our
• An additional orders for any
15% was added to reason.
the planned costs
to enable payment
to suppliers for
expedited delivery
should it be
needed.
Manufacturing If the 30% 25 $2,500 7.5 $750 Mary The first build • Use only • Add a
Integration interfaces Sperling, focusing on industry standard dedicated
Incompatibilities between the System integration and proven interface
new set of Lead testing interfaces. resolution
complex and surfaces • The first team to work
innovative issues. hardware build in parallel to
equipment will test interfaces mainline
are not for early project work
completely validation. to resolve
compatible, issues as fast
there will be as possible.
additional
integration
work
required,
increasing the
project
schedule and
budget.

DeeplyPracticalPM.com Page 40/89


MDV3 Project Management Plan
Team Turnover If team 20% 30 $3,000 6 $600 Charles Dissatisfaction • Empower the • Human
members do Wallace, is expressed team and reward resources
not find the Project to team leads initiative. department to
project and Manager or HR. • Provide pro-actively
organization competitive salary establish
sufficiently and benefits. channels to
rewarding and • Provide sincere sources of
enjoyable, recognition and qualified
they might appreciation of personnel,
leave for effort. prepared to
other • Continue regular recruit new
opportunities, team-building staff on very
increasing the including monthly short notice
project lunches and with very
schedule and quarterly off-site attractive
budget. events. hiring
packages.

DeeplyPracticalPM.com Page 41/89


MDV3 Project Management Plan
Scope Changes If the cost 20% 25 $2,500 5 $500 Kong Qui, Design • Professional • Perform a
and schedule Business reviews of business analysts scope analysis
driving scope Process prototypes, were used to to see if there
is not Lead mockups, and identify all cost is any non-
completely walkthroughs and schedule essential
identified identify driving project second
before project missing or requirements priority scope
execution incorrect during planning. that can be
begins, it will scope. • Business process removed from
be discovered gap analysis is the project, or
once design one of the early implemented
and build are activities in the in a later
underway schedule. follow-on
requiring • Detailed project, to
significant requirements avoid
replanning, documents will be increasing this
increasing the prepared and project's
project reviewed before schedule and
schedule and each phase of budget and
budget. design delaying
commences. facility
• All design and opening.
build proceeds in
several agile
iterations to
identify any
problems and
enable response
at the earliest
possible point.

DeeplyPracticalPM.com Page 42/89


MDV3 Project Management Plan
Security If the 20% 20 $2,000 4 $400 Cathy Dry-run • Dry-run testing • Identify
Certification manufacturing Kerr, security of the security former
Issues system does Security testing during test procedures is directors,
not meet all Lead the system incorporated as board
requirements build testing part of the system members, and
of the Magical surfaces build testing to senior
Management issues. obtain early consultants
Institute warning and from the
standard resolution. Magical
Secure Device • The leading Management
Manufacturing consulting Institute and
& Operations company Magical retain them
(MMI-321123- Security analyze any
G), the Certification issues and
security Assurance Inc. will oversee the
certification be retained to resolutions.
will be analyze the design
delayed, and review the
preventing early builds to
opening of the identify any issues
facility, and ensure
startup of proactive
production, resolution.
and delaying • Pilot production
availability of periods are built
the devices on into all phase
the market. rollouts to enable
any unexpected
issues to be
addressed before
full production.

DeeplyPracticalPM.com Page 43/89


MDV3 Project Management Plan
Procurement If the 20% 20 $2,000 4 $400 Andre Shipment and • Early notification • Turn to
Delays hardware Young, delivery of all hardware secondary
equipment Hardware tracking procurement suppliers and
does not Lead indicate requirements will order required
arrive on the delays. be provided as the items with
expected design phases payments for
schedule, the progress, so the expedited
builds will not procurement delivery.
be able to department can
proceed, proactively
increasing the identify suppliers
project that can provide
schedule and the items quickly
budget. once procurement
commences.
Operational If unexpected 20% 20 $2,000 4 $400 Son Inspection of • As per the Scope • Establish a
Surprises issues are Goku, QA devices from Change risk, a fully staffed
revealed once Lead initial great emphasis and dedicated
the system is production has been placed design, build,
in actual runs identify on early scope and
operation, issues. identification and operations
potentially agile iterative team to
difficult fixes design and builds provide rapid
and retrofits to minimize reaction
might be surprises. remediation
required • Each of the solutions.
delaying full three production
production, phases will first go
increasing the through a low
project production run
schedule and pilot.
budget.

DeeplyPracticalPM.com Page 44/89


MDV3 Project Management Plan
Resource If personnel 10% 30 $3,000 3 $300 Lucy Personnel • The President • Have
Unavailability are not Pevensie, indicate their has indicated to President re-
dedicated full- President work start all department emphasize to
time to this time will be heads that this the
project, they delayed due project is the first organization
might be to other priority for the that this
unavailable priorities. organization, and project is the
when required personnel must be first priority.
due to work allocated full-time
on other when required.
projects,
increasing the
project
schedule and
budget.

Total Risk
Budget: 50.5 $5,050

Table 8 - Risk Register

DeeplyPracticalPM.com Page 45/89


MDV3 Project Management Plan

6. Issues

See the DPPM section “Monitoring & Control: The Weekly Status Meeting”.

Also see the DPPM template “Project Issues List - Template”.

The required resources, schedule, and budget to address all of the anticipated MDV3 project
issues have been built into the baseline plan, with one issue outstanding.

The following issue lies outside the scope of this project to build the MDV3 facility, and is being
managed by the Magical Devices executive team:

 The site adjacent to our current facility that was acquired for the new manufacturing
facility was originally assumed to have sufficient electrical capacity to support full
production. The site capacity evaluation report (SCER) prepared during planning revealed
a shortfall in electrical capacity of 25% from the anticipated need. Therefore, as a
separate project, Magical Devices VP Manufacturing Ezekiel Rawlins is working with the
city of Oakville to ensure the power utility completes an upgrade to provide the expected
requirement. This work is planned for completion by the end of the third quarter following
project start, and so should be ready more than a year in advance of being needed. The
MDV3 project shall track this issue, and raise it for Executive team action if delays
threaten to impact the project’s projected production start date. It is anticipated that the
Magical Devices President may be able to leverage their existing relationship with the
Mayor of Oakville to help manage this issue if required.

DeeplyPracticalPM.com Page 46/89


MDV3 Project Management Plan

7. Stakeholders

See the DPPM section “Initiation: Stakeholders”.

Also see the associated document “MDV3 Stakeholder Register”.

This section describes the MDV3 key stakeholders. The project stakeholders are affected and can
affect the project, and therefore have been included in definition of the project scope and
development of the project plan, and will be included in regular communications as the project
progresses. The key project stakeholders, along with their role, key need, priorities, and planned
communications are described in the Stakeholder Register provided below. This register can also
be found in the attached document “MDV3 Stakeholder Register”.

Name Role Key Need Priorities Communications


Lucy Magical Additional Schedule, • Monthly project review
Pevensie Devices revenue Cost, Scope update.
President generation.
Ava Lee Magical Enhanced version Scope, • Monthly project review
Devices VP 3 magical devices Schedule, update.
Customer with at least 80 Cost • Involvement with project
Satisfaction greater team for device design and
effectiveness. development, coordination
of device user reviews.
Solomon Magical Cost control. Cost, • Monthly project review
Gursky Devices VP Schedule, update.
Finance Scope • Immediate notification of
any unexpected cost
changes.
Ezekiel Magical The latest Scope, • Monthly project review
Rawlins Devices VP manufacturing Schedule, update.
Manufacturing processes and Cost • Involvement with project
equipment. team for production line
build and test, inspections,
and user reviews.
Stephanie Magical Timely notification Schedule, • Monthly project review
Plum Devices VP of any changes in Scope, Cost update.
Human plans for staffing • Immediate notification of
Resources growth. any changes in schedule.
Jack Magical Knowledge of new Schedule, • Monthly project review
Reacher Devices VP device features Scope, Cost update.
Marketing & and schedule • Immediate notification of
Sales availability. any changes to scope.
Dave Magical Standards Scope, • Monthly project review
Robicheaux Devices compliant and Schedule, update.
Director of supportable Cost • Involvement with project
Facilities & facility. team for facility build and
Operations test, inspections, and user
reviews.

DeeplyPracticalPM.com Page 47/89


MDV3 Project Management Plan

Name Role Key Need Priorities Communications


Travis Mayor Advance notice of Schedule • Monthly updates by phone
McGee Oakville hiring plans and or meeting from the
schedule. President.
• Immediate notification of
any changes in hiring plans.
• Invitation to facility
opening.
Meg Executive Assurance of Scope • Quarterly updates on
Murray Director compliance with project progress and
Magical Magical regulatory compliance.
Management Management • Invitation to facility
Institute Institute opening.
(MMI) Regulations.

Table 9 - Stakeholder Register

DeeplyPracticalPM.com Page 48/89


MDV3 Project Management Plan

8. Resources

See the DPPM section “Planning: Resources”.

This section describes the project team, provides a resource loading across time, and describes the plans for management of
critical resources required to carry out the MDV3 project.

8.1 Project Team

See the DPPM sections “Planning: The Core Project Team”.

The Project Team that will carry out the MDV3 project is shown in the following organization chart.

Sponsor
Lucy Pevensie

Project Manager
Charles Wallace

Project Project Scheduler


Coordinator Jonathan
Ellie Arroway Livingston

Business System Lead Softw are Lead Hardw are Lead Security Lead Facilities Lead Quality Implementation Training Lead Support Lead
Process Lead Byomkesh Assurance Lead Lead
Kong Qiu M ary Sperling Bakshi Andre Young Cathy Kerr Irw in Fletcher Son Goku Heidi Geis Jean Cunliffe Henry Kiku

Business Quality Implementation


Process Team System Team Softw are Team Hardw are Team Security Team Facilities Team Assurance Team Training Team Support Team
Team

Figure 22 - Project Organization

Due to the critical importance of the MDV3 project to the company, the assigned Project Leads are the most senior and
experienced members from each department. The Project Leads report directly to the Project Manager for the purposes of
carrying out the MDV3 project, and are responsible for management of all work and the team members in their functional area.
The deliverables that each Project Lead is accountable for are listed in the owner column of the WBS Dictionary in Appendix B.

The various working level teams are drawn from the matrix, from the company functional departments. To ensure there are no
schedule delays, all team members shall be allocated full-time to this project during the periods they are required.

DeeplyPracticalPM.com Page 49/89


MDV3 Project Management Plan

See the DPPM sections “Overview: The Role Of The Project Manager”,
“Initiation: The Sponsor & Customer”, and “Planning: The Core Project Team”.

The roles and responsibilities of the MDV3 Project Sponsor, Project Manager, and Project Leads
are described in the table below.

Name Role Responsibilities


Lucy Pevensie Project Sponsor • Approval of the project plan, scope, schedule, budget,
and risk budget.
• Approval to any changes to the plan baseline once the
project is underway.
• Chair of the monthly project reviews.
• Maintenance of company support.
• Resolution of any issues the Project Manager is unable to
resolve.
Charles Project Manager • Preparation of a complete, accurate, and realistic project
Wallace plan.
• Management of the project to obtain the best scope,
schedule, budget, and risk performance possible.
• Management of the Project Leads.
• Ensure the project result is fit for purpose and fully
meets the stakeholder expectations.
• Formal statusing of the project progress once a month.
• Conduct of the monthly project reviews and presentation
of the project status to the Sponsor and key stakeholders.
• Chair of the weekly issues status meeting.
Ellie Arroway Project • Provide administrative and other support to the Project
Coordinator Manager as needed.
• Coordinate project meetings including the Monthly
Review and Weekly Status meetings.
• Maintain the project documentation including the Project
Issues List and Risk Register, meeting minutes, and other
documentation as required.
Jonathan Project Scheduler • Maintain the project Gantt schedule.
Livingston • Obtain current progress status from the Project Leads
and prepare the schedule status for the Monthly Project
Reviews.
• Prepare the Earned Value Reports for monthly reporting.
Kong Qiu Business Process • Develop the as-is and to-be business process baselines,
Lead and perform a gap analysis to determine what work is
needed to implement the to-be processes.
• Manage the business process team and all associated
work.
Mary Sperling System Lead • Develop the top-level system architecture, the system
test plan and system test procedures, and build the
integrated hardware and software system.
• Manage the system team and all associated work.
Byomkesh Software Lead • Refine the software detailed requirements, document a
Bakshi software development plan, prepare the software design,
develop the software test plan and test procedures to be
used for validation, and build the software to produce the
Magical Devices Version 3.

DeeplyPracticalPM.com Page 50/89


MDV3 Project Management Plan

Name Role Responsibilities


• Manage the software team and all associated work.
Andre Young Hardware Lead • Refine the hardware detailed requirements, document a
hardware development plan, prepare the hardware design,
develop the hardware test plan and test procedures to be
used for validation, and build the hardware to produce the
Magical Devices Version 3.
• Manage the hardware team and all associated work.
Cathy Kerr Security Lead • Refine the security detailed requirements, develop the
security architecture, and develop the security test plan
and test procedures to be used for validation and
certification of the secure system.
• Manage the security team and all associated work.
Irwin Fletcher Facilities Lead • Refine the facility detailed requirements, document a
facility build plan, prepare the facility design, put in place
the procurement with the contractor building the external
elements of the facility, and build the internal elements of
the facility to produce the Magical Devices Version 3.
• Manage the facilities team and all associated work.
Son Goku Quality Assurance • Ensure the hardware, software, system, security, and
Lead facility are fully tested and inspected to meet all the
requirements, are correctly configured, and will be fit for
purpose to produce the Magical Devices Version 3.
• Manage the quality assurance team and all associated
work.
Heidi Geis Implementation • Prepare and manage a comprehensive implementation
Lead plan to ensure the success of a multi-phase pilot and
rollout of the production system to produce the Magical
Devices Version 3.
• Manage the implementation team and all associated
work.
Jean Cunliffe Training Lead • Refine the training detailed requirements, document a
training plan, prepare the material to train the users of the
production system, and train the teams.
• Manage the training team and all associated work.
Henry Kiku Support Lead • Refine the support detailed requirements, document a
support plan, prepare the package of documentation and
processes to support the system and facilities, and
transition support to the operations teams.
• Manage the support team and all associated work.

Table 10 - Project Roles & Responsibilities

DeeplyPracticalPM.com Page 51/89


MDV3 Project Management Plan

8.2 Resource Loading

The following graph shows the resource loading by number of hours for the labour category
consisting of the Project Management Office, Project Leads, Project Teams, and Security
Consultant, by quarter across the course of the project.

Figure 23 - Resource Loading

Individual resource loading graphs for individuals and specific functional teams may be obtained
from the Resource Graphs in the attached Microsoft Project file “MDV3 Gantt Schedule”.

8.3 Critical Resources

See the DPPM section “Planning: Resource Planning”.

Two resources have been deemed critical to the success of the MDV3 project: software engineers
with expertise developing magical functionality, and magic dust. The following sections describe
the approach to management of these critical resources.

8.3.1 Software Engineers

The software engineering skill-set required to develop magical functionality is currently in high
demand and difficult to acquire. The project is taking the following approach to ensure these
critical resources are available as needed to complete the project on schedule.

The Magical Devices Human Resources department performed a qualifications and availability
assessment over the past year. Working with national HR consulting companies, they have
benchmarked the company salary structure with the rest of the market, and made adjustments
where needed to ensure salaries meet or exceed those available elsewhere in the industry.

The HR department has also identified sources for recruitment of qualified magical functionality
software developers. They are participating in job fairs at universities and magical institutes to
ensure wide awareness of the job opportunities with our company, and to recruit a steady

DeeplyPracticalPM.com Page 52/89


MDV3 Project Management Plan

pipeline of qualified candidates year over year. The recruitment advertising budget was also
increased by 25%, and has refocused its mix to allocate more of the spending on the online
marketplaces where magical software developers are most likely to be engaged.

As a result, the project currently has sufficient software development resources qualified in
magical development to carry out the project. An emphasis has been placed on realistic planning
to ensure the project execution goes as smoothly as possible. There will be a continued focus on
staff retention programs at the company level, including development, training, and feedback
mechanisms, to ensure all staff work in an enjoyable and fulfilling environment and continue to
see Magical Devices as an employer of first choice.

8.3.2 Magic Dust

A sufficient supply of gold, platinum, and titanium magic dust is essential for completion of the
equipment integration during the build of the production lines. Increasing demand for magic dust
over the past several years has tightened the available supply, increased the time from order to
delivery, and significantly increased prices. The project is taking the following approach to ensure
this critical resource will be available in sufficient supply to carry out this project.

An advance order for 70% of the amount of magic dust that is anticipated to be required for the
entire project shall be made with our standard suppliers on the first day of execution of the
project, to ensure a sufficient supply is on hand well before it is needed during the hardware
build. The remainder of the supply required shall be ordered as the first step in hardware
procurement once the full requirement is known, to ensure the full amount will be available well
before it is required as the hardware build completes.

In addition, during project planning the budget for magic dust was increased to meet the most
likely projected costs based on the rate of increase over the past twelve months. Another 15%
was then added to the planned costs to enable payment to the suppliers for expedited delivery
should this measure be needed.

Finally, three backup suppliers overseas have been identified, and sufficient research done to
preliminarily qualify them as potential candidates for provision of the magic dust requirement
should our regular suppliers be unable to fulfill our orders for any reason. These backup options
will be actioned immediately on any indication of delays from our regular supply channels.

The risk to supply of this critical resource has been added to the project risk register, with $800K
available in the risk budget to address any issues if they arise. The Hardware Lead Andre Young
shall manage this risk closely as the project progresses.

DeeplyPracticalPM.com Page 53/89


MDV3 Project Management Plan

9. Communications

See the DPPM section “Planning: Communications”.

This section describes the planned formal communications as the MDV3 project is carried out.

Formal project communications shall consist of weekly issue status meetings, monthly project
review meetings, change control board meetings, monthly communications to the company
personnel, quarterly updates to the Mayor of Oakville, quarterly updates to the Director of the
Magical Management Institute, and a press conference on facility opening. The following sections
provide additional information.

9.1 Weekly Issue Status Meetings

See the DPPM section “Monitoring & Control: The Weekly Heartbeat”.

The purpose of the Weekly Issue Status Meeting is to provide a regular communication
touchstone for the core team to discuss project-level issues and risks, coordinate steps for further
action where required, and keep the momentum of the MDV3 project going.

The Project Manager shall chair the meeting. Attendees shall include the Project Leads. The
meeting shall be held each week at 9:00 on Monday mornings. Duration shall be a maximum of
one hour.

The team leads shall review the risks on the Project Issues List for action, update, or closure as
required. New issues shall be recorded and potential resolutions discussed as time permits. The
Project Coordinator shall distribute the updated list to all Project Leads at the conclusion of the
meeting. A copy of the template used for the Project Issues List can be found in Appendix C.

At the end of each meeting the team shall also review the project Risk Register, make any
updates required, and coordinate further action as needed.

9.2 Monthly Project Review Meetings

See the DPPM sections “Monitoring & Control: The Monthly Heartbeat”, and
“Monitoring & Control: Earned Value Management (EVM)”

The purpose of the Monthly Project Review Meetings is to provide a regular opportunity for the
Project Manager to provide a project status update to the Sponsor, Customer, and Stakeholders
each month, and enable senior management to provide any required oversight and direction.

The Sponsor Lucy Pevensie, Magical Devices President, shall chair the meeting. The Project
Manager Charles Wallace shall conduct the meeting. Attendees shall include:

 Ava Lee, VP Customer Satisfaction.


 Solomon Gursky, VP Finance.
 Ezekiel Rawlins, VP Manufacturing.
 Dave Robicheaux, Director of Facilities & Operations.
 Stephanie Plum, VP Human Resources.
 Jack Reacher, VP Marketing & Sales.

The meeting shall be scheduled for one hour, and held at 13:00 on the first Tuesday of each

DeeplyPracticalPM.com Page 54/89


MDV3 Project Management Plan

month in the Executive boardroom.

At the start of each month, the Project Manager, Project Coordinator, and Project Scheduler shall
gather the current status of the project scope, schedule, cost, and risks for presentation at the
monthly review. A one page report format shall be used, a copy of which is provided in Appendix
D. The current copy of the risk register shall also be available. Any other relevant information
shall be provided as required and requested.

The monthly project status shall be provided using Earned Value Management metrics. Green,
yellow, red statusing will be provided for cost and schedule performance, where the thresholds for
the Cost Performance Index (CPI) and the Schedule Performance Index (SPI) are:

 Green: Above 0.95, project status is acceptable.

 Yellow. From 0.90 to 0.95, needs corrective action.

 Red: Below 0.90, requires urgent attention.

The Project Manager will present the project status to the Stakeholders at the monthly review.
The Project Manager shall bring options and recommendations for resolution of any significant
issues and risks wherever possible. Assistance and direction on priorities shall be requested
where needed. Plans for further action shall be coordinated where needed.

9.3 Change Control Board Meetings

See the DPPM section “Monitoring & Control: Managing Scope”.

The purpose of the Change Control Board Meetings is to review all changes to the scope,
schedule, budget, or previously baselined and approved deliverables such as designs and
documentation, to ensure all potential impacts are identified, that project manager or sponsor
approval is obtained as required, and appropriate communication of any approved changes takes
place with all affected parties. More information on this process can be found in Section 12 –
Change Control Process.

9.4 Monthly Company Updates

The purpose of the Monthly Company Updates is to keep the company personnel informed on the
progress of the new facility build.

An email from the Project Manager shall be sent to all company personnel once a month with an
update on the project progress and the expectations for the new facility opening and production
start date. The Project Manager shall also provide a verbal update at the quarterly all-hands.

9.5 Mayor Of Oakville Updates

The purpose of the Mayor Of Oakville Updates is to keep the Mayor Travis McGee updated on the
facility build progress, the status and any changes in hiring plans, and provide an invitation to the
facility opening.

The updates shall be provided by the Magical Devices President quarterly by telephone or
breakfast or lunch meeting as appropriate.

9.6 Executive Director Magical Management Institute Updates

DeeplyPracticalPM.com Page 55/89


MDV3 Project Management Plan

The purpose of the Director Magical Management Institute Updates is to provide updates on
project progress and regulatory compliance to Meg Murray, Executive Director of the Magical
Management Institute, to ensure smooth progress towards eventual MMI certification of the
Magical Devices Version 3.

The updates shall be provided quarterly by phone call from the Project Manager. The MMI
Executive Director shall be provided an invitation to the facility opening.

9.7 Facility Opening Press Conference

The purpose of the Facility Opening Press Conference is to inform the general public and citizens
of Oakville about the opening of the new facility, and to generate international press coverage
about the start of production and general availability of the Magical Devices Version 3.

The Magical Devices VP Marketing & Sales Jack Reacher and MDV3 Project Manager shall organize
the press conference. The event shall including a walkthrough of the new facility, and a
demonstration of the first run of Magical Devices Version 3. Invited attendees shall include the
Mayor of Oakville and city councillors, and local, provincial, national, and international press,
onsite and through virtual attendance.

DeeplyPracticalPM.com Page 56/89


MDV3 Project Management Plan

10. Quality

See the DPPM section “Monitoring & Control: Managing Quality”.

This section describes the approach to management of quality throughout the MDV3 project.

The quality of the project outputs is of paramount importance to the success of the effort, and will
be a key focus of the management and project team throughout the conduct of the project.

The four quality principles driving this project are derived from the Magical Devices Quality
Assurance Standard driving all quality efforts at Magical Devices, and are summarized below:

1. Planning. “Quality must be planned in, not inspected in”. While all project work shall be
subject to inspection and test on completion, quality shall be embedded in the work by the
teams as it is being done.

2. Benefits. Quality parts and processes reduce overall cost and schedule, since they
increase efficiency, reduce the amount of testing needed, reduce acceptance issues,
reduce certification issues, and reduce unexpected problems once in operation.

3. Continuous Improvement. The team will gather lessons learned throughout the project to
continuously build on incremental improvement as the work progresses.

4. Fit For Purpose. All project outputs must be “Fit for purpose”, able to genuinely do the job
for which they are intended, fully satisfying the needs of the Customer. This requirement
will also be included in the formal Terms and Conditions of all vendor contracts.

All project team members shall use the best practices and standards of their profession in the
conduct of their work. In addition, peer reviews and user reviews are built into the deliverable
work as key contributors to help maximize the quality of the output. More information on the use
of peer reviews and user reviews is provided in the following sections.

10.1 Peer Reviews

See the DPPM section “Monitoring & Control: Peer Reviews”.

Peer reviews are one of the most effective processes to ensure deliverables are high quality
outputs that are fully fit for purpose.

There are two types of peer reviews that will be used on this project: informal peer reviews that
will be used for all project deliverables, and formal peer reviews that are required for health,
safety, and legal sensitive deliverables. More information is provided below.

10.1.1 Informal Peer Reviews.

Informal peer reviews do not have the administrative overhead of formal peer reviews, and so are
easy to implement for any type of work. The process for informal peer reviews is formally
documented in the Magical Devices Quality Assurance standard, and summarized below:

1. The owner of every deliverable work output that is passed on to others on the project shall
ensure it has had a peer review before being finalized.

DeeplyPracticalPM.com Page 57/89


MDV3 Project Management Plan

2. For large items of work, multiple peer reviews shall be held through the process of creation
of the deliverable so that a review will require no more than an hour by each reviewer.

3. A peer review should include two or three peers to provide a comprehensive review from
more than one viewpoint.

4. Wherever possible, the owner of the deliverable shall hold a single consolidation meeting
with all of the peer reviewers to gather a consolidated set of comments and allow for
comments by peers on each other’s recommendations.

5. The owner of the deliverable may ask follow up questions for clarification of a comment,
however shall refrain from disputing the accuracy of a comment so that the consolidation
meeting stays focused on gathering a complete set of the comments. To ensure a focus
on this essential attribute of informal peer reviews, the deliverable owner shall say “Thank
you” following receipt of each comment.

6. The owner of the deliverable may then incorporate the comment in a revision of the
deliverable or discard any comment as they see fit in their professional judgement.

7. No formal records are required for informal peer reviews, although the owner must retain
a record of reviewer comments in their personal files until the project has been
successfully delivered in case they are ever required for review.

10.1.2 Formal Peer Reviews

Formal peer reviews are required for all deliverables that have health, safety, or legal
requirements to make certain any issues are resolved before finalization. The process for formal
peer reviews is formally documented in the Magical Devices Quality Assurance standard, and
summarized below:

1. The Quality Assurance organization shall ensure every deliverable work output with health,
safety, or legal requirements has had a formal peer review before being finalized. A QA
representative shall manage each formal peer review process.

2. For large items of work, multiple formal peer reviews shall be held through the process of
creation of the deliverable so that each review will require a manageable amount of work
by each reviewer.

3. A formal peer review should include three to five peers to provide a comprehensive review
from more than one viewpoint. The reviewers should be selected from outside of the
project team wherever possible to ensure a full and unbiased review.

4. Quality assurance shall convene and chair a single consolidation meeting with all of the
peer reviewers to gather a consolidated set of issues and allow for comments by peers on
each others recommendations. There is no set duration for a formal peer review
consolidation meeting. The QA representative shall record and manage the consolidated
set of issues from comment through resolution.

5. The owner of the deliverable may ask follow up questions of a reviewer for clarification of
issues, and may offer additional information if they believe an issue is not accurate. In the
event of a disagreement by the deliverable owner or reviewers on the accuracy of an
issue, the QA representative shall call for a vote among the reviewers, not including the
deliverable owner, with the QA representative breaking any ties. The votes of each

DeeplyPracticalPM.com Page 58/89


MDV3 Project Management Plan

member on any issues in dispute, whether or not passed by majority vote, shall be
recorded in the issue log for later follow-up if required. The QA representative may in
their sole discretion record an issue for follow-up if they believe it justified even if not
agreed by majority vote.

6. Each issue agreed, passed by majority vote, or included at the discretion of the QA
representative shall then be reviewed by the deliverable owner and appropriately
addressed by revision of the deliverable or by provision of additional relevant information
not available during the consolidation review meeting. Each resolution shall be reviewed
by the original reviewers for approval. The QA representative will usually defer to the
original reviewer’s decision on sufficiency of a resolution, however, if agreement cannot be
reached, the QA representative may pass an issue as resolved if they deem it appropriate,
provided this decision is approved by the Director of QA.

7. Formal records of all peer reviews and resolution actions shall be retained in the Quality
Assurance files for a period of at least five years following the end of the project.

10.2 User Reviews

See the DPPM section “Monitoring & Control: User Reviews”.

User reviews are also included in the project plan as key contributors to help ensure the project
result is fit for purpose.

Almost all the work on the project has been planned along agile principles, structured in a series
of increments, drafts, versions, or sprints with opportunities for review, formal statusing of
progress, and early adjustment as needed to ensure the project stays on track and delivers the
results required as the increments progress. This approach applies not just to the software work,
but also to the business process, system, hardware, facilities, and other work.

User reviews are incorporated in the work of the deliverables themselves and in the Quality
Assurance tests and inspections to present the work completed so far to the end-users to obtain
their in-progress assessment and identification of any scope errors, omissions, or other issues, for
adjustment as needed in the next increment.

The customer is represented on this project by the following stakeholders, who shall coordinate
attendance by the respective user groups and help manage and participate in reviews as
described below:

User Group Lead Lead Reviews Participate in Reviews


Ava Lee, Magical Software and devices. System.
Devices VP Customer
Satisfaction
Ezekiel Rawlins, Business processes, system, Facility.
Magical Devices VP production lines, equipment
Manufacturing elements of the training and
support programs.
Dave Robicheaux, Facility, facility elements of the Production lines.
Magical Devices training and support programs.
Director of Facilities

Table 11 - User Review Lead / Participation

DeeplyPracticalPM.com Page 59/89


MDV3 Project Management Plan

The process for conduct of user reviews is formally documented in the Magical Devices Quality
Assurance standard, and summarized below:

1. As deliverable drafts, builds, versions, increments, or sprints are finalized, a user review
will be held with the applicable user group. The deliverable team will present the work in
progress to the user group, using presentations, walkthroughs, demonstrations,
prototypes, and mockups as appropriate.

2. User comments shall be collected by the user group lead in a review table, such as the
template found in Appendix E.

3. Following collection of all of the comments, under the direction of the user group lead, the
users shall fill in the column “User Priority” to prioritize their comments using the following
categories:

1 = Essential to the project objective.


2 = Valuable comment, however recommended for implementation in the next
project or phase.
3 = For later investigation, insufficient information currently available.

4. In a separate meeting, under the direction of the deliverable owner with participation from
the Project Team Lead and Project Manager as required, the project team will review the
user priorities and fill in the column “Project Priority” according to the same priority scale,
in order to contribute their view on the best prioritization of the comments given their
understanding of the likely scope, schedule, and budget impacts.

5. The project team shall provide the user review table back to the user group lead.
Additional communications required to baseline the user priorities and project priorities
shall be held as required. The table will then be provided to the Project Sponsor to finalize
the Sponsor Decision column reflecting their decision on which items should assessed for
potential inclusion in the project.

6. The Priority 1 items identified by the Sponsor shall then be entered into the change control
process to determine a full impact analysis of the proposed change. The change shall be
included in the project and work commenced only if the change control process concludes
with a Sponsor decision to implement the comment with full knowledge of the time and
cost impacts, and communication to all affected parties has taken place as needed.

7. The project team and user groups shall implement each user review iteration as quickly as
possible to minimize the impact of any required changes, with the goal of obtaining a
finalized user review table for presentation to the Sponsor within four days of the
conclusion of each review, and analysis of the change impact of any Sponsor indicated
proposed changes being completed within eight days.

DeeplyPracticalPM.com Page 60/89


MDV3 Project Management Plan

11. Procurement

See the DPPM section “Planning: Procurement”.

This section describes the approach to procurement on the MDV3 project. The project requires
procurement of the following elements:

 Facility. A large contract with a building supplier to build the external elements of the
facility, other than the integration elements for the production lines and management and
control stations being built by Magical Devices.

 Building Material. The material required for the Magical Devices facility team to build the
internal elements of the facility required to integrate the production lines and management
and control stations.

 Hardware Equipment. The hardware equipment required for staging, piece build,
assembly, finishing, and QA for each of the three production lines.

 Magic Dust. The magic dust required for integration of the hardware equipment.

 Management Station & Control Station Hardware. The computers and control units for the
management station and the three production line control stations.

 Management Station Software. The software for operation of the management station.

 Control Station Software. The software for operation of the three control stations.

The approach for procurement of each these elements is described in the following sections.

11.1 Facility

A 5000 square meter production facility built on the site acquired adjacent to the current factory
is required to house the new production facility. A candidate set of construction companies was
identified during planning that is potentially capable of building the facility. A Solicitation of
Interest (SOI) was sent to the companies listing the top-level facility requirements and requesting
a response on their ability to build a compliant facility. A shortlist of the top three respondents
was baselined.

During project execution, following preparation of the detailed facility requirements, a request for
proposal (RFP) will be sent to this list of companies requesting bids. Vendors that comply with all
the mandatory requirements will then be evaluated using a best value calculation based on a
scoring of the firm’s years of experience building similar facilities, the workmanship guarantees,
and warranty provisions, and then the company with the best score / bid price ratio will be
selected to build the facility.

11.2 Building Material

The building material required for the Magical Devices facility team to build the internal elements
of the facility required to integrate the production lines and management and control stations are
commodity products, and so shall be procured through our existing standing offers, or through a
request for quote process based on a complete set of specifications, followed by placement of a
contract with the supplier providing the best price, availability, and warranty provisions.

DeeplyPracticalPM.com Page 61/89


MDV3 Project Management Plan

11.3 Hardware Equipment

A suite of hardware is required for build of the staging, piece build, assembly, finishing, and QA
stages of each of the three production lines. This equipment is available from more than one
supplier. A candidate set of vendors was identified during planning that is potentially capable of
supplying the anticipated elements. A Solicitation of Interest (SOI) was sent to the vendors
listing the top-level hardware requirements and requesting a response on their ability to provide
compliant components. A shortlist of the top five respondents was baselined.

During project execution, following preparation of the system architecture and detailed hardware
requirements, a request for proposal (RFP) will be sent to this list of vendors requesting bids.
Vendors that comply with all the mandatory requirements will then be evaluated using a best
value calculation based on a scoring of the firm’s years of experience providing the required
equipment, the availability guarantees, and warranty provisions, and then the vendor with the
best score / bid price ratio will be selected to provide the equipment.

11.4 Magic Dust

The magic dust required for integration of the hardware equipment is a commodity product
provided it meets the required quality specifications, however it has been identified as a critical
resource essential for completion of the project that is in high demand and short supply, and so
its procurement is being addressed with special processes. More information on the procurement
approach for magic dust is provided in Section 8.3.2 – Magic Dust.

11.5 Management Station & Control Station Hardware

The computers and control units for the management stations and three production line control
stations are commodity products, and so shall be procured through our existing standing offers,
or through a request for quote process based on a complete set of specifications followed by
placement of a contract with the supplier providing the best price, availability, and warranty.

11.6 Management Station Software

A suite of software is required to provide control of the assembled production lines and integrated
management of the entire production facility. A range of vendors provide generalized
management software capable of integrating a range of different vendor equipment based on
open management standards. A candidate set of vendors was identified during planning that is
potentially capable of supplying the anticipated elements. A Solicitation of Interest (SOI) was
sent to the vendors listing the top-level software requirements and requesting a response on
ability to provide compliant components. A shortlist of the top four respondents was baselined.

During project execution, following preparation of the system architecture and detailed hardware
and software requirements, a request for proposal (RFP) will be sent to this list of vendors
requesting bids. Vendors that comply with all the mandatory requirements will then be evaluated
using a best value calculation based on a scoring of the firm’s years of experience providing the
required software, the availability guarantees, and warranty provisions, and then the vendor with
the best score / bid price ratio will be selected to provide the software.

11.7 Control Station Software

The control station software used to manage the production lines is generally proprietary and
dependent on the selected hardware equipment, and so procurement of the control station
software will be included as part of the process for the procurement of the hardware equipment.

DeeplyPracticalPM.com Page 62/89


MDV3 Project Management Plan

12. Change Control Process

See the DPPM section “Monitoring & Control: Managing Scope”.

This section describes the process to be used to ensure all proposed changes to the MDV3 project
are managed in a controlled manner that take into account all the effects of any potential change.

Once this project plan is approved by the Sponsor, any changes to scope, schedule, budget, or
the risk budget must go through the formal change control process, as documented in the Magical
Devices Change Control Procedure, and summarized in this section.

In addition, any change to any deliverable once it is baselined and approved during project
execution, such as designs and documentation, must also go through the formal change control
process to ensure that all impacts of the change are identified and all affected parties are included
in the analysis and communications.

A summary of the change control process is provided below:

1. First the change must be formally documented on a Change Request Form, a copy of
which is provided for convenience in Appendix F.

2. If the change is urgently required due to imminent impact on the project success or
imminent affect on health, safety, security, or legal compliance, the Project Manager may
authorize the change immediately and then follow up with a full impact analysis and
communications with the Sponsor, Customer, and other relevant parties as soon as
practically possible.

3. Otherwise a Change Control Board (CCB) meeting shall then be convened to evaluate the
change with wide membership of any possibly affected party, including a representative
from all project core and support functions. The primary purpose of this first meeting shall
be solely to identify all the areas of potential impacts. The Project Manager shall chair the
meeting.

4. An individual that is closest to the change shall then be appointed to follow up after the
first meeting to complete an analysis and determine the full impact of the change to
scope, schedule, budget, risks, procurements, and any other affected project element.
Options and alternatives to address the change shall be considered. An updated
requirements baseline, work breakdown structure, precedence diagram, estimates, Gantt
schedule, and risk register shall be prepared for the change and any options as needed.

5. The Change Control Board shall then be reconvened to consider the impacts of the change
and select the best option if more than one resolution is possible.

6. If the Change Control Board considers the change to be necessary or otherwise beneficial,
and it does not affect the baselined project scope, schedule, budget, or risk budget
approved by the Sponsor, the Project Manager may authorize the change.

7. Otherwise if the change affects the baselined scope, schedule, budget, or risk budget
approved by the Sponsor, a recommendation on the change shall then be made by the
Change Control Board, as approved by the Project Manager, and submitted to the Sponsor
for their consideration. The change shall not be initiated unless and until formal approval
by the Sponsor is provided in writing.

DeeplyPracticalPM.com Page 63/89


MDV3 Project Management Plan

8. When a scope change results in an increase to the baselined project schedule and budget,
options shall always be considered for removal of offsetting scope to minimize the impacts,
and these options presented to the Sponsor and Customer wherever appropriate.

9. Once a decision on the change is made, the rationale for the decision and all relevant
documentation will be stored in the Change Control Log files. If the change is approved,
all required project documentation shall be updated, and all relevant parties shall be
informed in a timely manner.

DeeplyPracticalPM.com Page 64/89


MDV3 Project Management Plan

Appendix A - Requirements

See the DPPM section “Planning: Requirements”.

Also see the associated document “MDV3 Requirements”.

This appendix provides a listing of the MDV3 project requirements, including the unique identifier,
type, owner of each requirement, and preliminary traceability to the deliverables and test cases
that will satisfy them.

The deliverable traceability will be refined to a more detailed level as the system, software,
hardware, and facility designs are developed during execution. The test case allocations are
currently at the procedure level, and will be refined to individual test cases as the test
documentation is developed.

ID Type Requirement Owner Deliverabl Test


e Case
1000 Functionality The magical devices shall be Ava Lee SYB1.3 SYTP1.4
compliant with all requirements
in the industry standard "Magic
Componentry Functionality
Standard" (Version 10.52) from
the Magical Management
Institute.
1100 Functionality The magical devices shall weigh Ava Lee HWD1.3 QAHW1.3
less than 10 grams.
1200 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
capable of suspension of time
for at least ten hours in the local
universal neighborhood.
1300 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
capable of teleportation over a
distance of at least 100 meters.
1400 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
capable of projection of
holographic sightscapes that are
dynamic and indistinguishable
from reality from any angle and
in any lighting.
1500 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
automatically updatable over
the Internet and by telekinesis.
1600 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
remotely callable and able to
transport themselves to the
users location from anywhere on
the planet.
1700 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
configurable to disguise
themselves as a normal looking
computer, book, or kitten.

DeeplyPracticalPM.com Page 65/89


MDV3 Project Management Plan

ID Type Requirement Owner Deliverabl Test


e Case
1800 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
able to cooperate with other
devices in the same network
over WIFI and
telecommunications networks.
1900 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
capable of transmutation of any
metal or noble gas.
2000 Functionality The magical devices shall be Ava Lee SWD1.3 QASW1.5
producible in any colour,
including iridescent.
2100 Facility The manufacturing facility shall Dave FACD1.4 FACI1.7
be compliant with all Robicheaux
requirements of the Magical
Management Institute standard
"Magic Manufacturing
Requirements And
Specifications" (MMI-654321-D).
2200 Facility The facility shall fully comply Dave FACD1.4 FACI1.7
with all requirements of the Robicheaux
Magical Management Institute
standard "Safe Production Of
Devices With Magical Properties"
(MMI-987654-E).
2300 Facility The facility shall include Dave FACD1.4 FACI1.7
separate material staging and Robicheaux
shipping lines for rapidly
decongested material
management.
2400 Facility The facility shall comply with all Dave FACD1.4 FACI1.7
requirements of the standard Robicheaux
Design Considerations for
"Airborne Molecular
Contamination Filtration
Systems" (IEST-G-CC035.1).
2500 Equipment The production lines shall Ezekiel HWD1.3 QAHW1.3
include equipment to provide Rawlins
staging, piece build, assembly,
finishing, and QA functions.
2600 Equipment The production equipment shall Ezekiel HWD1.3 QAHW1.3
comply with all requirements of Rawlins
the standard "Vibration
Monitoring" (ISO 10816).
2700 Equipment The production equipment shall Ezekiel HWD1.3 QAHW1.3
comply with all requirements of Rawlins
the standard "Acoustic
Emissions" (ISO 22096).
2800 Equipment The production equipment shall Ezekiel HWD1.3 QAHW1.3
comply with all requirements of Rawlins
"Nanotechnologies Materials
Specifications" (ISO 12805).

DeeplyPracticalPM.com Page 66/89


MDV3 Project Management Plan

ID Type Requirement Owner Deliverabl Test


e Case
2900 Equipment All production equipment shall Ezekiel HWD1.3 QAHW1.3
run on 220V grounded power. Rawlins
3000 Equipment All production equipment shall Ezekiel HWD1.3 QAHW1.3
incorporate single function Rawlins
emergency shutdown features.
3100 Equipment All production equipment shall Ezekiel HWD1.3 QAHW1.3
use industry standard interfaces Rawlins
capable of connecting to
equipment from any other
vendor using the same standard
interface.
3200 Management The facility shall include a Ezekiel FACD1.4 FACI1.7
Station management station capable of Rawlins
instrumentation reporting and
control over all production lines.
3300 Management The management station Ezekiel SWD1.3 QASW1.5
Station software shall provide Rawlins
longitudinal tracking of all
production line performance
over time, with reporting
available on quantity,
productivity, efficiency, and
availability, and be available
broken down by mode, phase,
and device type.
3400 Management The management station Ezekiel SWD1.3 QASW1.5
Station software shall provide single Rawlins
screen dynamic dashboards
tracking the performance of
each production line.
3500 Control The facility shall include Ezekiel FACD1.4 FACI1.7
Station independent control stations for Rawlins
each of the three production
lines each providing separate
integration, control, and
reporting functionality.
3600 Control The control station software Ezekiel SWD1.3 QASW1.5
Station shall be able to control all Rawlins
equipment on a production line
from the allocated production
station.
3700 Control The control station software for Ezekiel SWD1.3 QASW1.5
Station any production line shall be Rawlins
configurable to be able to
simultaneously control any of
the other production lines.
3800 Supportability The computing and Dave HWD1.3 QAHW1.3
manufacturing equipment Robicheaux
componentry shall all be off-the-
shelf and available from multiple
suppliers.

DeeplyPracticalPM.com Page 67/89


MDV3 Project Management Plan

ID Type Requirement Owner Deliverabl Test


e Case
3900 Supportability All equipment vendors shall Dave HWD1.3 QAHW1.3
utilize a quality assurance Robicheaux
system that complies with all
requirements of "Quality
Management System" (CLSI
QMS13-A).
4000 Supportability All operating system and Dave SWD1.3 QASW1.5
middleware shall be free open Robicheaux
source software.
4100 Regulatory The manufacturing system shall Ava Lee FACD1.4 QASE1.1
be compliant with all security
requirements in the industry
standard "Secure Magical Device
Manufacturing" (MMI-321123-G)
from the Magical Management
Institute.
4200 Regulatory The devices shall be compliant Ava Lee SYB1.3 SYTP1.4
with all requirements in the
industry standard "Magic
Componentry Functionality
Standard (V10.52)" from the
Magical Management Institute.
4300 Capacity The facility shall be capable of Ezekiel FACD1.4 FACI1.7
producing 1M units in year 1 of Rawlins
operation.
4400 Capacity The facility shall be capable of Ezekiel FACD1.4 FACI1.7
production growth of 40% a Rawlins
year for at least ten years.
4500 Capacity The facility shall be capable of Ezekiel FACD1.4 FACI1.7
producing version 1 and version Rawlins
2 magical devices and
component parts to provide
long-term customer support.
4600 Capacity The facility's three production Ezekiel FACD1.4 FACI1.7
lines shall each be configurable Rawlins
to be able to produce health,
education, and environment
devices.
4700 Availability A failure in any single Dave HWD1.3 QASY1.2
component shall not bring down Robicheaux
the production capacity by more
than 10%.
4800 Availability The manufacturing system shall Ezekiel SYB1.3 SYTP1.4
have 99.999% uptime. Rawlins
4900 Availability The production equipment shall Dave SYB1.3 SYTP1.4
be capable of 24/7/365 Robicheaux
operation.
5000 Availability The production equipment shall Dave HWD1.3 QAHW1.3
be capable of component level Robicheaux
swap and replace for repair of
any faults.

DeeplyPracticalPM.com Page 68/89


MDV3 Project Management Plan

ID Type Requirement Owner Deliverabl Test


e Case
5100 Environmental The facility shall create zero Dave FACD1.4 FACI1.7
untreated waste. Robicheaux
5200 Environmental The facility shall use renewable Dave FACD1.4 FACI1.7
energy for all power Robicheaux
requirements.
5300 Environmental All packaging shall be fully Dave SYB1.3 SYTP1.4
recyclable. Robicheaux
5400 Environmental The facility shall comply with all Dave FACD1.4 FACI1.7
requirements of "Environmental Robicheaux
Management Systems" (ISO
14001).
5500 Security The facility shall be secure from Dave FACD1.4 QASE1.1
unauthorized access, with Robicheaux
secure biometric authentication
required for entry.
5600 Security Logon for operation and control Ezekiel SWD1.3 QASW1.5
of all equipment and control and Rawlins
management stations shall be
by secure biometric access.
5700 Training The training solution shall Ezekiel TRM1.4 TRM1.4
provide hands-on skills training Rawlins
immediately before deployment
of each phase.
5800 Training The training solution shall Ezekiel TRM1.4 TRM1.4
include online self serve Rawlins
refreshment training resources.
5900 Marketing The magical devices shall be Jack SYB1.3 SYTP1.4
orderable online and fully Reacher
customizable to the customer's
requirements.
6000 Marketing A device ordered online shall Jack SWD1.3 QASW1.5
immediately enter the Reacher
manufacturing queue, and be
automatically shipped to the
customer address when ready.
6100 Procurement All equipment vendors shall be Ezekiel FACB1.1 FACB1.1
ISO 9001 certified. Rawlins
6200 Procurement The facility building contractor Dave FACB1.1 FACB1.1
shall have experience building at Robicheaux
least five manufacturing
facilities of 5,000 square meters
or larger within the last five
years.

DeeplyPracticalPM.com Page 69/89


MDV3 Project Management Plan

Appendix B - Work Breakdown Structure Dictionary

See the DPPM section “Planning: The WBS Dictionary”.

This appendix provides a work breakdown structure dictionary with more information on the deliverables documented in Section
2.4 - Work Breakdown Structure, including a unique identifier, description, owner, and cost account.

WBS ID Work Breakdown Description Owner Cost


Structure Deliverable Account
MDV3 Magical Devices Version 3 The entire MDV3 project. Charles CA1000
Wallace
BPR1 Business Process Develop baselines for the as-is business processes, the Kong Qiu CA2000
to-be business processes, and then perform a gap
analysis to determine what work is needed to
implement the to-be processes.
BPRA1 Business Process As-Is Collect and document the existing set of as-is business Kong Qiu CA3000
processes to provide a consolidated baseline.
BPRA1.1 Business Processes As-Is Gather a consolidated, organized baseline of all the Kong Qiu CA4000
Draft current business processes used to produce version 2
of the magical devices, conduct a review, and identify
areas of remaining work.
BPRA1.2 Business Processes As-Is Finalize a final baseline of all the current business Kong Qiu CA5000
Final processes used to produce version 2 of the magical
devices.
BPRT1 Business Process To-Be Develop the to-be business processes to reflect the Kong Qiu CA6000
way we wish the new facility to perform.
BPRT1.1 Business Processes To-Be Prepare the new set of business processes to produce Kong Qiu CA7000
Draft version 3 of the magical devices, conduct a review,
and identify areas of remaining work.
BPRT1.2 Business Processes To-Be Finalize a final baseline of the new set of business Kong Qiu CA8000
Final processes to produce version 3 of the magical devices.
GAN1 Gap Analysis Perform a gap analysis to determine what work is Kong Qiu CA9000
needed to implement the to-be processes.
GAN1.1 Gap Analysis Draft Prepare an analysis of the changes between the as-is Kong Qiu CA10000
and to-be business processes, and the elements that
will need to be created or modified to meet the to-be
processes, conduct a review, and identify areas of
remaining work.
DeeplyPracticalPM.com Page 70/89
MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
GAN1.2 Gap Analysis Final Prepare a final analysis of the changes between the as- Kong Qiu CA11000
is and to-be business processes, and the elements that
will need to be created or modified to meet the to-be
processes.
SYS1 System Develop the top-level system architecture, the system Mary CA12000
test plan and system test procedures, and build the Sperling
integrated hardware and software system that will
produce the magical devices version 3.
SYA1 System Architecture Develop the top-level system architecture documenting Mary CA13000
the hardware, software, interfaces, and functional Sperling
components of the system required to produce the
magical devices version 3.
SYA1.1 System Architecture Draft Prepare a draft system architecture of the hardware, Mary CA14000
software, interfaces, and functional components of the Sperling
system required to produce the magical devices
version 3, conduct a review, and identify areas of
remaining work.
SYA1.2 System Architecture Final Prepare a final system architecture baseline of the Mary CA15000
hardware, software, interfaces, and functional Sperling
components of the system required to produce the
magical devices version 3.
SYTP1 System Test Planning Develop the system test plan and test procedures to Mary CA16000
be used to validate the working system. Sperling
SYTP1.1 System Test Plan Prepare a test plan identifying the processes, personal, Mary CA17000
facilities, equipment, and schedule required to conduct Sperling
testing of the system.
SYTP1.2 System Test Procedures Prepare a first draft of the procedures to be used to Mary CA18000
Draft 1 test the system and verify it meets the system Sperling
requirements, conduct a review, and identify areas of
remaining work.
SYTP1.3 System Test Procedures Prepare a second draft of the procedures to be used to Mary CA19000
Draft 2 test the system and verify it meets the system Sperling
requirements, conduct a review, and identify areas of
remaining work.
SYTP1.4 System Test Procedures Prepare a final baseline of the procedures to be used Mary CA20000
Final to test the system and verify it meets the system Sperling
requirements.

DeeplyPracticalPM.com Page 71/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
SYB1 System Build Build the integrated hardware and software system. Mary CA21000
Sperling
SYB1.1 System Build 1 Build the first version of the system to be used to Mary CA22000
produce the magical devices version 3, conduct a Sperling
review, and identify areas of remaining work.
SYB1.2 System Build 2 Build the second version of the system to be used to Mary CA23000
produce the magical devices version 3, conduct a Sperling
review, and identify areas of remaining work.
SYB1.3 System Build Final Build the final version of the system to be used to Mary CA24000
produce the magical devices version 3. Sperling
HW1 Hardware Refine the hardware detailed requirements, document Andre CA25000
a hardware development plan, prepare the hardware Young
design, develop the hardware test plan and test
procedures to be used for validation, and build the
production lines of hardware equipment to produce the
magical devices version 3.
HWP1 Hardware Planning Develop the hardware detailed requirements and a Andre CA26000
hardware development plan. Young
HWP1.1 Hardware Detailed Prepare detailed hardware requirements based on the Andre CA27000
Requirements system requirements previously documented during Young
the project planning stage, the gap analysis, and the
system architecture, identifying the detailed
specifications required for hardware design, build, and
testing, conduct a review, address any issues, and
prepare a final baseline.
HWP1.2 Hardware Development Plan Prepare a hardware development plan documenting Andre CA28000
the processes, personnel, facilities, and schedule Young
required to develop the hardware solution.
HWD1 Hardware Design Prepare the design for the hardware to produce the Andre CA29000
magical devices version 3. Young
HWD1.1 Hardware Design Draft 1 Prepare a first draft of a hardware design to meet all Andre CA30000
the detailed hardware requirements and produce the Young
magical devices version 3, conduct a review, and
identify areas of remaining work.
HWD1.2 Hardware Design Draft 2 Prepare a second draft of a hardware design to meet Andre CA31000
all the detailed hardware requirements and produce Young
the magical devices version 3, conduct a review, and
identify areas of remaining work.

DeeplyPracticalPM.com Page 72/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
HWD1.3 Hardware Design Final Prepare a final baseline of a hardware design to meet Andre CA32000
all the detailed hardware requirements and produce Young
the magical devices version 3.
HWTP1 Hardware Test Planning Develop the hardware test plan and test procedures to Andre CA33000
be used to validate the working system. Young
HWTP1.1 Hardware Test Plan Prepare a test plan identifying the processes, personal, Andre CA34000
facilities, equipment, and schedule required to conduct Young
testing of the hardware.
HWTP1.2 Hardware Test Procedures Prepare a first draft of the procedures to be used to Andre CA35000
Draft 1 test the hardware and verify it meets the detailed Young
hardware requirements, conduct a review, and identify
areas of remaining work.
HWTP1.3 Hardware Test Procedures Prepare a second draft of the procedures to be used to Andre CA36000
Draft 2 test the hardware and verify it meets the detailed Young
hardware requirements, conduct a review, and identify
areas of remaining work.
HWTP1.4 Hardware Test Procedures Prepare a final baseline of the procedures to be used Andre CA37000
Final to test the hardware and verify it meets the detailed Young
hardware requirements.
HWB1 Hardware Build Procure the equipment, and build the hardware to Andre CA38000
produce the magical devices version 3. Young
HWB1.1 Hardware Procurement Finalize all remaining hardware procurement not Andre CA39000
already in-house due to early procurement as the Young
design was developed. As the system architecture and
the hardware design are finalized, this item will be
refined into greater detail to break out the individual
elements of equipment required for staging, piece
build, assembly, finishing, QA, management stations,
control stations, and magic dust.
HWB1.2 Hardware Build 1 Build the first version of the hardware to be used to Andre CA40000
produce the magical devices version 3, conduct a Young
review, and identify areas of remaining work.
HWB1.3 Hardware Build 2 Build the second version of the hardware to be used to Andre CA41000
produce the magical devices version 3, conduct a Young
review, and identify areas of remaining work.
HWB1.4 Hardware Build 3 Build the third version of the hardware to be used to Andre CA42000
produce the magical devices version 3, conduct a Young
review, and identify areas of remaining work.

DeeplyPracticalPM.com Page 73/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
HWB1.5 Hardware Build Final Baseline the final version of the hardware to be used Andre CA43000
to produce the magical devices version 3. Young
SW1 Software Refine the software detailed requirements, document a Byomkesh CA44000
software development plan, prepare the software Bakshi
design, develop the software test plan and test
procedures to be used for validation, and build the
software to produce the magical devices version 3.
SWP1 Software Planning Develop the software detailed requirements and a Byomkesh CA45000
software development plan. Bakshi
SWP1.1 Software Detailed Prepare detailed software requirements based on the Byomkesh CA46000
Requirements system requirements previously documented during Bakshi
the project planning stage, the gap analysis, and the
system architecture, identifying the detailed
specifications required for software design, build, and
testing, conduct a review, address any issues, and
prepare a final baseline.
SWP1.2 Software Development Plan Prepare a software development plan documenting the Byomkesh CA47000
processes, personnel, facilities, and schedule required Bakshi
to develop the software solution.
SWD1 Software Design Prepare the design for the software to produce the Byomkesh CA48000
magical devices version 3. Bakshi
SWD1.1 Software Design Draft 1 Prepare a first draft of the software design to meet all Byomkesh CA49000
the detailed software requirements and produce the Bakshi
magical devices version 3, conduct a review, and
identify areas of remaining work.
SWD1.2 Software Design Draft 2 Prepare a second draft of the software design to meet Byomkesh CA50000
all the detailed software requirements and produce the Bakshi
magical devices version 3, conduct a review, and
identify areas of remaining work.
SWD1.3 Software Design Final Prepare a final baseline of the software design to meet Byomkesh CA51000
all the detailed software requirements and produce the Bakshi
magical devices version 3.
SWTP1 Software Test Planning Develop the software test plan and test procedures to Byomkesh CA52000
be used to validate the working system. Bakshi
SWTP1.1 Software Test Plan Prepare a test plan identifying the processes, personal, Byomkesh CA53000
facilities, equipment, and schedule required to conduct Bakshi
testing of the software.

DeeplyPracticalPM.com Page 74/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
SWTP1.2 Software Test Procedures Prepare a first draft of the procedures to be used to Byomkesh CA54000
Draft 1 test the software and verify it meets the detailed Bakshi
software requirements, conduct a review, and identify
areas of remaining work.
SWTP1.3 Software Test Procedures Prepare a second draft of the procedures to be used to Byomkesh CA55000
Draft 2 test the software and verify it meets the detailed Bakshi
software requirements, conduct a review, and identify
areas of remaining work.
SWTP1.4 Software Test Procedures Prepare a final baseline of the procedures to be used Byomkesh CA56000
Final to test the software and verify it meets the detailed Bakshi
software requirements.
SWB1 Software Build Procure off-the-shelf software, and build the software Byomkesh CA57000
to produce the magical devices version 3. Bakshi
SWB1.1 Software Procurement Finalize all remaining software procurement for not Byomkesh CA58000
already in-house due to early procurement as the Bakshi
design was developed. As the system architecture and
the software design are finalized, this item will be
refined to break out the individual elements of
software required for the production equipment,
management stations, and control stations.
SWB1.2 Software Sprint 1 Develop the first iteration of the software to produce Byomkesh CA59000
the magical devices version 3. Bakshi
SWB1.3 Software Sprint 2 Develop the second iteration of the software to Byomkesh CA60000
produce the magical devices version 3. Bakshi
SWB1.4 Software Sprint 3 Develop the third iteration of the software to produce Byomkesh CA61000
the magical devices version 3. Bakshi
SWB1.5 Software Sprint 4 Develop the fourth iteration of the software to produce Byomkesh CA62000
the magical devices version 3. Bakshi
SWB1.6 Software Sprint 5 Develop the fifth iteration of the software to produce Byomkesh CA63000
the magical devices version 3. Bakshi
SWB1.7 Software Final Baseline the final version of the software to be used to Byomkesh CA64000
produce the magical devices version 3. Bakshi
SEC1 Security Refine the security detailed requirements, develop the Cathy Kerr CA65000
security architecture, and develop the security test
plan and test procedures to be used for validation and
certification of the secure system.

DeeplyPracticalPM.com Page 75/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
SECD1 Security Design Refine the security detailed requirements and develop Cathy Kerr CA66000
the security architecture to be used to secure the
system.
SECD1.1 Security Detailed Prepare detailed security requirements based on the Cathy Kerr CA67000
Requirements system requirements previously documented during
the project planning stage, the gap analysis, and the
system architecture, identifying the detailed
specifications required for security design, build, and
testing, conduct a review, address any issues, and
prepare a final baseline.
SECD1.2 Security Architecture Prepare a baseline security architecture of the Cathy Kerr CA68000
hardware, software, processes, and functional
components required to meet the detailed security
requirements.
SECTP1 Security Test Planning Develop the security test plan and test procedures to Cathy Kerr CA69000
be used for validation and certification of the secure
system.
SECTP1.1 Security Test Plan Prepare a test plan identifying the processes, personal, Cathy Kerr CA70000
facilities, equipment, and schedule required to conduct
security testing of the system.
SECTP1.2 Security Test Procedures Prepare a first draft of the procedures to be used to Cathy Kerr CA71000
Draft 1 test the system and verify it meets the detailed
security requirements, conduct a review, and identify
areas of remaining work.
SECTP1.3 Security Test Procedures Prepare a final baseline of the procedures to be used Cathy Kerr CA72000
Final to test the system and verify it meets the detailed
security requirements.
FAC1 Facility Refine the facility detailed requirements, document a Irwin CA73000
facility build plan, prepare the facility design, put in Fletcher
place the procurement with the contractor building the
external elements of the facility, and build the internal
elements of the facility to produce the magical devices
version 3.
FACP1 Facilities Planning Develop the facility detailed requirements and a Irwin CA74000
hardware development plan. Fletcher

DeeplyPracticalPM.com Page 76/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
FACP1.1 Facilities Detailed Prepare detailed facility requirements based on the Irwin CA75000
Requirements system requirements previously documented during Fletcher
the project planning stage, the gap analysis, and the
system architecture, identifying the detailed
specifications required for the facility design, build, and
inspection, conduct a review, address any issues, and
prepare a final baseline.
FACP1.2 Facilities Build Plan Prepare a build plan documenting the processes, Irwin CA76000
personnel, equipment, and schedule required to Fletcher
develop the production facility.
FACD1 Facilities Design Prepare the design for the facility to produce the Irwin CA77000
magical devices version 3. Fletcher
FACD1.1 Facilities Design Draft 1 Prepare a first draft of a facilities design to meet all the Irwin CA78000
detailed facilities requirements and produce the Fletcher
magical devices version 3, conduct a review, and
identify areas of remaining work.
FACD1.2 Facilities Design Draft 2 Prepare a second draft of a facilities design to meet all Irwin CA79000
the detailed facilities requirements and produce the Fletcher
magical devices version 3, conduct a review, and
identify areas of remaining work.
FACD1.3 Facilities Design Draft 3 Prepare a third draft of a facilities design to meet all Irwin CA80000
the detailed facilities requirements and produce the Fletcher
magical devices version 3, conduct a review, and
identify areas of remaining work.
FACD1.4 Facilities Design Final Prepare a final baseline of a facilities design to meet all Irwin CA81000
the detailed facilities requirements and produce the Fletcher
magical devices version 3.
FACB1 Facilities Build Put in place the procurement with the facilities Irwin CA82000
contractor, and build the internal elements of the Fletcher
facility to produce the magical devices version 3.
FACB1.1 Facilities Procurement Finalize all remaining facilities procurement not already Irwin CA83000
in-house due to early procurement as the design was Fletcher
developed, and put the contract in place with the
contractor building the external elements of the
facility. As the facilities design is completed, this item
will be refined to break out the individual elements of
building material required to complete the facilities
build.

DeeplyPracticalPM.com Page 77/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
FACB1.2 Facilities Build 1 Build the first version of the facility to be used to Irwin CA84000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.3 Facilities Build 2 Build the second version of the facility to be used to Irwin CA85000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.4 Facilities Build 3 Build the third version of the facility to be used to Irwin CA86000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.5 Facilities Build 4 Build the fourth version of the facility to be used to Irwin CA87000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.6 Facilities Build 5 Build the fifth version of the facility to be used to Irwin CA88000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.7 Facilities Build 6 Build the sixth version of the facility to be used to Irwin CA89000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.8 Facilities Build 7 Build the seventh version of the facility to be used to Irwin CA90000
produce the magical devices version 3, conduct a Fletcher
review, and identify areas of remaining work.
FACB1.9 Facilities Build Final Build the final version of the facility to be used to Irwin CA91000
produce the magical devices version 3. Fletcher
QA1 Quality Assurance Conduct the quality assurance to ensure the hardware, Son Goku CA92000
software, system, security, and facility are fully tested
and inspected to meet all the requirements, are
correctly configured, and will be of the highest quality
and fit for purpose to produce the magical devices
version 3.
QAHW1 Hardware Test Conduct testing of the hardware to verify all the Son Goku CA93000
requirements are met.
QAHW1.1 Hardware Build 1 Test Conduct testing of the first hardware build to verify all Son Goku CA94000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next build.

DeeplyPracticalPM.com Page 78/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
QAHW1.2 Hardware Build 2 Test Conduct testing of the second hardware build to verify Son Goku CA95000
all the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next build.
QAHW1.3 Hardware Build 3 Test Conduct testing of the third hardware build to verify all Son Goku CA96000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the final baseline.
QASW1 Software Test Conduct testing of the software to verify all the Son Goku CA97000
requirements are met.
QASW1.1 Software Sprint 1 Test Conduct testing of the first software sprint to verify all Son Goku CA98000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next sprint.
QASW1.2 Software Sprint 2 Test Conduct testing of the second software sprint to verify Son Goku CA99000
all the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next sprint.
QASW1.3 Software Sprint 3 Test Conduct testing of the third software sprint to verify all Son Goku CA100000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next sprint.
QASW1.4 Software Sprint 4 Test Conduct testing of the fourth software sprint to verify Son Goku CA101000
all the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next sprint.
QASW1.5 Software Sprint 5 Test Conduct testing of the fifth software sprint to verify all Son Goku CA102000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the final baseline.
QASY1 System Test Conduct testing of the system to verify all the Son Goku CA103000
requirements are met.
QASY1.1 System Build 1 Test Conduct testing of the first system build to verify all Son Goku CA104000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the next build.

DeeplyPracticalPM.com Page 79/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
QASY1.2 System Build 2 Test Conduct testing of the second system build to verify all Son Goku CA105000
the allocated requirements are met, document any
deficiencies, and identify areas requiring remediation
in the final build.
QASC1 System Certification Conduct formal certification of the system to be ready Son Goku CA106000
to procure the magical devices version 3.
QASC1.1 System Certification Review all the prior system, hardware, software, and Son Goku CA107000
security testing, validate the readiness for system
operation, conduct any final certification activities
required, and formally certify the system ready for
production of the magical devices version 3.
QASE1 Security Test Conduct formal security certification of the system to Son Goku CA108000
be ready to produce the magical devices version 3.
QASE1.1 Security Test Final Conduct testing of the system to verify all the security Son Goku CA109000
requirements are met, conduct remediation of any
deficiencies, and retest any areas required.
QASEC1 Security Certification Conduct testing of the software to verify all the Son Goku CA110000
requirements are met.
QASEC1.2 Security Certification Final Review the security testing, validate the readiness for Son Goku CA111000
secure operation, conduct any final certification
activities required, and formally certify the system as
secure for production of the magical devices version 3.
FACI1 Facilities Inspection Conduct inspections of the facility to verify all the Son Goku CA112000
requirements and design are met.
FACI1.1 Inspection Build 1 Conduct an inspection of the first facilities build to Son Goku CA113000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.
FACI1.2 Inspection Build 2 Conduct an inspection of the second facilities build to Son Goku CA114000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.
FACI1.3 Inspection Build 3 Conduct an inspection of the third facilities build to Son Goku CA115000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.

DeeplyPracticalPM.com Page 80/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
FACI1.4 Inspection Build 4 Conduct an inspection of the fourth facilities build to Son Goku CA116000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.
FACI1.5 Inspection Build 5 Conduct an inspection of the fifth facilities build to Son Goku CA117000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.
FACI1.6 Inspection Build 6 Conduct an inspection of the sixth facilities build to Son Goku CA118000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the next build.
FACI1.7 Inspection Build 7 Conduct an inspection of the seventh facilities build to Son Goku CA119000
verify all the allocated requirements are met,
document any deficiencies, and identify areas requiring
remediation in the final build.
IMP1 Implementation Prepare and manage a comprehensive implementation Heidi Geis CA120000
plan to ensure the success of a multi-phase pilot and
rollout of the production system to produce the
magical devices version 3.
IMPP1 Implementation Planning Prepare an implementation plan documenting the Heidi Geis CA121000
processes, personnel, facilities, and schedule required
to implement the production system.
IMPP1.1 Implementation Plan Draft 1 Prepare a first draft of the implementation plan for a Heidi Geis CA122000
three phase pilot and rollout of the production system,
conduct a review, and identify areas to address in the
next version.
IMPP1.2 Implementation Plan Draft 2 Prepare a second draft of the implementation plan for Heidi Geis CA123000
a three phase pilot and rollout of the production
system, conduct a review, and identify areas to
address in the next version.
IMPP1.3 Implementation Plan Draft 3 Prepare a third draft of the implementation plan for a Heidi Geis CA124000
three phase pilot and rollout of the production system,
conduct a review, and identify areas to address in the
next version.

DeeplyPracticalPM.com Page 81/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
IMPP1.4 Implementation Plan Draft 4 Prepare a fourth draft of the implementation plan for a Heidi Geis CA125000
three phase pilot and rollout of the production system,
conduct a review, and identify areas to address in the
next version.
IMPP1.5 Implementation Plan Final Prepare a final baseline of the implementation plan for Heidi Geis CA126000
a three phase pilot and rollout of the production
system.
IMPP1.6 Implementation Readiness Review the system certification, security certification, Heidi Geis CA127000
Review facilities inspections, implementation plan, training
material, and support package to determine readiness
for progress to implementation.
IMPH1 Implementation Phase 1 Conduct a pilot and rollout of phase 1 of the system. Heidi Geis CA128000
IMPH1.1 Phase 1 Pilot Pilot the first production line, ramping up to full Heidi Geis CA129000
capacity.
IMPH1.2 Phase 1 Rollout Rollout full capacity of the first production line. Heidi Geis CA130000
IMPH2 Implementation Phase 2 Conduct a pilot and rollout of phase 2 of the system. Heidi Geis CA131000
IMPH2.1 Phase 2 Pilot Pilot the second production line, ramping up to full Heidi Geis CA132000
capacity.
IMPH2.2 Phase 2 Rollout Rollout full capacity of the second production line. Heidi Geis CA133000
IMPH3 Implementation Phase 3 Conduct a pilot and rollout of phase 3 of the system. Heidi Geis CA134000
IMPH3.1 Phase 3 Pilot Pilot the third production line, ramping up to full Heidi Geis CA135000
capacity.
IMPH3.2 Phase 3 Rollout Rollout full capacity of the third production line. Heidi Geis CA136000
TR1 Training Refine the training detailed requirements, develop a Jean CA137000
training plan, and prepare the material to train the Cunliffe
users of the production system, and train the teams.
TRP1 Training Planning Refine the training detailed requirements and Jean CA138000
document a training plan to train the users of the Cunliffe
production system.
TRP1.1 Training Detailed Prepare detailed training requirements based on the Jean CA139000
Requirements system requirements previously documented during Cunliffe
the project planning stage, the gap analysis, and the
system architecture.
TRP1.2 Training Plan Prepare a plan documenting the processes, personnel, Jean CA140000
facilities, and schedule required to develop the training Cunliffe
solution.
TRM1 Training Material Prepare the material to train the users of the Jean CA141000
production system. Cunliffe
DeeplyPracticalPM.com Page 82/89
MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
TRM1.1 Training Material Draft 1 Prepare the first draft of the material to training the Jean CA142000
production team in use of the system to produce the Cunliffe
magical devices version 3.
TRM1.2 Training Material Draft 2 Prepare the second draft of the material to training the Jean CA143000
production team in use of the system to produce the Cunliffe
magical devices version 3.
TRM1.3 Training Material Draft 3 Prepare the third draft of the material to training the Jean CA144000
production team in use of the system to produce the Cunliffe
magical devices version 3.
TRM1.4 Training Material Final Prepare the final baseline of the material to training Jean CA145000
the production team in use of the system to produce Cunliffe
the magical devices version 3.
TRPH1 Training Phases Conduct three phases of training for the pilots and Jean CA146000
rollout of the production system. Cunliffe
TRPH1.1 Phase 1 Training Train the team in use of the first production line for Jean CA147000
producing the magical devices version 3. Cunliffe
TRPH1.2 Phase 2 Training Train the team in use of the second production line for Jean CA148000
producing the magical devices version 3. Cunliffe
TRPH1.3 Phase 3 Training Train the team in use of the third production line for Jean CA149000
producing the magical devices version 3. Cunliffe
SU1 Support Refine the support detailed requirements, develop a Henry Kiku CA150000
support plan, prepare the package of documentation
and processes to support the system and facilities, and
transition support to the operations teams.
SUP1 Support Planning Refine the support detailed requirements and Henry Kiku CA151000
document a support plan to support the system and
facilities to produce the magical devices version 3.
SUP1.1 Support Detailed Prepare detailed support requirements based on the Henry Kiku CA152000
Requirements system requirements previously documented during
the project planning stage, the gap analysis, and the
system architecture, conduct a review, address any
issues, and prepare a final baseline.
SUP1.2 Support Plan Prepare a support plan documenting the processes, Henry Kiku CA153000
personnel, facilities, and schedule required to develop
the support solution.
SUPA1 Support Package Prepare the package of documentation and processes Henry Kiku CA154000
to support the system and facilities to produce the
magical devices version 3.
DeeplyPracticalPM.com Page 83/89
MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
SUPA1.1 Support Package Draft 1 Prepare the first version of the package to be used to Henry Kiku CA155000
support the magical devices version 3 production
system.
SUPA1.2 Support Package Draft 2 Prepare the second version of the package to be used Henry Kiku CA156000
to support the magical devices version 3 production
system.
SUPA1.3 Support Package Draft 3 Prepare the third version of the package to be used to Henry Kiku CA157000
support the magical devices version 3 production
system.
SUPA1.4 Support Package Final Prepare the final version of the package to be used to Henry Kiku CA158000
support the magical devices version 3 production
system.
SUPS1 Phase Support Transition support to the operations teams. Henry Kiku CA159000
SUPS1.1 Phase 1 Support Transition Transition support of the first production line from the Henry Kiku CA160000
development team to the operations support team.
SUPS1.2 Phase 2 Support Transition Transition support of the second production line from Henry Kiku CA161000
the development team to the operations support team.
SUPS1.3 Phase 3 Support Transition Transition support of the third production line from the Henry Kiku CA162000
development team to the operations support team.
PM1 Project Management Establish the project management office to manage Charles CA163000
the project as it progresses through execution and Wallace
closing, hold a kick-off meeting to coordinate all
members of the project, manage the risk budget, and
conduct the activities required to successfully close out
the project.
PMA1 Project Management Establish the project management office to manage Charles CA164000
Activities the project as it progresses, and hold a kick-off Wallace
meeting to coordinate all members of the project.
PMA1.1 Project Management Office The project manager, project scheduler, and project Charles CA165000
coordinator for the entire project. Wallace
PMA1.2 Kick-off Meeting Assemble the full team to review the project plan, Charles CA166000
answer any questions, identify any unknown issues, Wallace
conduct some team building, and set a coordinated
foundation for the rest of the project. As per the risk
management plan, 70% of the anticipated requirement
for Magic Dust will also be procured on the first day of
the project.

DeeplyPracticalPM.com Page 84/89


MDV3 Project Management Plan
WBS ID Work Breakdown Description Owner Cost
Structure Deliverable Account
PMRB1 Risk Budget Manage the risk budget to minimize the risks to the Charles CA167000
project budget and schedule performance. Wallace
PMRB1.1 Risk Buffer Provide a risk buffer of time and cost to protect the Charles CA168000
pilot and rollout dates once the project plan is Wallace
approved.
PMC1 Project Closure Conduct the activities required to close out the project. Charles CA169000
Wallace
PMC1.1 Project Closure Readiness Review the status of all previous elements of the Charles CA170000
Review project, and assure readiness for project closure. Wallace
PMC1.2 Final Procurements Closure Review the production line rollouts, support, and all Charles CA171000
remaining open procurements, resolve any outstanding Wallace
issues, and conduct formal closure.
PMC1.3 Lessons Learned Meeting Review all lessons learned documentation collected Charles CA172000
during the project, conduct a final lessons learned all Wallace
team meeting, and assemble a final set of lessons
learned.
PMC1.4 Lessons Learned Report Prepare a final lessons learned report, send it to all Charles CA173000
stakeholders, and flow recommended actions to the Wallace
relevant parts of the organizations.
PMC1.5 Project Final Report Prepare a project final report, documenting what Charles CA174000
happened with scope, time, cost, the business case, Wallace
major risks, major lessons learned, and
recommendations for next steps.

DeeplyPracticalPM.com Page 85/89


MDV3 Project Management Plan

Appendix C - Project Issues List Format

See the DPPM section “Monitoring & Control: The Weekly Heartbeat”.

Also see the DPPM template “Project Issues List - Template”.

For convenient reference, this appendix provides a copy of the Project Issues List format used for
the coordination of the Weekly Issues Status Meeting described in Section 9.1 – Weekly Issues
Status Meetings. The Project Issues list shall track the issue name, status, lead, and expected
resolution due date for each issue. This Microsoft Word table format is easily sortable with the
Layout / Sort command after any additions or updates to put the issues in order by Lead / Due
Date or Due Date / Lead as desired.

-----

Project ABC - Issues List

Issue Status Lead Due


Space Shortage Converting meeting room 5 to working area Anderson 2050-01-15
with desks.

Use:

* Add rows for new items as needed, and then collect together by Lead or Due Date with the
menu item Table / Sort.

* Enter dates in format YYYY-MM-DD so the Layout / Sort command works consistently.

DeeplyPracticalPM.com Page 86/89


MDV3 Project Management Plan

Appendix D - Monthly Project Report Format

See the DPPM section “Monitoring & Control: One Page Monthly Report”.

Also see the DPPM template “Project Monthly Report - Template”.

This appendix provides the format of the one page report to be used for the monthly project
review meetings in Section 9.2 – Monthly Project Review Meetings.

An example of the one page report can be found below. The top left quadrant provides a Gantt
schedule snapshot showing the current status of scope on schedule. The top right quadrant
provides status on the current cost performance, and for the MDV3 project shall include the
current Earned Value metrics. The bottom left quadrant provides the current status of the top
three issues and risks. And the bottom right quadrant provides any relevant information on the
current status of the customer groups.

Additional information on project performance shall also be provided to the monthly review board
as required and on request. A copy of the current risk register will usually also be available for
review.

G Scope & Schedule R Cost Y


Milestone CPI SPI

Milestone 1 0.92 0.81


Milestone 2 0.94 0.84
Milestone 3 0.86 0.86
:
:
:

(Any cost data avail; this example uses earned value info.)

Total 0.94 0.88


BAC = 7.4M EAC = $7.8M ETC = $3.2M VAC = $0.4M
Issues Customer

* Major issues, top three maximum, their status, and any


assistanc e required.
* The end-user of the project, whatever is relevant, anything
* ... on their mind, the status of user reviews, any satisfaction
metric s, any assistance required.
* ...
* ...
Risks
* ...
* Major risks, top three maximum, their status, and any
assistanc e required. * ...

* Risk register can be on hand as bac kup if requested. * ...

* ...

DeeplyPracticalPM.com Page 87/89


MDV3 Project Management Plan

Appendix E - User Review Template

See the DPPM section “Monitoring & Control: User Reviews”.

Also see the DPPM template “User Review - Template”.

For convenient reference, this appendix provides a copy of the review template used for the user
review process summarized in Section 10.1.2 – Formal Peer Reviews.

-----

User Review: [Deliverable ABC Draft 1]

Issue User Project Sponsor


Priority Team Decision
Priority
Add this... 1 1 1
Change this... 1 2 1
Remove that... 1 1 2
Enhance that... 1 1 1
Add this... 2 2 2
Remove that... 2 2 2
Add that... 2 2 3
Change this... 3 3 3
Enhance that... 3 3 3

Priorities:

1 = Essential to project objective, should be analyzed for impact if this is the final sponsor
decision.
2 = Good idea, but recommended for next project or phase.
3 = Record for later investigation.

DeeplyPracticalPM.com Page 88/89


MDV3 Project Management Plan

Appendix F - Change Request Form

See the DPPM section “Monitoring & Control: Managing Scope”.

See the DPPM template “Change Request - Template”.

For convenient reference, this appendix provides a copy of the formal Change Request form used
for the process summarized in Section 12 - Change Control Process.

-----

Change Request

Instructions: This form must be completed for any requested change to any baselined and
approved project element, including scope, schedule, budget, risk budget, or project deliverables,
no matter how minor, and submitted through the Project Manager for proper consideration of all
the impacts and communications with all affected parties.

Identification
Project:
Requester:
Date Of Request:
Requested Change
Change:
Reason / Benefit:
Known Impacts
Deliverables:
Requirements:
Contracts:
Schedule:
Cost:
Risks:
Other:
Alternatives & Options
Alternatives:
Options:
Sign Off
Requester:
Date:

DeeplyPracticalPM.com Page 89/89

You might also like