PREPARED BY- Quality team

CHECKLIST FOR BITUMEN WATERPROOFING.

PROJECT NAME- DATE-

SR ACTIVITY TO BE DONE ACCEPTANCE OBSERVATION


NO CRITERIA WITH
DEVIATION

A PROCEDURE BEFORE FIXING


1 Is the surface cleaned/grinding work done?

2 Are tie rod holes filled with CNS 50 chemicals?

3 The honeycomb and rough surface are cleared


with Gp2 chemical
4 Cracks repair chemicals need to be applied over
the vertical surface. ( Fosroc sp50)
5 1st coat of chemical needs to be applied
horizontally. (Dr. Fixit pidifin 2k)
6 2nd coat of chemical needs to be applied
vertically. (Dr. Fixit pidifin 2k)
7 The primer chemical single coat needs to be
applied. (Tikki drum S)
8 Is a bitumen sheet applied? (2mm thickness)

9 Are air voids removed from the bitumen sheet?

10 Is brick size checked? (190*90*90mm)


11 Is brick work mix is approved? (1:4) ( Dr. Fixit
101-200ml)
12 Is brick work is done overall periphery over Raft
and wall joint?
CONTRACTOR- SITE ENGINEER- QA/QC ENGINEER- PROJECT MANAGER-