1.00 38-40mm (1-1/2") Cement concrete (1:2:4) Screeding and 3mm Punning (1:1) with floor hardener 3kg/10sq.

ft
Rate analysis for 10 sq. m

SN Source Particulars Qty Unit Rate Amount Total Amount


Screeding and Punning 10.00 Sq-m 376.60 3,766.00
a Labor 4,519.20
Chipping 10.00 Sq-m 75.32 753.20
Cement 0.19 MT 14400.00 2,736.00
Sand 0.18 Cu-m 3708.60 667.54
b Materials 6,900.41
12mm Aggregate 0.36 Cu-m 3885.20 1,398.67
Floor hardener(Sika or Equivalent) 32.28 Kg 65.00 2,098.20

Actual Rate 11,419.61


Rate per sq.m 1,256.16 Overhead and profit 10% 1,141.96
Rate per sq.ft 116.74 Total 12,561.57

2.00 Granite 230/Sq-ft


Rate for 1 Sq-Ft
SN Source Particulars Qty Unit Rate Amount Total Amount
Granite Fitting 1.00 Sq-ft 80.00 80.00
a Labor 90.00
Chipping 1.00 Sq-ft 10.00 10.00
Granite 1.1 Sq-ft 230.00 253.00
b Material Mortar 1 Sq-ft 70.00 70.00 328.00
Grout 1 Sq-ft 5.00 5.00

Real rate 418.00


Overhead and profit 10% 41.80
Total rate 459.80
Rate per sq.ft 459.80

Single Moulding 65.00 R-Ft

Grooving 25.00 R-Ft

Estimated Granite Quantity


Staircase 1,300.00 Sq-Ft
Parapet Top/Window Sill 1,100.00 Sq-Ft

Total 2,400.00 Sq-Ft