Professional Documents
Culture Documents
Black Eyed Peas III
Black Eyed Peas III
Prede- Time t
Activity Description
cessor/s (days)
A 16 Process permits
B A 10 Organize team
C B 18 Book performers
D A 24 Reserve venue
E C 20 Schedule rehearsals
F C 12 Advertise
G D,F 22 Sell tickets
H D 8 Subcontract staging
I E,G,H 14 Conduct & evaluate concert
1 2 3 4
6 7 8
1 2 3 4
6 7 8
Time Cost Crash Critical Crash Time Crash Cost Time t (days)
Activity (days) ($000)
Allowed Increase Cost/Day Path? Normal Crashed
A
B
C
D
E
F
G
H
I
Total (Critical Path)
Col\Row B C D E F G
116 Prede- Time t (days) Cost ($000)
Activity
117 cessor/s Normal Crashed Normal Crashed
118 A 16 14 13 15
119 B A 10 9 17 20
120 C B 18 17 10 12
121 D A 24 22 16 18
122 E C 20 18 11 15
123 F C 12 11 15 18
124 G D,F 22 20 12 14
125 H D 8 5 14 20
126 I E,G,H 14 13 14 15
127 Due Date (days) 86
Col\Row B C D E F G H
134 Time Cost Crash Crash Time Crash Cost Slack
Activity (days) ($000) (Allowed)
135 Allowed Increase Cost/Day
136 A 2 2 1 2 2 0
137 B 1 3 3 0 0 1
138 C 1 2 2 1 2 0
139 D 2 2 1 0 0 2
140 E 2 4 2 0 0 2
141 F 1 3 3 0 0 1
142 G 2 2 1 2 2 0
143 H 3 6 2 0 0 3
144 I 1 1 1 1 1 0
145 Total 6 7 9