226 Mushangwa 2nd street Extn

Harare Zimbabwe
+263780712276
www.capevalley.co.zw
info@capevalley.co.zw
WARNING LETTER FOR NON
COMPLIANCE OF CONTRACT

Date 29 August 2023

2b Bryanstone Close
Greendale
Harare

Dear T. Majuru for MKM Construction

It has come to our attention that the project, Unit 9 & 10 – Pagomo which was
due to finished foundation slab work on the 31st of August 2023 has been delayed
till an unknown date. This delay has caused us great inconvenience and has
resulted in additional costs. See current project overview and previous POW
attached.

We would like to remind you that as per the terms of our contract (section 10 sub-
section 10.1.1) timely completion of the project is of utmost importance. The delay
in the completion of the project may lead to termination under (section 12) of your
contract. We had placed our trust in your ability to complete the project within the
agreed timeframe, which unfortunately has not been met.

We expect all contractors working with us to be fully committed to meeting the


project deadlines and fulfill their contractual obligations.
We are therefore issuing you a warning letter regarding the delay in the project
completion and demand that you take corrective measures immediately to expedite
the completion of the project.
226 Mushangwa 2nd street Extn
Harare Zimbabwe
+263780712276
www.capevalley.co.zw
info@capevalley.co.zw
WARNING LETTER FOR NON
COMPLIANCE OF CONTRACT

We expect the project to be completed by the new deadline without further delay.
Provide a revised Gantt chart on the remaining stages to completion within 24hrs
upon receiving this notice

We urge you to take prompt action and ensure that such a delay does not occur in
the future. We intend to maintain a good working relationship with you, but we
require your full cooperation to ensure that all projects are completed on time.

Signature
Eng. P. P Simango Cc Mr. I Chakuchichi (Technical Director)
CAPEVALLEY CONSTRUCTION COMPANY (PVT) LTD
PROJECT OVERVIEW % COMPLETE
Status for all top-level tasks. To see the status for subtasks, click on the chart and update the
outline level in the Field List.

100%
WED 2/8/23 - FRI 1/9/23 90%
80%
% COMPLETE
70% 63%

63%
60%
50%
40%
30%
20%
MILESTONES DUE 10%
Milestones that are coming soon.
0%
Name Finish STRATHAVEN UNIT 9 & 10 CONSTRUCTION

LATE TASKS
Tasks that are past due.

UNIT 9 & 10 Name

INSPECTION
Start

Fri 11/8/23
Finish

Fri 11/8/23
Duration

1 day
% Complete

0%
Resource
Names

Building

MKM
Inspectorate

BRICK WORK Thu 17/8/23 Wed 23/8/23 5 days 90% MKM

INSPECTIONS Thu 24/8/23 Thu 24/8/23 1 day 0% Structural


Engineer
,Building
Inspectorate

BACKFILLING AND Thu 24/8/23 Mon 28/8/23 3 days 0% MKM


COMPACTION

MESH FIXING Tue 29/8/23 Tue 29/8/23 1 day? 0% MKM


ID Task Task Name Duration Start Finish 30 Jul '23 6 Aug '23 13 Aug '23 20 Aug '23 27 Aug '23 3 Sep '23
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 STRATHAVEN UNIT 9 & 10 23 days? Wed 2/8/23 Fri 1/9/23
CONSTRUCTION
2 PRELIMINERIES 5 days Wed 2/8/23 Tue 8/8/23
3 CONTRACT 1 day Mon 7/8/23 Mon 7/8/23 MKM & CC
AGREEMENT AND
4 MOBILIZATION 1 day Tue 8/8/23 Tue 8/8/23 MKM
5 PROCUREMENT OF 1 day Wed 2/8/23 Wed 2/8/23 CC
MATERIALS
6 SUBSTRUCTURE 23 days? Wed 2/8/23 Fri 1/9/23
7 CLEARING 1 day Wed 2/8/23 Wed 2/8/23 TLB
8 SETTING OUT 1 day? Wed 9/8/23 Wed 9/8/23 MKM
9 EXCAVATIONS 1 day? Thu 10/8/23 Thu 10/8/23 MKM
10 TRIMMING AND LEVELLING
1 day? Fri 11/8/23 Fri 11/8/23 MKM
11 COMPACTION 1 day? Wed 9/8/23 Wed 9/8/23 MKM
12 INSPECTION 1 day Thu 10/8/23 Thu 10/8/23 Structural Engineer
13 INSPECTION 1 day Fri 11/8/23 Fri 11/8/23 Building Inspectorate
14 FOOTING 3 days Mon 14/8/23Wed 16/8/23 MKM
15 BRICK WORK 5 days Thu 17/8/23 Wed 23/8/23 MKM
16 INSPECTIONS 1 day Thu 24/8/23 Thu 24/8/23 Structural Engineer ,Building Inspectorate
17 BACKFILLING AND 3 days Thu 24/8/23 Mon MKM
COMPACTION 28/8/23
18 MESH FIXING 1 day? Tue 29/8/23 Tue 29/8/23 MKM
19 TUBING & PIPE LAYING1 day? Wed 30/8/23Wed 30/8/23 MKM
20 CONCRETE SLAB 2 days Thu 31/8/23 Fri 1/9/23 MKM

Task Project Summary Manual Task Start-only Deadline

Project: UNIT 9 & 10 POW Split Inactive Task Duration-only Finish-only Progress
Date: Wed 30/8/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1