DAILY PROJECT UPDATE APRIL 19, 2023

Fence
• On-going stone cladding inside
• Automated sliding gate – P 630k

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Firepit contour

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Firepit
• Roof – delayed delivery of materials
(flashing)
• On-going glass measurement for
quotation

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Pavement
• On-going stone cladding

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Boathouse
• On-going installation of bamboo
bracing
• On-going fabrication of gates

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

PVC vertical blinds @ office

Plain – P 90/sqft

Corrugated curve – P 95/sqft

FOXBRIDGE CONSTRUCTION Curve w/ design – P 116/sqft BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

PVC vertical blinds @ office

Panel 3
Panel 2

Panel 4
Panel 1

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Curtains @ bedroom

Side panel block-out Sheering curtain

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE APRIL 19, 2023

Curtains @ bedroom

Room 4
Combi blinds

Room 3 & 5
Side panel block-out

FOXBRIDGE CONSTRUCTION BINTUAN, CORON