DAILY PROJECT UPDATE MAY 26, 2023

Retaining wall @ side fence


• On-going concrete pouring

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE MAY 26, 2023

Fence
• On-going stone cladding @
main fence
• Possible inspection date for
motorized gate: June 6

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE MAY 26, 2023

Landscape – grass installation @ front area

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE MAY 26, 2023

Landscape – grass installation @ front area

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE MAY 26, 2023

Boathouse
• On-going installation of
bamboo bracing
• On-going fabrication of gates
• Remaining bamboo poles to
be installed: 6 pcs

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


DAILY PROJECT UPDATE MAY 26, 2023

Procurement & delivery updates


No. Item Status
1 2 units ATV processing for refund

2 Water closet replacement (room 1) installed

3 Roof shingles for utility house installed

4 Materials for finishing, painting delivered on site

5 Landscape grass @ front installed

6 Electric winch ETA on site: May 28


on-going fabrication;
7 Bi-fold doors, utility house door
possible delivery end of May
on-going fabrication;
8 Attic ladder (room 1)
possible delivery end of May
9 Motorized main gate processing

10 Tools cabinet for boathouse ETA on site: June 2


vendor still completing orders;
11 Speedboat motor
ETA on site: 1st – 2nd week of June
FOXBRIDGE CONSTRUCTION BINTUAN, CORON