Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

zzzz ENERGY

zzzzz ENERGY LIMITED


SITE VISIT REPORT

FOR
Sectional Replacement Of W43s Flow-line
Location: Cawthorne Channel 3
Date Of Visit: 16/05/2024
Purpose Of Visit
The joint site visit aims is to inspect, scope and propose appropriate remedial measures for the
leakage of W43s flow line when contracted.

NNPC Participants
1. xxxxxx

zzzz Energy
1. xxxxxxx

Findings/Observations
1. 2nos points along a section of W43s flow line has a visible leak.
2. The leak is due to corrosion attack.
3. ICs connection was also seen at some point on the W43s line.

Recommendations
We recommend that the followings should be considered;
1. The leak sections should be replaced.
2. New materials should be use for installation after replacement before hook-up.

Work Scope/activities
 Mobilization Equipment/Personnel/Materials to Site.
 Bush clearing along ROW.
 Excavation work
 Depressurization and isolation
 Unbolting and bolting of flush header.
 Flushing of line pipe.
 Cutting, grinding and welding.
 Radiography of welded joints.
zzzz ENERGY
 Hydrotesting of line.
 Sleeving of welded joints.
 Lowering and backfilling of trench
 House-keeping and demobilization.
MATERIALS

S/N Description of materials/Equipment Quantity


1 4” sch. 40 PE coated pipe 8nos
2 7/8”x145mm stud bolt and nut 32nos
3 4”x600# SPW gasket 4nos
4 3/4"x125mm stud bolt and nut 32nos
5 3”x600# SPW gasket 3nos
6 Canusa shrink sleeves 12nos
7 Swamp buggy 1no
8 Lay barge 1no
9 Material barge 1no
10 Thug boat 1no
11 Crew boat 1no
12 Welding machine 2nos

Conclusion
The work can be executed successfully without shutting down the facility.

Name:
Designation:
Signature:

You might also like