Cawthorne 3 - W43s Site Visit Report.
Cawthorne 3 - W43s Site Visit Report.
FOR
Sectional Replacement Of W43s Flow-line
Location: Cawthorne Channel 3
Date Of Visit: 16/05/2024
Purpose Of Visit
The joint site visit aims is to inspect, scope and propose appropriate remedial measures for the
leakage of W43s flow line when contracted.
NNPC Participants
1. xxxxxx
zzzz Energy
1. xxxxxxx
Findings/Observations
1. 2nos points along a section of W43s flow line has a visible leak.
2. The leak is due to corrosion attack.
3. ICs connection was also seen at some point on the W43s line.
Recommendations
We recommend that the followings should be considered;
1. The leak sections should be replaced.
2. New materials should be use for installation after replacement before hook-up.
Work Scope/activities
Mobilization Equipment/Personnel/Materials to Site.
Bush clearing along ROW.
Excavation work
Depressurization and isolation
Unbolting and bolting of flush header.
Flushing of line pipe.
Cutting, grinding and welding.
Radiography of welded joints.
zzzz ENERGY
Hydrotesting of line.
Sleeving of welded joints.
Lowering and backfilling of trench
House-keeping and demobilization.
MATERIALS
Conclusion
The work can be executed successfully without shutting down the facility.