WEEKLY PROJECT UPDATE SEPTEMBER 20, 2023

OUTSIDE MAIN BUILDING – SIDE FENCE


• Plastering outside – on-going (completion: today)
• Installation of metal bars – completed
• Installation of lighting – completed

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


WEEKLY PROJECT UPDATE SEPTEMBER 20, 2023

OUTSIDE MAIN BUILDING – MAIN FENCE


• Stone cladding – on-going
• Installation of lighting– on-going
• Welding works – completed

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


WEEKLY PROJECT UPDATE SEPTEMBER 20, 2023

FIREPIT ROOF
• Painting @ bamboo roof

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


WEEKLY PROJECT UPDATE SEPTEMBER 20, 2023

INSIDE MAIN BUILDING – ROOM 2 TOILET


• Application of waterproofing, etc.
• 24-hr leak test – completed, no leaks
• Installation of tiles – completed
• Direction of water flow to the floor drain

MATERIALS DELIVERY:
No. Item Status
1 Starlink Installed and functional on site
2 Vertical blinds (office) Delivered on site
3 Other SDP lights ETA on site: Sept. 23
4 Mini ref (collab kitchen) For payment
5 Tiles (shower area @ BH) For payment
6 Cushion For payment
FOXBRIDGE CONSTRUCTION BINTUAN, CORON
PROPOSED BOAT RAMP SEPTEMBER 2023

Straight line projection on


this side up to 16m only
due to intersection w/
bamboo fence of Hikari

Straight line projection up


Straight line projection to 16m only due to
(35m from boathouse) intersection w/ bamboo
fence of Hikari

FOXBRIDGE CONSTRUCTION BINTUAN, CORON


PROPOSED BOAT RAMP SEPTEMBER 2023

Option 1 Option 2
• Yellow block – 2.4m length straight projection (existing)
• Yellow block – 12m length straight projection (extended
• Red block – approx 38m angled ramp up to mangrove
width to accommodate trailer approach)
corner (extended width to accommodate approach)
• Orange block – location of 1st winch (existing)
• Orange block – location of 1st winch (existing)
• Purple line – boat landing/floaters
• Blue block – proposed location of 2nd winch
FOXBRIDGE CONSTRUCTION BINTUAN, CORON
PROPOSED BOAT RAMP SEPTEMBER 2023

ESTIMATED MATERIAL COSTS


• Additional winch and chain – PhP 277k
• Concreting works – PhP 962k

FOXBRIDGE CONSTRUCTION BINTUAN, CORON