PROJECT :COBBLESTONE

LOCATION :BARODA TOWN


Variation
Item Description Unit QTY Rate
1. EARTH WORK
1.1 back filling around masonry retain wall m3 150 148.58
1.2 Establishment of vertical alignment
1.2.1 Excavation to level and compaction
a. soft Material (Cut-fill) M3 200 100.32
1.3 Construction of Embankment
a. Borrow Material Production,Loading Unloading,Transporting,m3 210 206.252
Total Carried to Summary
2.MASONRY WORKS
2.1 50cm thick Masonry work along sides of the road m3 45 3429.68
2.2 Pointing stone masonry wall at one side m2 120 170.25
Total Carried to Summary
SubTotal
15%Vat
Grand Total With Vat 15%
Total Amount

22287

20064

43312.92
85,663.92

154335.6
20,430.00
174,765.60
260,429.52 0.15
39,064.43
299,493.95
timising dimension Description

1, Masonry work along sides wich need to support by short retain cobble stone slope
60 L=60m ,W=0.5m ,D=1.5m
0.5
1.5
45 m3
2, BACK FILLING around masonry wall
60 L=60m ,W=1m ,D=2.5m
2.5
1 150 m3
3 ,Borrow Material Production,Loading Unloading,Transporting, Spreading and Compacting Using Dump
100 L=100m ,W=7m ,D=0.3m
7
0.3
210 m3

4.Excavation to level and compaction


100 L=100M,W=2M&D=1M
2
1 200 m3
5. Pointing stone masonry wall at one side
60 L=60m d=2.5m
2 120 m2