Final Payment 3ffaa 2016 Sirefame
Final Payment 3ffaa 2016 Sirefame
We certify that the contractor is know entitled to the sum of birr 1,026,413.81 (One miliyon, twenty six thousand and four hundred thirteen 81/100 )
Birr only
Contractor:- Kadir,mohammed FI
Sharikoota DATE OF MESUREMENT 22/9/2016E.C
Location: Goroo Gutuu ,Berooda twon
SUMMERY OF WORK
Item no Description Excoueted Amount
Contract Amount previous Work This month Work Total to date
1 EARTH WORK 414,178.08 390,488.28 23689.80 414178.08
2 428400.00
Red Ash / dire dawa 428,400.00 358,428.00 69972.00
3 Cobble Stone 1,461,996.00 1,223,203.32 238,792.68 1,461,996.00
4 Cobble Stone Paving 180,000 150,600.00 29,400.00 180,000.00
5 Filling Void by fine aggregete foe 00size 158,400.00 132,528.00 25,872.00 158,400.00
6 Curb Stone 1,315,926.00 1,050,303.90 265,622.10 1,315,926.00
8 Ford 40,642.08 - 40,642.08 40,642.08
7 Masonry Work 102,890.40 - 102,890.40 102,890.40
………………………………………….. ……………………………
BOQ OF BARODA ROAD OF COBBLESTONE AND MASONARY WORK
Project: Cobblestone
Cilent:- Berooda Administration office
Location: Beroda Town
Contractor :- Waldaya Kadir ,Mohammeed fi sharkota
SUPERVISOR:- Eng Yasin . M
Amount of Work
NODescription Contract
UNIT Contract Qty Executed Qty RATE Excuted Amount
Amount
EARTH WORK
1
clear the site to remove all un wanted gravel and soil material 141498
from both side of road 4200 4,200.00 33.69 141,498.00
1.2 trench excavation depth not exceeding 1.5m in ordinary soil M3 60 60.00 317.83 19,069.80 19069.8
1.3 Enginer M3
36 36.00 44.73 1,610.28 1,610.28
1.4 Road surface shall be compacted by hand compactor M2 3600 3,600.00 70.00 252,000.00 252,000.00 0
Total Carried summary 414,178.08 414,178.08
2 Red Ash / dire dawa
supply and spread red ash or dire dawa sand to level of 5 to 7 cm
base and surface shall be well compacted then base course of fine
crashed aggregate size from stone crusher site ,keeping the design
slope so as to enable cobblestone paving following the slope . M3 252 252 1,700.00 428,400.00 428,400.00
3 Coblestone
Transportand fix 15*25cm shaped curb stones ,30to 70cm long ,at
every 15m interval across the walkway pavement and side
walk ,along both sides of the road with a cement mortar base of
1:4mix and backed with C-15 concrete on the external sides of the
road and crushed aggregate bucket , plasterer knife,and price
include loading cost, Ml 1620 1620 812.30 1,315,926.00 1,315,926.00
7 Ford
Masonary work
25cm thick stone hard core m2 30 30 484.34 14,530.20 14,530.20
concrete C-20 works 10cm thick Ground slabs m3 3 3 8,703.96 26,111.88 26,111.88
Total Carried summary 40,642.08 40,642.08
8 Masonary retain wall
50cm thick masonary work along sides of the road with a cement
mortar M3 30 30 3,429.68 102,890.40 102,890.40
ALL TOTAL CARRIED SUMMARY 4,102,432.56 4,102,432.56
VAT 15% 615,364.88 615,364.88
GRAND Total With Vat 15% 4,717,797.44 4,717,797.44
For Contractor For Client For Supervisor Approved by:-
Name:_____________________ Name:_____________________ Name:____________________Name:_____________
A. SUB STRUCTURE
4200.00 M 2
1.2 60
1 60.00m3
1 1,2. Excavation trench of side work masonary for cobble stone project
60.00
1.3 0.6
1 36m3
1.3. Cartaway excass soil material
1.4 600.00
6.00
3600.00m2 1.4. Road surface compact by hand compactor
600.00 2/ Supply and spread red ash or dire dawa sand to level of 5 to 7 cm base
2 6.00
0.07
252.00m3
3/Supply Cobbelstone and Stone made of basaltic black hard.
3 600.00
6.00 3600.00m2
0.04
144.00m3
6/ Curb stone
6 600.00
2 1440.00
M
6.00
30 180ml
1620.00
7./ Masonry work along sides wich need to support by short retain cobble stone slope
7 60.00 length
1 Depth
0.5 width
30m3
0.1 3m3
BOQ
Project: Cobblestone
Cilent:- Berooda Administration office
Location: Beroda Town
Waldaya
Contractor :- Kadir ,Mohamm
SUPERVISOR:- eed
EngfiYasin
sharkota
.M
Variation
1 back filling around masonry retain wall m3 150 148.58 22287
1, Masonry work along sides wich need to support by short retain cobble stone slope
60 L=60m ,W=0.5m ,D=1.5m
1 0.5
1.5 45
140 m3
pointing stone masonry wall at one side
60 L= 60M d 2.5m
5 2 120 m2
pacting Using Dumptruck, Tractor, Animal Cart, Labour and loaded from a