Professional Documents
Culture Documents
RZK NSS AVN IRF QAC 90101 00 E - EN - Signed
RZK NSS AVN IRF QAC 90101 00 E - EN - Signed
27-SEP-2023
REVISION:
Balaji Suresh
E 27-SEP-2023 Issued for review Mangeram Tyagi
Radhakrishnan Balakrishna
Balaji Suresh
D 20-JULY-2023 Issued for review Mangeram Tyagi
Radhakrishnan Balakrishna
Balaji Suresh
C 28-MAR-2023 Issued for review Mangeram Tyagi
Radhakrishnan Balakrishna
Issued for Inter Discipline Balaji
B 16-MAR-2023 Mangeram Tyagi Sadha Baskaran
Review Radhakrishnan
Issued for Discipline Balaji
A 13-FEB-2023 Mangeram Tyagi Sadha Baskaran
Internal Review Radhakrishnan
Approvals:
Date: 27-SEP-2023
Signed:
Date: 27-SEP-2023
Sures
Digitally signed by Suresh
Signed: DN: cn=Suresh,
o=Neftestroiservice Ltd,
Date: ou=QA/QC Department,
h
email=rzk-
mgrqaqc@nss.kz, c=US
Date: 2023.09.30 15:50:01
+05'30'
HOLD RECORD:
Where a <HOLD> status has been included within the body of the document please indicate its location by
detailing the relevant page number.
REVISION HISTORY:
Specify significant changes from previous revisions of the document:
TABLE OF CONTENT
1. PURPOSE
2. SCOPE
4. ABBREVIATIONS.
9. VISUAL INSPECTION.
12. FUNCTIONAL TEST FOR VALVE - MANUAL OPENING / CLOSING OF THE SSSV, MV &
WV VALVES.
17. SIGNOFF
1. PURPOSE:
The document outlines the procedure for factory acceptance testing (FAT) of wellhead control
panels which serves for SSSV valves, MV valves, WV Valves & fusible plugs (Based on client
specification RZK-NSS-000-SDR-INS-00001-00-C.
2. SCOPE:
The scope is to carry out the FAT of the Wellhead Control Panel, broadly outlined as below:
The procedure is Typical for wellhead hydraulic panel 5+1 spares, the control and check activities
are related to the following project, Avanceon Project: Ref: F23-02-001.
4. ABBREVIATIONS:
The following abbreviations are used throughout this procedure:
BV Ball Valve.
HP High Pressure
LP Low Pressure.
MP Medium Pressure.
PM Pump / Motor.
PG Pressure Gauge.
FA Flame Arrester
FB Filler Breather.
NV Needle Valve.
PT Pressure Transmitter.
LS Level Switch.
HR Hydraulic Regulator.
PS Pressure Switch.
Finally - Check all the BV, NV, HR, PT & LT ☐ Visual As per approved
10.7 Check PID, RZK-NSS-AVN-PID-
and all the components fixed in panels are as
per PID. ENG-0001-00_0
NOTE 1:
CLOSING TIME DELAYS PROVIDED THROUGH THE FLOW CONTROL VALVE (F-FCV-01) IS
FOR LOGIC VERIFICATION PURPOSE ONLY, ACTUAL TIME DELAYS WILL BE SET DURING
THE COMMISSIONING STAGE OF THE RESPECTIVE WELL.
NO CRITERIA
SSSV MANUAL 10.1.1. Make sure the all the bulk heads are FOR THIS.
OPENING & properly connected with temporary
CLOSING THIS IS
pressure gauges to monitor the INTERNAL TEST
pressure at the outlet side. ACTIVITY.
OBSERVE MV
SUPPLY LINE
MV MANUAL 10.1.5. Pull the Handle Valve (MV-PB-02) to open PRESSURE
OPENING & the MV, observe the pressure gauge (PG- GAUGE PG-06
CLOSING
06) and shall read 340 barg in supply line. READS 340
BARG.
OBSERVE MV
10.1.6. Push the Handle Valve (MV-PB-02) to close SUPPLY LINE
the MV, observe pressure gauge (PG-06) PRESSURE
GAUGE PG-06
and shall reads 0 Barg.).
READS 0 BARG.
Client /
sl:no: Mode of Accepted criteria
Activity
inspection TPI sign
off.
After the completion of all tubing
assembly activities if no further activities
are required the equipment will be
cleared for the pressure testing.
Pressure gauges & chart recorders using
for the test should have a valid calibration
certificate as per specification or relevant
National / International Standards.
A minimum of two pressure gauges is
required for the test system. One pressure LP Header (Logic
Pressure) - 7 barg
gauge shall be on the test pump and the
MP Header
other(s) on the test system. Their accuracy (Medium Pressure)
shall be within 1 % of one another. - 340 barg
The test fluid shall be filled at the lowest HP Header (High
Pressure) - 2 barg
01 point in the system to minimize entrapped Visual
air. All vents shall be open during filling. 15 minutes –
After test pressure is reached and before above pressure x
1.1 times, all
the commencement of inspection of the tubing should
system, the isolation valve between the hold pressure
without any
test manifold and the system under leakage.
pressure test shall be closed and the test
pump disconnected.
During pressure test minimum 2 pressure
hold steps should be maintained to
stabilize the volume of test.
During depressurizing test line drop down
pressure shall be minimum 2 steps.
Pressure Test:
AVANCEON will provide the following services and equipment to perform the flushing process.
2. Requirements:
Prior to flushing:
Remove all relief valves and cap tubing
Cap all output bulkheads
Check calibration certificates of all equipment used.
5. Completion:
Note: All the field tubes shall be flushed before connecting to Avanceon panel to prevent the
contamination from field lines.
13. COMPLETION:
13.1. Isolate all the pressure connections to the panel bulkheads.
AVANCEON Representatives:
CLIENT Representatives: