Professional Documents
Culture Documents
WP Sectional
WP Sectional
DANGAN KERJA TANAH DAN TEMBOK PENAHAN DI PARCEL K2, BANDAR ENSTEK DAERAH SEREMBAN UNTUK TETUAN THP ENSTEK DEVELOPMENT SDN BHD.
ID WBS Task Name Duration Start Finish
Mar Apr May Jun Jul Aug Sep Oct Nov
1 1 Parcel K2 , Bandar enstek. 184 days Tue 16/4/24 Wed 16/10/24 Parcel K2 , Bandar enstek.
6 1.2.1 performance bond and insurance 184 days Tue 16/4/24 Wed 16/10/24
performance bond and insurance
7 1.3 site preparation and earthwork 166 days Tue 16/4/24 Sat 28/9/24 site preparation and earthwork
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Enstek Techpark 2, Package 13
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Master Work Programme
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Prepared By: GESB Verified By: JURUTERA BUDIMAN Approved By: THPED Page 1 of 1