WORK PROGRAM FOR SECTIONAL CADANGAN KERJA TANAH DAN TEMBOK PENAHAN DI PARCEL K2, BANDAR ENSTEK DAERAH

DANGAN KERJA TANAH DAN TEMBOK PENAHAN DI PARCEL K2, BANDAR ENSTEK DAERAH SEREMBAN UNTUK TETUAN THP ENSTEK DEVELOPMENT SDN BHD.
ID WBS Task Name Duration Start Finish
Mar Apr May Jun Jul Aug Sep Oct Nov
1 1 Parcel K2 , Bandar enstek. 184 days Tue 16/4/24 Wed 16/10/24 Parcel K2 , Bandar enstek.

2 1.1 milestone 184 days Tue 16/4/24 Wed 16/10/24 milestone

3 1.1.1 project start 0 days Tue 16/4/24 Tue 16/4/24


16/4
4 1.1.2 project finish 0 days Wed 16/10/24 Wed 16/10/24
16/10
5 1.2 Prelimineries Work 184 days Tue 16/4/24 Wed 16/10/24 Prelimineries Work

6 1.2.1 performance bond and insurance 184 days Tue 16/4/24 Wed 16/10/24
performance bond and insurance
7 1.3 site preparation and earthwork 166 days Tue 16/4/24 Sat 28/9/24 site preparation and earthwork

8 1.3.1 Site preparation 45 days Tue 16/4/24 Thu 30/5/24


Site preparation
9 1.3.2 Earthwork 166 days Tue 16/4/24 Sat 28/9/24
Earthwork
10 1.3.3 Temporary silt trap 7 days Mon 6/5/24 Sun 12/5/24
Temporary silt trap
11 1.3.4 Temporary pipe culvert 4 days Tue 23/4/24 Fri 26/4/24
Temporary pipe culvert
12 1.3.5 Earthdrain 30 days Tue 23/4/24 Wed 22/5/24
Earthdrain
13 1.3.6 check dam 25 days Wed 8/5/24 Sat 1/6/24
check dam
14 1.3.7 Silt fence 25 days Tue 30/4/24 Fri 24/5/24
Silt fence
15 1.4 Reinforced earth retaining wall 159 days Sat 11/5/24 Wed 16/10/24 Reinforced earth retaining wall

16 1.4.1 RE Wall works 140 days Sat 11/5/24 Fri 27/9/24


RE Wall works
17 1.4.2 V shape drain 15 days Thu 26/9/24 Thu 10/10/24
V shape drain
18 1.4.3 Turfing works 12 days Mon 23/9/24 Fri 4/10/24
Turfing works
19 1.4.4 1000mm (high) M.s Railing 24 days Mon 23/9/24 Wed 16/10/24
1000mm (high) M.s Railing
20 1.5 Reinforced Concrete Retaining Wall 158 days Mon 6/5/24 Thu 10/10/24 Reinforced Concrete Retaining Wall

21 1.5.1 Excavation work 80 days Mon 6/5/24 Wed 24/7/24


Excavation work
22 1.5.2 lean conc 88 days Mon 20/5/24 Thu 15/8/24
lean conc
23 1.5.3 200mm crusher run 88 days Mon 13/5/24 Thu 8/8/24
200mm crusher run
24 1.5.4 Base slab 78 days Mon 13/5/24 Mon 29/7/24
Base slab
25 1.5.5 wall concreting 93 days Wed 10/7/24 Thu 10/10/24
wall concreting
26 1.6 Brick retaining wall 170 days Tue 30/4/24 Wed 16/10/24 Brick retaining wall

27 1.6.1 excavation work 88 days Wed 22/5/24 Sat 17/8/24


excavation work
28 1.6.2 lean conc 141 days Wed 29/5/24 Wed 16/10/24
lean conc
29 1.6.3 200mm laying crusher run base 140 days Wed 29/5/24 Tue 15/10/24
200mm laying crusher run base
30 1.6.4 concreting brickwall base 170 days Tue 30/4/24 Wed 16/10/24
concreting brickwall base
31 1.6.5 Brickwork 164 days Tue 30/4/24 Thu 10/10/24
Brickwork
32 1.6.6 plastering work 165 days Sat 4/5/24 Tue 15/10/24
plastering work
33 1.7 as built drawing 2 days Sun 13/10/24 Mon 14/10/24
as built drawing
34 1.8 Site cleaning 2 days Tue 15/10/24 Wed 16/10/24
Site cleaning
35 1.9 Project finish 0 days Wed 16/10/24 Wed 16/10/24
16/10

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Enstek Techpark 2, Package 13
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Master Work Programme
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Prepared By: GESB Verified By: JURUTERA BUDIMAN Approved By: THPED Page 1 of 1