Project: WP5 - 2300 CLUBHOUSE STRUCTURAL WORKS, Hann Reserve Project

Location: Bamban (New Clark City), Tarlac


Subject: JOB HAZARD ANALYSIS – INSTALLATION OF FENCE
WORK ACTIVITY OSH HAZARD OSH OPORTUNITIES

1. Preparing to move Unidentified and/or unmitigated


YES
materials. hazards, or unsafe conditions.

Muscle strains, pulls and repetitive


motion injuries.

YES

2. FOUNDATION
Cuts / Bruises
PREPARATION

Backpain /
Bodyache

Slipping on descending/muddy YES


terrain; Trips on tree roots and
vines; Hot outdoor temperature.

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

3.) INSTALLATION OF
Backpain /
TEMPORARY GUIDE
Bodyache
CASING

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature.
YES
YES

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

Topple of tripod, Failure of winch


Cut of winch rope.
4.) DRILLING OF Fire from diesel,
PILE BOREHOLE operating engine. Soil
collapse inside the bore.
Environmental health hazard

Stack of tires on loose ground.


Sharp edge contact
High
noise during hammering /
pressurizing to insert the cone.
Flying object durig
hammering

YES

Backpain /
Bodyache

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature.

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

6.) FABRICATION OF Unidentified and/or unmitigated


STEEL CAGE hazards, or unsafe conditions.

Muscle strains, pulls and repetitive


motion injuries.

YES
YES

Cuts / Bruises

Fumes inhalation, Eloctrocution

Eye iritation

hand and skin alergies

7.) LOWERING OF
THE Backpain /
REINFORCEMENT Bodyache
CAGE

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature. YES

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

8.) CONCRETE Backpain /


PLACEMENT Bodyache

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature.
YES

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

9.) CONCRETING Hand laceration

Body pain

Slipping and tripping

Dust inhalation
Eye Irritation YES

Struck by struck against

Scattered materials
10.) EXTRACTION OF
TEMPORARY Struck by struck
CASING

back pain

Slipping and tripping YES

Heat exposure

Topple of tripod, Failure of winch


Cut of winch rope.
11.) DRILLING OF Fire from
STEEL CASING diesel, operating engine.
Soil collapse inside the bore.
Environmental health hazard

Stack of tires on loose ground.


Sharp edge contact
High
noise during hammering /
pressurizing to insert the cone.
Flying object durig
hammering

YES

Backpain /
Bodyache

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature.

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

Personnel hit by the movement of


the piling machine.
Working in live
areas.
12.) BORED PILING
Sling broken, load drop.
TEST
Slip, Trip & Fall.
Inclement
weather condition.
Fire & explosion

YES
Personnel hit by the movement of
the piling machine.
Working in live
areas.
Sling broken, load drop. YES
Slip, Trip & Fall.
Inclement
weather condition.
Fire & explosion

Personnel hit by the movement of


the piling machine.
Working in live
areas.
Sling broken, load drop.
Slip, Trip & Fall.
Inclement
weather condition.
Fire & explosion

13.) TOLERANCE OF
PILE INSTALLATION Backpain /
IN PILE Bodyache
FOUNDATION
CONSTRUCTION

Slipping on descending/muddy
terrain; Trips on tree roots and
vines; Hot outdoor temperature. YES

Muscle pains due to frequent


walking / standing.

Insect bites, animal bites, exposure


to bacteria and fungi.

Personnel hit by the movement of


the piling machine.
Working in live
areas.
14.) BOAR PILLING Sling broken, load drop. YES
Slip, Trip & Fall.
Inclement
weather condition.
Fire & explosion

Repetitive motion or other


15.) Housekeeping
ergonomic concerns

Heavy manual lifting/moving

YES

Nothing follows
STRUCTURAL WORKS, Hann Reserve Project
mban (New Clark City), Tarlac
ANALYSIS – INSTALLATION OF FENCE
OSH CONTROL MEASURES SEVERITY PROPABILITY RATING CRITERIA
Consider all potential hazards: weather, wet or slippery
conditions, overhead hazards, proximity to trails and/or visitor
2 2 4 NEGLIGIBLE
traffic patterns/volume, slope, loose footing, elevation, fatigue,
hazardous insects or plants, etc

Each employee should be provided training on the safe and


proper use of the most important, primary tool their bodies
(Strong, Alert, Focused, Energetic, or SAFE training). Proper
techniques of stretching, lifting, bending, moving, rolling rocks,
securing good footing, the importance of good nutrition and
hydration.

Each employee will be given time on the job to properly stretch


and warm-up before and during physical activity for a period of
2 2 4 NEGLIGIBLE
time deemed appropriate by the crew leader, or on-site
supervisor.

Employees will be encouraged to switch hands often and vary


the types of activities performed to limit exposure to repetitive
motion injuries.

The appropriate number of workers should be used to move


materials. This decision may vary between individuals.

Employees shall be taught on proper materials/equipment


handling. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection) + cotton
gloves

Proper standing and sitting posture shall be encouraged. Proper


lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self 2 3 6 MINOR
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection).

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm
and face&neck protection clothing

Proper standing and sitting posture shall be encouraged. Proper


lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection). 2 3 6 MINOR
2 3 6 MINOR

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm
and face&neck protection clothing
The tripod to be placed with sound ground condition.
The legs to be
secured properly to avoid topple.
Daily physical inspection to be carried out before starting
the boring works. Bentonite solution to be drain in
designated place only to avoid soil contamination.
Use of ppe (Safety shoes, gloves,hardhat, vest,
eye glass and dust mask.

CPT rig to be placed on sound ground or loose soil to be


compacted. Avoid to touch on sharp edge
of rig part during positing of penetrometer cone.
Use ear protection to avoid high noise for hammering.
Maintain safe distance of man power to
equipment/machine. Workplace must be
barricated and install appropriate signage.
Isolate the area for unauthorized entry.
2 3 6 MINOR
Proper standing and sitting posture shall be encouraged. Proper
lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection).

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm and
face&neck protection clothing

Consider all potential hazards: weather, wet or slippery


conditions, overhead hazards, proximity to trails and/or visitor
traffic patterns/volume, slope, loose footing, elevation, fatigue,
hazardous insects or plants, etc

Each employee should be provided training on the safe and


proper use of the most important, primary tool their bodies
(Strong, Alert, Focused, Energetic, or SAFE training). Proper
techniques of stretching, lifting, bending, moving, rolling rocks,
securing good footing, the importance of good nutrition and
hydration.

Each employee will be given time on the job to properly stretch


and warm-up before and during physical activity for a period of
time deemed appropriate by the crew leader, or on-site
supervisor.

Employees will be encouraged to switch hands often and vary


the types of activities performed to limit exposure to repetitive
motion injuries.
2 3 6 MINOR
The appropriate number of workers should be used to move
materials. This decision may vary between individuals.
2 3 6 MINOR

Employees shall be taught on proper materials/equipment


handling. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection) + cotton
gloves

Patos must be needed prior to start the work activities.


Proper training of all workers involved
to activity should be required.

Use of welding apron, welding gloves, face shield and wear of


long sleeves. Use of respirator mask to avoid fumes inhalation

use of safety gogles and proper wash your eyes if necesssary.

proper use of safety gloves and long sleeves, always wash your
hands after the work activity

Proper standing and sitting posture shall be encouraged. Proper


lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety 2 3 6 MINOR
jacket, hard hat, reflectorized vest, eye protection).

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm and
face&neck protection clothing

Proper standing and sitting posture shall be encouraged. Proper


lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection). 2 3 6 MINOR

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm and
face&neck protection clothing
HausekeepingProper posture of the body, observe manual
lifting, use of safety gloves.
Conduct of patos, toolbox meeting,proper coordination and
installed Signage(Observe manual lifting)
Hardhat, boots,safety gloves, safety shoes and reflectorized
vest
Housekeeping, watering, use of dust mask
wash eyes, use of safety glass 2 3 6 MINOR

observe of workplace, eliminate obstacles, use of hardhat and


always chin strap is on
Hausekeeping before and after work.
Conduct of patos prior to activity, toolbox meeting
Hardhat, boots,safety gloves, safety shoes and reflectorized
vest

Observe of workplace, eliminate obstacles, use of hardhat and


always chin strap is on

Proper postrure of the body, stretch the body before proceeding


to the activity
Hausekeeping, signage(slippery/tripping area), eliminate all
obstacles and proper use of safety shoes 2 3 6 MINOR

Temporary shelter, take abreak if necessary, drink of plenty


water

involve worker must be check the BP., assigned a first aider

toolbox meeting, patos prior to start the work activity


The tripod to be placed with sound ground condition.
The legs to be
secured properly to avoid topple.
Daily physical inspection to be carried out before starting
the boring works. Bentonite solution to be drain in
designated place only to avoid soil contamination.
Use of ppe (Safety shoes, gloves,hardhat, vest,
eye glass and dust mask.

CPT rig to be placed on sound ground or loose soil to be


compacted. Avoid to touch on sharp edge
of rig part during positing of penetrometer cone.
Use ear protection to avoid high noise for hammering.
Maintain safe distance of man power to
equipment/machine. Workplace must be
barricated and install appropriate signage.
Isolate the area for unauthorized entry.
2 3 6 MINOR
Proper standing and sitting posture shall be encouraged. Proper
lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety
jacket, hard hat, reflectorized vest, eye protection).

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm and
face&neck protection clothing

Pile machine & its operator should be certified. Banks man


should be available at the site to control the movement of heavy
vehicles/equipment.Keep away all unauthorized people during
movement of heavy vehicle/equipment.Be careful of nearby live
areas. Ensure Close HSE monitoring /supervision. Ensure
appropriate & inspected accessories being utilized for drilling.
Make sure that drilling bit is appropriately and correctly fixed
with safety locking pins. Keep away during the drilling operation

2 3 6 MINOR
Pile machine & its operator should be certified. Banks man
should be available at the site to control the movement of heavy
vehicles/equipment.Keep away all unauthorized people during
movement of heavy vehicle/equipment.Be careful of nearby live
2 3 6 MINOR
areas. Ensure Close HSE monitoring /supervision. Ensure
appropriate & inspected accessories being utilized for drilling.
Make sure that drilling bit is appropriately and correctly fixed
with safety locking pins. Keep away during the drilling operation

Pile machine & its operator should be certified. Banks man


should be available at the site to control the movement of heavy
vehicles/equipment.Keep away all unauthorized people during
movement of heavy vehicle/equipment.Be careful of nearby live
areas. Ensure Close HSE monitoring /supervision. Ensure
appropriate & inspected accessories being utilized for drilling.
Make sure that drilling bit is appropriately and correctly fixed
with safety locking pins. Keep away during the drilling operation

Proper standing and sitting posture shall be encouraged. Proper


lifting procedure shall be monitored.
Buddy-buddy system must be required

Employees shall be given a briefing on what to expect on the


worksite; Cliff areas shall be clearly identified and marked; Self
hydration is encouraged. Basic
(Safety shoes / boots, work trousers, long sleeves / safety 2 3 6 MINOR
jacket, hard hat, reflectorized vest, eye protection).

Proper standing and sitting posture shall be encouraged.


Breaktime rest shall be observed.
Employees shall be aware of different flora and fauna that may
be present on site and may pose threath to their health.
Basic PPE + wear arm and
face&neck protection clothing

Pile machine & its operator should be certified. Banks man


should be available at the site to control the movement of heavy
vehicles/equipment.Keep away all unauthorized people during
movement of heavy vehicle/equipment.Be careful of nearby live
2 3 6 MINOR
areas. Ensure Close HSE monitoring /supervision. Ensure
appropriate & inspected accessories being utilized for drilling.
Make sure that drilling bit is appropriately and correctly fixed
with safety locking pins. Keep away during the drilling operation

Perform a last minute risk assessment before performing any


material handling task.
Make sure to check the path of travel for any obstacles before
moving any materials.
Perform a proper warm up and stretch before performing any
2 2 4 NEGLIGIBLE
material handling task.
The PPE required for any material handling tasks are: Safety
glasses, appropriate gloves and appropriate non slip footwear.
Additional PPE may be required depending upon environment
conditions.

Nothing follows