Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

BERITA ACARA PT.

LAHAT PULAU PINANG BARA JAYA


PERHITUNGAN VOLUME Engineering Department
OVERBURDEN DAN BATUBARA Site Lubuk Betung, Merapi Selatan
Mine Engineer - Deni Pradesta
Tanggal 01 Nov - 30 Nov 2023 Mine Survey - Wahyu

Dibuat Oleh : Wahyu


Berikut hasil perhitungan Overburden dan Batubara dari Tanggal 01 Nov - 30 Nov 2023

1 Volume Batubara :
Coal Getting On Pit BCM - MT
Density Batubara (Bituminus) 1.3
Total Volume Batubara - BCM - MT

2 Volume Overburden :
Total Volume 01 Nov - 30 Nov 2023 37,135.670 BCM

Volume Material Volume Batubara


= 37,135.670 BCM - - BCM
= 37,135.670 BCM

3 Striping Ratio (SR) :


Volume Material (Overburden) Volume Batubara
= 37,135.670 BCM - MT
:
= SR ACT #DIV/0!
#DIV/0!
= SR TAR 4.9

4 Total Cut Volume OB (TARGET) 89,694.20 BCM


Total Cut Volume OB (ACTUAL) 37,135.67 BCM
Actual to Target - 52,558.53 BCM
Persentase Tercapai OB = 41.40% Persen
Total Cut Volume COAL (TARGET) MT
Total Cut Volume COAL (ACTUAL) - MT
Persentase Tercapai COAL #DIV/0! Persen

5 Survey VS Truck Count (OB & CG)


Survey OB 37,135.670 BCM
Truck Count OB 42,077.300 BCM
Selisih 12% Persen
Survey CG - MT
Truck Count CG MT
Selisih #DIV/0! Persen

6 Fuel Consumption
Solar Issued during the month for OB & Coal 41,634 Liter
Fuel Untuk Kegiatan
Penambangan di PIT 2
Fuel Ratio 1.12 Liter/BCM
Notes : 1. Fuel Ratio < 0.85
2. Pekerjaan TNB dibagian expose a telah ter cut oleh LPPBJ pada tanggal 19/11/2023 shift 2 sehingga perhitungan OB
yang telah dikerjakan di adjust berdasarkan truckcount LPPBJ sehingga didapatkan volume 385.44 bcm

Diukur dan Diolah Oleh : Diverifikasi Oleh: Diketahui Oleh:


Surveyor Mine Plan Engineer Dept head Engineering SPV Trainer Junior Engineering
PT Lahat Pulau Pinang Bara Jaya PT Lahat Pulau Pinang Bara Jaya PT Lahat Pulau Pinang PT Tritama Niaga Berjaya PT Tritama Niaga Berjaya
Bara Jaya

Wahyu Asdin Erwin Hafizurahman Dwi Saputra


Deni Pradesta Iwan S Sihombing

Diketahui Oleh: Diketahui Oleh:


Kepala Teknik Tambang Project Manager
PT Lahat Pulau Pinang Bara Jaya PT Tritama Niaga Berjaya

Joni Suherna Eko Bambang Istanto Nugroho


PT. LAHAT PULAU PINANG BARA JAYA
LAMPIRAN 1 Engineering Department
HASIL PERHITUNGAN VOLUME BY SURPAC Site Lubuk Betung, Merapi Selatan
Tanggal 01 Nov - 30 Nov 2023 Mine Survey - Wahyu

VOLUME BY SURPAC 6.3.2


Berikut hasil perhitungan Overburden Tanggal 01 Nov - 30 Nov 2023

VOLUME OVERBURDEN TNB PIT 2 SELATAN

DTM CUT AND FILL VOLUME REPORT

VOLUME BY SURPAC 6.3.2

VOLUME COAL TNB PIT 2 SELATAN

DTM CUT AND FILL VOLUME REPORT


PT. LAHAT PULAU PINANG BARA JAYA
LAMPIRAN 2 Engineering Department
HASIL SURPAC DAN ACTUAL LAPANGAN Site Lubuk Betung, Merapi Selatan
Mine Survey - Wahyu
Tanggal 01 Nov - 30 Nov 2023