PLUMBING

1. ALL WORK SHALL CONFORM TO ALL APPLICABLE BUILDING CODES.


2. GENERAL NOTES, SYMBOLS LIST, AND DETAILS ARE APPLICABLE TO ALL PLUMBING DRAWINGS.
3. ALL THE LAYOUTS ARE AS PER THE FINAL ARCHITECTURAL PLAN.
4. DRAINAGE MATERIAL SHALL BE PVC SCH 40 AND AS PER APPROVED MATERIAL SUBMITTAL
5. THE WATER SUPPLY PIPE SHALL BE PVC SCH 80 FOR COLD WATER AND CPVC FOR HOT WATER
SERVICES
6. HOT WATER PIPES ARE TO BE PROVIDED WITH INSULATION MINIMUM 9MM THICKNESS,
MATERIAL TO BE AS PER APPROVED SUBMITTAL
7. ALL THE MATERIAL SHALL BE AS PER APPROVED MATERIAL TECHNICAL SUBMITTAL
8. THE ELECTRIC WATER HEATER IS EXPOSED HANGING ON THE WALL UNLESS OTHERWISE NOTED.
9. THE SLOPE IN THE DRAINAGE PIPE IS AS PER SBC 701 I.E. 1% FOR ALL THE INTERNAL PIPES.
10. EASTERN TYPE W.C. TO INCLUDE P-TRAP IF NOT PROVIDED BUILT-IN
11. VENT PIPE IS TAKEN TO ROOF WITH VENT COWL PROVIDED AT TOP
12. ALL THE CEILING CLEANOUTS TO BE PROVIDED THE ACCESS DOOR FOR MAINTENANCE
13. NECESSARY SUPPORT TO BE PROVIDED FOR ALL THE PLUMBING SERVICES
14. MULTI-FLOOR DRAIN TO BE PROVIDED WITH A THRUST SUPPORT AT THE BOTTOM
15. THE ACCOMMODATION AC DRAIN TO BE CONNECTED TO THE MULTI-FLOOR DRAIN
16. A/C DRAIN WHERE FD IS NOT AVAILABLE TO BE DRAINED TO THE SOAK-AWAY PIT.
17. ALL THE PLUMBING FIXTURES ARE AS PER APPROVED MATERIAL SUBMITTALS
18. AT LEAST ONE ISOLATED VALVE IS TO BE PROVIDED IN EACH TOILET TO ISOLATE FROM OTHER
NETWORKS FOR MAINTENANCE
19. THE WATER SUPPLY PIPE IS SIZED AS PER SBC 701 BASED ON WSFU GIVEN IN THE CODES.
20. DRAINAGE PIPE IS SIZED BASED ON DFU GIVEN IN SBC 701

HVAC

1. THE HEAT LOAD CALCULATIONS ARE PERFORMED ON HAP SOFTWARE AS PER DESIGN CRITERIA
PROVIDED IN THE EMPLOYER’S REQUIREMENT
2. ALL THE AC EQUIPMENT TO PROVIDE HEAT AND COOL OPERATION
3. THE SELECTION OF THE EQUIPMENT TO BE DONE ON T3 CONDITIONS AND ARE CAPABLE OF
WORKING AT HIGH TEMPERATURE
4. THE REFRIGERANT PIPE SIZES TO BE AS PER THE MANUFACTURER'S RECOMMENDATIONS
5. THE PIPE INSULATION THICKNESS TO BE A MINIMUM 13 MM AND AS PER THE APPROVED
MATERIAL
6. THE CONDENSATE DRAIN TO BE PROVIDED WITH THE P-TRAP BEFORE CONNECTION TO THE
DRAINAE NETWORK
7. THE EXHAUST AIR IS AS PER ASHRAE 62.1 AND SBC 501 REQUIREMENTS
8. CDP PIPE MATERIAL SHALL BE PVC SCH 40
9. GI DUCTING WHERE APPLICABLE TO BE AS PER SMACNA STANDARDS
10. PACKAGE UNITS TO BE PROVIDED VIBRATION ISOLATORS