Professional Documents
Culture Documents
Construction Methodology - 15MB VCR Tank
Construction Methodology - 15MB VCR Tank
Construction Methodology - 15MB VCR Tank
CONSTRUCTION METHODOLOGY
2.0 SCOPE
2.1 This procedure covers the construction method and sequences in the .
CONSTRUCTION OF 15 MB VCR TANK.
.
3.0 REFERENCES
3.1 API 650 12TH Edition
3.2 Approved Construction Drawing
3.3 Project Specifications
4.2 SAFETY
4.2.1 Safety shall be a primary concern in the execution of the
works. A Safety Engineer will be mobilized to ensure Safety
Programs and Policies are being implemented. He shall see
to it that all workers are properly oriented with the hazards
of the work.
SAFETY PRECAUTIONS
c. Make sure that the load does not exceed the rated load
capacity of lifting devices.
d. Check electric chain blocks and hooks for defect. Give special
attention to chain/sling or any lifting device, which is added
to make certain it is secured.
4.2.3 All personnel involved in the erection process must wear proper
personal protective equipment and must be well oriented on safety
policies and procedures.
4.2.5 Advise all personnel working near the area that there will be an
erection approaching on site and isolate the area by installing
barricade or barrier to avoid from entering inside unless authorized
to conduct a work within a limited area.
0
Centerline
270 90
180
6.1.4 Welding shall start from the center and radiate towards the
circumference. Final weld line shall be welded after the
completion of the fillet weld on the shell plate to the bottom
plate.
6.2 SHELL PLATE ERECTION
6.2.1 Prior to erection, all marking such as shell plate main and
auxiliary circular line accessories orientation and other
markings which are to be projected towards the top of the
tank, shall be inscribed clearly on the bottom / annular
plates. After the installation of bottom and annular plates,
perform full welding on all annular butt joints and then
conduct radiographic testing 50% of annular radial joints
before fit-up of shell plates.
6.2.2 Locate each shell plate joints and accessories on the shell circular
line, at the same time; auxiliary reference line shall be mark
inside the circular line to check shell plate roundness.
6.2.3 Each plate shall be supported by straight channel temporarily
attached to shell, down diagonally to the bottom plate to
maintain the plumb ness. It will be removed as soon as the
second course has been installed and fitted – up.
IMPORTANT BRACE TO MAINTAIN
PLUMB NESS OF FIRST COURSE
6.2.4 After erection, fit – up of all vertical joints on first course shell plates
install strong back piece to prevent buckling before
commencing for full welding.
6.2.5 First course shell roundness, level and plumb ness shall be primarily
checked and adjusted within the tolerance stated on API
standard latest edition.
6.2.6 Once the first course shell plates finish the necessary inspection
intended for the tank. Perform full welding on all vertical
butt joints.
6.2.7 Full welding shall be carried-out using back-step method to prevent
distortion and other defects that will hamper to the integrity
of the tank. Make sure to follow approved Welding Procedure
Specification (WPS).
6.2.8 Conduct radiographic testing after all the vertical joints on first
course are completed to monitor and check the soundness
of welding.
6.2.9 Install strong back on the top of horizontal joints of the first course
shell plates.
6.2.10 Start fit-up of second course shell plates until it completed. Conduct
again the needed inspection as per API standard.
6.2.11 Then begin full welding of vertical joints from second course followed
by horizontal joints from first to second ring.
6.2.12 It is important to complete the full welding of the second course
6.2.13 Conduct radiographic testing again on the completed full welded
joints before erection of third course.
6.2.14 Same procedure shall be follow on the next succeeding shell plates
to be erected.
RADIOGRAPHIC TEST Required for shell plate butt – welds, annular plate
butt – welds, and flush type connections with butt –
weld. However, weld joints on bottom plates and
roof plates or for welds joining roof plate to top
angle, top angle to shell, shell to bottom and
appurtenances shall not require radiography.
DYE PENETRANT TEST Liquid penetrant examination is specified for the
tanks as per API 650 standard.
VACUUM TEST Vacuum box testing and examination is applicable
only to the joints of the following:
o Bottom plates
o Roof plates
HYDROSTATIC TEST This test is limited to water filling only.
DIESEL TEST This test shall be carried-out on the root-pass weld of
the internal portion of shell to annular joint. Diesel
fuel oil will be apply on the external portion of shell
to annular joints.
TESTING, INSPECTION AND REPAIRS
1. Prior to acceptance, all work activities shall be completed to the satisfaction
of the client’s inspectors or the client itself. The entire tank when filled with
product shall be secured and free from any leakages.
2. All rubbish and other temporary materials remained for sometime shall be
removed or dispose when the erection is completed. Erection group shall
leave the site in good condition and free from any obstructions.
INSPECTION OF WELDS
1. Butt Welds Radiographic film shall be reviewed and evaluated by
QC personnel and submitted to client’s inspector with proper and
complete document prior to weld acceptance. In addition, the
inspector may visually inspect the butt weld joint for possible cracks,
arc strike, excessive undercuts, surface porosity, and other defects.
2. Fillet Welds Dye penetrant tests, diesel fuel oil tests, leak test
and vacuum test, these are all applicable for testing of fillet weld
joint. Inspector shall perform visual inspection for possible crater
cracks. For welds applied on nozzles, manholes, cleanout opening
and any other permanent attachment, undercutting shall not exceed
1/64”.
3. The edges of all welds shall merge with the surface of the plate
without sharp angle and the maximum acceptable undercutting is
1/64”of the base metal form vertical joints shall not exceed 1/32”
depth for horizontal butt joint.
Full welding of circumferential joint between bottom to shell plates
shall be done after the erection of the third course shell plates.
All shell plate butt joint shall be accurately matches and retain in
position during welding operation. Misalignment in completed vertical
joints shall not exceed 10% of the thickness or 1/16” whichever is
larger.
Completed horizontal butt joints shall not project beyond the face of
the lower plate by more than 20% of the upper plate thickness
except that 1/16” projection is acceptable for upper plates less than
5/16” thick.
The maximum plumb ness error of the top of the shell relative to the
bottom of the shell shall not exceed 1/200 of the total tank height.
4. Peaking – provide 2 pcs. Sweep board or any equivalent 36” long,
one with inside radius curve and one outside radius curve for peaking
check – up. Peaking shall not exceed ½” or 12mm.
5. Banding - provides one - piece sweep board or equivalent 36” long
for banding check – up. Banding shall not exceed ½” or 12mm.
REPAIR OF DEFECTS
1. All defects found in welds shall be called to the attention of the
client’s inspector for approval shall be obtained before defects are
repaired.
2. Defects in weld shall be repaired by arc gouging or melting – out the
defects from one side or both sides of the joint as required, and re -
welding. All repaired weld joints shall be checked by repeating the
original method of inspection in accordance with API Standard.s