SCOPE OF WORKS

 UP-GRADATION or INSTALLATION OF NEW STREET


LIGHT FEEDER PILLAR
PROCEDURE FOR OBTAINING APPROVALS FROM RTA
 Apply and obtain Preliminary Design NOC from RTA by consultant

 Apply and obtain Final Design NOC from RTA by consultant

 Submission of shop drawings by contractor

 Lux calculation submission for the proposed street lighting network by


contractor

 Material submittal by contractor

 Apply and obtain Construction NOC from RTA by project contractor


PROCEDURE FOR OBTAINING APPROVALS FROM DEWA
 Apply and obtain Building NOC from DEWA by Consultant/Contractor

 Apply and obtain LV/HV Design Approval from DEWA by contractor

 Estimate from DEWA for proposed power Connection and Payment

 Construction of new substation if required

 Apply for DEWA inspection

 Cable termination at Substation

 Power supply release


WORK FLOW CHART
PROJECT

RTA DEWA

INFO
DESIGN
CSD IIPD
TP
CONST
POWER Distribution & Transmission
SUPPLY Maintenance Line Maint.

BUILDING
NOC

FINAL
LV DESIGN
APPROVAL

LV CABLE
ESTIMATE
LAYING

INSPECTION

SUPPLY
RELEASE
SITE EXECUSION – INSTALLATION OF FEEDER PILLAR