MINIMUM REQUIREMENT FOR STEAM BLOWING

Date : 6/6/2024
No SYSTEM/EQUIPMENT NOS STATUS REMARKS TARGET DATE

1 DEMIN WATER AVAILIBILITY - Available

2 COOLING SYSTEM
CIRCULATING WATER PUMP 2 Completed CWP 3 ( DONE), CWP 4 NOT YET
CLOSED COOLING WATER PUMP 2 Completed
STABILITVOLT TANK 1 Completed

3 FEED WATER SYSTEM


MoV FEED WATER SUPPLY Completed
FEED WATER FLOW Not Yet NOT FUNCTION
FEED WATER PUMP 2 Not Yet BFP 2B (DONE), BFP 2A (ONGOING)
DAERATOR 1 Not Yet LEVEL TRANSMITTER AND LEVEL SWITCH NOT YET
* DRAIN PUMP & DRAIN TANK Completed

4 COMBUSTION SYSTEM
PRIMARY AIR FAN 1 Completed
SECONDARY AIR FAN 1 Completed
FLUIDIZING AIR FAN 2 Completed RUNNING IF USING COAL (IN CASE)
COMBUSTION INSTRUMENT Not Yet AIR FLOW (ON GOING)

5 FLUE GAS SYSTEM


IDF 2 Completed
FLUE GAS Instrument Not Yet PRESSURE SWITCH FURNACE PRESSURE NOT YET

6 BOILER WATER AND STEAM SYSTEM


ECONOMIZER 1 Completed
STEAM DRUM 1 Not Yet LEVEL TRANSMITTER NOT OK
FURNACE 1 Completed
START UP VENT 2 Completed

7 CHEMICAL DOSING SYSTEM


AMINE 2 Completed
HYDRAZINE 2 Completed
PHOSPHATE 2 Completed
MINIMUM REQUIREMENT FOR STEAM BLOWING

Date : 6/6/2024
No SYSTEM/EQUIPMENT NOS STATUS REMARKS TARGET DATE

8 SAMPLING RACK Not Yet

9 FUEL OIL & BURNER SYSTEM


OIL SUPPLY 2 Completed
BURNER 2 Not Yet ON GOING

10 BLOWDOWN AND DRAINAGE SYSTEM


CBD 1 Not Yet
INTERMITTEN BLOWDOWN TANK 1 Completed

11 MAIN STEAM LINE & TEMPORARY


MAIN STEAM LINE 1 Completed MAIN STEAM LINE & MOTORIZED VALVE (COMPLETED)
TEMPORARY LINE & MOV Not Yet TEMPORARY LINE AND MoV NOT YET INSTALLED (ON GOING)

12 REFRACTORY DONE WAITING INSPECTION AFTER RDO

13 BOILER INTERLOCK Not Yet MFT AND OFT NOT READY


14 COMPRESSOR Completed
15 FIRE FIGHTING DONE STILL MANUAL
16 ENERGIZE BACK FEEDING 150 Kv Not Yet
17 0THER
TARGET PLATE
CONSUMABLE OF CHEMICAL DOSING
CONSUMABLE OF OIL
HSE & MADICAL AID
TRAVELLING SCREEN
* SUMP PUMP WWTP
* COAL HANDLING
EVALUATION FOR STEAM BLOWING ( OIL FIRING)

WATER SYSTEM SERVICE POND DEMIN TANK 1 DEMIN TANK 2


.....M ........M ........M

COMBUSTION AND FLUE IDF 2A IDF 2B SAF PAF


GAS SYSTEM √ √ √ √

FEED WATER SYSTEM BFP 2A BFP 2B DAERATOR TANK DRAIN PUMP 1


X √ X √

COOLING WATER SYSTEM CWP 3 CWP 4 CCWP 1 CCWP 2


X √ √

FUEL OIL SYSTEM HSD OIL PUMP 1 HSD OIL PUMP 2


√ √

BURNER SYSTEM UNDER BURNER 1 UNDER BURNER 2


X X

STEAM DRUM INSPECTION LEVEL TRANSMITTER


√ X

REFRACTORY WIND BOX FURNACE BURNER AREA CYCLONE

CHEMICAL DOSING AMINE HYDRAZINE PHOSPHATE


√ √ √

BOILER INTERLOCK MFT OFT


X X
AIR BALANCE TEST X

ENERGIZE 150 Kv X

TEMPORARY BLOWING INSTALLATION FUNCTION TEST MoV


LINE AND MoV X X

BOILER LIGHT UP TENTATIVE


DEMIN WATER AND SERVICE WATER IS AVAILABLE

- ALL BOILER FANS IS READY


- FURNACE PRESSURE SWITCH AND AIR FLOW NOT YET

- BFP 2A ON GOING
- DAERATOR LEVEL TRANSMITTER AND SWITCH NOT YET

STABILITVOLT TANK - CWP 4 ON GOING


COMPLETED

PLC BURNER NOT READY

- INDICATION LEVEL TRANSMITTER STILL PROBLEM

LOOP SEAL - WAITING INSPECTION

COMPLETED
ALL BOILER FANS RUNNING

ON GOING

TO BE REVIEW AGAIN