Minimum Requirement For Steam Blowing
Date : 6/6/2024
No SYSTEM/EQUIPMENT NOS STATUS REMARKS TARGET DATE
2 COOLING SYSTEM
CIRCULATING WATER PUMP 2 Completed CWP 3 ( DONE), CWP 4 NOT YET
CLOSED COOLING WATER PUMP 2 Completed
STABILITVOLT TANK 1 Completed
4 COMBUSTION SYSTEM
PRIMARY AIR FAN 1 Completed
SECONDARY AIR FAN 1 Completed
FLUIDIZING AIR FAN 2 Completed RUNNING IF USING COAL (IN CASE)
COMBUSTION INSTRUMENT Not Yet AIR FLOW (ON GOING)
Date : 6/6/2024
No SYSTEM/EQUIPMENT NOS STATUS REMARKS TARGET DATE
ENERGIZE 150 Kv X
- BFP 2A ON GOING
- DAERATOR LEVEL TRANSMITTER AND SWITCH NOT YET
COMPLETED
COMPLETED
ALL BOILER FANS RUNNING
ON GOING
TO BE REVIEW AGAIN