BS 7074-3 1989

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

BRITISH STANDARD BS 7074-3:

1989

Application, selection
and installation of
expansion vessels and
ancillary equipment for
sealed water systems —
Part 3: Code of practice for chilled and
condenser systems

UDC 621.642.3:697.43:621.175:001.4:620.1:[006.76(083.75)]
BS 7074-3:1989

Committees responsible for this


British Standard

The preparation of this British Standard was entrusted by the Refrigeration,


Heating and Air Conditioning Standards Policy Committee (RHE/-) to
Technical Committee RHE/7, upon which the following bodies were
represented:

Associated Offices Technical Committee


Association of Consulting Engineers
Association of Manufacturers of Domestic Unvented Supply Systems
Equipment (MODUSSE)
British Marine Equipment Council
Building Services Research and Information Association
Chartered Institution of Building Services Engineers
Heating and Ventilating Contractors’ Association
HEVAC Association
Institute of Domestic Heating Engineers
Sealed Expansion Vessel Association
Waterheater Manufacturers’ Association

This British Standard, having


been prepared under the
direction of the Refrigeration,
Heating and Air Conditioning
Standards Policy Committee,
was published under the
authority of the Board of BSI
and comes into effect on
31 July 1989 Amendments issued since publication
© BSI 09-1999
Amd. No. Date of issue Comments

The following BSI references


relate to the work on this
standard:
Committee reference RHE/7
Draft for comment 87/73421 DC

ISBN 0 580 17147 7


BS 7074-3:1989

Contents

Page
Committees responsible Inside front cover
Foreword ii
Section 1. General
1 Scope 1
2 Definitions 1
3 Symbols, designations and units 2
4 Connection of expansion vessel to the system 2
5 Testing and commissioning 3
6 Maintenance 5
7 Workmanship 5
Section 2. Chilled water systems
8 Design considerations 6
9 Application 6
10 Ancillary equipment 7
Section 3. Condenser water systems
11 Design considerations 12
12 Application 12
13 Ancillary equipment 13
Appendix A Examples of recommended procedure for
the calculation of the size of expansion vessels 16
Figure 1 — System pressure variations: recommended
arrangement 4
Figure 2 — System pressure variations: neutral point at
pump discharge 4
Figure 3 — System pressure variations: neutral point
remote from pump 5
Figure 4 — Chilled water system 10
Figure 5 — Typical expansion percentage of water mixed
with anti-freezing agent versus temperature 11
Figure 6 — Condenser water (heat reclaim) system 15
Table 1 — Symbols, designations and units 2
Table 2 — Expansion percentages (e) for various flow
temperatures (tf) from 4 °C initial temperature 8
Publications referred to Inside back cover

© BSI 09-1999 i
BS 7074-3:1989

Foreword

This British Standard code of practice has been prepared under the direction of
the Refrigeration, Heating and Air Conditioning Standards Policy Committee.
The code complements BS 4814 and gives recommendations in its three Parts for
the installation of expansion vessels in domestic heating and supply systems
(Part 1); low and medium temperature hot water heating systems (Part 2); chilled
water and condenser systems (Part 3); and boosted hot water supply systems.1)
The code deals with the work involved in the general planning, designing and
installation of the various systems when the expansion and contraction of the
system water is catered for in a sealed diaphragm type vessel. In all other
respects the customary design process should be followed for the appropriate
system.
A British Standard does not purport to include all the necessary provisions of a
contract. Users of British Standards are responsible for their correct application.
Compliance with a British Standard does not of itself confer immunity
from legal obligations.

Summary of pages
This document comprises a front cover, an inside front cover, pages i and ii,
pages 1 to 18, an inside back cover and a back cover.
This standard has been updated (see copyright date) and may have had
amendments incorporated. This will be indicated in the amendment table on the
inside front cover.

1)
Planned.

ii © BSI 09-1999
BS 7074-3:1989

Section 1. General

1 Scope 2.6
This Part of BS 7074 gives recommendations on the expansion volume (Va)
application of expansion vessels complying with the increase in volume of water due to expansion of
BS 4814 having a maximum pressure of 7 bar2) for water when raised to the design ambient
use in the following two types of system. It includes temperature
description, design considerations and application. 2.7
Sections 1 and 2 cover chilled water systems. final system design pressure (Pf)
Sections 1 and 3 cover condenser water systems. the pressure occurring at the mid-height of the
NOTE 1 Condenser water systems are normally associated expansion vessel at the maximum design system
with the heat reject side of refrigeration plant. temperature
Recommendations are also given on: 2.8
a) the application and use of ancillary equipment initial cold water fill temperature (ti)
and the basic reference temperature is taken to be 4 °C
b) testing, commissioning and maintenance.
2.9
NOTE 2 The titles of the publications referred to in this
standard are listed on the inside back cover. initial system design pressure (Pi)
the pressure occurring at the mid-height of the
2 Definitions expansion vessel at cold fill. This is equal to the
static height pressure plus the pressure margin
For the purposes of this Part of BS 7074 the
following definitions apply. 2.10
lowest working pressure component (LWPC)
2.1
charging pressure the component having the lowest working pressure
in the system
the initial pressure to which the gas/air side of the
vessel is charged (which is equal to the initial 2.11
system design pressure) maximum acceptance factor (A)
2.2 the ratio of maximum acceptance volume of the
closed valve head (Pc) system to total volume
the maximum head developed by a pump under a 2.12
no-flow condition maximum acceptance volume (V)
2.3 the volume of water which the vessel may be
design acceptance factor (a) allowed to contain
the ratio of the volume of water due to expansion, to 2.13
total vessel volume maximum vessel temperature
2.4 the maximum water temperature at which the
diaphragm (or membrane) vessel may be allowed to operate continuously
the flexible means by which the chamber of an 2.14
expansion vessel is partitioned to maintain maximum vessel working pressure
separation between the expanding hot water and the maximum pressure that the vessel may be
the gas or air which in consequence becomes allowed to contain in operation
compressed. It may be either a literal diaphragm
clamped between two parts (or halves) of the vessel, 2.15
or a bag located by its mouth which is secured to the pressure depth (Pd)
point of the water connection to the vessel the vertical distance between the component being
2.5 considered and the mid-height of the expansion
vessel situated above it
expansion percentage (e)
the expansion percentage increase in volume when 2.16
water is heated to the design ambient temperature pressure margin (Ps)
the additional pressure imposed on the circuit to
exclude air from the system at the highest point

2)
1 bar = 105 N/m2 = 100 kPa.

© BSI 09-1999 1
BS 7074-3:1989

2.17 4 Connection of expansion vessel to


safety valve set pressure (Pmax) the system
the pressure at which the safety valve is set for 4.1 General
operation
The neutral point of the system is the point of
2.18 connection of the pipework to the expansion vessel.
static height pressure (Ph) It is recommended that the expansion vessel is in
the pressure created by the column of water the system return pipework close to the heat
between the uppermost part of the circuit and the exchanger. The filling position should be into the
mid-height of the expansion vessel expansion pipework.
2.19 The point of connection of the expansion vessel(s)
system flow temperature (tf) into the system having been clearly defined, the
physical location of the vessel can be anywhere.
the maximum designed temperature of the water
circulating in the system 4.2 Location of pump relative to expansion
vessel
2.20
total system volume (Vs) 4.2.1 General. When the pump in the system is not
operating the only pressure existing varies between
the total volume of water in the complete system
Pi and Pf depending upon the water temperature.
2.21 When the pump is started the pressure within the
total vessel volume (Vt) system will change from its original static pressure
the volume occupied by gas/air when the vessel is conditions to a completely new set of pressure
empty of water conditions. This new pressure condition is defined
as the pump head and is indicated by the pressure
3 Symbols, designations and units drop between the suction and discharge of the
pump. The pressure at the pump discharge will be
The symbols for physical quantities, their higher than the system pressure at the pump
designations and units used in this code of practice suction by an amount equal to the pump head. The
are given in Table 1. pressure drop due to friction within the system will
Table 1 — Symbols, designations and units gradually decrease the system pressure from that
Symbol Designation Unit existing at the pump discharge to the lower pressure
existing at the pump suction.
A Maximum acceptance factor —
With the pump running, the system pressure will
a Design acceptance factor — change generally as illustrated in Figure 1, Figure 2
e Expansion percentage — and Figure 3. Attention is drawn to the point of no
Pc Closed valve head bar gauge pressure change being relative to the point of
Pd Pressure depth bar gauge connection of the expansion vessel into the system.
The pump only has the ability to create the pressure
Pf Final system design pressure bar gauge
difference across itself and therefore there is no
Ph Static height pressure bar gauge reason why the full pump head should not appear on
Pi Initial system design pressure bar gauge the suction side of the pump as shown in Figure 2. It
will be noted that the position of no pressure change
Pmax Safety valve, set pressure bar gauge (the neutral point) is different from that shown in
Ps Pressure margin bar gauge Figure 1. By dictating the point of no pressure
ta Maximum ambient °C change (the neutral point), system pressure changes
temperature by pump operation can be controlled. In Figure 3,
where the neutral point has been changed once
tf System flow temperature °C again, a new set of pressure characteristics pertain.
ti Initial cold water fill °C
temperature
V Maximum acceptance volume L
Va Expansion volume L
Vs Total system volume L
Vt Total vessel volume L

2 © BSI 09-1999
BS 7074-3:1989

4.2.2 Neutral point. The point of no pressure change, 4.2.5 Neutral point remote from pump. By locating
or the neutral point, is the point where the the expansion vessel at some distance from the
expansion vessel is connected to the system. This is pump, the system pressure change due to pump
because the air gas cushion in the expansion vessel operation would appear as shown in Figure 3. The
follows basic gas laws and the change in gas expansion vessel junction would be the neutral
pressure has to be accompanied by a change in gas point and all pressure system changes would be
volume. A change in gas volume in the vessel has to referred from that point. Pressure gauge readings at
be accompanied by a change of water volume in the the pump suction and discharge would show
vessel. partially positive and partially negative readings
It follows that a change in water volume in the with reference to the original non-operating static
vessel has to be accompanied by a change of water pressure condition. The pressure changes would be
volume in the system; since water is incompressible, a function of the system pipe friction pressure drop
pump operation cannot increase or decrease the between the pump and the vessel. It is emphasized
system water volume therefore pump operation that the problems created in systems where the
cannot change vessel pressure. Since vessel neutral point is such that the pump head is all
pressure cannot change due to pump operation, the under suction (see Figure 2) are more likely to occur
junction of the expansion vessel with the system has in higher head pump systems. Therefore in dealing
to be a point of no pressure change regardless of with microbore systems it is important that the
whether or not the pump operates. relative position of the neutral point and pump be
fully understood in order that the most satisfactory
4.2.3 Neutral point at pump suction. Figure 1
system operation can be effected.
illustrates a system in which the neutral point is
located at the pump suction. The pressure changes 4.2.6 Recommended arrangement. If the expansion
caused by pump operation are therefore added to vessel is placed at the suction side of the pump, the
the original system static pressure. Because all pump suction pressure will not change regardless of
system pressure changes are additive and positive whether or not the pump is operated; because the
there is no possibility of pump cavitation or air being pump suction cannot change, the pump discharge
drawn into the system. pressure has to change. The pump differential head
is then manifested as a positive increase in pressure
4.2.4 Neutral point at pump discharge. Figure 2
at the pump discharge as shown in Figure 1.
shows a system where the point of no pressure
change is located at the pump discharge. All The pressure increase due to pump head will then
pressure changes caused by pump operation are decrease around the system, depending upon the
subtracted from the original pressure and are of a various friction losses in the system until at the
negative type; under certain conditions this can pump suction the original static pressure is
cause unsatisfactory results. If the pressure obtained. Because the pump suction pressure is
decrease below the original static pressure is great unchanged due to pump operation it is suggested
enough, the system pressure could drop, circulation that the chiller be placed at the pump suction; this
will be unstable and pump cavitation can occur with is the recommended relative arrangement of pump,
a resultant pump failure. If the pressure drops chiller and expansion vessel within a system.
below atmospheric pressure, air can be sucked in at
the vent, air pockets are created and circulation 5 Testing and commissioning
blocked, it is strongly recommended therefore that 5.1 Pressure testing the system
the neutral point should not be located at the pump
Expansion vessels, pressure switches, safety
discharge.
valve(s) and fill unit have to be isolated prior to
hydraulic pressure testing. This is to ensure that
these components are not damaged by over
pressurization.

© BSI 09-1999 3
BS 7074-3:1989

Figure 1 — System pressure variations: recommended arrangement

Figure 2 — System pressure variations: neutral point at pump discharge

4 © BSI 09-1999
BS 7074-3:1989

Figure 3 — System pressure variations: neutral point remote from pump


5.2 Commissioning 6 Maintenance
The recommended procedures given in the Maintenance instructions provided by the
Chartered Institute of Building Services Engineers manufacturers of the equipment installed should be
(CIBSE) Commissioning Codes should be followed closely followed. These should be handed to the user.
for the system. For condensing systems the
operation of the low and high pressure alarm 7 Workmanship
switch(es) should be checked. The condensing
system should be allowed to cool and then be Work on sealed systems as described in this Part of
partially drained to allow the pressure to drop such this code of practice should be carried out by
that the setting of the low pressure switch can be competent persons.
checked. For chilled water the system should be
allowed to cool to normal operating temperature and
then be partially drained to allow the setting of the
low pressure alarm to be checked. The pressure
should then be raised to the normal pressure
consistent with the operating temperature. Then
the system should be allowed to return to ambient
temperature. The filling unit should be started and
pressure raised to check the high pressure alarm
switch. The pressure should then be reduced to a
pressure consistent with the ambient temperature.
This is best carried out when the expansion vessel
has been isolated, which reduces the volume of
water necessary to raise the pressure.

© BSI 09-1999 5
BS 7074-3:1989

Section 2. Chilled water systems

8 Design considerations j) Provision should be made for automatically


maintaining a full system. A unit should be
Successful and continuing safe operation of a
provided with all necessary safety devices, to the
system (see Figure 4) depends on the use of the
requirements of the local water authority.
correct equipment properly installed to a good
design, well engineered and effectively maintained. 9 Application
It is important to note that expansion vessels
constructed in accordance with BS 4814 are not to 9.1 Assuming that the remainder of the system has
be subjected to a pressure greater than 7 bar. been designed following customary design practice,
To ensure satisfactory operation of a chilled water during shut down or failure periods provision for
system the following items need to be considered at expansion has to be made to accommodate
the design stage, in addition to the customary expansion as the water temperature rises to
design procedures applicable to the system. ambient. The procedure for the design of a chilled
water system should follow the recommendations
a) The preferred position of the expansion given in 9.2 and 9.3.
vessel(s) and ancillary equipment is in the
immediate vicinity of the cooling plant whether 9.2 Select a position for the expansion equipment,
this be at basement, roof or intermediate level. which should preferably be in the immediate
Provision has to be made for the additional space vicinity of the cooling plant.
required. 9.3 Calculation of the sizes of the vessels should be
b) The availability of adequate water supply and based on the following.
the method of filling and maintaining a full a) Water content of the system in litres (Vs) (this
system. has to include all circulatory pipework, cooling
c) Maximum allowable working pressure at the units, chilled water plant and any form of heat
expansion vessel(s). Additional pressures will exchangers that may be incorporated).
occur at some items of equipment due to static b) Maximum ambient temperature (ta) in °C.
head; circulating pump(s) may also impose c) Expansion percentage (e) (see Table 23)).
additional pressures. d) Static height pressure (Ph) in bar gauge.
d) The position in the system of the circulating e) Initial system design pressure (Pi) in bar
pump(s) relative to the point of connection of the gauge.
expansion vessel(s) into the system.
The margin normally added to the static height
e) Pump operating characteristics under all pressure is 0.3 bar. This added pressure
system operating conditions. The pump should margin (Ps) is necessary to expel air from the
not be the type incorporating packed glands.
system, also to permit system control pressure
f) Flow and return temperatures and maximum differentials.
ambient temperature. If the maximum design
Pi = Ph + Ps
system temperature specified by the system
designer exceeds the maximum vessel f) Final system design pressure (Pf) in bar gauge;
temperature the manufacturer’s instructions where the expansion vessel is located:
should be followed with regard to diaphragm 1) at the lowest point in the installation: Pf is
protection. necessary to calculate the design acceptance
g) Total water content of the system. factor (a). Pf can then be calculated by taking
NOTE The addition of anti-freeze or similar fluid will affect the component having the lowest working
the expansion percentage coefficient and may also affect the pressure (LWPC) and deducting the pump
diaphragm material (see Figure 5). head available at LWPC;
h) Capacity, size and number of expansion
vessel(s). It is important that the correct
procedure is followed when selecting vessel(s).
The vessel(s) and expansion pipework should not
be thermally insulated.
i) The need for and position of ancillary
equipment such as air separators, air vents,
control and safety devices.

3) Ifan anti-freeze solution is used, the expansion factor will be substantially increased dependent upon the solution strength.
Figure 5 shows values for a typical anti-freeze solution. The appropriate expansion factor should be applied when calculating the
size of the vessel, see also note to clause 8 g).

6 © BSI 09-1999
BS 7074-3:1989

2) at high level, i.e. roof plant rooms: in these i) Based on the selected vessel a revised
circumstances Pf will be lower than in 1) and acceptance factor a1 should be calculated as
because the entire system is below the plant follows:
room a minimum value of 0.7 bar may be Va
adopted for Pi. The expansion vessel volume a 1 = --------------------------
calculation [see 9.3 h)] should be made using V t + 10 %
the vessel manufacturer’s recommended if the calculated factor a1 exceeds the
acceptance factor and the procedure set out manufacturer’s recommended value, a larger
in 9.3 i), j) and k) followed to calculate a1, Pf vessel has to be selected. a1 is then re-calculated
and Pmax. To ensure that the working pressure
to obtain an acceptable lower value.
of the unit at the base of the system is not
exceeded, calculate Pd. Add Pmax to Pd and the j) Re-calculate the new value of Pf in bar gauge,
pump closed-valve-head and compare the related to the selected vessel. The new final
result with the unit working pressure. If this is system design pressure will be:
exceeded either re-select a unit with a higher P i + a1
working pressure, or calculate the size of the P f = -------------------
1 – a1
vessel to achieve a lower working pressure.
k) Calculate the safety valve set pressure Pmax in
g) Design acceptance factor (a):
bar gauge.
( Pf + 1) – ( Pi + 1) Pmax = Pf + 0.3 bar, for systems up to 5 bar;
a = --------------------------------------------------
-
Pf + 1 for systems operating above 5 bar:
where Pf + 1 and Pi + 1 expresses Pf and Pi Pmax = Pf + 15 %
respectively in absolute units. 9.4 Due account has to be made for the position of
h) The total vessel volume (Vt) in L, can now be the pump/neutral point relative to the heat
calculated as follows: exchange unit.
NOTE An example of a calculation of the size of expansion
Va vessels for a chilled water system is given in A.1.
V t = -------
-
a
where Va = Vs × e
10 Ancillary equipment
10.1 General
To allow for contingencies and operational
variances a margin should be added. It is For the satisfactory operation of a system
recommended that this should be at least 10 %. containing an expansion vessel certain items of
A vessel should be selected with a volume equal ancillary equipment will need to be
to or higher than the above final volume incorporated. 10.2 provides a list and commentary
(Vt + 10 %). as appropriate, but does not necessarily comprise a
complete control or safety system as may be
required for certain projects; neither will every
system need to incorporate all the ancillaries listed.

© BSI 09-1999 7
BS 7074-3:1989

Table 2 — Expansion percentages (e) for various flow temperatures (tf)


from 4 °C initial temperaturea
æV ö
e = ç -------a÷ 100
è Vsø
tf e tf e tf e tf e

°C % °C % °C % °C %

0 0.02 30 0.44 60 1.71 150 9.06


2 0.01 32 0.50 70 2.28 155 9.64
4 0.00 34 0.57 80 2.91 160 10.20
6 0.01 36 0.64 82.2 3.07 165 10.82
8 0.02 38 0.70 90 3.60 170 11.45

10 0.03 40 0.78 100 4.35 180 12.75


12 0.06 42 0.86 105 4.77 190 14.15
14 0.08 44 0.94 110 5.15 200 15.65
16 0.11 46 1.03 115 5.62
18 0.14 48 1.12 120 6.01

20 0.18 50 1.21 125 6.52


22 0.23 52 1.30 130 7.00
24 0.28 54 1.40 135 7.50
26 0.33 56 1.50 140 8.00
28 0.38 58 1.60 145 8.53
a These values originate from the “Steam tables 1964” of the National Engineering Laboratory (published by
HMSO Edinburgh) and were derived from Table C2-2 of the CIBSE Guide 1970 by taking the reciprocal of the
density expressed in millilitres per gramme and stating this as a percentage, using the volume of one millilitre
of water at 4 °C as unity.
Example: Consider water at 100 °C, density = 958.3 kg/m3
6 3
1 × 10 10
mL/g = ------------------------------ = --------------- = 1.0435
958.3 ×10
3 958.3

therefore percentage expansion from unity at 4 °C = (1.0435 – 1) 100 = 4.35 %

Ancillaries may be combined; when this is done the 10.2 Components


composite unit needs to be designed to meet the 10.2.1 System initial fill connection. Due to the time
higher requirements of the individual items taken it is preferable not to use the automatic
included. make-up units for the initial filling. To facilitate the
All ancillaries should, where practicable, be so initial filling of the system a temporary fill
constructed that they fail safe. connection may be made from a water mains supply
All ancillaries should comply with any relevant in accordance with water byelaws. For protection of
British Standards. the mains supply to the installation when filling
from a temporary connection, the following items
should be incorporated at the point of filling:
pressure reducing valve, pressure gauge,
non-return valve, anti-vacuum valve, stop cocks.
The temporary hose connection has to be removed
after the system has been filled. Care should be
exercised to ensure that the fill pressure does not
exceed the calculated value of Pi at the operating
temperature or Pf at ambient temperature.

8 © BSI 09-1999
BS 7074-3:1989

10.2.2 Automatic make-up unit. The automatic 10.3.4 Pressure switches should operate
make-up unit is a device to ensure the initial system consistently within ± 0.15 bar of the set point and
design pressure is maintained. A separate small required value. Incremental adjustment is
pump and associated cold water break tank is preferable. The switch should be provided with a
provided for the purpose of introducing water into device to indicate clearly when it has tripped out.
the system to make up for losses, etc. This may Audio alarms should be attenuatable and audio and
incorporate a small hydraulic accumulator to reduce visual alarms should be positioned where they can
the frequency of pump starting. be clearly identified.
The electrical supply to this unit should not be 10.3.5 Temperature limit switches and temperature
subject to unauthorized disconnection. controllers should operate consistently within ± 2 °C
10.2.3 Safety valve. A device to ensure that the of the set point and required value. Incremental
pressure in the system does not exceed a adjustment is preferable. The switch should be
predetermined level. provided with a device to indicate clearly when it
has tripped out.
10.2.4 Pressure gauge.
10.4 Constructional details
10.2.5 Thermometer.
10.2.6 High pressure alarm switch. An audio and/or Ancillaries should be selected from those
visual device indicating when a predetermined constructed of corrosion-resistant material of
maximum system pressure is reached. The pressure adequate strength.
at which this alarm operates should not be less All fasteners should comply with relevant
than 0.35 bar below the safety valve pressure standards.
setting. All electrical wiring and equipment should comply
10.2.7 Low pressure switch. A device which causes with the detailed requirements of the Regulations
the chiller to shut off when a predetermined for the Electrical Equipment of Buildings (published
minimum system pressure is reached. A manual by the Institution of Electrical Engineers), or be in
reset and/or alarm may be incorporated. accordance with appropriate regulations.
10.2.8 Temperature controller (thermostat). A device Dials or scales, where fitted, should be clearly
to control the system water-flow temperature. The visible.
thermostat should be set so as to prevent the All equipment (valves, pipework and fittings)
formation of ice. should meet the requirements of the local water
10.2.9 Air separator. A device that separates air and authority.
other gases from suspension in the system water. 10.5 Installation instructions
10.2.10 Automatic air vent. A device that Clear instructions regarding installation, operation
automatically allows air to be vented from a part of and maintenance should be included with each
a system. Hygroscopic devices are not ancillary item.
recommended.
10.6 Marking
10.3 Pressure and temperature ratings
Each ancillary item should carry the following
10.3.1 The maximum operating temperature and/or information:
pressure should be stated on a label affixed to the
ancillary, or clearly stated in the instructions for a) manufacturer’s or agent’s name or symbol;
installing and operating the ancillary. b) serial number or batch number where
10.3.2 Where the maximum operating pressure is practicable;
stated in accordance with 10.3.1 the test pressure c) temperature rating or pressure rating where
should be 1.5 times the stated value. appropriate;
10.3.3 The lift pressure of a safety valve should be d) electrical rating where appropriate;
determined by the manufacturer and should be e) indication of year of manufacture;
clearly stated on a label affixed to the body of the f) the number of the relevant British Standard
valve. The operating mechanism should be sealed by where applicable.
the manufacturer.

© BSI 09-1999 9
10

BS 7074-3:1989
NOTE The temperatures shown are approximate and vary according to climatic conditions and equipment used.
Figure 4 — Chilled water system
© BSI 09-1999
© BSI 09-1999

BS 7074-3:1989
Figure 5 — Typical expansion percentage of water mixed with anti-freezing agent versus temperature
11
BS 7074-3:1989

Section 3. Condenser water systems

11 Design considerations j) Provision should be made for automatically


maintaining a full system. A unit should be
Successful and continuing safe operation of a
provided with all necessary safety devices, to the
system (see Figure 6) depends on the use of the
requirement of the local water authority.
correct equipment properly installed to a good
design, well engineered and effectively maintained. 12 Application
It is important to note that expansion vessels
constructed in accordance with BS 4814 are not to 12.1 Condenser water circuits are often sealed to
be subjected to a pressure greater than 7 bar. obtain the following benefits:
To ensure satisfactory operation of a condenser a) reduction of corrosion and maintenance to the
water system the following items need to be condenser unit;
considered at the design stage, in addition to the b) permits heat reclamation to facilitate energy
customary design procedures applicable to the conservation.
systems. NOTE When an anti-freeze solution is used, e.g. as in a heat
a) The preferred position of the expansion reclaim system using run-around coils, the expansion factor will
be substantially increased dependent upon the solution strength.
vessel(s) and ancillary equipment is in the Figure 5 shows values for a typical anti-freeze solution. The
immediate vicinity of the heat transfer plant appropriate expansion factor should be applied in sizing the
whether this be at basement, roof or intermediate vessel, see also note to clause 11 g). Heat transfer values are
level. Provision has to be made for the additional reduced when anti-freeze solution is used and should be taken
into account.
space required.
Assuming that the remainder of the system has
b) The availability of adequate water supply and been designed following customary design practice,
the method of filling and maintaining a full the procedure for the design of a sealed system
system. should follow the recommendations given in 12.2
c) Maximum allowable working pressure at the and 12.3.
expansion vessel(s). Additional pressures will 12.2 Select a position for the expansion equipment,
occur at some items of equipment due to static which should preferably be in the immediate
head; circulating pump(s) may also impose vicinity of the heat transfer plant.
additional pressures.
12.3 Calculation of the sizes of the vessels should be
d) The position in the system of the circulating based on the following.
pump(s) relative to the point of connection of the
expansion vessel(s) into the system. a) Water content of the system in litres (Vs)
(this has to include all circulatory pipework and
e) Pump operating characteristics under all heat transfer equipment).
system operating conditions. The pump should
not be the type incorporating packed glands. b) Flow water temperature (tf) in °C.
f) Flow and return temperatures and maximum c) Expansion percentage (e) [see Table 2 and note
ambient temperature. If the maximum design to 12.1 b)].
system temperature specified by the system d) Static height pressure (Ph) in bar gauge.
designer exceeds the maximum vessel e) Initial system design pressure (Pi). The margin
temperature, the manufacturer’s instructions normally added to the static height pressure
should be followed with regard to diaphragm is 0.3 bar. This added pressure margin (Ps) is
protection. necessary to expel air from the system, also to
g) Total water content of the system. permit system control pressure differentials:
NOTE The addition of anti-freeze or similar fluid will affect Pi = Ph + Ps
the expansion percentage coefficient and may also affect the
diaphragm material (see Figure 5). f) Final system design pressure (Pf) in bar gauge;
h) Capacity, size and number of expansion where the expansion vessel is located:
vessel(s). It is important that the correct 1) at the lowest point in the installation: Pf is
procedure is followed when selecting vessel(s). necessary to obtain the design acceptance
The vessel(s) and expansion pipework should not factor a. Pf can then be calculated by taking the
be thermally insulated. component having the lowest working
i) The need for and position of ancillary pressure (LWPC) and from this deducting the
equipment such as air separators, air vents, safety valve lifting pressure margin and the
control and safety devices. pump head available at LWPC

12 © BSI 09-1999
BS 7074-3:1989

2) at high level, i.e. roof plant rooms: in these for systems operating above 5 bar:
circumstances Pf will be lower than in 1) and Pmax = Pf + 15 %
because the entire system is below the plant
room a minimum value of 0.7 bar may be 12.4 Due account has to be made for the position of
adopted for Pi. The expansion vessel volume the pump/neutral point relative to the heat
calculation [see 12.3 h)] should be made using exchange unit.
the vessel manufacturer’s recommended NOTE An example of a calculation of the size of expansion
vessels for a condenser water system is given in A.2.
acceptance factor and the procedure set out
in 12.3 i), j) and k) followed to calculate a1, Pf
and Pmax. To ensure that the working pressure
13 Ancillary equipment
of unit at the base of the system is not 13.1 General
exceeded, calculate Pd. Add Pmax to Pd and the For the satisfactory operation of a system
pump closed-valve-head and compare the containing an expansion vessel certain items of
result with unit working pressure. If this is ancillary equipment will need to be
exceeded either re-select a unit with a higher incorporated. 13.2 provides a list and commentary
working pressure, or calculate the size of the as appropriate, but does not necessarily comprise a
vessel to achieve a lower working pressure. complete control or safety system as may be
g) Design acceptance factor (a); required for certain projects; neither will every
( Pf + 1 ) – ( Pi + 1 ) system need to incorporate all the ancillaries listed.
a = ----------------------------------------------
- Ancillaries may be combined; when this is done the
Pf + 1
composite unit needs to be designed to meet the
where Pf + 1 and Pi + 1 expresses Pf and Pi higher requirements of the individual items
respectively in absolute units. included.
h) The total vessel volume (Vt) in L, can now be All ancillaries should, where practicable, be so
calculated as follows: constructed that they fail safe.
V All ancillaries should comply with any relevant
Vt = ------a- British Standards.
a
13.2 Components
where Va= Vs × e
13.2.1 System initial fill connection. Due to the time
To allow for contingencies and operational
taken it is preferable not to use the automatic
variances a margin should be added. It is
make-up unit for the initial filling. To facilitate the
recommended that this should be at least 10 %.
initial filling of the system a temporary fill
A vessel should be selected with a volume equal
connection may be made from a water mains supply
to or higher than the above final volume
in accordance with water byelaws. For protection of
(Vt + 10 %).
the mains supply to the installation when filling
i) Based on the selected vessel a revised from a temporary connection, the following items
acceptance factor a1 should be calculated as should be incorporated at the point of filling:
follows: pressure reducing valve, non-return valve,
anti-vacuum valve, stop cocks. The temporary
Va connection has to be removed after the system has
a 1 = ---------------------------
-
V t + 10 % been filled. Care should be exercised to ensure that
the fill pressure does not exceed the calculated value
if the calculated factor a1 exceeds the of Pi.
manufacturer’s recommended value a larger
vessel has to be selected. a1 is then re-calculated 13.2.2 Automatic make-up unit. The automatic
to obtain an acceptable lower value. make-up unit is a device to ensure the initial system
design pressure is maintained. A separate small
j) Re-calculate the new value of Pf in bar gauge, pump and associated cold water break tank is
related to the selected vessel. The new final provided for the purpose of introducing water into
system design pressure will be: the system to make up for losses, etc. This may
P i + a1 incorporate a small hydraulic accumulator to reduce
Pf = -------------------
- the frequency of pump starting.
1 – a1
The electrical supply to this unit should not be
k) Calculate the safety valve set pressure subject to unauthorized disconnection.
Pmax = Pf + 0.3 bar, for systems up to 5 bar;

© BSI 09-1999 13
BS 7074-3:1989

13.2.3 Safety valve. A device to ensure that the 13.4 Constructional details
pressure in the system does not exceed a Ancillaries should be selected from those
predetermined level. constructed of corrosion-resistant material of
13.2.4 Pressure gauge. adequate strength.
13.2.5 Thermometer. All fastenings should comply with relevant
13.2.6 High pressure switch. A device which causes standards.
the heat source to shut off when a predetermined All electrical wiring and equipment should comply
maximum system pressure is reached. The pressure with the detailed requirements of the Regulations
at which this switch operates should not be less for the Electrical Equipment of Buildings (published
than 0.3 bar below the safety valve pressure setting. by the Institution of Electrical Engineers), or be in
A manual reset and/or alarm may be incorporated. accordance with appropriate regulations.
13.2.7 Low pressure switch. A device which causes Dials or scales, where fitted, should be clearly
the heat source to shut off when a predetermined visible.
minimum system pressure is reached, All equipment (valves, pipework and fittings)
normally 0.3 bar below Pi. should meet the requirements of the local water
13.2.8 Temperature controller (thermostat). A device authority.
to control the system water-flow temperature. 13.5 Installation instructions
13.2.9 Air separator. A device that separates air and
Clear instructions regarding installation, operation
other gases from suspension in the system water.
and maintenance should be included with each
13.2.10 Automatic air vent. A device that ancillary item.
automatically allows air to be vented from a part of
a system. Hygroscopic devices are not 13.6 Marking
recommended. Each ancillary item should carry the following
13.3 Pressure and temperature ratings information:
a) manufacturer’s or agent’s name or symbol;
13.3.1 The maximum operating temperature and/or
pressure should be stated on a label affixed to the b) serial number or batch number where
ancillary, or clearly stated in the instructions for practicable;
installing and operating the ancillary. c) temperature rating or pressure rating where
13.3.2 Where the maximum operating pressure is appropriate;
stated in accordance with 13.3.1 the test pressure d) electrical rating where appropriate;
should be 1.5 times the stated value. e) indication of year of manufacture.
13.3.3 The lift pressure of a safety valve should be
determined by the manufacturer and should be
clearly stated on a label affixed to the body of the
valve. The operating mechanism should be sealed by
the manufacturer. Adjustable safety valves, or
safety valves that allow the opening pressure to be
increased deliberately or otherwise, would not be in
accordance with the recommendations of this
standard.
13.3.4 Pressure switches should operate
consistently within ± 0.15 bar of the set point and
required value. Incremental adjustment is
preferable. The switch should be provided with a
device to indicate clearly when it has tripped out.
Audio alarms should be attenuatable and audio and
visual alarms should be positioned where they can
be clearly identified.
13.3.5 Temperature limit switches and temperature
controllers should operate consistently within ± 2 °C
of the set point and required value. Incremental
adjustment is preferable. The switch should be
provided with a device to indicate clearly when it
has tripped out.

14 © BSI 09-1999
© BSI 09-1999

BS 7074-3:1989
Figure 6 — Condenser water (heat reclaim) system
15
BS 7074-3:1989

Appendix A Examples of recommended procedure for the calculation of the size


of expansion vessels
A.1 Example 1: Chilled water system
A four storey building is to be cooled by provision of air conditioning units through which chilled water is
to be circulated from a central plant room situated on the roof. The height of the plant room at roof level
is 2 m and from ground floor to roof is 14 m. The capacity of the system is 6 000 L and the working solution
will be 35 % anti-freeze and 65 % water. The flow and return temperatures at the evaporator will be 4 °C
and 10 °C respectively. The maximum ambient temperature is taken to be 24 °C. The circulating pump will
be situated as shown in Figure 4 and the anticipated head is 100 kN/m2. Because a roof top plant room is
used pressures exceeding Pf will occur at other points in the system. After taking account of clause 8 and
referring to 9.3, the calculation of the size of the vessel is undertaken as follows.
The system water content (Vs) is 6 kL; the maximum ambient temperature (ta) is 24 °C; from Figure 5, e
will be 0.9 %. The highest point in the system cannot exceed the height of the roof top plant room which
is 2 m, therefore Ph = 2 ÷ 10.24) giving 0.196 bar.
The initial system design pressure Pi = Ph + Ps, where Ps is 0.35 bar; therefore Pi = 0.196 + 0.35 = 0.546 bar.
In practice it has been found advantageous to ensure that Pi is always at least 0.7 bar.
The roof location of the plant room requires a different approach to the calculation of Pf. The total vessel
volume (Vt) is calculated using the manufacturer’s recommended design acceptance factor a):
Va
V t = -------
-
a
6000 × 0.9
where Va is ----------------------------- giving 54 L
100
and a is 0.35 as a manufacturer’s recommendation.
54
V t = ----------- = 154.28 L
0.35
To this is added a 10 % margin giving a calculated vessel volume of 169.70 L.
The manufacturer’s literature is consulted to select an appropriate sized vessel (s), which, for this example
could be 180 L capacity, providing a 16.67 % margin.
The new acceptance factor ai, will be

The final working pressure (Pf) is now calculated:

The safety valve set pressure (Pmax) will be 1.4285 + 0.5 = 1.9285 bar and the nearest practical valve setting
would be 2 bar.
The ground floor air conditioning units will experience maximum pressure when the safety valve is about
to open and this could coincide with an isolating valve being closed on the suction side of the pump so that
the pump closed-valve-head is imposed on the system.
Maximum working pressure = Pmax + Pd + Pcv where Pd is 13 m ÷ 10.24) giving 1.275 bar and Pcv
is 100 kN/m2 + 15 % giving 1.15 bar.
Therefore maximum working pressure = 2 + 1.275 + 1.15
= 4.425 bar
It is recommended that the system be filled to Pf, i.e. 1.4285 bar, before the chiller is put into service so that
the pressure may drop to Pi when at normal working temperature.

4)
The factor 10.2 is used to convert static height pressure of water to pressure in bar gauge.

16 © BSI 09-1999
BS 7074-3:1989

A.2 Example 2: Condenser water system


The system is to have a closed condenser water circuit for the chiller having a capacity of 450 L and a
cooling tower located close by. The heat transfer medium is a solution of 35 % anti-freeze and 65 % water
with flow and return temperature at the condenser of 21 °C and 37 °C respectively. The pump is located
between the expansion vessel connection and the condenser with a head of 70 kN/m2. After taking account
of clause 11 and referring to 12.3, the calculation of the size of the vessel is under-taken as follows.
The system content (Vs) is 450 L; the flow water temperature is 37 °C; from Figure 5, e will be 1.6 %.
For Ph and Pi the minimum value for Pi of 0.7 bar is used.
The roof location of the plant room requires a different approach to the calculation of Pf. The total vessel
volume (Vt) is calculated using the manufacturer’s recommended design acceptance factor a):

450 ´ 1.6
where Va is ------------------------ giving 7.2 L
100
and a is 0.35 as a manufacturer’s recommendation.

To this is added a 10 % margin giving a calculated vessel volume of 22.62 L.


The manufacturer’s literature is consulted to select an appropriate size vessel(s), which for this example
could be 25 L capacity, providing a 21 % margin.
The new acceptance factor ai, will be:

The final working pressure (Pf) is now calculated:

The safety valve set pressure (Pmax) will be:


Pmax = Pf + 0.5 = 1.3876 + 0.5 = 1.8876
and the nearest practical valve setting would be 2 bar.

© BSI 09-1999 17
18 blank
BS 7074-3:1989

Publications referred to

BS 4814, Specification for expansion vessels using an internal diaphragm, for sealed hot water heating
systems.
Chartered Institution of Building Services Engineers — Commissioning Codes — Guide, 1970.
Institution of Electrical Engineers — Regulations for the Electrical Equipment of Buildings.

© BSI 09-1999
BS 7074-3:
1989
BSI — British Standards Institution
BSI is the independent national body responsible for preparing
British Standards. It presents the UK view on standards in Europe and at the
international level. It is incorporated by Royal Charter.

Revisions

British Standards are updated by amendment or revision. Users of


British Standards should make sure that they possess the latest amendments or
editions.

It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using
this British Standard would inform the Secretary of the technical committee
responsible, the identity of which can be found on the inside front cover.
Tel: 020 8996 9000. Fax: 020 8996 7400.

BSI offers members an individual updating service called PLUS which ensures
that subscribers automatically receive the latest editions of standards.

Buying standards

Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.

In response to orders for international standards, it is BSI policy to supply the


BSI implementation of those that have been published as British Standards,
unless otherwise requested.

Information on standards

BSI provides a wide range of information on national, European and


international standards through its Library and its Technical Help to Exporters
Service. Various BSI electronic information services are also available which give
details on all its products and services. Contact the Information Centre.
Tel: 020 8996 7111. Fax: 020 8996 7048.

Subscribing members of BSI are kept up to date with standards developments


and receive substantial discounts on the purchase price of standards. For details
of these and other benefits contact Membership Administration.
Tel: 020 8996 7002. Fax: 020 8996 7001.

Copyright

Copyright subsists in all BSI publications. BSI also holds the copyright, in the
UK, of the publications of the internationalstandardization bodies. Except as
permitted under the Copyright, Designs and Patents Act 1988 no extract may be
reproduced, stored in a retrieval system or transmitted in any form or by any
means – electronic, photocopying, recording or otherwise – without prior written
permission from BSI.

This does not preclude the free use, in the course of implementing the standard,
of necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.

If permission is granted, the terms may include royalty payments or a licensing


agreement. Details and advice can be obtained from the Copyright Manager.
BSI Tel: 020 8996 7070.
389 Chiswick High Road
London
W4 4AL

You might also like