Professional Documents
Culture Documents
Test Paper of Geotech1
Test Paper of Geotech1
2.
4.
9.
5.
6.
JH ACADEMY
Page 1
Sub: Geotechnical Engineering
11. A coarse grained soil has a void ratio 0.75 and specific gravity is 2.75. the
critical gradient at which quick sand condition occurs is a) 0.25 b) 0.50 c) 0.75
d) 1.00 12. The weight of a Pycnometer containing 400g sand and water full to the
top is 2150gr. The weight of Pycnometer full of clean water is 1950g. if specific
gravity of the soil is 2.5, the water content is a) 5% b) 10% c) 15% d) 20% 13. A
permeameter of 82.5mm diameter contains a column of the fine sand 460mm long. When
water flows through it under a constant head at a rate of 191 , the loss of head
between two points 250mm apart is 380mm. calculate the coefficient of permeability?
If the falling head test is made on the same sample using a stand pipe of diameter
30mm, in what time the water level in stand pipe fall from 1560mm to 1066mm above
out flow level? 14. A 10m thick layer of clay is under lained by a 4m thick layer
of sand. The water table is at a depth of 4m from the ground level. The void ratio
of clay is 0.65 and specific gravity is 2.67 water content above the saturated soil
is 17% and void ratio of the sand is 0.567 and G= 2.65. Determine total and
effective stress. 15. A borrow area soil has a natural water content of 10% and the
bulk density of 1.8Mg/ . The soil is used for an embankment to be compacted at 18%
moisture content to a dry density of 1.85Mg/ . Determine the amount of water to be
added to 1 of borrow soil. How many of excavated soil required for embankment. 16.
A new canal is excavated to a depth of 5m below ground level through a soil having
the following characteristics. C=14KN/ the slope of banks is . Calculate the factor
of safety with respect to cohesion when the canal runs full. If it is suddenly and
JH ACADEMY
Page 2
Sub: Geotechnical Engineering
21. The load from a continuous footing of width 2m, which may be considered to be
strip load of considerable length, is 200KN/ . Determine the maximum principal
stress at 1.5m depth below the footing, if the point lies (i) directly below the
centre of the footing (ii) directly below the edge of the footing, (iii) 0.8m away
from the edge of the footing. 22. In a laboratory consolidometer test on a 20mm
thick sample of saturated clay taken from a site, 50% consolidation point was
reached in 10min. Estimate the time required for the clay layer of 5m thickness at
the site for 50% compression if there drainage only towards the top. What is the
time required for the clay layer to reach 50% consolidation if the layer has double
drainage instead of single drainage. 23. A layer of soft clay is 6m thick and lies
under a newly constructed building. The weight of sand overlying a clay layer
produces a pressure of 2.6Kg/ and the new construction increases the pressure by
1.0kg/ . If the compression index is 0.5. Compute settlement. Water content is 40%
and specific gravity of grains is 2.65. 24. A vane, 10cm long and 8cm in diameter,
was pressed into soft clay at the bottom of a bore hole. Torque was applied and
gradually increased to 45N-m when failure took place. Subsequently, the vane
rotated rapidly so as to completely remould the soil. The remoulded soil was
sheared at a torque 18N-m. Calculate the cohesion of clay in the natural and
remoulded states and also the value of the sensitivity. 25. A cut 9m deep is to be
made in clay with a unit weight of 18KN/ and cohesion of 27KN/ . A hard stratum
exists at a depth of 18m below the ground surface. Determine from Taylor’s
stability number of factor of safety is 1.5. 26. In a consolidation test the
following results were obtained. When the load was changed from 50KN/ to 100KN/ ,
JH ACADEMY
Page 3
Sub: Geotechnical Engineering
32. A building 10m in plan is built on a raft foundation resting on the surface.
The soil profile consists of 4m dense sand over 3m thick silty clay resting on
rock. The water table is at 2m below ground level. Consolidation test conducted on
UDS of clay layer gave the following results. Initial and final void ratios and
corresponding stresses are , =1.0, ̅ KN/ . If the weight of the building is 1000KN.
What is the settlement? 33. Calculate the ultimate bearing capacity per unit area
of (i) strip footing 2.5m wide (ii) square footing 4.75 (iii) circular footing 5.2m
dia. The footing is supported on a soil for which the following data is available.
KN/ .c=17KN/ , depth=1.75m,
JH ACADEMY
Page 4
Sub: Geotechnical Engineering
of uniform clay laboratory unconfined compression tests on undistributed samples
indicates an average unconfined compressive strength of 75KN/ . Calculate the
ultimate load capacity of the pile. Take adhesion factor as 0.8 and as 9. 44. A
group of 4 4 piles is driven to bear in a dense sand layer 2.5m thick. Pile spacing
is 1.0m c/c, diameter is 0.4m. the total load on top is 3000KN. A compressible
layer of clay, 2m thick exists below dense sand. Clay is underlained by rock. Find
the settlement of pile group if co-efficient of volume compressibility of clay
layer is 1.5 /KN. 45. A smooth vertical wall of 4.5m high, retains a soil with c=
25KN/ , The horizontal backfill surface carries a uniform surcharge load 50KN/ .
The retaining wall is tend to move towards the soil. What is the magnitude and
point of application of total pressure? 46. Determine the safe load carrying of
pile group consists of 9 friction pile of 30cm diameter and 12m lengths driven in
soft clay. F.S=3, 0.6. 47. A square pile group of 16 piles penetrates through a
filled up soil of 3m depth. The pile diameter of 250mm and file spacing is 0.75m.
The unit cohesion of the material is 18KN/ . And the unit weight of soil is 15KN/
compute the negative skin friction on the group. 48. The load carrying capacity
(against shear failure) of a surface square footing founded on sandy soil is 800
KN. If the size of the square footing is reduced by one half, what will be its load
carrying capacity against shear failure? 49. Determine the depth at which a
circular footing of 3.3m diameter be found to be provided to carry a safe load of
1500KN with a factor of safety of 2.40. the
JH ACADEMY
Page 5
Sub: Geotechnical Engineering
59. A barrow pit soil has a dry density of 17KN/ . How many cubic meters of this
soil will be required to construct an embankment of 100 volume with a dry density
of 16KN/ a) 94 b) 106 c) 100 d) 90 b) c) d) =
60. The void ratio and specific gravity of a soil are 0.65 & 2.72 respectively. The
degree of saturation (%) corresponding to water content of 20% is a) 65.3 b) 20.9
c) 83.7 d) 54.4 61. A saturated soil mass has a total density 22KN/ and water of
10%. The bulk density and dry density of the soil are a) 12KN/ and 20KN/ b) 22
&20KN/ c) 19.8 &19.8KN/ d) 23.2 & 19.8KN/
66. In this natural condition, a soil sample has a mass of 1-980kg and a volume of
0.001 . After being completely dried in an oven, the mass of sample is 1.8kg.
Specific gravity G is 2.7. Unit weight of water is 10KN/ . The degree of saturation
of the soil is a) 0.65 b) 0.70 c) 0.54 d) 0.61 67. The maximum possible value of
group index for a soil is . 68. The description sandy silty clay signifies that a)
The soil contains unequal proportions of the three constituents in the order sand >
silt > clay b) The soil contains equal proportions of sand, silt and clay c) The
soil contains unequal proportions of three constituents such that clay>silt>sand d)
There is no information regarding the relative proportions of the three 69. The
Atterberg limits of clay are 38%, 27% and 24.5%. Its natural water content is 30%.
The clay is in state. 70. A soil having particles of nearly the same size is known
as a) Well graded b) Uniformly graded c) Poorly graded d) Gap graded 71. The
consistency of saturated cohesive soil is affected by a) Water content b) Particle
size distribution c) Density index d) Co-efficient of permeability 72. The equation
of A-line in the plasticity chary is . 73. The particle size distribution curves
are extremely useful for the classification of a) Fine grained soils b) Coarse
grained soils c) Both fine and coarse grained soils d) Silts and clays
62. The water content of saturated soil and the specific gravity of soil solids
were found to be 30% and 2.7 respectively. Assuming the unit of water to be 10KN/ ,
the saturated unit weight (KN/ ) and the void ratio of the soil are a) 19.4, 0.81
b) 18.5, 0.30 c) 19.4, 0.45 d) 18.5, 0.45 63. The saturated unit weight of the sand
(KN/ ) is to be find for water content= 20%, G= 2.7 and =10KN/ a) 15 b) 18 c) 21 d)
24 64. A saturated undistributed sample from a clay stratum has moisture content of
22.22% and specific weight is 2.7. assuming =10KN/ , the void ratio and saturated
unit weight of clay respectively are a) 0.6 and 16.875KN/ b) 0.3 and 20.625KN/ c)
0.6 and 20.625KN/ d) 0.3 and 16.975KN/ 65. In a compaction test, G, W, S, and e
represent the specific gravity, water content, degree of saturation and void ratio
of the soil sample respectively. If represents unit weight of water and represents
the dry unit weight of the soil, the equation for zero-air voids line is a)
JH ACADEMY
Page 6
Sub: Geotechnical Engineering
74. Consistency index for a clay soil is a) b) c) LL-PL d) 0.5w 75. Some of the
structural strength of a clayey material is lost by remolding is slowly recovered
with time. This property of soils to undergo an isothermal gel-to-sol-to-gel
transformation upon agitation and subsequent rest is termed a) Isotropy b)
Anisotropy c) Thixotropy d) Allotropy 76. The values of liquid limit and plasticity
index for soils having common geological origin in a restricted locality usually
define a) A zone above A-line b) A straight line parallel to A-line c) A straight
line perpendicular to A-line d) Points may be anywhere in the plasticity chart 77.
The toughness index of a clayey soils is given by a) Plasticity index/flow index b)
Liquid limit/plastic limit c) Liquidity index/plastic limit d) Plastic limit/
liquidity index 78. Soil has been compacted in an embankment at bulk density of
2.15Mg/ and a water content of 12%. The value of specific gravity of soil solids is
2.65. The water table is well below the foundation level. Estimate the dry density,
void ratio, degree of saturation and air content of compacted soil. 79. The un
drained cohesion of a remoulded clay soil is 10KN/ . If the sensivity of the clay
is 20, the corresponding remoulded compressive strength is a) 5KN/ b) 10KN/ c)
20KN/ d) 200KN/
82. Laboratory sieve analysis was carried out on a soil sample using complete set
of standard IS sieves. Out of 500gr. Of soil used in the test, 200g was retained on
IS600 size, 250g was retained on IS-500 sieve and remaining 50g was retained on IS-
425 sieve a) The Coefficient of uniformity of soil is a. 0.9 b. 1.0 c. 1.1 d. 1.2
b) The classification of soil is a. SP b. SW c. CI d. GW 83. Sieve analysis on a
dry soil sample of mass 1000g showed that 980g and 270g of soil pass through 4.75mm
and 0.075mm sieve, respectively. The liquid limit and plastic limit of the soil
fraction pass through 425 sieves are 40% and 18% respectively. The soil may be
classified as a) SC b) MI c) CI d) SM 84. Group symbols to silty sand and clayey
sand are respectively a) SS and CS b) SM and CS c) SM and SC d) MS and CS
80. A soil mass contains 40% gravel, 50%sand & 10% silt. The soil can be classified
as a) Silty sandy gravel having co-efficient of uniformity less than 60
JH ACADEMY
Page 7
Sub: Geotechnical Engineering
85. The liquid limit (LL), plastic limit (PL) and shrinkage limit (SL) of a
cohesive soil satisfy the relation a) LL>PL>SL b) LL>PL>SL c) LL>PL<SL d) LL<PL>SL
86. The laboratory test results of a soil sample are given be Percentage finer than
4.75mm=60 Percentage finer than 0.075mm=30 Liquid limit=35% plastic limit=27% The
soil classification is a) GM b) SM c) GC d) ML-MI 87. A fine grained soil has
liquid limit of 60 and plastic limit of 20. AS per the plasticity chart, according
to IS classification the soil is represented by the letter symbols a) CL b) CJ c)
CH CL-ML 88. A construction site is 3m thick clay layer is followed by a 4m thick
gravel layer, which is resting on impervious rock. A load of 25KN/ is applied
suddenly at the surface. The saturated unit weights of the soil are 19KN/ and 20KN/
for the clay and gravel layers, respectively. The water table is at the surface
draw diagrams showing variation with depth of total neutral and effective stresses
in the layers. 89. The soil profile at the bottom of the valley comprises 2m of and
overlying 10m of clay. The clay layer itself is resting on highly permeable
weathered sand stone. The unit wt. of sand above water table, which is 1m below the
water table it is 20KN/ . The saturated unit wt. of clay is 22KN/ . If the water
table in the sand stone layer is under artesian condition, corresponding to a stand
pipe level at 5m above the ground plot the variation of (i) total stress (ii) pore
water pressure (iii) effective stress with depth. 90. State true or false:
effective stresses in a sand layer below a lake do not alter as level fluctuates.
94. The total unit weight of the glacial outwash is 16KN/ =10KN/ . The specific
gravity of the solids is 2.67. the water content of the soil is 17% calculate a) b)
c) e d) S 95. A layer of saturated clay 5m thick is over laid by sand 4.0m deep.
The water table is 3m below the top surface. The saturated unit weight of sand is
18KN/ and 20KN/ respectively. Above the water table, the unit weight of sand is
17KN/ . Calculate the effective pressures on a horizontal plane at a depth of
9mbelow the ground surface. What will be the increase in the effective pressure at
9m if the soil gets saturated by capillary, up to height of 1m above the water
table? =9.81KN/
JH ACADEMY
Page 8
Sub: Geotechnical Engineering
96. A 5m thick clay layer lies between two layers of sand each 4m thick, the top of
the upper layer of sand being at ground level. The water table is 2m below the
ground level but the lower layer of sand is under artesian pressure the piezometric
surface being 4m above ground level. Of clay is 20KN/ & of sand is 19KN/ . Above
water table of sand is 16.5KN/ . Calculate the effective stresses at top and bottom
of the clay layer. 97. Data from a sieve analysis conducted on a given sample of
soil showed that 67% of the particles passed through 75 . The and of the finer
fraction was found to be 45% and 33% respectively. The group symbol is a) SC b) MI
c) CH d) MH 98. For the soil strata shown in fig. the water table is lowered by
drainage by 2m and if the top 2m thick silty sand stratum remains saturated by
capillary action even after lowering of water table. The increase in effective
vertical pressure in KPa at mid height of clay layer will be
100. Assuming that a river bed level does not change and the depth of water in
river was 10m, 15m and 8m during the months of February, July and December.
Respectively of a particular year. =20KN/ . 10KN/ . The effective stress at a depth
of 10m below river bed during these months would be Feb July dec a) 300 350 320 b)
100 100 100 c) 200 250 180 d) 300 350 280 101. The coefficient of permeability of a
soil is 5 cm/sec for a certain pore fluid. If the viscosity of the pore fluid is
reduced to half, the co-efficient of permeability will be a) 5 cm/sec b) 10 cm/sec
c) 2.5 cm/sec d) 1.25 cm/sec 102. The piezometric head at point C, in the
experimental set up shown in fig. when
JH ACADEMY
Page 9
Sub: Geotechnical Engineering
the flow takes under constant head through the soils A and B is a) 0 cm b) 40 cm c)
80 cm d) 120 cm
103. According to Darcy’s law for flow through porous media, the velocity is
proportional to a) Effective stress b) Hydraulic gradient c) Cohesion d) Stability
number 104. In a falling head permeameter test on a silty clay sample, the
following results were obtained: sample length 120mm; sample diameter;80mm; initial
head 1200 mm, final head 400mm, time for fall in head 6 minutes, stand pipe
diameter 4mm, find the coefficient of permeability of the soil in mm/sec 105. The
two tubes shown in fig. may be considered to be permeameter. Dimensions of the
sample in Fig (i) & (ii) are alike, and the elevations of head water and tail water
are the same for both the figures. A, B. . . etc. indicate points and
AB,AE. . .etc. indicate heads loss through these samples are a) (i) BD (ii) FB b)
(i) AC (ii) AE
106. Estimate the flow quantity (in liters/ sec) through the soil the pipe shown
below. The pressure heads at two locations shown in figure. The internal diameter
of pipe is 1m and coefficient of permeability is 1 m/sec
107. In filling head permeability test the initial head of 1.0m dropped to 0.35m in
3 hours, the diameter of stand pipe 5mm. the soil specimen was 200mm long and 100mm
diameter. The coefficient of permeability of the soil is a) 4.86 cm/sec b) 4.86
cm/sec c) 4.86 cm/sec
JH ACADEMY
Page 10
Sub: Geotechnical Engineering
d) 4.86 cm/sec a) b) c) d)
108. In a constant head permeameter with cross section area of , when the flow was
taking place under a hydraulic gradient of 0.5, the amount of water collected in 60
section is 600 cc. the permeability of the soil is a) 0.002 cm/s b) 0.02 cm/s c)
0.2 cm/s d) 2.0 cm/s 109. The soil profile below a lake with water level at
elevation =0 m and lake bottom at elevation =-10 m is shown in fig. where k is
permeability co-efficient. A piezometer installed in sand layer shows a reading of
+10 m elevation. Assume that the piezometric head is uniform in the sand layer. The
quantity of water (in ) flowing into the lake from the sand layer through the silt
layer per unit area of lake bed is a) 1.5 b) 2.0 c) 1.0 d) 0.5
111. A sampling tube has inner diameter of 72mm and an outer of 75mm. The area
ratio is . 112. A saturated clay layer of 5m thickness takes 1.5 year for 50%
primary consolidation when drained on both sides. Its coefficient of volume
change /KN. Determine coefficient of compressibility (in ) and the coefficient of
permeability (in m/yr.) Assume KN/ 113. The coefficient of consolidation is used
for a) Establishing the duration of primary consolidation b) Establishing the
amount of settlement for a load increment c) Determining the depth to which the
soil is stressed when loads are applied on the surface of a soil deposit d)
Determining the pre-consolidation pressure for soil deposits known to be over-
consolidated. 114. A standard Oedometer test in the laboratory indicated that 0.02
m thick clay specimen took 0.5 day to undergo 90% primary consolidation. How many
days will a 2m thick layer of identical clay sandwiched between sand layers and
subjected to an identical stress increment take to undergo the same? 115. The
number of flow channels and head drops is 4 and 12 respectively. If the difference
in the U/s and d/s water levels is 3 m, what is the discharge per m width of a
sheet pile wall, if K=0.1 m/s? 116. A footing 1.5 m square is located 1.5 m below
the surface of a uniform soil deposit of density 20 KN/ . If the total thickness of
the deposit, which is underlain by rock strata, is 3.5 m, compute the primary
JH ACADEMY
Page 11
Sub: Geotechnical Engineering
consolidation settlement of footing when it carries a load of 225 KN. 2:1
distribution is to be used. Consider 2 layers. 117. A homogeneous anisotropic earth
dam which is 20m high constructed on an impermeable foundation. m/s and m/s. the
water level on reservoir side is at 18m from the base of the dam. Downstream side
is dry. It is seen that there are 4 flow channels and 18 equi potential drop in a
square flow net drawn in the transformed dam section. Estimate the quantity of
seepage per unit length. 118. In the laboratory test on a clay sample of thickness
25mm drained at top only, 50% consolidation occurred in 11 minutes. Find the time
required for the corresponding clay layer in the field 3m thick and drained at top
and bottom, to undergo 70% consolidation. Assume a) b) c) d)
119. A 20 mm diameter well fully penetrates a confined aquifer of 30m depth. For a
pumpage of 35 lit/sec the steady draw downs at 100 m and 300m distances from the
well are observed as 3.2m and 2.5m respectively. Estimate the K in m/day and
transmissibility of the aquifer in / day. Estimate also the draw down at the well.
(Transmissibility= permeability depth of aqifer) 120. A clay layer 8m thick is
subjected to a pressure of 70 KN/ . If the layer has a double drainage and
undergoes 50% consolidation ( ) in one year. Determine the coefficient of
consolidation? If the K is 0.04 m/year find settlement in one year. Use KN/ 121. A
soil mass has co-efficient of horizontal and vertical permeability as cm/s and 4
cm/s respectively. The transformed permeability of an equivalent isotropic soil
mass is
JH ACADEMY
Page 12
Sub: Geotechnical Engineering
The effective permeability soil is given by a) b) c) d) ( ( )
⁄
134. A 6m thick clay layer under goes 90% consolidation four times faster under two
way drainage as compared to one drainage in an identical clay of 15m thick, two way
drainage will be faster as compared to one way drainage by e) 8 times f) 4 times g)
2.5 times h) 2 times 135. The average effective over burden pressure on 10 m thick
homogeneous saturated clay layer is 150 KPa. Consolidation test on an undisturbed
soil sample taken from the clay layer showed that the void ratio decreased from 0.6
to 0.5 by increasing the stress intensity from 100 KPa to 300KPa (a=2.65) a) The
initial void ratio of clay layer is a. 0.209 b. 0.563 c. 0.746 d. 1.000
JH ACADEMY
Page 13
Sub: Geotechnical Engineering
b) The total consolidation settlement of the clay layer due to the construction of
a structure imposing an additional stress intensity of 200 KPa is a. 0.1 m b. 0.25
m c. 0.35 d. 0.5m 140. and strength.
can be by
137. A saturated clay stratum draining both at the top and bottom undergoes 50%
consolidation in 16 years under an applied load. If additional drainage layer were
present at the middle of the clay stratum, 50% consolidation would occur in a) 2
years b) 4 years c) 8 years d) 16 years 138. A well of diameter 20 cm fully
penetrates a confined aquifer. After a long period of pumping at rate of 2720
lit/min. The observations of draw down taken at 10 m and 100 m distances from the
centre of the well are found to be 3m and 0.5m respectively. The transmissibility
of the aquifer is a) 676 day b) 576 day c) 526 day d) 249 day 139. In a
consolidated drained tri axial test, a specimen of clay fails at a cell pressure of
60 KN/ . The effective shear strength parameters are KN/ and determine the
compressive strength.
144. The appropriate field test to determine the undrained shear strength of soft
clay is a) Plate load test b) Static cone penetration test c) Standard penetration
test d) Vane shear test 145. A given saturated clay is known to have effective
strength parameters of KPa and = . A sample of this clay was brought to failure
quickly so that no dissipation of the pore water pressures could occur. At failure
it was known that , = 10KPa and =20 KPa a) Estimate the values of at failure b)
What was the effective normal stress on the failure plane? c) What was the value of
un drained shear strength ?
JH ACADEMY
Page 14
Sub: Geotechnical Engineering
146. Vane test is normally used determining in situ shear strength of a) Soft clays
b) Sand c) Stiff clays d) Gravel for
147. What is the shear strength in terms of effective stress on a plane within a
saturated soil mass at a point where the total normal stress is 295 KPa and the
pore water pressure 120KPa? The effective shear strength parameters are 12 KPa And
= 148. If an element of a stressed body is in a state of pure shear with a
magnitude of 80N/ , the magnitude of maximum principal stress at that location is
a) 80 N/ b) 113.14 N/ c) 120 N/ d) 56.57N/ 149. In a drained tri axial compression
test conducted on dry sand, failure occurred when deviator stress was 218 KN at a
confining pressure of 61 KN . What is the effective angle of shearing resistance
and inclination of failure plane to major principle plane? e) f) g) h) a) 150. If
the effective stress parameters of a soil are =10 KPa and = , the shear strength on
a plane within the saturated soil mass at a point where the total normal stress is
300 KPa and pore water pressure is 150 KPa will be a) 90.5 KPa b) 96.6KPa c)
101.5KPa d) 105.5KPa 151. If the principal stresses in a two dimensional case are -
10 MPa and 20
151. A direct shear test was conducted on a cohesion less soil (c=0). Specimen
under a normal stress of 200KN/ . The specimen failed at a shear stress of 100KN/ .
The angle of internal friction of soil is a) 26.6 b) 29.5 c) 30.0 d) 32.6
152. An infinite slope, with a slope angle of , is made up of a cohesion less soil
having and KN/ . It experiences seepage with the water table at the surface. If the
unit weight of water is 10 KN/ , the factor of safety against failure, without
seepage and with seepage will be and Respectively. .
JH ACADEMY
Page 15
Sub: Geotechnical Engineering
155. A slope is excavated to a depth of 10m in a deep of 10m in a deep layer of
saturated clay of unit weight 20 KN/ . The relevant shear strength parameters are
KN/ and . The rock edge is at a great depth. The Taylor stability coefficient
coefficient for and slope angle is 0.18. the factor of safety of the load is a) 2.0
b) 2.1 c) 2.2 d) 2.3 156. A point load of 700 KN is applied on the surface of thick
layer of saturated clay. Using Boussinesq’s elastic analysis, the estimated
vertical stress ( ). At a depth of 2m and radial distance of 1.0m from the point of
application of the load is a) 47.5 KPa b) 47.6 KPa c) 47.7 KPa d) 47.8 KPa 157. An
infinite slope is to be constructed in a soil. The effective stress strength
parameters of the soil are . The saturated unit weight of the slope is 20 KN/ . And
the KN/ . Assuming that seepage is occurring parallel to the slope, the maximum
slope angle for a factor of safety of 1.5 would be a) 10. b) 11. c) 12. 14. 158. A
canal having side slopes 1:1 is proposed to be constructed in a cohesive soil to a
depth of 10m below the ground surface. The soil properties are KPa, e= 1.0, G= 2.65
a) If Taylor’s stability number, and if the canal flows fall, the factor of safety
with respect to cohesion against failure of the canal bank slopes will be a. 3.7 b.
1.85 c. 1.0 d. None b) If there is a sudden draw down of water in the canal and if
Taylor’s stability number for the reduced value of is 0.126, the factor of safety
with respect to cohesion against the failure of bank slopes will be a. 1.85 b. 1.18
c. 0.84 d. 0.53
161. The vertical stress at point due to the point load Q on the ground surface as
shown in fig. is . According to Boussinesq’s eqn, the vertical stress at will be a)
b) c) d)
JH ACADEMY
Page 16
Sub: Geotechnical Engineering
167. Soils transported by wind are known as soil. 162. An unsupported excavation is
to be made in a clay layer. If KN/ , c= 30KN/ and a. Calculate depth of tension
cracks b. Calculate the maximum possible unsupported depth c. Draw the active
pressure distribution diagram 163. Two consolidated drained shear tests on silt
yielded the following data: 0.2 0.46 0.4 0.88 If this material is used as a
backfill for a smooth vertical retaining wall of 10m height, what is the active
earth pressure at the base of the wall? Density of the fill is 1.6g/cc. 168. Plot
the active earth pressure distribution on the retaining wall shown by Rankine’s
theory for data given below 10 KN/ KN/ C=15 KN/
164. A large scale bearing capacity test on a footing of size 1.05 m at a depth of
1.5 m yielding on ultimate value of 141 KN unconfined compressive tests on the soft
saturated clay yielded a strength of 0.03 N/ . =1.6g/cc. How much does the test
value differ from that obtained using Terzaghi’s bearing capacity equation? 165.
For the trial slip circle shown in fig. calculate the factor of safety W= 346 KN/m
KN/ 20 KN/ radius = 9 m
169. The total active thrust on a vertical wall 3m high retaining a horizontal sand
backfill KN/ , when the water table is at the bottom of the wall, will be a) 30
KN/m b) 35 KN/m c) 40 KN/m d) 45 KN/m 170. Compute the intensity of passive earth
pressure at a depth of 8 m in cohesion less sand with an angle of internal friction
of when water rises to the ground level. KN/ , KN/
171. A vertical excavation was made in a clay deposit having unit weight of 22
KN/ . It caved in after the digging reached 4 m depth. Assuming . Calculate the
magnitude of cohesion 172. Two footings, one circular and the other square, are
founded on the surface of a purely cohesion less soil. The diameter of the circular
footing is same as that of the side of the square
166. A vertical wall 6 m high above the water table, retains a soil slope, 18 KN/
c=0, Ka= ?
JH ACADEMY
Page 17
Sub: Geotechnical Engineering
footing. The ratio of their ultimate bearing capacities is a) b) ⁄ ⁄
c) 1.0 d) 1.3 173. To have zero active pressure intensity at the tip of a wall in
cohesive soil one should apply a uniform surcharge intensity of a) tan b) cot c)
tan d) tan 174. 1. Find active earth pressure per meter of wall 2. find location of
the resultant line of action.
177. Soils that have been deposited from suspension in running water are called .
178. A sample of sand with G=2.65 has a porosity of 40%. Find out the . When fully
saturated when the degree of saturation is 50% 179. A clay sample has a liquid
limit of 42.5%, plastic limit of 22.4% and natural moisture content as 30%.
Determine its plasticity index and liquidity index. 180. In a shrinkage limit test
a 9.6 cc container was filled with soil slurry. The weight of the saturated soil
was 17.46 g. The slurry was then gradually dried first in atmosphere and then in an
oven at a constant temperature of C. The weight and volume of the dried soil were
11.58 g and 5.22 cc respectively. Determine the shrinkage limit of the soil. 181. A
sample of sand taken from a natural deposit has a porosity of 35%. For a volume of
495 cc the dry weights in the densest and loosest states are 1100 g and 800g
respectively. Compute the relative density of sand assuming the specific gravity of
solids to be 2.65 182. Laboratory sieve analysis was carried out on a soil sample
using complete set of sieves. Out of 1200 gm of sample, 480 gm retained on 4.75mm
sieve, 360 gm retained on 2 mm sieve and 240 gm retained on 75 sieve. Limit and
plastic limit of soil are 40%
175. A plate load test was conducted in sand on a 300 mm diameter plate. If the
plate settlement was 5 mm at a pressure of 100 KPa, the settlement of a5m
rectangular footing at the same pressure will be a) 9.4 b) 18.6 c) 12.7 d) 17.8
176. Estimate the resultant thrust and its location.
JH ACADEMY
Page 18
Sub: Geotechnical Engineering
and 20% respectively. Find cc, classify the soil according to IS. and
183. A barrow pit density is 18 KN/ . How many soil required to construct an
embankment of 200 with KN/ . 184. A compaction of an embankment is carried out in
300mm thick horizontal layers. The rammer used for compaction has the foot of area
0.05 sq.m. The energy developed per drop of the hammer is 40 kg-m. Assuming 50%
more energy I each pass due to overlap, calculate the number of passes required to
develop compactive energy equivalent to Indian standard (light compaction for each
layer). 185. The end of a clean glass tube is inserted in pure water. What is the
height of capillary rise, if the tube is a) 0.1 mm b) 0.001 mm in diameter. 186. A
sample of soil for a constant head permeability test yields following data: dia of
permeameter= 7.6 cm. length of soil sample = 20 cm, head causing flow = 15 cm,
quantity of water collected in 10 min = 150 cc. , KN/ . Determine a) Coefficient of
permeability in cm/s b) Superficial velocity flow c) Seepage velocity 187. For the
cases 1 and 2 of fig determine the pressure head, elevation head, total head and
head loss at the entering end, exit end and point X of the sample.
188. a) What is the quantity of water flowing per minute? b) To what height above
xx would the water rise in a piezometer inserted at points 1, 2 & 3? c) What is the
effective stress at mid height of soil A? Soil A: K= cm/s = 18 KN/ Soil B: K= cm/s
= 20 KN/
189. An deposit of fine sand the water table is 3m below the ground surface but the
sand up to a height of 1 m above the water table is saturated by capillary water.
The sand above this height may be considered dry. For the sand = 2.68 and ��=40%
calculate the effective stress at a depth of 8m 190. A falling head permeability
test was performed on a sand sample and the following data were recorded. c/s area
of permeameter=100 . Length of soil sample is 15 cm. area of stand
JH ACADEMY
Page 19
Sub: Geotechnical Engineering
pipe =1 , time taken for the head to fall from 150 cm to 50 cm =8min. temperature
of water= C dry mass of the soil specimen =2.2 kg and compute coefficient of
permeability of the soil for a void ratio of 0.70 and temperature of C 8.95 mill
poises 10.09 mill poises 191. Two rows of sheet piles are driven to a depth of 4.4
m below the bed of a river to form a coffer dam. Excavation is then carried out
within the coffer Dam up to a depth of 3.3m below water level by keeping the area
free from water by pumping. The river bed is sand with K=3 cm/s and is under lain
by an impermeable stratum at a depth of 6.0m below the river bed. What is the
quantity of flow into the coffer dam per hour per m. Length of the sheet pile
walls? Is there any danger of quick condition developing at the bottom of
excavation?
198. The effective stress shear strength parameters of a soil are = 25 KN/ and .
Determine the shearing resistance on a plane within
JH ACADEMY
Page 20
Sub: Geotechnical Engineering
a submerged soil mass where the total normal stress is 328 KN/ and pore water
pressure is 114 KN/ . 199. A symmetrical 16 pile group in soft clay, with
unconfined compressive strength of 40 KN/ is to be used as foundation for a column.
The piles are 300 mm in diameter and 10 m long. Determine the maximum load the
group can carry with piles failing (i) individually and (ii) as a block.
200. A precast pile is driven with a drop hammer weighing 50 KN with a fall of
1.5m. the average penetration of the load carrying capacity of pile according to
engineering news formula.
JH ACADEMY
Page 21