Installation of Potable Water at Baracbac Doliman
Installation of Potable Water at Baracbac Doliman
TECHNICAL S P E C I F I C A T I O N S
1. PROJECT BILLBOARD
A. For the information and guidance of the public about the on-going projects.
B. Standard size of 8ft x 8ft tarpaulin with white background printed all major details
about the project.
2. MOBILIZATION AND SETTINGS UP OF RIG
A. Preparation works for drilling, it should be based on planed depth and well
construction in the long term drilling activities.
A. The borehole for the well itself shall be drilled using a single drilling pass, in the
diameters specified. Once the drilling, sampling, geophysical borehole logging, and isolated
aquifer zone testing are completed.
A. Installation 2hp submersible pump and testing of pump leak and pressure test.
Upon completion of the all works covered, it is the duty of the contractor to remove and
clean all surface including the surroundings from paints and spots, dirt and other unsightly
objects. All finished shall be inspected and approved by the engineer. Any portion of the work
found not in conformity to standards shall be removed and or repaired at no extra cost before
the final turnover of the project.
Prepared By: