PROJECT PROJECT PROJECT END

PROJECT NAME
DURATION START DATE DATE

New Kitchen Renovation 27 May 01, 2017 May 28, 2017

May 01, 2017


May 02, 2017
May 03, 2017
May 04, 2017
May 05, 2017
May 06, 2017
Task
ID Task Description Duration Start Date End Date
1 Demolition 4 May 01, 2017 May 05, 2017 x x x x x
2 Install new tiles 2 May 06, 2017 May 08, 2017 x
3 Reroute current plumbing 2 May 09, 2017 May 11, 2017
4 Paint walls and ceiling 2 May 12, 2017 May 14, 2017
5 Install baseboards 1 May 15, 2017 May 16, 2017
6 Install fixtures 1 May 17, 2017 May 18, 2017
7 Place new appliances 1 May 19, 2017 May 20, 2017
8 Install new cabinetry 3 May 21, 2017 May 24, 2017
9 Install new lighting 1 May 25, 2017 May 26, 2017
10 Final delivery with customer 1 May 27, 2017 May 28, 2017
x
May 07, 2017

x
May 08, 2017

x
May 09, 2017

x
May 10, 2017

x
May 11, 2017

x
May 12, 2017

x
May 13, 2017

x
May 14, 2017

x
May 15, 2017

x
May 16, 2017

x
May 17, 2017

x
May 18, 2017

x
May 19, 2017
x
x May 20, 2017
May 21, 2017
x

May 22, 2017


x

May 23, 2017


x

May 24, 2017


x

May 25, 2017


x

May 26, 2017


x

May 27, 2017


x

May 28, 2017


May 29, 2017
May 30, 2017
May 31, 2017