Professional Documents
Culture Documents
Case Study On Long-Term Ground Settlement of Reclamation Project On Clay Deposits in Nansha of China (Soft Soil Creep - China)
Case Study On Long-Term Ground Settlement of Reclamation Project On Clay Deposits in Nansha of China (Soft Soil Creep - China)
Wei-Qiang Feng, Xian-Chang Zheng, Jian-Hua Yin, Wen-Bo Chen & Dao-Yuan
Tan
To cite this article: Wei-Qiang Feng, Xian-Chang Zheng, Jian-Hua Yin, Wen-Bo Chen & Dao-Yuan
Tan (2019): Case study on long-term ground settlement of reclamation project on clay deposits in
Nansha of China, Marine Georesources & Geotechnology, DOI: 10.1080/1064119X.2019.1704319
Figure 1. (a) Geometrical location of Binhai Garden reclamation site in Nansha, China, (b) locations of cone penetration tests, groundwater level monitoring points,
and ground settlement monitoring points at the reclamation site.
In this study, a typical reclamation project in Nansha, deposited. The thickness of soft clay layer varies from 10 m
which is Binhai Garden reclamation project, was selected to to 30 m. This soft soil is widely distributed in Nansha areas.
conduct the long-term settlement analysis because serious Many subsidence-related geologic hazards have been
settlement problems occurred in this reclamation project. encountered in this region due to the poor engineering
The undisturbed soil specimens were taken from the site, properties of soft clay. The substratum of the clayey soil is
and multi-staged incremental oedometer tests were con- usually silty sandy layer, regarded as a drained boundary.
ducted on fourteen undisturbed clayey soils to obtain the
values of compressibility parameter of the clayey soil along
the depth. Afterwards, triaxial hydraulic conductivity tests 2.2. Binhai Garden reclamation project
were conducted on nine soil samples to gain the values of In the 2000s, Binhai Garden reclamation project was con-
hydraulic conductivity. Then, the new simplified method, structed nearby a reclamation island of Nansha, which ini-
proposed by Yin and Feng (2017), and finite element model- tially was a paddy field. Three phases were subsequently
ing using soft soil creep (SSC) model and soft soil (SS) reclaimed before the construction of buildings in Nansha,
model for clayey soil were used to analyze the long-term (named as Phase 1, Phase 2, Phase 3), as illustrated in
ground settlement. In the reclamation project, the settle- Figure 1(b). According to geotechnical investigations, the
ments of different locations were monitored from January deposited clayey soil is around 20–30 m in depth, and
2011 and the measured data are regarded as the reference to underneath the clayey soil, there is a sandy soil layer with a
evaluate the performances of the new simplified method and
thickness of 2–10 m. Occasional sandy soil layer with 2 m in
finite element modeling.
thickness is encountered within the clayey soil in Phase 2
due to the complexity of deposition process. The site did
2. Geological and geotechnical conditions in Nansha not undergo any loading before the reclamation construc-
tion. As a result, the clayey soils are in the normally consoli-
2.1. Description of geological condition dated state, i.e., over-consolidation ratio (OCR) equals to 1.
Nansha area is situated in the geometric center of the Pearl Table 1 lists the construction information of three phases
River Delta, south of Guangzhou city, nearby the Shizi in Binhai Garden reclamation project. During the construc-
Ocean. Binhai Garden reclamation project lies 1 km to the tion, it is regarded as a ramp loading in the construction
south of Nansha. The plan view of Nansha area is shown in period for three phases. The unit weight of filling materials
Figure 1(a). Due to the long-term river alluvium and tides is 17.5 kN/m3, and the surcharge loadings are obtained from
retreat, organic silty clays including the silt and silty soil the heights of the reclamations and listed in Table 1. After
were deposited with some irregular silty sands. The deposits the reclamation, the building construction was directly car-
were formed during the Holocene (Wei and Wu 2011). ried out without any ground treatment. Foundations of the
During the sedimentary of transgression-regression cycles, building were designed as concrete piles with high strength,
the soft clay in Nansha is interactive and terrestrially which were directly seated on the bedrock.
MARINE GEORESOURCES & GEOTECHNOLOGY 3
2.2.2. Basic properties of soils in Binhai Garden Figure 2. Results of cone penetration tests at the site of three phases of Binhai
reclamation project Garden reclamation project.
Fourteen undisturbed soil samples were taken from the site
of three phases in the reclamation project with different
4 W.-Q. FENG ET AL.
Figure 3. Measured depths of groundwater with time in Binhai Garden reclamation project.
depths, as plotted in Figure 2. The soil samples were taken three disturbed soil samples were taken from the Farmland
in January 2014 and the laboratory tests including basic and shown in Figure 4. Figure 4 shows the basic properties
property tests, oedometer tests, and triaxial hydraulic con- of fourteen Nansha clays taken from the site of Binhai
ductivity tests were conducted in February 2014. It should Garden reclamation project. The organic content of clayey
be noted that the depth of eleven undisturbed soil samples soil is in the range of 1.7–4.2%, and the water content, w,
taken from site are also illustrated in Figure 2, whereas other mostly stays in the range of 40–70%. The density, qsoil ,
MARINE GEORESOURCES & GEOTECHNOLOGY 5
For the multi-staged incremental oedometer test, the regarded as the reference of the initial stress–strain state at
diameter of the specimen is 70 mm, and the thickness is the site. Therefore, based on the results of three phases and
19 mm (Yin 1999; Cheng and Yin 2005; Feng et al. 2017). farmland, it is deduced that the void ratio, e, in the middle
Top and bottom of the specimen were attached with filter of soil layer could be regarded as the initial void ratio.
paper. The silicone grease was utilized to minimize the pos- It can be observed that there is nearly no apparent verti-
sible friction (Sridharan and Gurtug 2004). The loading was cal pre-consolidation pressure, rzp , in these curves, which
applied with Wykeham Farrance conventional oedometers, illustrates the tested soil is in the normally consolidated
following the procedures described in British Standard state. This feature is consistent with the geotechnical investi-
(1990). The loading sequence is listed as: (loading) 10 kPa gation about the farmland. This confirms that we can take
! 25 kPa ! 50 kPa ! 100 kPa ! 200 kPa ! (unloading) the soil weight as the pre-consolidation pressure, rzp , to
100 kPa ! 50 kPa ! 25 kPa ! (reloading) 50 kPa ! determine the over-burden loading history. In other words,
100 kPa ! 200 kPa ! (loading) 400 kPa. In the loading the value of OCR is 1. Bjerrum (1954) discussed how the
stage, the loadings were maintained for 1 day while the load- apparent pre-consolidation pressure is related to the plasti-
ings were kept for more than 1 h during the unloading and city index and the leaching of the clayey soils. Lunne et al.
reloading stages, as suggested by Yin and Tong (2011). The (2006) emphasized the influences of sample disturbance and
temperature was kept at 2060:5 C in the soil laboratory to sampling equipment on the soil parameters including the
minimize the temperature effect. pre-consolidation pressures. Therefore, more advanced geo-
For the triaxial hydraulic conductivity test, the hydraulic technical test on Nansha clay is worth conducting in the
consolidation cell was adopted with the diameter of 70 mm future. Cr represents the slope of unloading-reloading lines
and the height of 140 mm. The effective confining pressure in the curves of e log r0z , and Cc denote the slope of linear
was controlled, and the void ratio can be calculated from portion of e log r0z at normally consolidated state. The
the measured water volume during the consolidation stage. corresponding values for parameters Cr and Cc can be
The detailed procedures followed BS 1377-6 (1990). The rate
obtained and plotted in Figure 9. It is found that Cr ranges
of flow Q was measured in the triaxial permeability test
from 0.0414 to 0.0734, and Cc varies from 0.122 to 0.423.
within 4 hours for each effective confining pressure. The ver-
These values are very close to those of Hong Kong Marine
tical hydraulic conductivity (kv in unit of m/s) can be calcu-
Deposits (HKMD) (Zhu, Yin, and Graham 2001; Yin and
lated as:
Feng 2017; Feng and Yin 2017; Feng et al. 2017).
1:63QL
kv ¼ Rt 104 (2)
Afðp1 p2 Þ pc g
3.2. Viscosity of Nansha clay
where L is the height of soil specimen (in mm), A is the
cross area of the soil sample (in mm2), ðp1 p2 Þ is the dif- It has been demonstrated, from the results of multi-staged
ference of the bottom and top pressure in the test, pc is the incremental oedometer test, that the viscous behavior of
loss of the pressure in the triaxial cell, which is calibrated as Nansha clayey soil is also an important feature (Luo and
1 kPa, Rt is the correction factor of temperature on the vis- Chen 2014). As shown in Figure 7, the creep behavior is
cosity of water, and it is taken as 1 when the temperature also observed, and creep coefficient, Cae , is defined in this
is 20 C. study to describe the viscous behavior:
De
Cae ¼ (3)
3.1. Compressibility of Nansha clay D log ðtÞ
Taking one soil specimen in Phase 1 as an example, the where De is the change of void ratio, D log ðtÞ represents the
relationships of vertical strain and time (in log scale) in change of time in log-scale. Figure 10 presents the evolution
loading, unloading, and reloading stages are shown in of creep coefficient versus r0z for three stages of Nansha clay
Figure 7. Figure 8 presents the curves of e logðr0z Þ (void with varying depths. It is found that values of creep coeffi-
ratio versus log vertical effective stress), obtained from con- cient, Cae , increases linearly with the vertical loading within
ventional oedometer test, for all undisturbed samples from 100 kPa, while values of creep coefficient remain constant
different depths. when the loading is larger than 200 kPa. This is because the
From the experimental results of samples at different undisturbed soil specimens from the field are mostly below
depths in Phase 1 and Phase 2, it is found that initial void the depth of 10 m, and the added fill loading is also grad-
ratio, eo , in the middle part of the clayey soil layer is larger ually transferred to the soil skeleton structure in the process
than that at the top and the bottom. This is because of the of sedimentation. Previous test results are also used to com-
top and bottom drainage boundary of consolidation and pare with the measured creep coefficient, and the data are
sedimentary process of clayey soils. However, since the in good consistency with the tested result in Phase 2 and
period after completion of the filling is very short for Phase Phase 3. In order to minimize the errors, the average value
3, the initial void ratio, eo , in this Phase decreases with the of creep coefficient is adopted: for Phase 1, the value of
depth, which is mainly related to the sedimentary effect. In creep coefficient, is taken as 0.01414, and the creep coeffi-
addition, the soil specimens taken from the farmland nearby cients for Phase 2 and Phase 3 are 0.00935 and 0.01047,
Binhai Garden were also tested and their results are respectively.
MARINE GEORESOURCES & GEOTECHNOLOGY 7
Figure 7. Relationship of strain versus log(time) from a multi-staged oedometer test on a soil sample (from 10 m depth) in Phase 1 of Binhai Garden reclamation
project under loading, unloading, and reloading stages.
3.3. Hydraulic conductivity of Nansha clay above, and the corresponding hydraulic conductivity values
are obtained as 3.004 109 m/s, 1.95 109 m/s, and
The hydraulic conductivity is an important parameter in
1.82 109 m/s for Phase 1, Phase 2, and Phase 3, respect-
many geotechnical settlement problems (Nagaraj and Miura ively, as presented in Figure 11. Values of Ck are obtained
2001). Triaxial testing was conducted on nine soil specimens as 0.4432, 0.935, 0.3788 for Phase 1, Phase 2, and Phase 3,
to obtain the hydraulic conductivity value of Nansha clay, respectively. It should be noted that only the values of
and results of the calculated values from Equation (2) with vertical permeability were measured in the triaxial hydraulic
different void ratios are plotted in Figure 11. conductivity tests because there is no horizontal drainage in
Based on triaxial hydraulic conductivity tests, there is a the site of Binhai Garden. Generally, the horizontal perme-
nonlinear relationship between the permeability of Nansha ability is 2 times that of the vertical permeability (Zhu, Yin,
clayey soils and void ratio (Tavenas et al. 1983), expressed as: and Graham 2001).
kv ¼ kv0 exp ½ðe e0 Þ=Ck (4)
where kv0 is the initial hydraulic conductivity corresponding 3.4. Parameters of sandy soil in Nansha
to the initial void ratio, e0 , e is the void ratio and Ck is a There are relatively few studies on the sandy soil in Nansha
constant to describe the relationship of hydraulic conductiv- because settlement problems are mainly related to the clayey
ity and void ratio. The initial void ratio, e0 , is taken as the soil. Zhang and Huang (2012) conducted a series of labora-
value in the middle depth of each phase, as mentioned tory tests of the silty sand in Guangzhou, and found that
8 W.-Q. FENG ET AL.
phase are listed in Table 2. For the SS model, all the parameter
values are in consistent with those in Table 2 but no creep par-
ameter. It should be noted that the crusty layer was not consid-
Figure 10. Relationships of creep coefficient versus vertical stress: (a) Phase 1, ered in the finite element simulation since the actual site
(b) Phase 2, and (c) Phase 3.
before the fill construction was used as farmland. The con-
struction period was considered in the finite element simula-
monitored data, as shown in Figure 3. In the FE modeling,
tions by setting the stage of adding fill as the consolidation
the implicit algorithm with Newton-Raphson’s method was
type, where the loading is assumed to increase linearly within
utilized to solve the partial differential equations for the
the construction period.
couple of excess porewater pressure dissipation and creep
deformation.
Figure 12 shows the profile of simulation models for three 4.2. The new simplified method for multi-layer soils
phases of the Binhai Garden reclamation project, and the pro- with creep
file is mainly based on the results from CPTs. It can be
observed that Phase 1 and Phase 3 are typical double layered Degago et al. (2011) reviewed the difference of Hypothesis
soil profile, and Phase 2 is a multi-layered soil profile. The ini- A and Hypothesis B and summarized the experimental data
tial pre-consolidation state of the clayey soil was considered by from previous literature to assess whether the creep occurs
setting OCR ¼ 1, the horizontal deformation was fixed to be during the consolidation phase, and they proved that the
zero for the lateral boundaries, and both vertical and horizon- measured time-dependent deformation of clays generally
tal deformations were fixed to be zero at the bottom boundary. exhibits a good agreement with Hypothesis B. Yin and Feng
The soil layers were set to be drained both at the surface and at (2017) proposed and validated a new simplified method to
the bottom. The global mesh was pre-set to be fine to make calculate the consolidation settlement of clayey soils with
sure the mesh was dense enough for obtaining accurate results. creep subjected to an instant loading. Feng and Yin (2017)
The parameter values of SSC model for the soil layer of each extended the new simplified Hypothesis B method for
10 W.-Q. FENG ET AL.
(5)
Pn
where i¼1 S}primary}, i is the totalP“primary consolidation”
n
settlement of multi-layer soils, Pn i¼1 Screep, i is the creep
settlement of multi-layer soils, i¼1 Sf , i is the summation of
Pn “primary consolidation” settlement of multi-layer soils,
final
i¼1 Screep, f , i is the total creep settlement P
of multi-layer soils
calculated from the instant loading path, ni¼1 S}secondary}, i is
the total creep settlement of multi-layer soils calculated from
the delayed loading path, as illustrated in Figure 13; The
instant loading path represents path of soil elements close to
the drainage boundary, whose stress–strain state occurs
instantly, the influence of excess porewater pressure could
be neglected, whereas the delayed loading path refers to the
path of soil elements far away from the drainage boundary,
whose stress–strain state is delayed due to the dissipation of
excess porewater pressure; Ua is the average degree of con-
solidation for double soil layers. a is a parameter to describe
the de-coupling phenomenon of consolidation and creep,
which is simplified as a constant by Yin and Feng (2017). In
this study, it is suggested to take a¼Ua for the thick soil
layer because the de-coupling phenomenon of consolidation
and creep is affected by the average degree of consolidation
of the soil layer. For multi-layer soils, each stratum is influ-
enced by the action of the other in the interface (Zhu and
Yin 1999, 2005). The average degree of consolidation, mv ,
for double-layered soils is determined
8
>
> Tc X 1
cn
>
> 1 exp ðk2n TÞ T Tc
<T k 4
Tc
n¼1 n
Ua ðT, Tc Þ ¼
>
> X1
cn
>
:1
>
k4 T
1 exp ðk2n Tc Þ exp k2n ðT Tc Þ T > Tc
n¼1 n c
(6)
where T and Tc are the normalized time factor and normalized
construction time factor, respectively, T ¼ ðH pffiffiffiffi
cv1 cv2 t
c þH c Þ2
pffiffiffiffi ,
1 v2 2 v1
Tc ¼ ðH pffiffiffiffi
cv1 cv2 tc
c þH c Þ2
pffiffiffiffi , kn is the root of the equation sinh þ
1 v2 2 v1
Table 2. Values of parameters in the soft soil creep model and the Mohr–Coulomb model used in finite element modeling of the reclamation.
Soil layer csoil (kN/m3) E 0 (kPa) j k l kz (m/day) c0 (kPa) /0 ( )
Phase 1 Clay 16 – 0.0242 0.0614 0.00194 2.6 104 0.1 30
Sand 18 4000 – – – 1.73 101 0.1 35
Phase 2 Clay 16 – 0.0203 0.0575 0.00188 1.7 104 0.1 30
Sand 18 4000 – – – 1.73 101 0.1 35
Phase 3 Clay 16 – 0.0221 0.0609 0.00242 1.6 104 0.1 30
Sand 18 4000 – – – 1.73 101 0.1 35
Note: k Z is the modified compression index, k ¼ 2:3ð1þe
Cc
0Þ
, j is the modified swelling index, j 2Ce
2:3ð1þe0 Þ ,
Cae
l is the modified creep index, l ¼ 2:3ð1þe 0Þ
:
MARINE GEORESOURCES & GEOTECHNOLOGY 11
8
>
> 2½mv1 H1 n sin ðkn nÞ þ mv2 H2 x sin ðkn xÞ2
>
< for condition 1
x2 n2 ðmv1 H1 þ mv2 H2 Þ½mv1 H1 n sin 2 ðkn nÞ þ mv2 H2 x sin 2 ðkn xÞ
cn ¼ (7)
>
> 2½mv1 H1 n cos ðkn nÞ2
>
: for condition 2
x2 ðmv1 H1 þ mv2 H2 Þ½mv1 H1 n cos 2 ðkn nÞ þ mv2 H2 x sin 2 ðkn xÞ
! !
Ce r0zp, j Cc r0zf , j
efj ¼ log þ log (8)
ð1 þ eo Þ r0zo, j ð1 þ eo Þ r0zp, j
Table 3. Values of parameters in the new simplified method for the reclamation.
Soil layer eo csoil (kN/m3) E 0 (kPa) Ce Cc Cae kz (m/day) to (day)
Phase 1 Clay 1.67 16 – 0.0746 0.3777 0.0119 2.6 104 1
Sand 1 18 4000 – – – 1.73 101 –
Phase 2 Clay 1.257 16 – 0.0529 0.299 0.0098 1.7 104 1
Sand 1 18 4000 – – – 1.73 101 –
Phase 3 Clay 1.525 16 – 0.011 0.3541 0.0141 1.6 104 1
Sand 1 18 4000 – – – 1.73 101 –
Table 4. Summary of values in the new simplified method for the reclamation.
Clay Sand
1
No. sf 1 (m) mv1 (kPa ) cv1 (m /day)
2
sf 2 (m) mv2 (kPa1) cv2 (m2/day) p q
Phase 1 1.017 0.001 0.0257 0.113 0.00025 14.679 0.706 0.963
Phase 2 0.680 0.001 0.0155 0.119 0.00028 0.0609 0.33 0.86
Phase 3 1.246 0.001 0.0184 0.113 0.00025 14.679 0.780 0.970
Figure 14. The mechanism of ground settlement problems in Binhai Garden reclamation project.
Figure 15. (a) Ground settlements versus log(time) from finite element modeling and new simplified method calculation for Phase 1 and (b) comparison of
measured settlement and computed settlements from the finite element analysis and new simplified method.
MARINE GEORESOURCES & GEOTECHNOLOGY 13
5.1. Settlement problem analysis in Binhai Garden 5.2. Comparison of the measured and predicted
reclamation project settlements for Binhai Garden reclamation project
Figure 14 illustrates the differential settlement mechanism 5.2.1. For phase 1 of Binhai Garden reclamation project
of the reclamation project. After the construction of the fill According to the geotechnical investigations, fill construc-
and buildings, large consolidation settlement occurred in tion of Phase 1 was started from January 2000 and com-
the clayey soil layer due to the surcharge of added fills, pleted in January 2001, and the settlement was monitored
while ignorable settlement was observed in the buildings from January 2011. The monitored data, the results from
because the foundations of building are concrete piles with finite element simulations and the calculation results from
high strength (Ec ¼ 32 GPa), which were directly inserted the new simplified method are plotted in Figure 15.
into rock bed. The permeability of concrete piles in the It is found that the settlement of Phase 1 is close to the
geotechnical design report is 2 1012 m/s, which is too end of consolidation after ten years’ consolidation and the
small to be neglected. The difference between the ground creep settlement would contribute the main settlement in
settlement and building settlement leads to serious future. Comparing the monitored settlement data of Point 2,
settlement problems, as described in three phases of the which is nearby the location of the calculated soil layers,
reclamation project (see Figure 6). Therefore, the ground with the finite element simulations, it can be observed that
settlement due to the surcharge loading is regarded as the monitored data agree well with the results from finite elem-
major factor that induces the settlement problems in the ent modeling with the SSC model as well as the results from
reclamation project. the new simplified method. From the curves of FE simula-
tion and new simplified method, it is estimated that the
ground settlement of Phase 1 will be within 0.07 m in the
coming ten years (from 2019 January). Comparatively, the
finite element modeling with the SS model gradually under-
estimates the settlement from January 2011.
The viscosity of marine clay has a significant influence
on the dissipation of excess pore water pressure (Yin et al.
2011). Figure 16 presents the dissipation of excess pore
water pressure along depth in the finite element modeling.
It is found that there is an obvious difference of the excess
pore water pressures in the finite element analysis with the
SSC model and the SS model in January 2002, which is
related to the viscosity effect. In the undrained condition,
the creep would induce an increase of excess pore water
pressure, which could therefore reduce the effective stress
on the soil skeleton when the total earth pressure is constant
(Yin et al. 1994; Yin and Zhu 1999). In the fully coupled
finite element modeling, the difference of excess pore water
pressure between the analysis with the SSC model and the
Figure 16. Analysis of dissipation of excess pore water pressure versus depth at SS model decreases from January 2011 to January 2021,
different times from finite element simulation for Phase 1. which indicates that the compensated elastic deformation is
Figure 17. (a) Ground settlements versus log(time) from finite element modeling and new simplified method calculation for Phase 2 and (b) comparison of
measured settlement and computed settlements from the finite element analysis and new simplified method.
14 W.-Q. FENG ET AL.
a gradually displaying process in the subsequent time of nearby Point 8 in Phase 2 in coming ten years can reach
Phase 1. Therefore, the creep behavior has a large influence 0.14 m, and it is observed that the settlement of Phase 2 is still
on the total settlement in the prediction. in the consolidation stage, as illustrated in Figure 17(a). Thus,
it is necessary to adopt the ground improvement techniques to
avoid more serious settlement problems.
5.2.2. Phase 2 of Binhai Garden reclamation project The response of excess pore water pressure after the con-
Soil layer of Phase 2 in Binhai Garden reclamation project is struction, as shown in Figure 18, demonstrates that it is in
a multi-layered condition. The actual fill construction lasted the main consolidation stage from January 2011 to January
for 2 years (from 2004 to 2006). The beginning of 2004 is 2021. The creep compression induces more than 9 kPa in
selected as the initial time for Phase 2 and Figure 17 shows excess pore water pressure (the difference of pore water
the curves of settlement-log(time) from finite element simu- pressure between simulations with SSC model and those
lations and new simplified method calculation for soil pro- with SS model) in January 2011. After ten years, the largest
file of Phase 2. The monitored settlement data of Point 8 (it difference is within 6 kPa. As a result, the compensated elas-
is close to the soil profile, as shown in Figure 1(b)) are also tic deformation in the fully coupled analysis is also displayed
plotted in Figure 17. in the consolidation stage of Phase 2.
According to the finite element simulations, the ground
settlement after January 2011 is still in the consolidation stage.
Figure 17(b) compares the finite element simulations and new 5.2.3. Phase 3 of Binhai Garden reclamation project
simplified method predictions with the monitoring settlement Figure 19 displays the simulated results from finite element
of Point 8 (2011 January to 2018 December). The settlements modeling and new simplified method calculation as well as
the monitored settlements of Point 13 in Phase 3. In the
field, the fill construction of Phase 3 began in January 2005,
and finished in January 2009. In other words, the construc-
tion period is 4 years.
Because the time of monitoring settlement is very close
to the completion of fill construction, the ground settlement
from January 2011 to January 2021 is in the early stage of
consolidation for clayey soil layers. The predicted settlement
in coming ten years will be as large as 0.36 m. To solve the
settlement problems, repair works will inevitably be con-
ducted. As a comparison, the predicted ground settlement
with the SS model is very close to that with the SSC model
(as illustrated in Figure 19(b)) because it is mainly in the
consolidation stage for Phase 3.
Again, the response of excess pore water pressure is ana-
lyzed in the finite element modeling along depth in Figure 20.
Figure 18. Analysis of dissipation of excess pore water pressure versus depth at It is seen that the difference of excess pore water pressures
different times from finite element simulation for Phase 2. between the finite element modeling with the SSC model and
Figure 19. (a) Ground settlements versus log(time) from finite element modeling and new simplified method calculation for Phase 3 and (b) comparison of meas-
ured settlement and computed settlements from the finite element analysis and new simplified method.
MARINE GEORESOURCES & GEOTECHNOLOGY 15
6. Conclusions
References
In this study, the settlement problems in three phases of a rec- Brinkgreve, R. B. J., S. Kumarswamy, and W. M. Swolfs. 2015. Plaxis,
lamation project in Nansha are analyzed. The cone penetration Reference Manual. Delft: Plaxis BV.
tests (CPTs) were conducted nearby the site of the reclamation British Standard. 1990. BS 1377-6: Methods of Test for Soils for Civil
project. Fourteen undisturbed soil specimens were taken from Engineering Purposes.
Bjerrum, L. 1954. Geotechnical Properties of Norwegian Marine Clays.
different depths in the field at the same site and tested in soil
Geotechnique 4 (2): 49–69. doi:10.1680/geot.1954.4.2.49.
laboratory. Then, the finite element (FE) analysis and new Bjerrum, L. 1967. Engineering Geology of Norwegian Normally-
simplified method were performed and results are compared Consolidated Marine Clays as Related to Settlements of Buildings.
with the measured settlements for three phases of the Geotechnique 17 (2): 83–118. doi:10.1680/geot.1967.17.2.83.
16 W.-Q. FENG ET AL.
Chen, X. P., G. Y. Huang, and Z. S. Liang. 2003. Study on Soft Soil Tavenas, F., P. Jean, P. Leblond, and S. Leroueil. 1983. The Permeability
Properties of the Pearl River Delta. Chinese Journal of Rock of Natural Soft Clays. Part II: Permeability Characteristics. Canadian
Mechanics and Engineering 22 (1): 137–141. Geotechnical Journal 20 (4): 645–660. doi:10.1139/t83-073.
Cheng, C. M., and J.-H. Yin. 2005. Strain-Rate Dependent Stress-Strain Vermeer, P. A., and H. P. Neher. 1999. A soft soil model that accounts for
Behaviour of Undisturbed Hong Kong Marine Deposits under creep. Proc., Plaxis Symposium “Beyond 2000 in Computational
Oedometric and Triaxial Stress States. Marine Georesources & Geotechnics”, Balkema, Rotterdam, 249–262.
Geotechnology 23 (1–2): 61–92. doi:10.1080/10641190590953818. Wei, X., and C. Wu. 2011. Holocene Delta Evolution and Sequence
Degago, S. A., G. Grimstad, H. P. Jostad, S. Nordal, and M. Olsson. Stratigraphy of the Pearl River Delta in South China. Science China
2011. Use and Misuse of the Isotache Concept with respect to Creep Earth Sciences 54 (10): 1523–1541. doi:10.1007/s11430-011-4238-6.
Hypotheses A and B. Geotechnique 61 (10): 897–908. Yin, J. H. 1999. Non-Linear Creep of Soils in Oedometer Tests.
Feng, W. Q., B. Lalit, Z. Y. Yin, and J. H. Yin. 2017. Long-Term Non- Geotechnique 49 (5): 699–707. doi:10.1680/geot.1999.49.5.699.
Linear Creep and Swelling Behavior of Hong Kong Marine Deposits Yin, J.-H., and W.-Q. Feng. 2017. A New Simplified Method and Its
in Oedometer Condition. Computers and Geotechnics 84: 1–15. doi: Verification for Calculation of Consolidation Settlement of a Clayey
10.1016/j.compgeo.2016.11.009. Soil with Creep. Canadian Geotechnical Journal 54 (3): 333–347.
Feng, W.-Q., and J.-H. Yin. 2017. A New Simplified Hypothesis B Method doi:10.1139/cgj-2015-0290.
for Calculating Consolidation Settlements of Double Soil Layers Yin, J.-H., and J. Graham. 1989. Viscous-Elastic-Plastic Modelling of
Exhibiting Creep. International Journal for Numerical and Analytical One-Dimensional Time-Dependent Behaviour of Clays. Canadian
Methods in Geomechanics 41 (6): 899–917. doi:10.1002/nag.2635. Geotechnical Journal 26 (2): 199–209. doi:10.1139/t89-029.
Feng, W.-Q., and J.-H. Yin. 2019. Development and Verification of a Yin, J.-H., and J. Graham. 1994. Equivalent Times and One-
New Simplified Method for Calculating Settlement of a Thick Soil Dimensional Elastic Viscoplastic Modelling of Time-Dependent
Layer with Nonlinear Compressibility and Creep. International Stress-Strain Behaviour of Clays. Canadian Geotechnical Journal 31
Journal of Geomechanics (accepted). (1): 42–52. doi:10.1139/t94-005.
Liu, Y. J., Z. M. Li, S. M. Wu, and J. W. Wu. 2010. Statistic Analysis of Yin, J. H., J. Graham, J. I. Clark, and L. Gao. 1994. Modelling
Physical–Mechanical Indexes and Microstructure Parameters of Soft Soil in Unanticipated Pore-Water Pressures in Soft Clays. Canadian
Nansha Area. Journal of Guangdong University of Technology 27 (2): 21–26. Geotechnical Journal 31 (5): 773–778. doi:10.1139/t94-088.
Lunne, T., T. Berre, K. H. Andersen, S. Strandvik, and M. Sjursen. Yin, J. H., and F. Tong. 2011. Constitutive Modeling of Time-
2006. Effects of Sample Disturbance and Consolidation Procedures Dependent Stress–Strain Behaviour of Saturated Soils Exhibiting
on Measured Shear Strength of Soft Marine Norwegian Clays. Both Creep and Swelling. Canadian Geotechnical Journal 48 (12):
1870–1885. doi:10.1139/t11-076.
Canadian Geotechnical Journal 43 (7): 726–750. doi:10.1139/t06-040.
Yin, J. H., and J. G. Zhu. 1999. Elastic Viscoplastic Consolidation
Lunne, T., O. Eide, and J. D. Ruiter. 1976. Correlations between Cone
Modelling and Interpretation of Pore-Water Pressure Responses in
Resistance and Vane Shear Strength in Some Scandinavian Soft to
Clay underneath Tarsiut Island. Canadian Geotechnical Journal 36
Medium Stiff Clays. Canadian Geotechnical Journal 13 (4): 430–441.
(4): 708–717. doi:10.1139/t99-041.
doi:10.1139/t76-043.
Yin, J.-H., J.-G. Zhu, and J. Graham. 2002. A New Elastic Visco-Plastic
Luo, Q. Z., and X. P. Chen. 2014. Experimental Research on Creep
Model for Time-Dependent Behaviour of Normally and Over-
Characteristics of Nansha Soft Soil. The Scientific World Journal
Consolidated Clays: theory and Verification. Canadian Geotechnical
2014: 968738. doi:10.1155/2014/968738.
Journal 39 (1): 157–173. doi:10.1139/t01-074.
Mesri, G. 2009. Effects of Friction and Thickness on Long-Term
Yin, Z. Y., M. Karstunen, J. H. Wang, and C. Yu. 2011. Influence of
Consolidation Behavior of Osaka Bay Clays. Soils and Foundations
Features of Natural Soft Clay on Behaviour of Embankment. Journal
49 (5): 823–824. doi:10.3208/sandf.49.823. of Central South University of University 18 (5): 1667–1676. doi:10.
Mesri, G., and B. Vardhanabhuti. 2006. Closure of “Secondary 1007/s11771-011-0887-z.
Compression” by Mesri and Vardhanabhuti. Journal of Geotechnical Zhang, F. Z., and L. J. Huang. 2012. Mechanical Behavior of Silty Sand
and Geoenvironmental Engineering 132 (6): 817–818. doi:10.1061/ in Guangdong. Journal of Yangtze River Scientific Research Institute
(ASCE)1090-0241(2006)132:6(817). 29 (7): 67–72 (in Chinese).
Mitchell, J. K., and T. L. Brandon. 1998. Analysis and Use of CPT in Zhu, G. F., and J. H. Yin. 1999. Consolidation of Double Soil Layers
Earthquake and Environmental Engineering, Keynote Lecture. under Depth-Dependent Ramp Load. Geotechnique 49 (3): 415–421.
Proceedings of ISC’98 1: 69–97. Zhu, G., and J. H. Yin. 2005. Solution Charts for the Consolidation of
Nagaraj, T. S., and N. Miura. 2001. Soft Clay Behaviour Analysis and Double Soil Layers. Canadian Geotechnical Journal 42 (3): 949–956.
Assessment. Rotterdam, The Netherlands: Balkema. doi:10.1139/t05-001.
Nash, D., and M. Brown. 2013. Influence of Destructuration of Soft Zhu, G., and J. H. Yin. 2012. Analysis and Mathematical Solutions for
Clay on Time-Dependent Settlements: Comparison of Some Elastic Consolidation of a Soil Layer with Depth-Dependent Parameters
Viscoplastic Models. International Journal of Geomechanics 15 (5): under Confined Compression. International Journal of Geomechanics
A4014004. doi:10.1061/(ASCE)GM.1943-5622.0000281. 12 (4): 451–461. doi:10.1061/(ASCE)GM.1943-5622.0000152.
Nash, D. F. T., and S. J. Ryde. 2001. Modelling Consolidation Zhu, G., J.-H. Yin, and J. Graham. 2001. Consolidation Modelling of
Accelerated by Vertical Drains in Soils Subject to Creep. Soils under the Test Embankment at Chek Lap Kok International
Geotechnique 51 (3): 257–273. Airport in Hong Kong Using a Simplified Finite Element Method.
Shen, S. L., Z. F. Wang, and W. C. Cheng. 2017. Estimation of Lateral Canadian Geotechnical Journal 38 (2): 349–363. doi:10.1139/t00-103.
Displacement Induced by Jet Grouting in Clayey Soils. Geotechnique Zhu, H.-H., C.-C. Zhang, G.-X. Mei, B. Shi, and L. Gao. 2017.
67 (7): 621–630. doi:10.1680/jgeot.16.P.159. Prediction of One-Dimensional Compression Behavior of Nansha
Shen, S. L., H. N. Wu, Y. J. Cui, and Z. Y. Yin. 2014. Long-Term Clay Using Fractional Derivatives. Marine Georesources &
Settlement Behaviour of Metro Tunnels in the Soft Deposits of Geotechnology 35 (5): 688–697. doi:10.1080/1064119X.2016.1217958.
Shanghai. Tunnelling and Underground Space Technology 40: Zhu, Q. Y., Y. F. Jin, and Z. Y. Yin. 2019. Modeling of Embankment
309–323. doi:10.1016/j.tust.2013.10.013. beneath Marine Deposited Soft Sensitive Clays considering
Sridharan, A., and Y. Gurtug. 2004. Swelling Behaviour of Compacted Straightforward Creep Degradation. Marine Georesources &
Fine-Grained Soils. Engineering Geology 72 (1–2): 9–18. doi:10.1016/ Geotechnology: 1–17. doi:10.1080/1064119X.2019.1603254.
S0013-7952(03)00161-3. Zou, S. F., X. Y. Xie, J. Z. Li, Z. J. Wang, and H. Y. Wang. 2019.
Stolle, D. F. E., P. A. Vermeer, and P. G. Bonnier. 1999. A Rheological Characteristics and One-Dimensional Isotache Modelling
Consolidation Model for a Creeping Clay. Canadian Geotechnical of Marine Soft Clays. Marine Georesources & Geotechnology 37 (6):
Journal 36 (4): 754–759. doi:10.1139/t99-034. 660–670. doi:10.1080/1064119X.2018.1473903.