Professional Documents
Culture Documents
Guia para El Desarrollo de Planta de Minerales
Guia para El Desarrollo de Planta de Minerales
development studies
P. R. Whincup*
This paper presents guidelines for studies required for the development of mineral processing
facilities from initial feasibility studies through to commissioning. Mining project schedule and cost
overruns can often be attributed to inadequate metallurgical testwork, engineering and cost
estimating leading up to commitment to the project. In some cases this may result from lack of
understanding of, and commitment by the project proponent to, the requisite metallurgical and
engineering studies during the development stages. Guidelines for metallurgical testwork,
process development, engineering and estimating requirements for each stage of precommit-
ment studies are described together with those for the engineering phase.
Keywords: Mineral process plant, Metallurgical testwork, Engineering and cost studies, Feasibility studies
This paper is part of a special issue on Metallurgical Plant Design and Operating Strategies
For most projects a sample weight of between 5 and to see production through at least one base metals ‘low
10 kg for each mineralisation type should be sufficient. cycle’.
Scoping study testwork would typically cost Unless capital data are available from a recent ore
USD30 000 to USD50 000 including sample collection processing plant of the type and capacity envisaged,
and freight. preliminary capital estimates will usually require some
Results of testwork would provide the basis on which engineering and vendor pricing, which would typically
to develop process options. For each option a strengths, cost USD50 000 to USD100 000.
weaknesses, opportunities and threats (SWOT) analysis Capital estimates would be based on:
is recommended as at a low level of cost certainty this (i) assumed flowsheet showing all major mechan-
may be the only way to differentiate between options. ical equipment and ‘base case’ major process
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
192 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
Whincup Guidelines for mineral process plant development studies
Figure 1 shows an example of the capital estimating scoping study stage as they usually impact materially on
process for a large simple base metals mineral processing project economics and resource cut-off grade.
plant covering the required range of processing rates for Realisation costs include concentrate transport, treat-
the example described above. ment and refining charges and can amount to 10–15% of
In this example a contingency of 20% was allowed and the in situ ore value. Indicative transport costs can be
represents the lower limit of the range of contingency obtained from specialist road transport and rail freight
allowances applicable to a properly conducted scoping operators. Treatment and refining charges are available
study. At this and subsequent stages of the project an from commodities research groups.
enthusiastic but inexperienced project proponent may be It is recommended that at the scoping stage a risk and
tempted to delete or reduce the contingency. This is an opportunity register be established and reviewed during
early warning sign that a project could be heading for each subsequent stage.
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
cost overruns. Time required for a scoping level processing study will
Bench marking at this level of study is valuable as a be dependent on availability of data; however, for
check but care needs to be taken that a comparative planning purposes a minimum of six months is
project and scope are being examined. Capital estimates recommended.
using this methodology are considered to be accurate to
no better than ¡30%. Prefeasibility studies
Preliminary processing cost estimates for each treat- The prefeasibility study (PFS) has three functions:
ment rate would be produced from either current cost (i) to evaluate all process options by establishing
data from similar operations or from first principles. The preliminary financials for each
setting-up of a processing cost model that reflects fixed (ii) selection of one or two options for more detailed
and variable cost components is recommended. Once cost analysis
established, the model can then be used over a range of (iii) refinement of capital and operating cost esti-
processing rates and refined as the project develops. mates, metallurgical recoveries and concentrate
Table 1 shows typical sources of scoping level quality ranges for project financial modelling.
processing cost estimates. These objectives would be met by metallurgical test-
For projects where a concentrate would be produced work, and engineering and cost studies.
for transport to a downstream processing facility Testwork would be aimed at providing sufficient data
realisation costs must be taken into account at the on which to:
Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 193
Whincup Guidelines for mineral process plant development studies
(i) undertake comparative evaluations of process processing costs may be required to identify preferred
options process options.
(ii) establish the key preliminary design criteria on Bench scale batch tests will usually suffice but the
which to base the engineering work needed to number and complexity of tests required will be specific
upgrade capital and processing cost estimates to to the mineralogy of the prospect.
prefeasibility level. Following determination of a preferred process route
Testwork will typically also produce samples for tailing some optimisation testwork should be undertaken,
storage, environmental and marketing studies. particularly to determine the grind/recovery relationship
The source of sample material for prefeasibility for major mineralisation types, and in the case of
testwork would be as for the scoping study testwork, a concentrate, the grind/recovery/concentrate grade
i.e. drill core. However, a minimum total sample weight relationship.
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
for each mineralisation type of y50 kg would be A single locked cycle test and single test on reground
required for bench scale concentration or extraction middling for each major mineralisation type would
testing. An additional 80–100 kg of unbroken composite usually be the limit of prefeasibility testwork.
core sample material would be required for comminu- Reagent optimisation would not normally be done at
tion testing. Residual sample and selected test products this stage unless reagent selection has potential to
should be retained in storage until at least completion of materially impact project viability.
plant performance testing or abandonment of the The study metallurgist should consider engaging an
project. independent third party to review the metallurgy and
It is strongly recommended that the detailed test processing aspects of PFS and subsequent studies
programme be developed well in advance of sample leading up to commitment to the project.
selection, in consultation with the selected laboratory and An allowance of at least USD70 000 to USD100 000
with one or more specialist metallurgical consultants to is recommended for prefeasibility level testwork for
reduce the risk of significant additional sample material simple metallurgical processes. Complex processes such
and testwork being required at detailed feasibility or as those for refractory gold mineralisation treatment
design stage to resolve flowsheet uncertainties. would need to be estimated on a case by case basis but a
The scope of comminution testwork on a composite cost within a range of USD200 000 to USD500 000
sample or, depending on variability of the lithology, a would not be unexpected.
number of individual samples of the major lithology Engineering at prefeasibility level would usually be
types, should be sufficient to establish the comminution undertaken by an engineering consultancy experienced
circuit. Testwork would usually include: in the design type of the mineral processing facility
(i) unconfined compressive strength (UCS) anticipated. For most ores any one of over 20
(ii) Bond crushing work index (CWI) internationally recognised engineers would be appro-
(iii) Bond rod mill work index (RWI) priate. Selection of the engineer would be based on
(iv) Bond ball mill work index (BWI) considerations of cost, relevant experience, quality,
(v) abrasion index (AI). availability of people and location.
SAG Mill Comminution Tests (SMC Tests) may not be Prefeasibility engineering would typically cover deliv-
required at this stage if there are other strong indicators ery of an engineering and cost study covering:
that the mineralisation would or would not be suitable (i) key design criteria
for SAG milling:5 (ii) preliminary flowsheets and piping and instru-
(i) mineralisation is not from a very competent mentation diagrams (PIDs)
uniform zone or a fully oxidised clayey zone (iii) preliminary mass balance, including plant pre-
(ii) UCS.180 MPa liminary water balance
(iii) BWI.20 kWh t21 (iv) site selection and layout drawings
(iv) RWI is not significantly higher than the BWI (v) a limited number of preliminary general arrange-
and both are not significantly .15 kWh t21. ment (GA) drawings and plans and sections
6
Morrell has provided guidelines for the number of taking into account safety, operability and
comminution samples required using classical statistical maintainability. It is not unusual to commence
analysis of comminution parameters starting with a the development of 2D CAD and in some
minimum of 10 samples, respectively representative of instances 3D models at this stage to provide
each production year, if possible, as well as guidance on GA and plan layouts with sufficient detail to
selection of tests, test equipment and modelling techniques. allow preliminary materials takeoffs (MTOs) for
It is advisable to have preliminary comminution cost estimating
parameters of potential ore types bench marked for (vi) preliminary mechanical and electrical equipment
SAG milling amenability using a specialist comminution lists
consultant. (vii) preliminary electrical load list
Initial prefeasibility leaching, flotation, gravity and (viii) preliminary MTOs and commodity pricing
other beneficiation testwork would focus on elimina- (ix) capital cost estimate
tion of process options. For example, combinations (x) processing cost estimate
of flotation, gravity and cyanide leach tests on a (xi) preliminary schedule including a capital disbur-
copper–gold ore would be aimed at resolving questions sement schedule
such as whether to include a gravity circuit for gold (xii) study report.
removal, merits of intensive cyanide leach on a gravity Engineering design should take into account known
gold concentrate or cyanidation of an auriferous environmental and regulatory constraints.
pyrite flotation concentrate. Comparative capital and Capital estimates would be typically based on:
194 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
Whincup Guidelines for mineral process plant development studies
(i) mechanical and electrical equipment pricing participation arrangements. For smaller compa-
using a single vendor quotation nies use of a mineral commodity marketing
(ii) structural steelwork, plate work, concrete, consultant is suggested.
major piping and architectural MTOs and At this point the financial and technical aspects of the
single vendor written quotation project are reviewed and further testwork, options
(iii) factored costs for other commodities shown in evaluation and value engineering may be required before
Fig. 1, and including architectural. Use of committing to feasibility level studies. Corporate self-
factors for prefeasibility direct capital estimates discipline may be required so as not to rush into a
assumes that the process plant is typical of those detailed feasibility study with significant technical issues
from which the engineer has derived the factors. unresolved.
If however, the process plant is known, for A time of 8–12 months for the PFS could be assumed
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 195
Whincup Guidelines for mineral process plant development studies
(ii) mineral liberation analyser (MLA) or QemSCAN scale testing hydrometallurgical processes must be
bulk modal analysis. considered as issues such as penalty element build-up
The following two stage approach to comminution and side reactions leading to scaling may not be
testing is also suggested by Morrell.6 apparent during bench scale testing.
In the first, limited stage, sufficient samples are tested Testwork samples should be made available to
to carry out a statistical analysis, following which a equipment vendors to enable equipment specification
more extensive programme is undertaken, based on and pricing. These will include, for example, settling
results of the first. The wider the spread of results from testwork for thickener sizing and viscosity testing for
the first stage, the more samples would be needed for the pump selection. Samples of testwork residues should be
second. The first stage would typically involve four to retained for testing by the tailing storage facility
five samples from each domain.
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
engineer.
Comminution test requirements for samples from The cost of feasibility level testwork will vary but the
each domain are as for the comminution testing following may be taken as a general guide for a large
recommended for PFSs together with: orebody with three domains:
(i) Bond AI and UCS if not included in previous
test programmes
(ii) JK Mineral Research Center (JKMRC) drop Mineralogy USD100 000
weight tests or the recently developed JK rotary Comminution USD250 000
breakage tests (JKRBT) Bench scale testing USD300 000 to USD400 000
Vendor testwork USD50 000
(iii) SMC Test
Pilot scale testwork USD250 000 to .USD1 000 000
(iv) if geotechnical core is being point load tested
then consideration could be given to having
point load testing done on comminution test These allowances exclude the cost of sample collection
samples to provide a link between the two and freight.
databases. Point load tests correlate quite well Feasibility process plant engineering should be
with the SMC Test results and hence the awarded to an appropriately qualified and experienced
geotechnical data can provide a good indication process plant engineer in a process where tenders are
of SAG mill competency variability. evaluated on:
The crushed products from the drop weight and SMC (i) ability to meet the scope and deliverables
Test can be reused for the Bond mill work index work if (ii) experience in the type of facilities proposed
sample quantity is a problem. (iii) price
Pilot scale comminution testing is not generally (iv) acceptability to proposed financiers (usually
required as comminution consultant databases are now decided at the prequalification stage)
sufficiently large to preclude the need for pilot scale (v) quality of the proposed study team
testing; unless rarer circuits are being designed (e.g. (vi) availability and timing
single stage autogenous grinding milling or high pressure (vii) location.
grinding rolls). The project metallurgist plays a role in the engineering
Other feasibility bench scale testwork is process and cost study by:
specific but, for example, for a large copper–gold (i) timely provision of results of metallurgical
orebody for which treatment by flotation to produce a testwork
saleable concentrate is proposed, the testwork should (ii) providing input to the plant design operating
include for each ore type as a minimum: and maintenance philosophies
(i) roughing and cleaning batch tests to establish (iii) making process related decisions
baseline flotation conditions (iv) participating in Hazard and Operability
(ii) bench scale locked cycle tests to establish (HAZOP) studies
optimum grind sizes, flotation conditions and (v) initiating value engineering, if required
reagent regime leading to definition of a standard (vi) sign-off of key process documents
test flowsheet. (vii) provision of any necessary processing cost input
Variability testing for the recovery and throughput using data, e.g. manning schedule.
the standard test flowsheets should be undertaken: Engineering deliverables will include:
(i) by production year in which composites repre- (i) detailed design criteria
senting production periods are evaluated (ii) detailed flowsheets
(ii) characterisation of the deposit by testing a variety (iii) mass balances for both design and operating
of samples representing the spatial distribution of departures
each mineralogical and lithological zone within (iv) life of mine ore treatment and production
the deposit. schedule by ore type
Pilot scale beneficiation testing needs to be considered. (v) PIDs
For simple mineralogy, and established unit processes, (vi) detailed site layout drawings showing site roads,
pilot scale testwork is usually not justified. Indicators of hardstand, plant service buildings and services
the need for pilot scale testing include unusually (consideration may need to be given at this stage
complex mineralogy and use of new or uncommon of the project to provision for future expansion
technology. Between a clear case for not including pilot of the ore processing facilities)
scale testing and clear necessity lies a range of situations (vii) GA and plan/section drawings taking into
for which consideration would be given to time, cost and account safety, constructability, operability and
risk to arrive at a decision. As a general principle pilot maintainability. The applicable CAD 2D or 3D
196 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4
Whincup Guidelines for mineral process plant development studies
model would be considerably refined and the risk of items being omitted or double counted,
optimised from that commenced at prefeasibility particularly at the process plant/mine and process plant/
level infrastructure interfaces.
(viii) mechanical and electrical equipment lists The feasibility study should include a project risk
(ix) electrical load list analysis of risks associated with the delivery and
(x) data sheets and specifications for any critical operation of the process plant.
long delivery equipment (e.g. grinding mills and For planning purposes a minimum of 12 months
large transformers) should be allowed for completion of processing facilities
(xi) MTOs and written quotation pricing for all feasibility studies.
commodities
(xii) estimated construction hours and construction
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4 197
Whincup Guidelines for mineral process plant development studies
Operations Strategies (MetPlant) 2008, 18–19 August 3. N. Cusworth: ‘Predevelopment expenditure’, in ‘Cost estimation
handbook for the Australian Mining Industry’, (ed. M. Noakes
2008, Perth, Western Australia. http://www.ausimm.
and T. Lanz), 252–259; 1993, Melbourne, AusIMM.
com.au/metplant2008/. 4. M. J. Warren: ‘Pre-feasibility and feasibility studies: a case for
improvements’, Proc. Mining Industry Optimisation Conf.,
References Sydney, Australia, June 1991, AusIMM, p 1–11.
5. AMMTEC Ltd: Technical feature: ‘Comminution’, available at: http://
1. M. E. White: ‘Feasibility studies-scope and accuracy’, in ‘Mineral www.ammtec.com.au/public_panel/technical.php#comminution
resource and ore reserve estimation – the AusIMM guide to good (originally accessed February 2008, last accessed 07 August 2010).
practice’, (ed. A. C. Edwards), 412–434; 2001, Melbourne, 6. S. Morrell: ‘Generating optimum value from ore characterisation
AusIMM. programs in design and geometallurgical projects associated with
2. D. J. Noort and C. Adams: ‘Effective mining project management comminution circuits’, Proc. 10th Mill Operators Conf., Adelaide,
systems’, Proc. Int. Mine Management Conf., Melbourne, South Australia, October 2009, AusIMM, 167–170.
Published by Maney Publishing (c) IOM Communications Ltd and the Australasian Institute of Mining and Metallurgy
198 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2010 VOL 119 NO 4