ITEM RATE AL KHAIR FOAM SHED 2800 sft.

Sr.# ITEM ITEM RATE UNIT


1 EXCAVATION 18 Cft
2 BACK FILLING 20 Cft
3 3" TO 4" P.C.C 25 Sft
4 RCC SLAB CONCREAT 55 Sft
5 RCC COLUMN & BEAM 100 Cft
6 RCC FOUNDATION CONCREAT 75 Cft
7 SHUTTERING F.F.L LEVEL 80 Sft
8 SHUTTERING F.F.L LEVEL UPTO 20' 120 Sft
9 STEEL CUTTING BENDING FIXING 8 PER Kg
10 PLAIN CEMENT FLOOR CONCREAT FINISH 40 Sft
11 BED LEVEL DRESSING 10 Sft
12 HAMER 1 LEYAR 10 Sft
13 BRICK WORK UPTO F.F.L LEVEL 50 Sft
14 BRICK WORK UPTO 15' LEVEL 55 Sft
15 BRICK WORK UPTO 20' LEVEL 60 Sft
16 PLAIN CEMENT PLASTER 35 Sft