1 m3 - beton mutu rendah f'c 7,5 MPa, Slump (100 ± 25) mm, agregat maks 19 mm secara manual

a. Tenaga : - Pekerja 1,650 OH 112.300,00 185.295,00


- Tukang besi 0,275 OH 120.000,00 33.000,00
- Kepala tukang 0,028 OH 125.000,00 3.500,00
- Mandor 0,009 OH 130.000,00 1.170,00 Rp 222.965,00

b. Bahan : - Semen / PC 250 kg 1.450,00 362.500,00


- Pasir beton 888 kg 142,86 126.857,14
- Koral beton 1.009 kg 166,67 168.166,67
- Air 202 ltr 120,00 24.240,00 Rp 681.763,81

c. Peralatan :
Rp -
Rp 904.729,00

d. Overhead + Keuntungan 10% 904.729,00 90.472,90 Rp 90.472,90


HSP Rp 995.202,00 Rp 109.472,22 Rp 19.904,04
Harga Setelah Ppn+Pph Rp 1.124.578,00