Professional Documents
Culture Documents
WWTP O&M CH03 - Primary Treatment 2015
WWTP O&M CH03 - Primary Treatment 2015
Revised 2015
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
Table of Contents
CHAPTER 3: Primary Treatment
3.0 Process Principles and Objectives…………………………….……………………………………………………… 3-1
3.1 Description……………………………………………………………………………………………………………………... 3-1
1.1 Flow Control…………………………………………….….………………………………………………………………. 3-3
1.2 Rectangular Primary Clarifier………………….……………………………………….…………………..………. 3-4
1.3 Circular Primary Clarifier …………………………….………………………………………………………………. 3-7
1.4 Sludge and Scum Pumping……………….…………………………………………………………………………. 3-8
1.5 Alarm Summary…………………………………………………………………………………………………………… 3-10
3.2 Operation……………………………………………………………………………………………………………………….. 3-11
2.1 Prestart………………………………………….….…………………………………………………………………………. 3-12
2.2 Startup…………………………………………..…………………………………………………………………………….. 3-12
2.3 Normal…………………………………………………………………………………………………………………………. 3-13
2.4 Shutdown: Rectangular Clarifier.……………..………………………………………………..………………… 3-14
2.5 Shutdown: Circular Clarifier…………………...……………………………………………………………………. 3-15
3.3 Process Control……………………………………………………………………………………………………………….. 3-15
3.1 Sampling and Laboratory Analysis……………………………………………………………………………….. 3-15
3.2 Process Control Factors………………………………………………………………………………………………… 3-16
3.3 Process Calculations and Control Data………………………………………………………………….……… 3-16
3.4 Other Process Impacts……………………………………..……………………………………………………………3-18
3.4 Troubleshooting……………………………………………………………………………………………………………… 3-19
3.5 Preventative Maintenance…………………………………………………………………………………….………… 3-21
5.1 Housekeeping………………………………………………………………………………………………………………. 3-21
5.2 Hose Down……………….....……………………………………………………………………….…………………….. 3-22
5.3 Inspection………………...………….……………………………………………………………………………………… 3-22
5.4 Flushing……………………………………………………………………………………………………………………….. 3-22
3.6 Safety………………………………………………………………………………………………………………………………. 3-23
ii
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
List of Tables
Table 3-1 Primary Treatment Equipment Summary……………………………………….…………………….…… 3-1
Table 3-2 Primary Clarification Flow Control Gates…………………………………………….….…………………. 3-3
Table 3-3 Primary Treatment System Alarm Summary.......…..…………………………………………….…… 3-10
List of Figures
Figure 3-1 Primary Sedimentation Process and Instrumentation Diagram…………………………….…… 3-24
Figure 3-2 Primary Sludge Pumps Process and Instrumentation Diagram……………….…………………. 3-25
Figure 3-3 Clarifier Flow Control Gates……………………………...…..…………………………………………….…… 3-26
Figure 3-4 Rectangular Primary Clarifier ….…………………………………………………………..…………………….3-27
iii
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.1 Description
The primary treatment system includes the rectangular primary clarifier, the circular primary clarifier,
and the sludge and scum pumping systems associated with each of these units.
Table 3-1: Primary Treatment Equipment Summary
Units Function Operating Conditions
RECTANGULAR PRIMARY CLARIFIER
Units - 1 The reduced velocity and Length: 104 feet
Equipment No. detention time in the clarifier Width: 21.5 feet
permits the solids in the raw
T 1301 Depth: 11 feet
sewage to either float or sink
Operation: The rectangular primary clarifier
operates continuously.
RECTANGULAR PRIMARY CLARIFIER SLUDGE COLLECTOR
Units - 1 Continuously moves sludge Flights: Fiberglass
Equipment No. that accumulates on the Drive motor: 1.5 hp
bottom of the rectangular
COL 1303 Operation: The sludge collector runs
clarifier into the sludge hopper
continuously.
at the influent end of the
clarifier.
3-1
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-2
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-3
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-4
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-5
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
1) Water Sprays. Water sprays located across the tank drive the scum towards the influent end of
the clarifier. Three 1-inch spray headers are provided; each is equipped with five spray nozzles
mounted 6 inches above the surface of the water. The flow of water to each of the headers is
controlled by a ball valve. The spray headers are mounted at a 1 percent slope down toward the
isolation ball valve.
Additional spray headers drive the scum across the tank to the helical scum skimmer at the
influent end of the clarifier. A 1-1/2-inch line serves these sprays.
Water is supplied to the clarifier's spray water system from the high pressure reclaimed water
system (3WHP) via a 2-1/2-inch line. The inlet water pressure is reduced from about 70 psi to 15
psi by pressure control valve PCV 1301. An isolation gate valve and a water strainer are also
provided for the spray water service. These units are located near the northwest corner of the
clarifier. A 2-inch line supplies water to the spray headers which drive the scum to the influent
end of the tank.
2) Scum Skimmer. Scum skimmer HK 1302 consists of a two-bladed, helical skimmer with synthetic
rubber wipers that scrape a metal skimming beach. The skimming beach is curved to
accommodate the arc of the skimmer wiper blades. In order for the skimming system to work
properly, the minimum depth of the water over the bottom of the beach should be about 3/4-
inch; the maximum depth over the bottom of the beach at peak wet weather flow should be
about 2 inches. The water surface elevation should never exceed the elevation of the skimming
beach's crest, or the scum trough will fill with water.
Most of the scum collected by the skimmer is moved along the skimming beach and discharged
into the scum trough. A metal closure piece at the discharge end of each skimming blade
prevents scum from flowing back into the clarifier; it also prevents excess quantities of water
from being discharged into the scum trough. A 6-inch line connects the scum trough to scum
pump P 1320 located in the adjacent primary gallery. The pipe invert is flush with the bottom of
the scum trough.
The scum skimmer is driven by a 0.5 hp motor.
3) Control. The scum skimmer is powered through MCC-2A in the Secondary Control Building. The
main breaker for the skimmer is located there, along with READY and RUN lights, a RESET
pushbutton, and a blown fuse indicator.
The scum skimmer is controlled by HAND-AUTO and START-STOP selector switches located at
the scum skimmer drive. An ON-OFF switch and a 0 to 30 minute timer are provided at the CVU
for use in the automatic mode of operation.
a) Automatic Control. With the HAND-OFF-AUTO switch in the AUTO position, the ON-OFF
switch at the plant SCADA system is used to start the scum skimmer. The scum skimmer will
run for the time period set on the timer. Note that the skimmer will not run unless the
sludge collector in the rectangular clarifier is running.
b) Manual Control. The scum skimmer runs continuously when the HAND-AUTO switch is in
the HAND position and the START-STOP switch is set to START.
3-6
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.1.2D Aeration
Aeration is supplied to the wastewater upstream of the rectangular primary clarifier using coarse bubble
diffusers. The six diffusers are connected to a 2-inch manifold by means of a 1-inch line. A 4-inch line
supplies agitation air from the headworks area to this system. Ball valves control the flow of air to the
individual diffusers and can be used to isolate the diffusers for maintenance.
3-7
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
system ; this alarm is actuated if high torque is sensed at the clarifier drive. The clarifier drive
unit stops on high torque and must be manually reset at the drive unit to restart the clarifier
drive.
3-8
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
2) Control. Primary sludge pump 1 is controlled by an ON-OFF selector switch at the pump drive.
The pump runs continuously with the switch in the ON position to remove sludge from the
rectangular primary clarifier. The operating status of the pump (ON) is indicated at the main
control panel.
3-9
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
1) Piping. A 6-inch plug valve controls the flow of scum from the clarifier's scum pit to the pump.
This valve is normally open. The pump discharge piping is equipped with a 6-inch plug valve.
A low flow switch is provided on the pump suction piping while a high discharge pressure switch
and a pressure gauge are provided on the discharge piping.
A pig launcher is provided so that the discharge piping can be cleaned.
2) Control. An ON-OFF selector switch and a RESET pushbutton are located at local scum pump
panel PNL 1321 in the primary treatment gallery. An ON pushbutton is also provided at the
scum pit, adjacent to the scum skimmer control switch. The scum pump is manually controlled
from either of these locations; with the ON-OFF switch in the ON position or the ON push-
button pressed, the scum pump runs continuously.
The scum pump will shut down when high discharge pressure (120 psig and rising) or loss of flow
are sensed. The pump must be manually reset at the local control panel (PNL 1321) before the
pump can be restarted.
The operating status of the scum pump is indicated at PNL 1321 (READY or RUNNING) and the
plant SCADA system (ON). Scum pump alarms are indicated at the local panel, including HIGH
PRESSURE and LOW FLOW. Each of these conditions actuates a common trouble alarm for the
scum pump on the plant SCADA systemr (PRIMARY SCUM PUMP TROUBLE).
3-10
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
P&ID
Alarm Name and Probable Cause Suggested Response
Designation
YA-130 REC CLARIFIER SHEAR PIN Acknowledge the alarm on the plant SCADA
Alarm is indicated on the plant SCADA system.
system. $ Visually verify the broken shear pin.
$ Broken shear pin in the drive unit for $ Drain the clarifier and check for
the rectangular primary clarifier. obstructions. Use the circular primary
clarifier to maintain primary treatment of the
raw sewage.
$ Replace the shear pin with a size and type
specified by the equipment manufacturer.
FLL-132 LOW FLOW Acknowledge the alarm on the plant SCADA
Alarm is indicated at the local scum system.
pump control panel (PNL 1321). A $ Check to ensure that the scum pit valve is
PRIMARY SCUM PUMP TROUBLE open.
alarm is indicated on the plant SCADA $ Determine if the scum pit has been pumped
system. dry.
$ No flow is detected in the scum $ Check for an obstruction in the line.
pump suction piping.
PLH-132 HIGH DISCHARGE PRESSURE Acknowledge the alarm at the plant SCADA
Alarm is indicated at the local scum system.
pump control panel (PNL 1321). A $ Visually verify the discharge pressure on the
PRIMARY SCUM PUMP TROUBLE gauge.
alarm is indicated on the plant SCADA $ Check to ensure that the downstream
system. valves are open.
$ The pump discharge pressure $ Check for an obstruction in the line.
exceeds the set point (120 psig,
$ Check the pressure trip setting for accuracy
rising).
and the proper set point.
UA-132 SCUM PUMP TROUBLE Acknowledge the alarm at the plant system.
Alarm is indicated at the plant SCADA $ Check the local scum pump control panel to
system. determine the cause of the alarm (low flow
$ Low flow or high discharge pressure or high discharge pressure).
at the scum pump.
3.2 Operation
Operations personnel should be familiar with the manufacturers' equipment manuals and O&M
instructions prior to operation of the primary treatment process. Pertinent safety instructions should
also be reviewed. The operations procedures described in this section should never preclude good, safe
operating techniques or City directives.
These instructions are provided on the assumption that the contractor and equipment manufacturers
have completed dry and wet testing of all systems and that auxiliary systems are operable. All control
switches are set at OFF.
3-11
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.2.1 Pre-Start
Step Remarks/Response
1. Perform preventive and corrective 1. Refer to the manufacturers' equipment manuals.
maintenance as necessary.
2. Inspect the primary clarifiers. 2. Make sure that all debris and tools are removed and
power is supplied to all equipment. Check the clarifier
weirs, sludge collectors, and scum collectors.
3. Inspect and prepare the equipment 3. Open the suction and discharge valves on the primary
and auxiliary system valves and gates sludge pumps. Open the valves on the 3W water lines to
for proper operation. the scum sprays. Remove slide gates SG 1304, SG 1305,
and SG 1306 from the effluent launders of the rectangular
primary clarifier. Check that the tank drain valves for the
two clarifiers are closed.
4. Inspect the grit removal system. 4. Verify that it is ready for operation.
5. Inspect the primary clarifier isolation 5. The slide gate should be closed.
slide gate (GT 1120).
6. Set the circular clarifier shutdown 6. The shutdown timer is located on the plant SCADA
timer. system. It is initially set for 60 minutes.
3.2.2 Start-up
The following instructions place the rectangular primary clarifier into active service, while preparing the
circular primary clarifier for standby operation.
Step Remarks/Response
1. Introduce flow to the rectangular 1. Open slide gates SG 1301, SG 1302, and SG 1303. Open
primary clarifier. the gates slowly to avoid any structural or equipment
damage from excessive hydraulic forces. Adjust the gates
to the desired opening.
2. Monitor filling of the tank. 2. Observe filling of the tank to identify potential problems.
When the water level reaches the bottom of the influent
gates, proceed with the remainder of the operation.
3. Start the sludge collector in the 3. Set the ON-OFF switch at the drive unit to the ON
rectangular primary clarifier. position. Observe collector operation for smoothness.
Check the drive for noise, heat, and vibration.
4. Start the agitation air system in the 4. Open the 1-inch ball valves on the agitation air lines and
influent channel. adjust the air supply to the diffusers. This assumes the
aeration blowers are on-line; if not, the blowers will need
to be started. If all of the systems supplied with air are not
in operation, it may be necessary to adjust the operation of
the aeration blowers.
5. Start the water sprays at the 5. The spray water headers are used to drive the scum
rectangular primary clarifier. towards the influent end of the rectangular clarifier. Water
is supplied to the spray headers from the reclaimed water
system.
3-12
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
Step Remarks/Response
6. Set the scum skimmer for automatic 6. Turn the HAND-OFF-AUTO switch to the AUTO position
operation. and set the scum skimmer timer at the plant SCADA
system. The skimming cycle will be manually initiated using
the ON-OFF switch at the plant SCADA system when a
sufficient amount of scum has collected at the skimmer.
7. Start primary sludge pump 1. 7. Turn the ON-OFF switch at the pump drive to ON after
the clarifier tank is full. The pump will run continuously.
8. Observe primary sludge pump 1. 8. Check for noise, heat, and vibration.
9. Set the circular clarifier control for 9. Set the HAND-OFF-AUTO switch at the drive unit to
automatic operation. AUTO so that the clarifier rake drive will operate whenever
slide gate GT 1120 opens. Check the setting of the circular
clarifier shutdown timer; the timer is initially set at 60
minutes.
10. Set the primary clarifier isolation 10. Turn the OFF-ON switch at the gate operator to OFF. In
gate (GT 1120) for automatic this mode, the gate will automatically open when influent
operation. flows exceed 5.25 mgd to divert wastewater to the circular
primary clarifier.
11. Set primary sludge pump 2 for 11. Set the HAND-OFF-AUTO switch at the pump to AUTO.
automatic operation. Under this mode of operation, the sludge pump will
operate whenever the circular clarifier runs.
If the circular primary clarifier is to operate in conjunction with the rectangular primary clarifier at all
plant flows, slide gate GT 1120 must be opened manually by placing the OFF-ON selector switch to
ON and then depressing the OPEN pushbutton at the nearby gate operator panel. As wastewater
completely covers the clarifier floor, start the rake drive by setting its control switch to HAND. When
the clarifier is about one-half full, start primary sludge pump 2 by setting its local controller to HAND.
3.2.3 Normal
Step Remarks/Response
1. Check the equipment controls and 1. All alarms should be clear. Control switches and
the plant SCADA system. controllers should all be in the desired position or mode of
operation.
2. Inspect the surface of the clarifiers 2. No rising or floating sludge should be present; the
for floating sludge or solids. Also note effluent should be relatively clear and free of heavy solids.
changes in the appearance of the There should not be a build-up of solids on the walls, weirs,
influent wastewater. or equipment. Collect samples if anything unusual is
observed.
3. Check the scum collection system. 3. Scum should be forced to the skimmer. There should
Operate the skimmer when sufficient not be a build-up of scum on the clarifier walls, weirs, or
scum has collected. equipment.
4. Inspect the sludge collector in the 4. Heat, noise, and vibration should be normal. The chains
rectangular clarifier and the rake drive in the rectangular clarifier should be in good condition;
in the circular clarifier. scum and rags should be removed from the chains.
5. Check for torque overload at the 5. Check the sludge pumping system or investigate for a
clarifiers. blocking obstruction of the rake or sludge collector if high
torque occurs.
6. Check operation of the sludge 6. Primary sludge pump 1 operates continuously. Primary
pumps. sludge pump 2 runs whenever the circular clarifier runs
unless the trickling filter snail pump is operating.
3-13
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
Step Remarks/Response
7. Check the operation of the flow 7. The flow splitting system at the headworks diverts half of
splitting system if the automatic the flow to the circular primary clarifier when the total
control option is in effect. influent flow exceeds 5.25 mgd. The clarifier and sludge
pump 2 should start when the gate opens; these units stop
after the gate has closed and the shutdown timer at the
plant SCADA system has timed out.
8. Pump down the primary scum pits. 8. The scum pump for the rectangular clarifier is manually
Thoroughly wash the scum pits down controlled (ON-OFF); the pump will stop on low flow or
to prevent excessive odor generation. high discharge pressure. Primary sludge pump 2 is used to
pump scum from the circular clarifier; the pump is
manually controlled for pumping scum.
9. Periodically check the influent and 9. Determine the clarifier operating efficiency and compare
effluent BOD, SS, settleable solids, pH, against the design criteria and operating history.
and temperature.
10. Wash down the clarifiers. 10. Hose down the inlet area to remove grease and slime
accumulations. The effluent weir and launder trough
should also be cleaned to avoid algal and slime growths.
11. Check the sludge pump area. 11. Hose down the area as needed.
3-14
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
9. If the tank is to remain empty for an 9. To prevent rust formation on the equipment.
extended period of time, fill the tank
with reclaimed water.
10. Test the equipment periodically to
ensure that it will operate when
needed.
3-16
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
The data required for calculation of the pounds of solids in the primary influent or effluent includes:
1) The wastewater flow rate in million gallons per day (mgd).
2) The solids concentration in the wastewater in milligrams per liter (mg/l).
Example: Determine the amount of solids in the influent and primary effluent for the following
conditions:
Influent flow = 3.0 mgd
Influent suspended solids = 200 mg/l
Influent BOD5 = 180 mg/l
Primary effluent solids = 80 mg/l
Primary effluent BOD5 = 125 mg/l
The solids into and out of the clarifier can be calculated as follows:
The BOD removal efficiency in the primary clarifier is normally 30 percent, while the suspended solids
removal efficiency is normally 60 percent. If the clarifier performance is significantly below normal,
check the system for possible causes. Clarifier performance will be below normal during times when the
hydraulic loading significantly exceeds the clarifier design.
3-17
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
Example: Calculate the hydraulic detention time in the rectangular primary clarifier. The flow recorder
at the main control panel indicates a total plant flow of 5.2 mgd. The circular primary clarifier is out of
service for scheduled maintenance.
The data required for calculation of the percent total solids includes:
1) The grams of dry sludge in 30 to 40 milliliters of a primary sludge grab sample.
2) The volume of sludge sample dried, in milliliters (ml).
Example: Determine the total solids in the primary sludge if 0.3 grams of dry sludge were obtained from
a 30 ml sample.
The total solids concentration of the primary sludge will be about 1 to 2 percent. This is lower than the
concentration typically obtained in primary sludge since the sludge is pumped from the clarifiers
continuously rather than intermittently.
3-18
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.4 Troubleshooting
The purpose of this troubleshooting section is to assist the operator in determining the cause of process
problems and to assist the operator in finding solutions to these problems. This section is intended to
supplement the manufacturers' equipment manuals; refer to the manufacturers' equipment manuals for
equipment-specific troubleshooting information.
3-19
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-20
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.5.1 Housekeeping
The primary gallery will need special attention to minimize water or sludge accumulation on the floor.
All water and sludge should be quickly hosed into the primary gallery sump. Use a "squeegee" to
remove residual water on the floor. Clean up spills and leakage from equipment as soon as possible to
avoid sanitation and slipping hazards.
Touch up all rust spots on the primary clarification equipment with paint on a regular basis.
3-21
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.5.3 Inspection
The equipment in the primary treatment system should be routinely inspected as a part of the daily
operator rounds. Observe the operation of the equipment under the normal mode of operation;
equipment which is normally operated in the AUTO mode should also be operated briefly in the HAND
mode. Carefully observe and listen for any indication of abnormal operation, such as obstructions,
unusual noises, or vibration.
Observe the seal water discharge when the primary sludge and scum pumps are operating. Excessive
seal water discharge is an indication of mechanical seal failure.
Inspect the clarifier tanks annually. Check the sludge collector and rake and inspect the equipment for
wear or scoring; repair or replace equipment as necessary.
Check and record the running time of the sludge collectors, primary sludge pumps, and primary scum
pump.
Follow the manufacturers' recommendations for periodic detailed inspection of the equipment.
3.5.4 Flushing
There are several areas of potential plugging and fouling problems in the primary treatment system.
The operating staff should develop a procedure for unplugging each piece of equipment.
Flushing cocks are provided on the suction side of the primary sludge pumps. These can be used to flush
and unplug the sludge lines.
Flush the scum spray nozzles at the rectangular primary clarifier weekly.
Add flushing water to the circular primary clarifier continuously during the winter months when the flow
splitting system is used.
Inspect the drain lines at the scum and sludge pumps to ensure that the seal water is able to flow into
the sump. Unplug the drain by flushing with plant water.
Flush the primary gallery sump as needed to minimize odor generation. Inspect the basket filter for the
water heater and replace filter as needed. Flush water heater as needed.
3-22
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3.6 Safety
The hazards listed are associated with work in and around the primary treatment area. Refer to the City
of Port Angeles Public Works and Utilities Accident Prevention Program & Safety Manual.
Operations personnel should be familiar with the manufacturers' equipment manuals and O&M
instructions prior to operation of the primary treatment process. Pertinent safety instructions should
also be reviewed. The operations procedures described in this section should never preclude good, safe
operating techniques or City directives.
When in doubt on how to proceed in a given situation that may not be covered here, contact your
immediate supervisor.
3-23
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-24
Page 3-24
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-25
Page 3-25
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-26
Page 3-26
City of Port Angeles Wastewater Treatment Plant
Operations and Maintenance Manual: Chapter 3 – Primary Treatment
3-27
Page 3-27