Module Title : Commissioning & Maintenance

Assignment : 2

1. What is Commissioning? Please briefly describe its functions. Quote one definition
from the relevant institution and state your understanding of it.

2. State five (5) expectations of Commissioning from Owner, Designer or Contractor.

3. Name a common method to protect welded joints of chilled water pipes.


Immediately before applying insulation to chilled water pipes, there are various
process needed to be done. State TWO.

4. Briefly describe what is General Specifications and Particular Specifications.

5. Name and briefly describe the use of three (3) important documents that must be
included in the O & M Manual for the Operation & Maintenance of Facilities.

6. You are going to measure the air velocity in an existing 1000 x 1000 air duct by
portable instrument. Please state the details of your proposed method.

7. Name 2 equipment’s that are advisable to have Factory Tests before delivered to
site. Select one of the equipment above to state the steps of on-site factory test.

8. Drawings are important in plumbing works, Name any FOUR (4) types. Name Four
(4) items which are usually included in a Method Statement.

9. State the reason(s) for having a sample room/sample installation before actual
installation.

Commissioning & Maintenance Assignment 2 P. 1 of 1