CPM ESTIMATES (EVENTS)

TE

TL
1. Earliest Event Time (TE)
2. Latest Allowable Occurrence Time (TL)

Prof. A. S. Thorbole Department of Civil Engineering 1


CPM ESTIMATES (ACTIVITY)

1. Earliest Start Time (EST)= Earliest Event Time at its Tail


2. Earliest Finish Time (EFT)= (TE) of i + Activity time
duration
3. Latest Start Time (LST)= LFT- Activity time duration
4. Latest Finish Time (LFT)= Latest event time at the head
of activity arrow

Prof. A. S. Thorbole Department of Civil Engineering 2


C
3 4
4
A F

5 10
D
1 2
6
B
G
4 E
2 5
5

Prof. A. S. Thorbole Department of Civil Engineering 3


FORWARD PASS 10
6 C
3 4
4
A F

0 5 10
D 20
1 2
6
B
4 9 G
4 E
2 5
5

Prof. A. S. Thorbole Department of Civil Engineering 4


BACKWARD PASS 6 10
C
3 4
4
A 6 10 F

0 5 10
D 20
1 2
6
0 B
4 9 G
4 E 20
5 9
2
5
4 11

Prof. A. S. Thorbole Department of Civil Engineering 5


10Activity EST EFT LST LFT
6 C
3 4
4 A 0 5 1 6
A 6 10 F
10
0 5 B 0 4 0 4
D 20
1 2 D 4 6 4 66
0 B
4 9 G
4 E 20
2 5
5
4 11

Prof. A. S. Thorbole Department of Civil Engineering 6


Activity EST EFT LST LFT Total Float

A 0 5 1 6

B 0 4 0 4

D 4 6 4 6

E 4 9 6 11

F 10 20 10 20

G 9 18 11 20

Prof. A. S. Thorbole Department of Civil Engineering 7