Concurrent Delays Calculation Sheet
Concurrent Delays Calculation Sheet
W1A (IM) 30-Nov-20 31-Jan-21 30-Nov-20 16-Jun-22 13-Jul-22 13-Jul-22 27 Delay by Employer (change in design of retaining walls)
W1
W1B (BF1) 30-Nov-20 31-Jan-21 31-Jan-21 16-Jun-22 6-Jul-22 6-Jul-22 20 7 Delay by Contractor to complete Engineering Work
W2A (IM) 31-Jan-22 15-Feb-21 31-Jan-22 16-Jun-22 20-Aug-22 20-Aug-22 20 Delay by Employer (change in tiles specs)
W2
W2B (BF2) 31-Jan-22 15-Feb-21 15-Feb-21 16-Jun-22 26-Jun-22 26-Jun-22 -10 30 Delay by Contractor to complete Engineering Work
2-Aug-22 47 26-Jun-22 10 37