Professional Documents
Culture Documents
(Download PDF) Information Technology Project Management 5th Edition Marchewka Test Bank Full Chapter
(Download PDF) Information Technology Project Management 5th Edition Marchewka Test Bank Full Chapter
https://testbankfan.com/product/information-technology-project-
management-5th-edition-marchewka-solutions-manual/
https://testbankfan.com/product/information-technology-project-
management-4th-edition-marchewka-test-bank/
https://testbankfan.com/product/information-technology-project-
management-4th-edition-marchewka-solutions-manual/
https://testbankfan.com/product/information-technology-project-
management-providing-measurable-organizational-value-5th-edition-
marchewka-test-bank/
Information Technology Project Management Providing
Measurable Organizational Value 5th Edition Marchewka
Solutions Manual
https://testbankfan.com/product/information-technology-project-
management-providing-measurable-organizational-value-5th-edition-
marchewka-solutions-manual/
https://testbankfan.com/product/information-technology-project-
management-9th-edition-schwalbe-test-bank/
https://testbankfan.com/product/information-technology-project-
management-7th-edition-kathy-schwalbe-test-bank/
https://testbankfan.com/product/information-technology-project-
management-revised-6th-edition-schwalbe-test-bank/
https://testbankfan.com/product/information-technology-project-
management-8th-edition-kathy-schwalbe-test-bank/
Information Technology Project Management 5e - Marchewka
True/False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
2. Predecessor activities are activities that can be worked on at the same time as
another activity.
a. True
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
3. Predecessor activities are activities that must be completed before another activity
can be started.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
4. A parallel activity is a task that can be worked on at the same time as another
activity.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Information Technology Project Management 5e - Marchewka
5. Parallel activities can shorten the project schedule, but can have an impact on
project resources if a resource is assigned to two tasks at the same time.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
6. The critical path is the shortest path in the project network and also is the longest
time in which the project can be completed.
a. True
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
7. The critical path is the longest path in the project network and also is the shortest
time in which the project can be completed.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
8. Identifying the critical path is important because any change in the duration of the
activities or tasks on the critical path will affect the project’s schedule.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Ans: True
Difficulty: Easy
Information Technology Project Management 5e - Marchewka
10. Identifying the critical path is important because a project can only have one
critical path and it never changes.
a. True
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
11. PERT was developed in the 1950s to create a visual representation of scheduled
activities, their logical sequence, and interrelationships using a statistical
probability distribution.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
12. Installing a server before loading the operating system is an example of a finish-
to-start relationship.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
14. A start-to-finish activity is the most common relationship between two activities.
a. True
Information Technology Project Management 5e - Marchewka
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
15. The project budget is determined by the project schedule, the cost of the resources
assigned to each of the tasks, and by any other direct or indirect costs and
reserves.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
16. The direct costs of using a resource is the only type of cost that should be
considered when developing the project budget.
a. True
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
17. Sunk costs include such things as rent, utilities, insurance, and other
administrative costs.
a. True
b. False
Ans: False
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
Information Technology Project Management 5e - Marchewka
19. An over allocated resource would arise when Mary is assigned to work on two
tasks scheduled at the same time.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
20. Once the project schedule and budget are accepted by the client or sponsor, the
project plan becomes the baseline plan that will be used as a benchmark to track
the project’s actual progress.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: THE BASELINE PLAN
Ans: False
Difficulty: Easy
Ref: THE KICK-OFF MEETING
22. The kick-off meeting brings closure to the planning phase of the project.
a. True
b. False
Ans: True
Difficulty: Easy
Ref: THE KICK-OFF MEETING
Information Technology Project Management 5e - Marchewka
Multiple Choice
Ans: B
Difficulty: Easy
Ref: INTRODUCTION
2. The tool most closely associated with activity bars across a horizontal time axis
is:
Ans: B
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
3. _____ is considered the most useful and widely used project management tool.
Ans: B
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
4. _____ can be useful for tracking and monitoring project progress because because
they are simple and straightforward.
b) Gantt Charts
c) PERT
d) Activity on the Node
e) Critical Path Analysis
Ans: B
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
5. _____ provide valuable information about the logical sequence and dependencies
among the various activities and tasks:
Ans: D
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
6. _____ can help manage the Critical Path by providing information about which
activities can be delayed without affecting the deadline target date.
Ans: D
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
7. The amount of time an activity can be delayed before affecting the project
deadline is _____
a) slack
b) crash
c) fast-track
d) diversion
e) delay in any activity will delay the project
Information Technology Project Management 5e - Marchewka
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
8. The technique used to find the sequence of tasks with zero slack (or float) is most
closely associated with:
Ans: E
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
a) slacking.
b) floating.
c) diverting.
d) crashing.
e) fast tracking
Ans: D
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Information Technology Project Management 5e - Marchewka
a) slacking.
b) floating.
c) diverting.
d) crashing.
e) fast tracking
Ans: E
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
12. The technique used to help manage the Polaris submarine project and which bases
activity estimates on probabilistic estimates of three scenarios is most closely
associated with:
Ans: C
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
13. Starting the next task before the first task is complete is _____
a) lead
b) lag
c) negative lead
d) slack
e) float
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
14. An activity being analyzed under PERT was judged to most likely have a duration
of 40 days. When considering the time it would take to complete the activity if
every relevant factor went well, it was estimated to be able to be doable in 20
days and even under the worst case imaginable, the task would be take 50 days.
The estimates PERT duration of that activity is:
Information Technology Project Management 5e - Marchewka
a) 36.67 days
b) 38.33 days
c) 37.50 days
d) 28.33 days
e) 32.67 days
Ans: B
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
15. Based upon the following diagram and activity durations, the Critical Path is:
A 2
B 5
C 4
D 3
E 1
F 4
G 3
H 5
I 5
J 1
a) A+B+C+F+H+J
b) A+B+D+F+H+J
c) A+B+D+G+H+J
Information Technology Project Management 5e - Marchewka
d) A+B+D+G+I+J
e) A+B+E+G+I+J
Ans: B
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
16. _____ is well suited for developing simulations where the project manager can
conduct sensitivity analysis for schedule planning and risk analysis.
Ans: C
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
17. Under the Precedence Diagramming Method, the situation which occurs when a
relationship between two tasks that can or must start at the same time is called:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: B
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
18. Under the Precedence Diagramming Method, the most common relationship
between two activities which implies a logical sequence is called:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: A
Information Technology Project Management 5e - Marchewka
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
19. Installing the operating system on a computer before loading any application
packages is an example of:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: A
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
20. Under the Precedence Diagramming Method, the situation which occurs when
two activities can start at different times, have different durations, but are planned
to be competed at the same time is called:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: C
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
21. Under the Precedence Diagramming Method, the situation which occurs when
task A cannot end until task B starts is called:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: D
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
Information Technology Project Management 5e - Marchewka
22. Waiting to leave your shift until another person shows up is an example of:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: D
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
23. Under the Precedence Diagramming Method, the least common relationship
between two activities which occurs when they must complete at the same time is
called:
a) Finish-To-Start (FS)
b) Start-To-Start (SS)
c) Finish-To-Finish (FF)
d) Start-To-Finish (SF)
e) none of these
Ans: C
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
24. Critical Chain Project Management (CCPM) is based on the idea that
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
c) PERT
d) Theory of Constraints
e) Critical Path Analysis
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
Ans: C
Difficulty: Easy
Ref: PROJECT MANAGEMENT SOFTWARE TOOLS
Ans: D
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
28. To make a decision to attempt to build an application system based on what was
left after a previous attempt ended in failure primarily because of the large
investment the company made in the failed project most likely was made by a
manager who did not fully understand:
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Information Technology Project Management 5e - Marchewka
Ans: C
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
29. Rent, utilities, insurance and administrative costs are examples of:
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: B
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: C
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
31. Time and effort needed to gather experience on a technology or process are _____
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: D
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: E
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
a) Direct Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
34. The idea that there is a cost associated with using a resource is _____
a) Prorated Costs
b) Indirect Costs
c) Sunk Costs
d) Learning Curve Costs
e) Reserves Costs
Ans: A
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
a) Resource leveling
b) Resource constraining
c) Resource starving
d) Resource management
e) Resource addition
Ans: A
Information Technology Project Management 5e - Marchewka
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
36. Once the project schedule and project budget are approved they become the
_____
a) derivative plan
b) actual plan
c) baseline plan
d) project plan
e) schedule plan
Ans: C
Difficulty: Easy
Ref: THE BASELINE PLAN
Ans: E
Difficulty: Easy
Ref: THE KICK-OFF MEETING
Information Technology Project Management 5e - Marchewka
1. Define predecessor, successor, and parallel activities. Give a real world example
of each.
Ans: Predecessor activities are those activities that must be completed before another
activity can be started—e.g., a computer’s operating system must be installed before
loading an application package. On the other hand, successor activities are activities
that must follow a particular activity in some type of sequence. For example, a
program must be tested and then documented after it is compiled. A parallel activity
is an activity or task that can be worked on at the same time as another activity.
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
2. How can parallel activities help shorten the project schedule? Are there any
trade-offs?
Ans: Parallel activities may be thought of as an opportunity to shorten the project
schedule since separate tasks can be done at the same time instead of sequentially.
They also can be a trade-off since doing more than one thing at the same time can
have a critical impact on project resources.
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
4. What is the difference between crashing and fast tracking a project’s schedule?
Ans: Crashing a project’s schedule is the process of adding additional resources to
some activity on the critical path (or diverting resources from some activity with
some slack) in order to shorten the project. Fast-tracking on the other hand is
involved in finding activities that were originally planned to be sequential and
making them in parallel – that is doing them simultaneously.
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
5. Define the following and give a real world example of each (other than the ones
described in this book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-
to-Finish.
Ans:
• Finish-To-Start (FS)—A finish-to-start relationship is the most common
Information Technology Project Management 5e - Marchewka
working on task C can be dedicated to work solely on this particular task for this
project.
Difficulty: Medium
Ref: DEVELOPING THE PROJECT SCHEDULE
8. What is the critical chain? How is it different from the concept of a critical
path?
Ans: The critical chain is different from the critical path in that it also takes into
account resource contention.
Difficulty: Easy
Ref: DEVELOPING THE PROJECT SCHEDULE
9. Describe the steps necessary for estimating the cost of a particular activity or
task that has an estimated duration.
Ans:
1. Defining what resources will be needed to perform the work
2. Determining the quantity of resources that are needed
3. Defining the cost of using each resource
4. Calculating the cost of the task or activity
5. Ensuring that the resources are leveled, that is, resources have not been over
allocated
Difficulty: Easy
Ref: DEVELOPING THE PROJECT BUDGET
11. Why should the project manager ensure that the project resources are leveled?
Ans: The project manager should ensure that the project resources are leveled to
prevent resources from being over allocated – that is requiring the same resource to
be utilized on more than one task at the same time.
Difficulty: Medium
Ref: DEVELOPING THE PROJECT BUDGET
Difficulty: Medium
Ref: THE BASELINE PLAN
14. When does the project manager or team have the authority to begin executing
the project plan?
Ans: Once the project schedule and project budget has been approved by the project
client or upper management it becomes the baseline plan and then the project
manager and team has the authority to begin executing the plan.
Difficulty: Easy
Ref: THE BASELINE PLAN
Essay Questions
1. How does the work breakdown structure (WBS) link the project’s scope to the
schedule and budget?
2. What are the benefits and disadvantages of using Gantt charts as a project
management tool?
3. In what ways are project network diagrams similar to Gantt charts and what
additional strengths do they have?
4. Construct an Activity on the Node (AON) network diagram with at least 5 tasks that
illustrate predecessors, successors and parallel activities. Label the nodes
appropriately and assuming your tasks show estimated durations in days, state the
estimated time for completing your project.
5. Assume the following activities for a project along with their estimated durations
and predecessors. Describe how critical path analysis would be applied to this
project, and calculate the critical path. Define the concepts: slack/float,
expedite/crash, and fast tracking and explain what their implications are for this
project?
6. Three team members are given the task of estimating activity durations. Mr.
Optimist estimates the activity to take 2 days to complete. Ms. Pessimist estimates
the activity to take 5 days. Mrs. Realist claims that the most likely estimate is 4
days. What should their PERT analysis assign as an expected duration for the
activity and what are the benefits and implications of deploying this tool?
7. Describe the Precedence Diagramming Method along with the four fundamental
relationships that they are based on.
8. Describe the five steps that comprise the process of estimating the cost of a
particular activity. Illustrate the steps with a hypothetical example.
Information Technology Project Management 5e - Marchewka
9. Discuss the nature and relevance of direct, indirect, sunk, and learning curve costs
as well as the notion of contingency reserves.
III
By five o'clock that afternoon the last package of cards for
Garrod's shoes had been sent by messenger to H. G. Garrod at the
Biltmore Hotel. He was to give a decision next morning. At 5.30
Roger's stenographer tapped him on the shoulder.
"Mr. Golden, the superintendent of the building, to see you."
Roger turned around dazedly.
"Oh, how do?"
Mr. Golden came directly to the point. If Mr. Halsey intended to
keep the office any longer, the little oversight about the rent had
better be remedied right away.
"Mr. Golden," said Roger wearily, "everything'll be all right to-
morrow. If you worry me now maybe you'll never get your money.
After to-morrow nothing'll matter."
Mr. Golden looked at the tenant uneasily. Young men sometimes
did away with themselves when business went wrong. Then his eye
fell unpleasantly on the initialled suitcase beside the desk.
"Going on a trip?" he asked pointedly.
"What? Oh, no. That's just some clothes."
"Clothes, eh? Well, Mr. Halsey, just to prove that you mean what
you say, suppose you let me keep that suitcase until to-morrow
noon."
"Help yourself."
Mr. Golden picked it up with a deprecatory gesture.
"Just a matter of form," he remarked.
"I understand," said Roger, swinging around to his desk. "Good
afternoon."
Mr. Golden seemed to feel that the conversation should close on
a softer key.
"And don't work too hard, Mr. Halsey. You don't want to have a
nervous break——"
"No," shouted Roger, "I don't. But I will if you don't leave me
alone."
As the door closed behind Mr. Golden, Roger's stenographer
turned sympathetically around.
"You shouldn't have let him get away with that," she said. "What's
in there? Clothes?"
"No," answered Roger absently. "Just all my wife's shoes."
He slept in the office that night on a sofa beside his desk. At dawn
he awoke with a nervous start, rushed out into the street for coffee,
and returned in ten minutes in a panic—afraid that he might have
missed Mr. Garrod's telephone call. It was then 6.30.
By eight o'clock his whole body seemed to be on fire. When his
two artists arrived he was stretched on the couch in almost physical
pain. The phone rang imperatively at 9.30, and he picked up the
receiver with trembling hands.
"Hello."
"Is this the Halsey agency?"
"Yes, this is Mr. Halsey speaking."
"This is Mr. H. G. Garrod."
Roger's heart stopped beating.
"I called up, young fellow, to say that this is wonderful work you've
given us here. We want all of it and as much more as your office can
do."
"Oh, God!" cried Roger into the transmitter.
"What?" Mr. H. G. Garrod was considerably startled. "Say, wait a
minute there!"
But he was talking to nobody. The phone had clattered to the
floor, and Roger, stretched full length on the couch, was sobbing as if
his heart would break.
IV
Three hours later, his face somewhat pale, but his eyes calm as a
child's, Roger opened the door of his wife's bedroom with the
morning paper under his arm. At the sound of his footsteps she
started awake.
"What time is it?" she demanded.
He looked at his watch.
"Twelve o'clock."
Suddenly she began to cry.
"Roger," she said brokenly, "I'm sorry I was so bad last night."
He nodded coolly.
"Everything's all right now," he answered. Then, after a pause:
"I've got the account—the biggest one."
She turned toward him quickly.
"You have?" Then, after a minute's silence: "Can I get a new
dress?"
"Dress?" He laughed shortly. "You can get a dozen. This account
alone will bring us in forty thousand a year. It's one of the biggest in
the West."
She looked at him, startled.
"Forty thousand a year!"
"Yes."
"Gosh"—and then faintly—"I didn't know it'd really be anything like
that." Again she thought a minute. "We can have a house like
George Tompkins'."
"I don't want an interior-decoration shop."
"Forty thousand a year!" she repeated again, and then added
softly: "Oh, Roger——"
"Yes?"
"I'm not going out with George Tompkins."
"I wouldn't let you, even if you wanted to," he said shortly.
She made a show of indignation.
"Why, I've had a date with him for this Thursday for weeks."
"It isn't Thursday."
"It is."
"It's Friday."
"Why, Roger, you must be crazy! Don't you think I know what day
it is?"
"It isn't Thursday," he said stubbornly. "Look!" And he held out the
morning paper.
"Friday!" she exclaimed. "Why, this is a mistake! This must be last
week's paper. To-day's Thursday."
She closed her eyes and thought for a moment.
"Yesterday was Wednesday," she said decisively. "The laundress
came yesterday. I guess I know."
"Well," he said smugly, "look at the paper. There isn't any question
about it."
With a bewildered look on her face she got out of bed and began
searching for her clothes. Roger went into the bathroom to shave. A
minute later he heard the springs creak again. Gretchen was getting
back into bed.
"What's the matter?" he inquired, putting his head around the
corner of the bathroom.
"I'm scared," she said in a trembling voice. "I think my nerves are
giving away. I can't find any of my shoes."
"Your shoes? Why, the closet's full of them."
"I know, but I can't see one." Her face was pale with fear. "Oh,
Roger!"
Roger came to her bedside and put his arm around her.
"Oh, Roger," she cried, "what's the matter with me? First that
newspaper, and now all my shoes. Take care of me, Roger."
"I'll get the doctor," he said.
He walked remorselessly to the telephone and took up the
receiver.
"Phone seems to be out of order," he remarked after a minute; "I'll
send Bebé."
The doctor arrived in ten minutes.
"I think I'm on the verge of a collapse," Gretchen told him in a
strained voice.
Doctor Gregory sat down on the edge of the bed and took her
wrist in his hand.
"It seems to be in the air this morning."
"I got up," said Gretchen in an awed voice, "and I found that I'd
lost a whole day. I had an engagement to go riding with George
Tompkins——"
"What?" exclaimed the doctor in surprise. Then he laughed.
"George Tompkins won't go riding with any one for many days to
come."
"Has he gone away?" asked Gretchen curiously.
"He's going West."
"Why?" demanded Roger. "Is he running away with somebody's
wife?"
"No," said Doctor Gregory. "He 's had a nervous breakdown."
"What?" they exclaimed in unison.
"He just collapsed like an opera-hat in his cold shower."
"But he was always talking about his—his balanced life," gasped
Gretchen. "He had it on his mind."
"I know," said the doctor. "He's been babbling about it all morning.
I think it's driven him a little mad. He worked pretty hard at it, you
know."
"At what?" demanded Roger in bewilderment.
"At keeping his life balanced." He turned to Gretchen. "Now all I'll
prescribe for this lady here is a good rest. If she'll just stay around
the house for a few days and take forty winks of sleep she'll be as fit
as ever. She's been under some strain."
"Doctor," exclaimed Roger hoarsely, "don't you think I'd better
have a rest or something? I've been working pretty hard lately."
"You!" Doctor Gregory laughed, slapped him violently on the back.
"My boy, I never saw you looking better in your life."
Roger turned away quickly to conceal his smile—winked forty
times, or almost forty times, at the autographed picture of Mr.
George Tompkins, which hung slightly askew on the bedroom wall.
*** END OF THE PROJECT GUTENBERG EBOOK ALL THE SAD
YOUNG MEN ***
Updated editions will replace the previous one—the old editions will
be renamed.
1.D. The copyright laws of the place where you are located also
govern what you can do with this work. Copyright laws in most
countries are in a constant state of change. If you are outside the
United States, check the laws of your country in addition to the terms
of this agreement before downloading, copying, displaying,
performing, distributing or creating derivative works based on this
work or any other Project Gutenberg™ work. The Foundation makes
no representations concerning the copyright status of any work in
any country other than the United States.
• You pay a royalty fee of 20% of the gross profits you derive from
the use of Project Gutenberg™ works calculated using the
method you already use to calculate your applicable taxes. The
fee is owed to the owner of the Project Gutenberg™ trademark,
but he has agreed to donate royalties under this paragraph to
the Project Gutenberg Literary Archive Foundation. Royalty
payments must be paid within 60 days following each date on
which you prepare (or are legally required to prepare) your
periodic tax returns. Royalty payments should be clearly marked
as such and sent to the Project Gutenberg Literary Archive
Foundation at the address specified in Section 4, “Information
about donations to the Project Gutenberg Literary Archive
Foundation.”
• You comply with all other terms of this agreement for free
distribution of Project Gutenberg™ works.
1.F.
1.F.4. Except for the limited right of replacement or refund set forth in
paragraph 1.F.3, this work is provided to you ‘AS-IS’, WITH NO
OTHER WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED,
INCLUDING BUT NOT LIMITED TO WARRANTIES OF
MERCHANTABILITY OR FITNESS FOR ANY PURPOSE.