Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 36

Manage Safety and Environmental Protection

Determine areas of potential risk in the building and construction


workplace
Construction is a relatively hazardous undertaking. As Table 13-1 illustrates, there are
significantly more injuries and lost workdays due to injuries or illnesses in construction than
in virtually any other industry. These work related injuries and illnesses are exceedingly
costly. The Construction Industry Cost Effectiveness Project estimated that accidents cost
$8.9 billion or nearly seven percent of the $137 billion (in 1979 dollars) spent annually for
industrial, utility and commercial construction in the United States. Included in this total are
direct costs (medical costs, premiums for workers' compensation benefits, liability and
property losses) as well as indirect costs (reduced worker productivity, delays in projects,
administrative time, and damage to equipment and the facility). In contrast to most industrial
accidents, innocent bystanders may also be injured by construction accidents. Several crane
collapses from high rise buildings under construction have resulted in fatalities to passersby.
Prudent project managers and owners would like to reduce accidents, injuries and illnesses as
much as possible.
TABLE 13-1 Nonfatal Occupational Injury and Illness Incidence Rates

Industry 1996 1997 1998


Agriculture, forestry, fishing 8.7 8.4 7.3
Mining 5.4 5.9 4.4
Construction 9.9 9.5 8.6
Manufacturing 10.6 10.3 9.2
Transportation/public utilities 8.7 8.2 7.3
Wholesale and retail trade 6.8 6.7 6.1
Finance, insurance, real estate 2.4 2.2 1.8
Services 6.0 5.6 4.9

1
Note: Data represent total number of cases per 100 full-time employees
Source: U.S. Bureau of Labor Statistics, Occupational injuries and Illnesses in the United States
by Industry, annual

As with all the other costs of construction, it is a mistake for owners to ignore a significant
category of costs such as injury and illnesses. While contractors may pay insurance premiums
directly, these costs are reflected in bid prices or contract amounts. Delays caused by injuries and
illnesses can present significant opportunity costs to owners. In the long run, the owners of
constructed facilities must pay all the costs of construction. For the case of injuries and illnesses,
this general principle might be slightly qualified since significant costs are borne by workers
themselves or society at large.
However, court judgments and insurance payments compensate for individual losses and are
ultimately borne by the owners.
The causes of injuries in construction are numerous. Table 13-2 lists the reported causes of
accidents in the US construction industry in 1997. A similar catalogue of causes would exist for
other countries. The largest single category for both injuries and fatalities are individual falls.
Handling goods and transportation are also a significant cause of injuries. From a management
perspective, however, these reported causes do not really provide a useful prescription for safety
policies. An individual fall may be caused by a series of coincidences: a railing might not be
secure, a worker might be inattentive, the footing may be slippery, etc. Removing any one of
these compound causes might serve to prevent any particular accident. However, it is clear that
conditions such as unsecured railings will normally increase the risk of accidents. Table 13-3
provides a more detailed list of causes of fatalities for construction sites alone, but again each
fatality may have multiple causes.

2
TABLE 13-2 Fatal Occupational Injuries in
All accidents 1,107 1,190
Rate per 100,000 workers 14 14
Cause Percentage
Transportation incidents 26% 27%
Assaults/violentacts 3 2
Contact with objects 18 21
Falls 34 32
Exposure 17 15

TABLE 13-3 Fatality Causes in Construction, 1998


Cause Deaths Percentage
Fall from/through roof 66 10.6%
Fall from/with structure (other than roof) 64 10.2
Electric shock by equipment contacting power source 58 9.3
Crushed/run over non-operator by operating construction equipment 53 8.5
Electric shock by equipment installation or tool use 45 7.2
Struck by falling object or projectile (including tip-overs) 29 4.6
Lifting operation 27 4.3
Fall from/with ladder (includes collapse/fall of ladder) 27 4.3
Crushed/run over/trapped operator by operating construction equipment 25 4.0
Trench collapse 24 3.8
Crushed/run over by highway vehicle 22 3.5

Source: Construction Resource Analysis

Various measures are available to improve jobsite safety in construction. Several of the most
important occur before construction is undertaken. These include design, choice of technology
and education. By altering facility designs, particular structures can be safer or more hazardous

3
to construct.
Choice of technology can also be critical in determining the safety of a jobsite. Safeguards built
into machinery can notify operators of problems or prevent injuries. For example, simple
switches can prevent equipment from being operating when protective shields are not in place.
With the availability of on-board electronics (including computer chips) and sensors, the
possibilities for sophisticated machine controllers and monitors has greatly expanded for
construction equipment and tools. Materials and work process choices also influence the safety
of construction.
Educating workers and managers in proper procedures and hazards can have a direct impact on
jobsite safety. The realization of the large costs involved in construction injuries and illnesses
provides a considerable motivation for awareness and education. Regular safety inspections and
safety meetings have become standard practices on most job sites.
Pre-qualification of contractors and sub-contractors with regard to safety is another important
avenue for safety improvement. If contractors are only invited to bid or enter negotiations if they
have an acceptable record of safety (as well as quality performance), then a direct incentive is
provided to insure adequate safety on the part of contractors.

During the construction process itself, the most important safety related measures are to insure
vigilance and cooperation on the part of managers, inspectors and workers. Vigilance involves
considering the risks of different working practices. In also involves maintaining temporary
physical safeguards such as barricades, braces, guy lines, railings, toe boards and the like. Sets of
standard practices are also important, such as:

 Requiring hard hats on site.


 Requiring eye protection on site.
 Requiring hearing protection near loud equipment.
 Insuring safety shoes for workers.
 Providing first-aid supplies and trained personnel on site.

While eliminating accidents and work related illnesses is a worthwhile goal, it will never be
attained. Construction has a number of characteristics making it inherently hazardous. Large
4
forces are involved in many operations. The jobsite is continually changing as construction
proceeds. Workers do not have fixed worksites and must move around a structure under
construction. The tenure of a worker on a site is short, so the worker's familiarity and the
employer-employee relationship are less settled than in manufacturing settings. Despite these
peculiarities and as a result of exactly these special problems, improving worksite safety is a very
important project management concern.

Effects of Project Risks on Organization

The uncertainty in undertaking a construction project comes from many sources and often
involves many participants in the project. Since each participant tries to minimize its own risk,
the conflicts among various participants can be detrimental to the project. Only the owner has the
power to moderate such conflicts as it alone holds the key to risk assignment through proper
contractual relations with other participants. Failure to recognize this responsibility by the owner
often leads to undesirable results. In recent years, the concept of "risk sharing/risk assignment"
contracts has gained acceptance by the federal government. Since this type of contract
acknowledges the responsibilities of the owners, the contract prices are expected to be lower than
those in which all risks are assigned to contractors.
In approaching the problem of uncertainty, it is important to recognize that incentives must be
provided if any of the participants is expected to take a greater risk. The willingness of a
participant to accept risks often reflects the professional competence of that participant as well as
its propensity to risk. However, society's perception of the potential liabilities of the participant
can affect the attitude of risk-taking for all participants. When a claim is made against one of the
participants, it is difficult for the public to know whether a fraud has been committed, or simply
that an accident has occurred.
Risks in construction projects may be classified in a number of ways. One form of classification
is as follows:
1. Socioeconomic factors
 Environmental protection
 Public safety regulation
 Economic instability

5
 Exchange rate fluctuation
2. Organizational relationships
 Contractual relations
 Attitudes of participants
 Communication
3. Technological problems
 Design assumptions
 Site conditions
 Construction procedures
 Construction occupational safety

The environmental protection movement has contributed to the uncertainty for construction
because of the inability to know what will be required and how long it will take to obtain
approval from the regulatory agencies. The requirements of continued re-evaluation of problems
and the lack of definitive criteria which are practical have also resulted in added costs. Public
safety regulations have similar effects, which have been most noticeable in the energy field
involving nuclear power plants and coal mining. The situation has created constantly shifting
guidelines for engineers, constructors and owners as projects move through the stages of
planning to construction. These moving targets add a significant new dimension of uncertainty
which can make it virtually impossible to schedule and complete work at budgeted cost.
Economic conditions of the past decade have further reinforced the climate of uncertainty with
high inflation and interest rates. The deregulation of financial institutions has also generated
unanticipated problems related to the financing of construction.

Uncertainty stemming from regulatory agencies, environmental issues and financial aspects of
construction should be at least mitigated or ideally eliminated. Owners are keenly interested in
achieving some form of breakthrough that will lower the costs of projects and mitigate or
eliminate lengthy delays. Such breakthroughs are seldom planned. Generally, they happen when
the right conditions exist, such as when innovation is permitted or when a basis for incentive or
reward exists.
However, there is a long way to go before a true partnership of all parties involved can be forged.

6
During periods of economic expansion, major capital expenditures are made by industries and
bid up the cost of construction. In order to control costs, some owners attempt to use fixed price
contracts so that the risks of unforeseen contingencies related to an overheated economy are
passed on to contractors. However, contractors will raise their prices to compensate for the
additional risks.

The risks related to organizational relationships may appear to be unnecessary but are quite real.
Strained relationships may develop between various organizations involved in the
design/construct process. When problems occur, discussions often center on responsibilities
rather than project needs at a time when the focus should be on solving the problems.
Cooperation and communication between the parties are discouraged for fear of the effects of
impending litigation. This barrier to communication results from the ill-conceived notion that
uncertainties resulting from technological problems can be eliminated by appropriate contract
terms. The net result has been an increase in the costs of constructed facilities.

The risks related to technological problems are familiar to the design/construct professions which
have some degree of control over this category. However, because of rapid advances in new
technologies which present new problems to designers and constructors, technological risk has
become greater in many instances. Certain design assumptions which have served the
professions well in the past may become obsolete in dealing with new types of facilities which
may have greater complexity or scale or both. Site conditions, particularly subsurface conditions
which always present some degree of uncertainty, can create an even greater degree of
uncertainty for facilities with heretofore unknown characteristics during operation. Because
construction procedures may not have been fully anticipated, the design may have to be modified
after construction has begun. An example of facilities which have encountered such uncertainty
is the nuclear power plant, and many owners, designers and contractors have suffered for
undertaking such projects.

If each of the problems cited above can cause uncertainty, the combination of such problems is
often regarded by all parties as being out of control and inherently risky. Thus, the issue of
liability has taken on major proportions and has influenced the practices of engineers and

7
constructors, who in turn have influenced the actions of the owners.

Many owners have begun to understand the problems of risks and are seeking to address some of
these problems. For example, some owners are turning to those organizations that offer complete
capabilities in planning, design, and construction, and tend to avoid breaking the project into
major components to be undertaken individually by specialty participants. Proper coordination
throughout the project duration and good organizational communication can avoid delays and
costs resulting from fragmentation of services, even though the components from various
services are eventually integrated.

Attitudes of cooperation can be readily applied to the private sector, but only in special
circumstances can they be applied to the public sector. The ability to deal with complex issues is
often precluded in the competitive bidding which is usually required in the public sector. The
situation becomes more difficult with the proliferation of regulatory requirements and resulting
delays in design and construction while awaiting approvals from government officials who do
not participate in the risks of the project.

Capital investment appraisal


As investments involve large resources, wrong investment decisions are very expensive
to correct
Managers are responsible for comparing and evaluating alternative projects so as to
allocate limited resources and maximize the firm’s wealth
Basic techniques of making capital investment appraisal for evaluating proposed capital
investment projects

8
Investment appraisal methods

Considering the time valueIgnoring


of the time value of
money concept money concept

Net present value


Internal rate of return
Net present value method
Time value of money
When facing different investment proposals, the management should choose the project
that can generate the greatest addition of value to the company. For example,
Project A Project B
Initial investment $100 $100
Cash inflow at end of year
Year 1 $110
Year 2 $121
At first sight, some may think that project B is better because it has a higher cash inflow.
However, the time value of money concept states that a dollar today is always worth
more than a dollar in the future
The two projects are of equal value to the company because their present values are the
same

After taking timing of cash flow into consideration,


Project A Project B
Present value of cash flow

9
110 110
(interest rate is 10% per annum) 2
(1+10 %) (1+10 %)

= $100 $100
The two projects are of equal value to the company because their present values are the
same

Factors leading to the changes in value of money

Opportunity cost of money


Erosion of purchasing power due to inflation
Uncertainty and risk

Opportunity cost of money


Opportunity cost of money refers to the cost incurred or income forgone by not using the
money for other purpose
For surplus cash, the opportunity cost is the interest income forgone by investing the cash
in other investments or depositing it in the bank

Erosion of purchasing power due to inflation


Inflation refers to the continual increase in the general price level of goods or services
During a period of inflation, prices of goods increase while the purchasing power of
money decrease. The purchasing power of a dollar today is greater than that of the future

Uncertainty and risk


Investors tend to avoid risk. The uncertainty involved in future cash inflows is much
higher than that in present cash inflows
If the level of risk rises, investors will expect a higher return as compensation.
For example, suppose an investor expects $100 for return now. After adding a 10% risk
premium, he will expect $110 one year later
Since future events are always uncertain, all estimates of costs and benefits used in

10
economic evaluation involve a degree of uncertainty. Probabilistic methods are often
used in decision analysis to determine expected costs and benefits as well as to assess the
degree of risk in particular projects.
In estimating benefits and costs, it is common to attempt to obtain the expected or
average values of these quantities depending upon the different events which might
occur. Statistical techniques such as regression models can be used directly in this regard
to provide forecasts of average values.
Alternatively, the benefits and costs associated with different events can be estimated and
the expected benefits and costs calculated as the sum over all possible events of the
resulting benefits and costs multiplied by the probability of occurrence of a particular
event:

m
E [Bt ]=∑ ( Bt /q ) Pr ⁡{q }
q=1

m
E [Ct ]=∑ ( Ct /q ) Pr ⁡{q }
q=1

where q = 1,....,m represents possible events, (Bt|q) and (Ct|q) are benefits and costs
respectively in period t due to the occurrence of q, Pr{q} is the probability that q occurs,
and E[Bt] and E[Ct] are respectively expected benefit and cost in period t. Hence, the
expected net benefit in period t is given by:
E [ At ] =E [ Bt ] −E[Ct ]

For example, the average cost of a facility in an earthquake prone site might be calculated
as the sum of the cost of operation under normal conditions (multiplied by the probability
of no earthquake) plus the cost of operation after an earthquake (multiplied by the
probability of an earthquake).
Expected benefits and costs can be used directly in the cash flow calculations described
earlier.

11
In formulating objectives, some organizations wish to avoid risk so as to avoid the
possibility of losses. In effect, a risk avoiding organization might select a project with
lower expected profit or net social benefit as long as it had a lower risk of losses. This
preference results in a risk premium or higher desired profit for risky projects. A rough
method of representing a risk premium is to make the desired MARR higher for risky
projects.

Discounting
According to the time value of money concept, a dollar in one year is not worth the same
as a dollar in another year.
In evaluating a multi-year investment, cash inflows and outflows are generated in
different years
It is necessary to convert the cash flows for different years into a common value at a
common point of time, either at present or in the future.
Discounting is the process of reducing future cash flows to present values with the use of
an interest rate

FVn
Present value = ¿¿
Where FV = Future value of an investment
n= Number of years
r= Appropriate interest rate

Example
John has won a lucky draw. He is deciding whether to receive the
Prize money of $3000 today or the following set of cash flows over the next three years:
Year Cash flow
1 $1100
2 $1210
3 $1331

12
Future values Discount processes Present value
Year 1 $1100 $1100/1.1 $1000
Year 2 $1210 $1210/1.12 $1000
Year 3 $1331 $1331/1.13 $1000

Net present value method


Net present value (NPV) method is a process that uses the discounted cash flow of a
project to determine whether the rate of return on that project is equal to, higher than, or
lower than the desired rate of return
With the NPV method, we can compare the return on investment in capital projects with
the return on an alternative equal risk investment in securities traded in financial market
Calculation procedures
1. Determining the discount rate
2. Calculating the NPV:

FV 1
NPV =
¿¿

Where FV = future value of an investment


n = no. of years
r = Rate of return available on an equivalent risk
Security in the financial market
I 0= initial investment
3. Interpreting the NPV derived as follows:
NPVs Comments Reasons
<0 Reject the project The rate of return from the project is small than
the rate of return from an equivalent risk
investment
=0 Indifferent to accept or The rate of return from the project is equal to the
reject the project rate of return from an equivalent risk investment

13
>0 Accept the project The rate of return from the project is greater than
the rate of return from an equivalent risk
investment
Highest Accept the project If various project are considered, the project with
highest positive NPV should be chosen

Example
A company is considering making several investments in the Production facilities for the new
products with an estimated useful Life of four years. The cash inflows and outflows are listed as
follows:

Project

A B C D
$ $ $ $
Initial investment 900000 1000000 303730 1500000
Cash inflow
Year 1 120000 400000 100000 10000
Year 2 250000 400000 100000 10000
Year 3 400000 400000 100000 1000000
Year 4 1300000 400000 100000 1000000

The appropriate discount rate of these investments is 12%


Required:
(a) Calculate the NPV of each investment and determine whether to accept it or not
(assuming the company has unlimited resources)
(b) If the company has limited resources, determine which investment should be accepted by
referring to the highest NPV
(a). Project A

14
120000
NPV =
¿¿

= $517327 (accepting)

Project B
40000
NPV =
¿¿
= $214920(accepting)

Project C
100000
NPV =
¿¿
= $0 (indifferent to accept or reject)

Project D

10000
NPV =
¿¿
= -$135801(rejecting)

(b) With limited resources, the company should only accept project A because it generates the
highest NPV

Advantages of NPV
Consistency with the time value of money concept
Consideration of all cash flows
Adoption of cash flows instead of accounting profit

Internal rate of return

15
The internal rate of return is the annual percentage return achieved by a project, of which
the sum of discounted cash inflow over the life of the project is equal to the sum of
discounted cash outflows
If the IRR is used to determine the NPV of a project, the NPV will be zero.
The company will accept this project only if the IRR is equal to or higher than the
minimum rate of return or the cost of capital

Calculation procedures
1. By trial and error, find out the discount rate that will give a zero NPV

FV 1
NPV =
¿¿

Where FV = future value of an investment


n = no. of years
r = internal rate of return
I 0= initial investment
2. If the NPV is positive, try a higher discount rate in order to give a negative NPV and vice
versa
3. After getting one positive NPV and one negative NPV, use interpolation to find out the
rate giving zero NPV
P
IRR=L+ (H −L)
P−N
Where L = Discount rate of the low trial
H = Discount rate of the high trial
P = NPV of cash flows of the low trial
N = NPV of cash flows of the high trial

4. In evaluating an investment project, the IRR is compared with the management’s


predetermined rate

16
IRRs Comments Reasons
< lowest acceptable level of return Reject NPV<0
= lowest acceptable level of return Accept NPV=0
> Lowest accepted level of return Accept NPV>0
Highest Accept If several project are
considered, the highest IRR
should be chosen

Example
A project costs $400 and produces a regular cash inflow of $200 at the end of each of the next
three years. Calculate the IRR. If the minimum rate of return is 15 %, suggest with reason
whether you should accept the project or not.

$ 200
NPV =
¿¿
Assuming the discount rate is 22%

$ 200
NPV =
¿¿
Assuming the discount rate is 24%
$ 200
NPV =
¿¿

P
IRR=L+ ( H−L )
P−N
Where L = Discount rate of the low trial
H = Discount rate of the high trial
P = NPV of cash flows of the low trial
N = NPV of cash flows of the high trial

17
8.4
IRR=22 %+ (24−22 ) %
8.4−(−3.8 )
= 23.38%
Since the IRR (23.38%) is higher than the minimum rate of return (15%),
The project should be accepted

Payback period
Payback period is the period of time it takes for a company to recover its initial
investment in a project
The method measures the time required for a project’s cash flow to equalize the initial
investment
Acceptance criterion
< predetermined cutoff period Accept the project
> Predetermined cutoff period Reject the project

Example
A company is considering making the following mutually exclusive
Investments in the production facilities for the new products with an Estimated useful life of four
years. The cash inflow and outflows are
Listed as follows:

Project A$ Project B $

Initial investment 900000 1000000


Cash inflow at the end of year
Year 1 700000 600000
Year 2 100000 400000

18
Year 3 100000 400000
Year 4 1300000 400000

Project A : 3 years Project B: 2 years


Project B takes only two years to recover its initial investment. With
The shortest payback period, the company will accept project B

Advantages of payback period


Easy to adopt
Facilities further evaluation
 After obtaining an acceptable payback period, the project will be evaluated by
other financial capital budgeting techniques

Disadvantages of Payback period


Ignore the cash flows after payback period
Adopt an arbitrary standard for the payback period
Ignores the timing of cash flow

Discounted payback period


The payback period method is criticized for ignoring the timing of cash flows, therefore
discounted cash flows are used to calculate the discounted payback period

Example
A company is considering making the following mutually exclusive investments in the
production facilities for the new products with an estimated useful life of four years. The cash
inflow and outflows are listed as follows:

Project A Project B

19
Initial investment 900000 1000000
Cash inflow at the end of year
Year 1 700000 600000
Year 2 100000 400000
Year 3 100000 400000
Year 4 1300000 400000

Discount cash inflow (20%)

Project A Project B
$ $
Initial investment 900000 1000000
Discounted cash flow
700000 400000
Year 1 1 = 583333 1 =500000
1. 2 1.2

100000 400000
Year 2 2 = 69444 2 = 277778
1. 2 1.2

100000 400000
Year 3 3 = 57870 3 = 231481
1. 2 1.2

100000 400000
Year 4 4 = 626929 4 = 192901
1. 2 1. 2

Discount payback period


900000−710647
Project A 3+ = 3.3 years
626929

100000−777778
Project B 2+ = 2.96 years
231481
20
Accounting rate of return
The accounting rate of return compares the average accounting profit with the average
investment cost of project
The accounting profit can be expressed either before tax or after tax

Calculation procedures
Average net profit per year (¿ thelife of the project )
ARR =
Average investment cost

Total profit
Average net profit per year=
No . of life of the project

Initial investment
Average investment cost =
2

Acceptance criterion
In evaluating an investment project, the ARR of the project is compared with a predetermined
minimum acceptable accounting
Rate of return:

ARRs Comments
< minimum acceptable rate Reject project
= minimum acceptable rate Accept project
> minimum acceptable rate Accept project
Highest Choose highest ARR

Example
A company is considering whether to buy specialized machines For a new production line. The
purchase price of machinery is
$400000 and its estimated useful life is four years. There is no scrap
Value after four years

21
The project income statements:

Year1 Year 2 Year 3 Year 4


$ $ $ $
Revenue 310000 280000 280000 310000
Depreciation 10000 100000 100000 100000
Other expenses 150000 100000 110000 120000
Profit before tax 60000 80000 70000 90000
Taxation (15%) 9000 12000 10500 13500
51000 68000 59500 76500

Should the company buy the new machinery if the minimum acceptable
Rate of return is 20%?

51000+68000+59500+76500
Average net income =
4
= $63750

400000+0
Average investment =
2
= $200000

The cost of machinery is $400000 at the beginning


The cost of machinery is $0 at the end as depreciation is provided
On straight line method and there is no scrap value

$ 63750
ARR= = 31.875%
$ 200000

Since the ARR is 31.875%, which is higher than the minimum


Acceptable rate of 20%, the company should invest in the new machinery.

Advantages of ARR
It is easy to understand and compute

22
It avoids using gross figures. Therefore, it enables comparisons to be made between
projects with different useful lives

Disadvantages of ARR
It ignores the time value of money
ARR method seems to be less reliable than the NPV method. It adopts the accounting
profit instead of cash flows calculation. The change of depreciation method may also
alter the accounting profit

Inspect and report on areas of specific risk


Safety Inspections and Checklists
Even if safety inspections were not strongly recommended, they are an excellent way for the
department to reference the commitment to safe work practices, provide practical training in
safety awareness and minimize hazards at the workplace. These inspections provide a systematic
method for involving supervisors, employees, safety coordinators, and/or safety committees in
the process of eliminating workplace hazards.

Types of Safety Inspections


There are several ways to perform safety inspections of a workplace, task or job. The most
popular ways include using checklists, general knowledge, and risk mapping. To be effective,
safety inspections must be individualized or tailored to meet the needs of a specific workplace,
task or job.

Safety Checklist Inspections


A checklist is very good for the regular inspection of specific items. However, they may not be
as useful in identifying previously unrecognized hazards.
Many different checklists are available from a variety of sources. Unfortunately, since these
readymade checklists are generic, they rarely meet the needs of a specific workplace, task or job.
However, you may find them useful to inspect a part of your area. For instance, the owner's
manual for a table saw may have a checklist that works perfectly for inspecting the saw in a
department shop. Taking parts of several ready-made checklists and putting them together may
be an easy method of beginning the development of your customized checklist.

23
Risk Mapping Safety Inspections
The third inspection method is called risk mapping. It is a good method to use at a safety meeting
where everyone there is familiar with the workplace or process. This technique uses a
map/drawing of the workplace or a list of steps in a process. People in the group then tell the
leader the hazards they recognize and where they are located in the workplace or process. The
leader uses different colors or symbols to identify different types of hazards on the map or list of
steps. This type of inspection is valuable for involving all employees in identifying and resolving
safety hazards.

What should you include in your inspections?


When you do your inspections make sure you are looking at your entire operation's safety
program.
Remember to evaluate:
Processes
Equipment
Workplace environment
Employee training
Emergency plans
How often should you do inspections?
Safety inspections should be conducted at least every six months.
Who should do the inspections?
It has to be someone who is familiar with the workplace, task or job. The best way is to have a
supervisor and an employee from the area inspect together.

Workplace Inspections Procedure


To outline the activities required to ensure a consistent, planned, systematic appraisal of the
workplace to identify hazards and/or review established controls.
Workplace inspections ensure that:
 Identify hazardous conditions and review hazard control measures
 monitor and evaluate the effectiveness of health and safety practices and procedures

24
 Improve health and safety practices and procedures
 Measure Occupation Health and Safety (OHS) compliance
 Check new facilities, equipment, processes
 Collect information that identifies potential new safety initiatives
 Maintain interest in health and safety through consultation
 Display management commitment to health and safety
 Empower staff to ensure a safe work environment.
Managers, in consultation with their staff and the OHS representatives, are responsible for
developing and implementing a system of workplace inspections, consistent with the work area’s
risk profile.
Workplace inspections involve the following steps:
 Identifying the hazards
 Assessing and rating the risks
 Controlling the risks (using the Hierarchy of Control)
 Implementing the risk controls
 Monitoring and reviewing the risk controls
 Documenting the results
Property has specific responsibility for inspecting building infrastructure, essential services,
grounds and walkways, plant and equipment and security.

DETERMINE THE WORKPLACE TO BE INSPECTED


Determine the workplace to be inspected and nominate an OHS Committee Workgroup.
Inspections will need to be undertaken:
 Where equipment or layout of any work area is altered and increases risk
 If a new plant or work process is introduced
 Prior to commencement of work
The aim should be to complete a minimum of two inspections a year.
Individual work areas may elect to increase the number of inspections if there is an identified
need or increased risk profile.
OHS Committee

25
Workgroup
Form an Inspection Team
Form an inspection team which includes the following:
 A staff member(s) familiar with the work area
 A management representative or their delegate
 An OHS representative
 A delegate from the Health and Safety Unit.
At least one of the inspection team must be trained in the University process for workplace
inspections.
Obtain Checklists
A range of Workplace Inspections Checklists is available to assist in the inspection process. The
checklists are based on the hazard register for each area and have been reviewed by staff in the
relevant area. They also assist in recording information and triggering questions during the
inspection.
INSPECT THE WORKPLACE
Consider the following factors when inspecting:
Workplace Design (i.e. the physical workplace, both internal and external environment)
 Is the area suited to the work being carried out?
 Does it provide adequate space for occupants?
 Ensure the design meets relevant legislative requirements.
 Does it comply with the OHS Act and Regulations?

Systems of Work
 Are Policies and Procedures available?
 Are Safe Operating Procedures written and accessible?
 Is important information available to workers re hazards eg Hazard Register, Material
Safety Data Sheets?

Environment
Behavior

26
Identify risks
Assess and rate a risk

Report
Document the outcomes of your risk assessments on the Risk
Assessment Form Prepare a Workplace Safety Inspection Summary Report to the
Executive Dean/ Head of Office for action.
Provide a copy of the report to the Central OHS Committee.
Document the results
Document all assessments on the Risk Register Form and forward this, along with copies of any
completed Checklists and/or notes to the following people:
 Executive Dean
 Head of Department
 Health & Safety Unit
 OHS Representative
 Central OHS Committee Executive Dean/Head of Office

Advice on implementation of control measures at the building and


construction workplace

Managing potential risk

The best way to manage risks in international trade is to anticipate, reduce or avoid them. Seek
legal advise and develop a risk management plan that is shared with your staff.

Process

According to the standard ISO 31000 "Risk management – Principles and guidelines on
implementation, the process of risk management consists of several steps as follows:

Establishing the context

This involves:

27
1. identification of risk in a selected domain of interest
2. planning the remainder of the process
3. mapping out the following:
o the social scope of risk management
o the identity and objectives of stakeholders
o the basis upon which risks will be evaluated, constraints.
4. defining a framework for the activity and an agenda for identification
5. developing an analysis of risks involved in the process
6. mitigation or solution of risks using available technological, human and organizational
resources.

Identification

After establishing the context, the next step in the process of managing risk is to identify
potential risks. Risks are about events that, when triggered, cause problems. Hence, risk
identification can start with the source of problems, or with the problem itself.

 Source analysis - Risk sources may be internal or external to the system that is the target
of risk management.

Examples of risk sources are: stakeholders of a project, employees of a company or the weather
over an airport.

 Problem analysis- Risks are related to identified threats. For example: the threat of losing
money, the threat of abuse of confidential information or the threat of accidents and
casualties. The threats may exist with various entities, most important with shareholders,
customers and legislative bodies such as the government.

When either source or problem is known, the events that a source may trigger or the events that
can lead to a problem can be investigated. For example: stakeholders withdrawing during a
project may endanger funding of the project; confidential information may be stolen by
employees even within a closed network; lightning striking an aircraft during takeoff may make
all people on board immediate casualties.

28
The chosen method of identifying risks may depend on culture, industry practice and
compliance. The identification methods are formed by templates or the development of templates
for identifying source, problem or event. Common risk identification methods are:

 Objectives-based risk identification- Organizations and project teams have objectives.


Any event that may endanger achieving an objective partly or completely is identified as
risk.
 Scenario-based risk identification - In scenario analysis different scenarios are created.
The scenarios may be the alternative ways to achieve an objective, or an analysis of the
interaction of forces in, for example, a market or battle. Any event that triggers an
undesired scenario alternative is identified as risk.
 Taxonomy-based risk identification - The taxonomy in taxonomy-based risk
identification is a breakdown of possible risk sources. Based on the taxonomy and
knowledge of best practices, a questionnaire is compiled. The answers to the questions
reveal risks.
 Common-risk checking - In several industries, lists with known risks are available. Each
risk in the list can be checked for application to a particular situation.
 Risk charting - This method combines the above approaches by listing resources at risk,
threats to those resources, modifying factors which may increase or decrease the risk and
consequences it is wished to avoid. Creating a matrix under these headings enables a
variety of approaches. One can begin with resources and consider the threats they are
exposed to and the consequences of each. Alternatively one can start with the threats and
examine which resources they would affect, or one can begin with the consequences and
determine which combination of threats and resources would be involved to bring them
about.

Risk Assessment

Once risks have been identified, they must then be assessed as to their potential severity of
impact (generally a negative impact, such as damage or loss) and to the probability of
occurrence. These quantities can be either simple to measure, in the case of the value of a lost
building, or impossible to know for sure in the case of the probability of an unlikely event

29
occurring. Therefore, in the assessment process it is critical to make the best educated decisions
in order to properly prioritize the implementation of the risk management plan.

Even a short-term positive improvement can have long-term negative impacts. Take the
"turnpike" example. A highway is widened to allow more traffic. More traffic capacity leads to
greater development in the areas surrounding the improved traffic capacity. Over time, traffic
thereby increases to fill available capacity. Turnpikes thereby need to be expanded in a
seemingly endless cycles. There are many other engineering examples where expanded capacity
(to do any function) is soon filled by increased demand. Since expansion comes at a cost, the
resulting growth could become unsustainable without forecasting and management.

The fundamental difficulty in risk assessment is determining the rate of occurrence since
statistical information is not available on all kinds of past incidents. Furthermore, evaluating the
severity of the consequences (impact) is often quite difficult for intangible assets. Asset valuation
is another question that needs to be addressed. Thus, best educated opinions and available
statistics are the primary sources of information.

Potential risk treatments

Once risks have been identified and assessed, all techniques to manage the risk fall into one or
more of these four major categories:

 Avoidance (eliminate, withdraw from or not become involved)


 Reduction (optimize – mitigate)
 Sharing (transfer – outsource or insure)
 Retention (accept and budget)

Risk avoidance

This includes not performing an activity that could carry risk. An example would be not buying a
property or business in order to not take on the legal liability that comes with it. Another would
be not flying in order not to take the risk that the airplane were to be hijacked. Avoidance may
seem the answer to all risks, but avoiding risks also means losing out on the potential gain that

30
accepting (retaining) the risk may have allowed. Not entering a business to avoid the risk of loss
also avoids the possibility of earning profits.

Hazard prevention

Hazard prevention refers to the prevention of risks in an emergency. The first and most effective
stage of hazard prevention is the elimination of hazards. If this takes too long, is too costly, or is
otherwise impractical, the second stage is mitigation.

Risk reduction

Risk reduction or "optimization" involves reducing the severity of the loss or the likelihood of
the loss from occurring. For example, sprinklers are designed to put out a fire to reduce the risk
of loss by fire. This method may cause a greater loss by water damage and therefore may not be
suitable. Halon fire suppression systems may mitigate that risk, but the cost may be prohibitive
as a strategy.

Acknowledging that risks can be positive or negative, optimizing risks means finding a balance
between negative risk and the benefit of the operation or activity; and between risk reduction and
effort applied.

Modern software development methodologies reduce risk by developing and delivering software
incrementally. Early methodologies suffered from the fact that they only delivered software in
the final phase of development; any problems encountered in earlier phases meant costly rework
and often jeopardized the whole project. By developing in iterations, software projects can limit
effort wasted to a single iteration.

Risk sharing

Briefly defined as "sharing with another party the burden of loss or the benefit of gain, from a
risk, and the measures to reduce a risk."

The term of 'risk transfer' is often used in place of risk sharing in the mistaken belief that you can
transfer a risk to a third party through insurance or outsourcing. In practice if the insurance

31
company or contractor go bankrupt or end up in court, the original risk is likely to still revert to
the first party. As such in the terminology of practitioners and scholars alike, the purchase of an
insurance contract is often described as a "transfer of risk." However, technically speaking, the
buyer of the contract generally retains legal responsibility for the losses "transferred", meaning
that insurance may be described more accurately as a post-event compensatory mechanism. For
example, a personal injuries insurance policy does not transfer the risk of a car accident to the
insurance company. The risk still lies with the policy holder namely the person who has been in
the accident. The insurance policy simply provides that if an accident (the event) occurs
involving the policy holder then some compensation may be payable to the policy holder that is
commensurate to the suffering/damage.

Some ways of managing risk fall into multiple categories. Risk retention pools are technically
retaining the risk for the group, but spreading it over the whole group involves transfer among
individual members of the group. This is different from traditional insurance, in that no premium
is exchanged between members of the group up front, but instead losses are assessed to all
members of the group.

Risk retention

Involves accepting the loss, or benefit of gain, from a risk when it occurs. True self insurance
falls in this category. Risk retention is a viable strategy for small risks where the cost of insuring
against the risk would be greater over time than the total losses sustained. All risks that are not
avoided or transferred are retained by default. This includes risks that are so large or catastrophic
that they either cannot be insured against or the premiums would be infeasible. War is an
example since most property and risks are not insured against war, so the loss attributed by war
is retained by the insured. Also any amounts of potential loss (risk) over the amount insured is
retained risk. This may also be acceptable if the chance of a very large loss is small or if the cost
to insure for greater coverage amounts is so great it would hinder the goals of the organization
too much.

32
Create a risk management plan

Select appropriate controls or countermeasures to measure each risk. Risk mitigation needs to be
approved by the appropriate level of management. For instance, a risk concerning the image of
the organization should have top management decision behind it whereas IT management would
have the authority to decide on computer virus risks.

The risk management plan should propose applicable and effective security controls for
managing the risks. For example, an observed high risk of computer viruses could be mitigated
by acquiring and implementing antivirus software. A good risk management plan should contain
a schedule for control implementation and responsible persons for those actions.

According to ISO/IEC 27001, the stage immediately after completion of the risk assessment
phase consists of preparing a Risk Treatment Plan, which should document the decisions about
how each of the identified risks should be handled. Mitigation of risks often means selection of
security controls, which should be documented in a Statement of Applicability, which identifies
which particular control objectives and controls from the standard have been selected, and why.

Implementation

Implementation follows all of the planned methods for mitigating the effect of the risks.
Purchase insurance policies for the risks that have been decided to be transferred to an insurer,
avoid all risks that can be avoided without sacrificing the entity's goals, reduce others, and retain
the rest.

Review and evaluation of the plan

Initial risk management plans will never be perfect. Practice, experience, and actual loss results
will necessitate changes in the plan and contribute information to allow possible different
decisions to be made in dealing with the risks being faced.

Risk analysis results and management plans should be updated periodically. There are two
primary reasons for this:

33
1. To evaluate whether the previously selected security controls are still applicable and
effective
2. To evaluate the possible risk level changes in the business environment. For example,
information risks are a good example of rapidly changing business environment.

Risk management activities as applied to project management

In project management, risk management includes the following activities:

 Planning how risk will be managed in the particular project. Plans should include risk
management tasks, responsibilities, activities and budget.
 Assigning a risk officer – a team member other than a project manager who is responsible
for foreseeing potential project problems. Typical characteristic of risk officer is a
healthy skepticism.
 Maintaining live project risk database. Each risk should have the following attributes:
opening date, title, short description, probability and importance. Optionally a risk may
have an assigned person responsible for its resolution and a date by which the risk must
be resolved.
 Creating anonymous risk reporting channel. Each team member should have the
possibility to report risks that he/she foresees in the project.
 Preparing mitigation plans for risks that are chosen to be mitigated. The purpose of the
mitigation plan is to describe how this particular risk will be handled – what, when, by
whom and how will it be done to avoid it or minimize consequences if it becomes a
liability.
 Summarizing planned and faced risks, effectiveness of mitigation activities, and effort
spent for the risk management.

Establish and review communications and educational programs

34
Risk management and business continuity

Risk management is simply a practice of systematically selecting cost effective approaches for
minimizing the effect of threat realization to the organization. All risks can never be fully
avoided or mitigated simply because of financial and practical limitations. Therefore all
organizations have to accept some level of residual risks.

Whereas risk management tends to be preemptive, business continuity planning (BCP) was
invented to deal with the consequences of realized residual risks. The necessity to have BCP in
place arises because even very unlikely events will occur if given enough time. Risk
management and BCP are often mistakenly seen as rivals or overlapping practices. In fact these
processes are so tightly tied together that such separation seems artificial. For example, the risk
management process creates important inputs for the BCP (assets, impact assessments, cost
estimates etc.). Risk management also proposes applicable controls for the observed risks.
Therefore, risk management covers several areas that are vital for the BCP process. However, the
BCP process goes beyond risk management's preemptive approach and assumes that the disaster
will happen at some point.

Risk communication

Risk communication is a complex cross-disciplinary academic field. Problems for risk


communicators involve how to reach the intended audience, to make the risk comprehensible and
relatable to other risks, how to pay appropriate respect to the audience's values related to the risk,
how to predict the audience's response to the communication, etc. A main goal of risk
communication is to improve collective and individual decision making. Risk communication is
somewhat related to crisis communication.

Seven cardinal rules for the practice of risk communication

 Accept and involve the public/other consumers as legitimate partners (e.g. stakeholders).
 Plan carefully and evaluate your efforts with a focus on your strengths, weaknesses,
opportunities, and threats (SWOT).
 Listen to the stakeholders specific concerns.

35
 Be honest, frank, and open.
 Coordinate and collaborate with other credible sources.
 Meet the needs of the media.
 Speak clearly and with compassion.

36

You might also like