Professional Documents
Culture Documents
0000bf-C-G0-G000-Pe-Pro-0001-B04 Flange Management Procedure - 2
0000bf-C-G0-G000-Pe-Pro-0001-B04 Flange Management Procedure - 2
1.1 Added, fourth paragraph with relevant bolting certification and training
2.1 Reformatted into table and updated definitions
2.2 Reformatted into table
3.1
Deleted, As a minimum, equipment shall be designed, manufactured, tested
and delivered in accordance with the latest Engineering International Codes
and Standards as referenced in the following document.
The current edition or revision of the Codes and Standards referenced within
this specification shall be used at the time of activity.
Document Number
0000BF-C-G0-G000-PE-PRO-0001 Rev B04 - Date 10th January 2019 Page 2 of 31
This document is the property of Rumaila Operating Organisation. It must not be stored, reproduced or disclosed to others without written authorisation from the Company