Doc No.

PHE-VKBS-CZ03-CH-05

Revision no : 00 Date:

MSB IT/ITES BUILDING, PALLIKARANAI, CHENNAI


CHECKLIST FOR INSTALLATION OF TRANSFER PUMPS
Location / Area : Date :
Drawing No :
Name Plate Details
Pump Make: Pump Model: Serial No.:
Motor Make: Motor Model: Serial No.:
SR Verified
Activities / Items to be inspected
NO. Yes/ No N/A Remarks

1 The pumps installed are as per the approved TDS

2 The shop drawings are approved

3 Name plate details checked and recorded

4 The foundation is checked for proper level

Check the space around the pump is accessible


5
maintenance, service and inspection
Neoprene Vibration isolation pads are provided between
6 the pump base and foudation as recommended by
manufacturer

7 Check the orientation of the pump is correct

The pump is properly bolted and levelled on the


8
foundation
The piping connection to suction and delivery sides with
9 valves and accessories are installed as per approved shop
drawing

10 The flange joint bolts are properly tightened to avoid leak

The power cable are terminted to the motor terminals and


11
properly tightened.

12 The motor body is earthed as per recommendations

Comments / Remarks :

VKBS K RAHEJA

Name

Signature

Date