EXECUTION OF JOBS
S.N Activities Duration Responsibility
1. Closing of header valves in Pump house and inside shop. 09:00 AM – 10:00 AM AGM(OPR-II) WMD &DGM(MECH) CCS
2. Opening of drain valves inside tunnel and draining the pipeline. 10:00 AM -12:00 PM DM(PLM-II)WMD
3. Repair of pipeline 12:00 PM -4:00 PM DM(PLM-II) WMD
4. Closing drain valves & opening valves for checking leakages. 4:00 PM -04:15 PM AGM(OPR-II) WMD & DGM(MECH) CCS
5. Normalizing system 04:15 PM-05:00 PM DM(PLM-II) WMD
Contd….
-2-
S.N. Hazard Risk Prevention Responsibility
2. Fire safety. Major/serious injury may be caused to the 1. Cutting set with double back fire arrestors to DGM (PLM-II)
worker. be used. WMD
2. Oxygen and DA cylinders to be kept at safe
distance from work area.
3. Electrocution Major/serious injury may be caused to the Double earthing for welding transformer to be DGM (PLM-II)
worker. provided. WMD
Note : During the shutdown period Equipment Cooling water supply from Pump house will be unavailable.
DGM (PLM-II) WMD DSO (WMD) AGM (OPR-II) WMD AGM (EM-II) WMD