PROTOCOL TO INSTALL NEW DELIVERY LINE # 2 OF MOULD COOLING
CIRCUIT IN PH # 39

AGREED APPROVED

DGM I/c (UTILITIES) GM (SMS-II)


Date: .11.2018 to .11.2018

Time Activities Responsibility


Closing of Overhead Tank valve on Line # 2. PLM-II (WMD)
09:00 AM – 10:30 AM Closing of valves on Line # 2 for each machine. Mech. (CCS)
Day : 1 Opr-II (WMD)
Closing of header valve # 12 on Line # 2 in PH # 39. Opr-II (WMD)
10:30 AM- 04:00 AM Cutting, Blanking Old Delivery line & Connecting New PLM-II (WMD)
Day : 1 & 2 Delivery line in PH # 39 (Welding & Cutting work)
PLM-II (WMD)
04:00 AM – 06:00 AM Closing of drain valve. Charging of line and normalizing
Opr-II (WMD)
Day : 2 the system.
Mech. (CCS)
Note :
 During the shutdown Mould cooling water will be available through Line # 1 only.
 Only three pumps will work when isolation is achieved through closing of HV # 12 and two pumps will
be on standby. In case isolation is achieved through closing of HV # 11 then only one pump will be on
standby, three pumps will continue to be in operation.
 OHT will be available during the shutdown period.
 All Safety precautions to be taken during cutting & welding jobs.
 Housekeeping to be maintained during & after the work.

AGM (OPR-II) AGM (EM-II) AGM (MM-II) AGM (PLM-II) AGM (M)
WMD WMD WMD WMD CCS

DGM (O) DGM &DSO DGM (PLM) DGM (M) DGM (O)
WMD WMD WMD CCS CCS

DGM I/c (WMD) DGM I/c (M) CCS DGM I/c (O) CCS
जल प्रबंधन विभाग
भिलाई इस्पात संयंत्र
PROTOCOL TO INSTALL FILTER & REPAIR OF OHT VALVE OF SECONDARY
COOLING LINE # 1

AGREED APPROVED

DGM I/c (UTILITIES) GM (SMS-II)

Date: 30.10.2018

Time Activities Responsibility


Closing of Overhead Tank valve on Line # 1. PLM-II (WMD)
Closing of valves on Line # 1 (Top line) for each machine. Mech. (CCS)
09:00 AM – 10:30 AM
Opr-II (WMD)
Closing of header valve on Line # 1 in PH # 39. Opr-II (WMD)
12:00 Hrs.- 08:00 PM Introducing filter in line near PH # 39, Draining line No. #1 PLM-II (WMD)
(Welding & Cutting work)
PLM-II (WMD)
Closing of drain valve. Charging of line and normalizing
08:00 PM – 10:00 PM Opr-II (WMD)
the system.
Mech. (CCS)

Note :
 During shut down secondary cooling water will be available through Line # 2 only.
 All Safety precautions to be taken during cutting & welding jobs.
 Housekeeping to be maintained during & after the work.

AGM (PLM-II) AGM (OPR-II) AGM (M)


WMD WMD CCS

DGM (O) DSO DGM (PLM) DGM (M) DGM (O)


WMD WMD WMD CCS CCS

DGM I/c (WMD) DGM I/c (CCS)