AGREED APPROVED
AGM (OPR-II) AGM (EM-II) AGM (MM-II) AGM (PLM-II) AGM (M)
WMD WMD WMD WMD CCS
DGM (O) DGM &DSO DGM (PLM) DGM (M) DGM (O)
WMD WMD WMD CCS CCS
DGM I/c (WMD) DGM I/c (M) CCS DGM I/c (O) CCS
जल प्रबंधन विभाग
भिलाई इस्पात संयंत्र
PROTOCOL TO INSTALL FILTER & REPAIR OF OHT VALVE OF SECONDARY
COOLING LINE # 1
AGREED APPROVED
Date: 30.10.2018
Note :
During shut down secondary cooling water will be available through Line # 2 only.
All Safety precautions to be taken during cutting & welding jobs.
Housekeeping to be maintained during & after the work.