Execution of Job
S.N Activities Duration Responsibility
1. Clearance from Raw Material 09:00 AM AGM (WMD)
Station/P-Way for starting AGM (P. Way)
excavation work.
2. Excavation near track. 9.15AM to 12:00 PM AGM (WMD)
3. Repair work of pipeline 12:00 PM – 04:00 PM DGM(Mech.)SMS-2
4. Back filling and soiling of area. 04:00 PM-05:00 PM DGM(Mech.)SMS-2
5. Clearance to P way for normal 05:30 PM DGM(Mech.)SMS-2
movement on the track. AGM (WMD)
SAFETY PRECAUTIONS
S.N. Safety precautions Responsibility
1. All safety precautions will be taken in welding, cutting, DGM (Mech.) SMS-2
& pipe handling.
2. Double earthing should be ensured for welding DGM (Mech.) SMS-2
machine, if required.
3. Display of RED banner at both ends of affected area . DGM (Mech.) SMS-2
4. Keen supervision of job will be done. DGM (Mech.) SMS-2
5. Every person working in the vicinity of track will stay DGM (Mech.) SMS-2
around 3.0 Mtrs. Away from moving train whenever
they will be alerted by the supervisor.
6. All the equipments involved for carrying out the job DGM (Mech.) SMS-2
will be moved away at safe distance from the moving
train.
Contd…
-2-
Execution of Job
S.N Activities Duration Responsibility
1. Clearance from Raw Material 09:00 AM AGM (WMD)
Station/P-Way for track AGM (P. Way)
shutdown.
2. Excavation under the track. 9.15AM to 01:00 PM DGM (Mech.)SMS-2
3. Laying and alignment of pipeline 01:00 PM – 03:00 PM DGM(Mech.)SMS-2
4. Back filling and soiling of area 03:00 PM-05:00 PM DGM(Mech.)SMS-2
under the track
5. Clearance to P way for removal 05:30 PM DGM(Mech.)SMS-2
of block on the track AGM (WMD)
SAFETY PRECAUTIONS
S.N. Safety precautions Responsibility
1. All safety precautions will be taken in welding, cutting, DGM (Mech.) SMS-2
& pipe handling.
2. Double earthing should be ensured for welding DGM (Mech.) SMS-2
machine, if required.
3. Display of RED banner at both ends affected area DGM (Mech.) SMS-2
across the track.
4. Keen supervision of job will be done. DGM (Mech.) SMS-2
5. Every person working in the vicinity of track will stay DGM (Mech.) SMS-2
around 3.0 Mtrs. Away from moving train whenever
they will be alerted by the supervisor.
6. All the equipments involved for carrying out the job DGM (Mech.) SMS-2
will be moved away at safe distance from the moving
train.
Contd…
-2-
Execution of Job
S.N Activities Duration Responsibility
1. Clearance of In-charge shipping 09:00 AM DGM (P.Mill)
area Plate Mill/P Way for track AGM (P. Way)
shutdown.
2. Excavation under the track. 9.15AM to 01:00 PM DGM (Mech.)SMS-2
3. Laying and alignment of pipeline 01:00 PM – 03:00 PM DGM(Mech.)SMS-2
4. Back filling and soiling of area 03:00 PM-05:00 PM DGM(Mech.)SMS-2
under the track
5. Clearance to P way for removal 05:30 PM DGM(Mech.)SMS-2
of block on the track AGM (WMD)
SAFETY PRECAUTIONS
S.N. Safety precautions Responsibility
1. All safety precautions will be taken in welding, cutting, DGM (Mech.) SMS-2
& pipe handling.
2. Double earthing should be ensured for welding DGM (Mech.) SMS-2
machine, if required.
3. Display of RED banner at both ends affected area DGM (Mech.) SMS-2
across the track.
4. Keen supervision of job will be done. DGM (Mech.) SMS-2
5. Every person working in the vicinity of track will stay DGM (Mech.) SMS-2
around 3.0 Mtrs. Away from moving train whenever
they will be alerted by the supervisor.
6. All the equipments involved for carrying out the job DGM (Mech.) SMS-2
will be moved away at safe distance from the moving
train.
Contd…
-2-
Execution of Job
S.N Activities Duration Responsibility
1. Clearance of In-charge shipping 09:00 AM DGM (P.Mill)
area Plate Mill/P Way for track AGM (P. Way)
shutdown.
2. Excavation under the track. 9.15AM to 01:00 PM DGM (Mech.)SMS-2
3. Laying and alignment of pipeline 01:00 PM – 03:00 PM DGM(Mech.)SMS-2
4. Back filling and soiling of area 03:00 PM-05:00 PM DGM(Mech.)SMS-2
under the track
5. Clearance to P way for removal 05:30 PM DGM(Mech.)SMS-2
of block on the track AGM (WMD)
SAFETY PRECAUTIONS
S.N. Safety precautions Responsibility
1. All safety precautions will be taken in welding, cutting, DGM (Mech.) SMS-2
& pipe handling.
2. Double earthing should be ensured for welding DGM (Mech.) SMS-2
machine, if required.
3. Display of RED banner at both ends affected area DGM (Mech.) SMS-2
across the track.
4. Keen supervision of job will be done. DGM (Mech.) SMS-2
5. Every person working in the vicinity of track will stay DGM (Mech.) SMS-2
around 3.0 Mtrs. Away from moving train whenever
they will be alerted by the supervisor.
6. All the equipments involved for carrying out the job DGM (Mech.) SMS-2
will be moved away at safe distance from the moving
train.