ELE-VKBS-CZ03-CH-4

Revision no : 00 Date:

MSB IT/ITES Building, Pallikaranai, Chennai

Installation of Electrical wire

Location / Area : Date :

Drawing No :

Verified
SR
Activities / Items to be inspected
NO. Yes/ No N/A Remarks

1 Wires size, type, location, installation and outing as per drawing & specification.

2 Proper Colour coding is observed for phase , neutral and earth

Check of the conduit & trunking layout is complete before proceeding with the
3
installation / pulling

4 Proper marking / ferruling at both ends is placed

5 Check continuity of wires and compared with the tags

6 Check two different phase shall not be drawn in single conduit.

7 check lead wire of sufficient extra length shall be provide for termination.

8 No bare joints and joints with connector only.

9 Number of wires inside the conduit should be as per Standard.

Comments / Remarks :

VKBS K RAHEJA

Name

Signature

Date: