Professional Documents
Culture Documents
Minimize Evaporation Losses by
Minimize Evaporation Losses by
Liquefied petroleum gas (LPG) is stored and transported product pressure reduction, and flashes at the different pressure
in tanks as a cryogenic liquid, at a temperature below its boil- levels are compressed in two parallel, three-stage centrifugal
ing point near atmospheric pressure. Due to heat entering the compressors, before being condensed in a C3 air cooler and a C3
cryogenic tank during storage and transportation, a portion of compressor condenser. Liquid propane is collected in a C3 ac-
the LPG continuously evaporates, creating a gas called boiloff cumulator and flashed again to the high-pressure suction drum
gas (BOG). BOG causes evaporation losses in the LPG supply to restart the cycle.
chain over time. Boiloff vapors from propane tanks are sent to the low-pres-
It is imperative to minimize vaporization and displacement sure suction drums and then to the first compressor stage. No
losses due to the economic and safety problems that can result vapors develop from butane tanks due to the subcooling of the
from such losses. The amount of BOG depends on the design stored liquid product.
and operating conditions of LPG plants. In the LPG supply Two tanks each are used for C3 and C4 storage. Since the boil-
chain, BOG can be reliquefied or sent to the flare and burned. off calculation method can be used for both types of storage tanks,
The evaluation of BOG in a storage tank in all operating scenar- calculations are described for only one of the C3 storage tanks.
ios is important for the correct selection and design of a BOG
compressor. Operating modes. To load propane and butane to the ship, it
Different sources exist for the generation of BOG. These is necessary to cool down the pipelines at the lowest possible
sources include heat leaks from ambient air around the storage temperature, with the aim of reducing BOG production during
tank, heat ingress due to the dissipation of pumping power in- the entrance to the ship compartments. Three steps are need-
side the tanks, heat leaks from pipelines, flash vapor generated ed: preloading, loading and holding. Pre-loading includes two
by liquid rundown and displaced vapor from the tank due to parts—the initial phase and the final phase—to achieve cool-
liquid filling (known as the piston effect). ing of the pipeline with low flowrates and appropriate pipeline
In this study, boundary conditions and parameters have temperature, respectively.
been implemented to accurately estimate the amount of BOG As a general rule, each tank follows three steps during nor-
that evaporates at the C3 and C4 refrigeration and loading facili- mal operation:
ties at the Bandar Abbas gas condensate refinery in Iran. • Filling mode: The tank receives the product from the
process unit at rundown flowrates. During the filling
Study outline. The produced propane and butane from pro- mode, it is necessary to prepare the tank for ship
pane/butane splitter units are cooled down in the propane/ loading; in project documentation, this operation
butane refrigeration unit via open-cycle refrigeration, and then is called preloading.
run down to the associated refrigerated tanks and stored at at- • Emptying mode: When the ship is ready to receive
mospheric pressure before being exported to overseas markets the products (i.e., when the pipeline is at proper
via propane/butane carrier ships. temperature, parcels are at proper temperature,
As shown in FIG. 1, butane rundown is subcooled at the re- loading arms are connected, etc.), then it is possible
quired temperature level in two exchangers in series, both utiliz- to transfer the product from tank to ship. This
ing propane. The chilled butane is then sent to the storage tanks. operation is called loading.1
Propane is divided into two streams. One stream flows to the • Holding mode: The tank is full of product and ready
first exchanger and is flashed, and the other stream is sent to the for ship loading, but the ship has not yet arrived or is
high-pressure C3 suction drums and then flashed in the second not ready for loading. This operation is called holding.
exchanger. Liquid propane from the suction drum is utilized in To load propane to the ship, it is necessary to cool down
the second exchanger, and relevant flashed vapor is sent to me- the two pipelines at the lowest possible temperature, with the
dium-pressure C3 suction drums and then to the low-pressure aim of reducing BOG production when products enter the
C3 suction drums. ship compartments. Therefore, some days before the carrier
Liquid propane flashes to lower pressure levels in medium- ship arrives, circulation from the storage tank to the jetty and
and low-pressure suction drums before being pumped to refrig- back to the tank is started. This process is applied when the
erated storage tanks. Propane vapors result from the rundown pipelines are in equilibrium with the external temperature.
Gas Processing | JANUARY/FEBRUARY 2016 17
SPECIAL REPORT: PIPELINES, TERMINALS AND STORAGE
The preloading mode is the most critical operating mode 4. Vapor displacement due to liquid inlet in the tank
from the point of view of BOG production, due to the great 5. Rapid variation of barometric pressure.
quantity of hot fluid trapped in the pipeline. For this reason, Total BOG flowrate can be calculated with Eq. 1:
it is necessary to avoid a too-rapid displacement of the fluid to
prevent abnormal overdesign of the BOG compressor. BOGTotal = BOGTank + BOGTransferLine + BOGLoadingSystem +
One of the major sources of boiloff production in lique- BOGElectricalMotor + BOGATM + BOGCirculationSystem + (1)
fied gas handling is rollover, which can result in a boiloff rate BOGVaporDisplacement + BOGCompensationEffect
several times greater than normal, causing rapid over pressur-
ization while venting a considerable quantity of vapors to at- Note: The contribution of BOG due to rapid atmospheric
mosphere. When the liquid layer adjacent to a liquid surface pressure variation is not considered, and is negligible when
becomes denser than the layers beneath due to boiloff of light- compared to the other contributions. Also, the compensation
er fractions from the tank, stratification develops and causes effect due to outflow of liquid from the tank is not considered.
rollover due to rapid mixing as a result of density inversion. BOG is calculated utilizing simulation software. The ther-
An effective solution is the mixing of the liquid in the tanks. mophysical properties of propane are collected in TABLE 1. Re-
For this purpose, two circulating pumps are placed inside the quired information for the calculation of BOG is presented in
tank: one is always circulating the liquid and the other is used TABLE 2. Calculations for the contribution to BOG by heat ab-
for cooling the transfer line. sorbed in tanks are shown in Eqs. 2 and 3.
C4 Loading pipeline
C4 From tank
C4 Return pipeline C4 From jetty
Quench makeup supply line
Quench makeup return line
T quench in
P quench in Q C3
BOG return
line C3 Return pipeline
C4 From jetty
C3 Air cooler/ Ambient
compressor Q transfer line C3 Loading pipeline
C4 Return C3 Transfer T Fluid in Q C3 loading line C3 From jetty
line line P Fluid in Ambient
C3 BOG T loading
compressor P loading
Transfer Quench Return T Circ. out
fluid in makeup pipeline P Circ. out
fluid in fluid in
HP LP
Vapor displacement
Q Tank due to pumping in
MP
compressor
T Tank
BOG
C3 From bl.
P = SG H 0.581 88.2
= = 5.03 bar (8)
10.2 10.2 TABLE 2. Required information for boiloff rate calculation
Major consumption Value
5.03 1
H Transfer pump = 100 = 1.28 (9) Propane
581 0.68
where: Density, kg/m 3
581.5
Q Normal = 21.3 m3/h Storage tank operation pressure, barg 0.06
Q Max = 67.5 m3/h Storage tank height, m 28.8
Head = 88.2 m
η = 0.68 (ηShaft 0.75 × ηMotor 0.9) Storage tank diameter, m 31
ΔP = SG × ΔH Inlet of ship operating pressure, barg 2.5
The ΔH transfer line is calculated by HYSYS. External heat from sun exposure, % 0.1
BOG pertaining to lines (circulation, loading and transfer
line) can be calculated manually using Eqs. 10–14.2 Ambient temperature, °C 42/47
Rundown pressure, barg 0.06
BOG of line = 3.6 QL 1.05
(10) Rundown temperature, °C –42
Latent heat
Latent heat, kj/kg 398
5
Pr = Cpair µair = 1005 1.9 10 = 0.71 (11) Vapor pressure, barg 13.31
Kf 0.027
Wind velocity, m/s 13.5
BOG = Loading WLoading (21) Takeaway. The calculations described represent a simple
approach for engineers to estimate produced BOG ratio in
∆H Loading pump + ∆H Loading line
= (22) cryogenic systems for LPG and LNG. The BOG ratio can be
Fluid calculated manually or with the use of a process simulator. GP
∆P 1
∆H Loading pump = 100 (23) ACKNOWLEDGMENT
liq. The author thanks the board of directors and the process division of Faradast
Energy Falat Co., the general contractor of Bandar Abbas Gas condensation refinery,
Kp Ap for its support.
∆H Loading line = 3.6 (24)
WLoading NOMENCLATURE
λ Latent heat
α Vapor fraction
SG H 0.581 365.5
P= = = 21 bar (25) η Pump shaft efficiency
10.2 10.2 W Mass flow
Kp Average heat flux through the pipe, W/m2
21 1 Ap Piping external surface area, including insulation, m2
H Transfer pump = 100 581 0.68 = 5.02 (26) H Enthalpy
Kt Vaporization coefficient, considered equal to 0.001 for C3/C4
where: Vt Geometrical volume of tank, m3
ρ Density
Q Loading = 1,250 m3/h Kf Thermal conductivity of ambient air, W/km
Head = 365.5 m Kins Thermal conductivity of insulation, W/km
η = 0.72 (ηShaft 0.8 × ηMotor 0.9)
LITERATURE CITED
Calculations for the contribution to BOG by electric motors
1
Chen, C. C., “Fine-tune refrigerated LPG loading line operation,” Hydrocarbon
Processing, August 2005.
are shown in Eqs. 27–28. 2
Wordu, A. A. and B. Peterside, “Estimation of boiloff gas from refrigerated vessels
Q Electrical motor in liquefied natural gas plant,” International Journal of Engineering and Technology,
BOG = λ Fluid (27) Vol. 3, No. 1, January 2013.
3
Adom, E., et al. “Modelling of boiloff gas in LNG tanks: A case study,” International
⎡ 1 ⎤ Journal of Engineering and Technology, Vol. 2, No. 4, 2010, pp. 292–296.
Q Electrical motor = 3,600 × Power × ⎢1− ⎥ (28)
⎣ η ⎦ S. SHIVA SHAMEKHI is a process engineer in the process
where: engineering department of Faradast Energy Falat Co. She is
Power of loading pump = 904.3 kw working on a mega-size project for a gas condensation refinery
in Tehran, Iran. She holds BSc and MSc degrees from Amirkabir
Power of circulation pump = 172.7 kw. University of Technology in Iran. Her areas of specialization
include basic design of refrigeration plants and detailed
The calculation for the contribution to BOG by vapor dis- design of gas and petrochemical plants. She can be reached
placement is shown in Eq. 29. at S.Shamekhi@fefalat.com or s.shamekhi@gmail.com.