Monthly HCMI May 2011 (Final)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 122

PT.

HCMI CIBITUNG FACTORY


EXPANSION PROJECT

MONTHLY REPORT

MAY 2011
No. 01

PT. KAJIMA INDONESIA


MONTHLY PROGRESS REPORT PT. KAJIMA INDONESIA
REPORT NO. : 01
MONTH : May-11
FROM : 01 / May / 2011 ~ 31/ May / 2011 Yukio YASUDA Shinji IRIE
President Director General Manager

PROJECT HCMI CIBITUNG FACTORY EXTENSION PROJECT SCOPE OF CONSTRUCTION


WORK

OWNER PT. HITACHI CONSTRUCTION MACHINERY INDONESIA CONTRACT LUMP SUM


BASIS

CONTRACT SUM Rp. 154,000,000,000 ( Indonesia Rupiahs One hundred Fifty Four Billion Only) CONST. From : 02 May 2011
PERIOD Up to : and of March 2011 (Tentative)

BUILDER'S WORK
1. Structure Work. Total Site Area: 191,000.00 m²
- Foundation Work with Spun Pile, Press Pile & Bored Pile
- Upper structure with concrete reinforcement Main Building Area: 73,131.50 m²
- Steel structure work to roof
2. Finishing Work . Total Floor Area :
- Exterior Finishes : Color Metal Cladding, Weather shield paint finish to brick wall finish
Manual steel hanger door, Steel door with vision glass + louver - Ultra Large Comp Fact 8,863.00 m²
Curtain wall, Aluminium window Work & Groove sealant, etc. - Ultra Large Top Coat Fact 1,152.00 m²
- Excavator Paint Fact 8,767.00 m²
CONSTRUCTION - Internal finishes : Steel trowel finish, Dust Proof paint, Ceramic tile - Roof -1 2,556.00 m²
GUIDANCE Drywall partition with gypsum, Ceramic tile - Roof -2 3,915.00 m²
Gypsum tile, Gypsum board - Touch Up Paint Fact 254.00 m²
Roofing Boltless zincalume, Flashing zincalume - Training Centre
Emulsion paint to external wall, 3 Floor 6,430.00 m²
Emultion paint to wall and ceiling gypsum - Motor Cycle Park 1,288.00 m²
- Guard House 58.0 m²
EXTERNAL WORK ( CANOPY WORK )
- External Road : Concrete reinforcement, Total Area : 33,283.00 m²
- Drainage Work : RC Open ditch, concrete cover & River stone drainage
- Stock Yard : Concrete reinforcement,
- Fence and Gate : BRC Fence, Manual Steel pipe sliding door No. of Stories 3 Stories
Floor Height : 4.5~4.2 m
M & E WORKS Max. Height of Bldg : 21.24 m
- Mechanical Work : Plumbing & Firefighting, Utility System, HVAC System, Ventilation fan,
Water Supply piping Drainage piping Sanitary fixture, Fire Extinguisher
- Electrical Work : Sub Station, Main Feeder, Lighting & Receptacle, Sound system,
Telephone Land System, Public address, CCTV & Fire alarm system

Last Month : 0.00% TOTAL NO. OF WORKFORCE TOTAL WORKING DAY


PROGRESS This Month : 6.28% Cumulative : 6.28% 8,767 31
1) AHEAD ( 0.89 ) WK MTH
Schedule : On Schedule ( √ )
2) DELAY ( 0 ) ( IV ) ( I )
Commencement -02 May 2011
Comment
Breaking Ceremony 04 may 2011, Contract sign 03 may 2011
JAPANESE LOCAL
NO. OF SITE STAFF
1 15
RISK CONTROL PROBLEM NOTES
CONTRACT AND SCOPE OF WORK (MARK X IF APPLY) DESCRIBE ANY PROBLEM
1) REQUESTED EXTRA SCOPE OF WORK NOT IN CONTRACT
2) PENDING V.O. PROPOSAL BY CLIENT
3) REJECTED V.O. PROPOSAL BY CLIENT
4) SERIOUS PROBLEM IN CONTRACT CONDITION
DESIGN DOCUMENTS
1) DESIGN COORDINATION
2) DRAWING ISSUE
3) SHOP DRAWING AND SUBMITAL APPROVAL
4) DISCREPANCY BTW, OWNER REQUIREMENT AND DRWG
SUBCONTRACTOR AND SUPPLIER
1) SUB/SUPPLIER FINANCIAL STATUS
2) SUBCONTRACT AMOUNT AND BUDGET
3) EXTRA COST CLAIM BY SUBCONTRACTORS/SUPPLIERS
4) CAPABILITY
PAYMENT
1) OWNER PAYMENT
2) SUB/SUPPLIER OVER PAYMENT
OVERALL CONSTRUCTION SCHEDULE
1) DESIGN RELATED
2) APPROVAL BY OWNER AND/OR DESIGN
3) MATERIAL DELIVERY
4) SITE MANPOWER
OTHERS
1) QUALITY CONTROL
2) SAFETY CONTROL (ACCIDENT)
3) COST CONTROL
4) LD OR RETAINAGE
5) MANPOWER
6) PURCHASING
7) OWNER RELATION
8) DESIGN RELATION
9) OTHER PROBLEM/POTENCIAL PROBLEM
WORK PROGRESS CHART

100.000

100 96.402
98.644
93.170
83.423
80
Percentage (%)

60 61.827

40 38.500

26.002
20 18.770

6.28 11.477
5.390
0.00
0
0.000
May-11
Apr-11

Aug-11

Sep-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12
Jun-11

Jul-11

Oct-11

Month
PLANNED ACTUAL

WORK PROGRESS FOR THIS MONTH:


BUILDING WORK M & E WORK EXTERNAL WORK
TRAINING CENTER & HEAD OFFICE TEMPORARY ME WORK
- EARTH WORK Mechanical Works : DEMOLITION WORK:
- PILING WORK - Chipping & Repair Road - CANTEEN
ULTRA LARGE COMPONENT FACT-2 - Under Construction ( Piping Works, Drain Water - - PARKING & TREE

- PAINT BOOTH & OTHER AREA AT WEST


- EARTH WORK Fire Fighting Works, Water Suply ), Location : SIDE OF FACT.
- PILING WORK - TRAINING CENTER BUILDING & HEAD OFFICE W - STOCK YARD AREA

ULTRA LARGE TOPCOAT PAINTING BOOTH - EXCAVATOR PAINT FACTORY WORKS


- EARTH WORK - OFFICE, CANTEEN & PARKING AREA EXISTING RC PAVEMENT & DRAINAGE :
Electrical Works : - PAVING WORK

- MAIN FEEDER SYSTEM FOR BUILDING FACILITY - DRAINAGE WORK


:
TRAINING CENTER & OFFICE :
- TELEPHONE SYSTEM : - SOIL INVESTIGATION WORK
- LAN SYSTEM
- PUBLIC ADDRESS SYSTEM
- EXTERNAL LIGHTING SYSTEM
- LIGHTNING PROTECTION
WORK PROGRESS FOR NEXT MONTH :

BUILDING WORK M & E WORK EXTERNAL WORK


TRAINING CENTER & HEAD OFFICE : TEMPORARY ME WORK : DEMOLITION WORK :
- EARTH WORK - CIVIL WORKS - EXCAVATOR PAINT FACTORY
- PILING WORK - MECHANICAL WORKS
ULTRA LARGE COMPONENT FACT-2 : - ELECTRICAL WORKS
- EARTH WORK
- PILING WORK
- CONCRETE WORK
- REINFORCED WORK :
- FORM WORK
EXCAVATOR PAINT FACTORY
- EARTH WORK
- PILING WORK
- CONCRETE WORK
- REINFORCED WORK
- FORM WORK
WEEKLY PROGRESS QUANTITY REPORT

PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT


LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

A. TEMPORARY WORK LOT 1.00 4.76218 4.76218 0.0909 0.0909 1.0000 0.4329 0.0000 0.4329

B. TEMPORARY ME WORK LOT 1.00 0.99306 0.99306 1.0000 0.0561 0.5192 0.5754
B.1 CIVIL WORKS LOT 1.00 0.11371 0.0183 0.0000 0.0183
B.1.1 CABLE CONECTION WORK LOT 1.00 0.09158 0.0183 0.0000 0.0183
A Chipping & Repair Road for :
- HV. Cable Route lot 1.00 0.00749 0.2000 0.2000 0.0818 0.0015 0.0000 0.0015
- Feeder Cable Route lot 1.00 0.01582 0.2000 0.2000 0.1727 0.0032 0.0000 0.0032
- Fire Alarm Cable Route lot 1.00 0.03413 0.2000 0.2000 0.3727 0.0068 0.0000 0.0068
- Telephone System Cable Route lot 1.00 0.01415 0.2000 0.2000 0.1545 0.0028 0.0000 0.0028
- Sound System Cable Route lot 1.00 0.01415 0.2000 0.2000 0.1545 0.0028 0.0000 0.0028
- Cable Fiber Optic & Data lot 1.00 0.00583 0.2000 0.2000 0.0636 0.0012 0.0000 0.0012

B.1.2 RENOVATION EXISTING GENSET ROOM LOT 1.00 0.02213 0.0000 0.0000 0.0000
A Additional Louver for Ventilation
- Demolish existing wall lot 1.00 0.00045 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
- Disposed & clean rubbish out project site lot 1.00 0.00035 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
- Steel Louver, size : 4.250mm (W) x 1.600mm (H) nos 2.00 0.01318 0.0000 0.0000 0.0000 0.5956 0.0000 0.0000 0.0000
- Oil Paint Fin. to Steel Louver lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0240 0.0000 0.0000 0.0000
- Repair & Touchup existing wall lot 1.00 0.00177 0.0000 0.0000 0.0000 0.0801 0.0000 0.0000 0.0000

B Extension Pit
- Demolish existing slab lot 1.00 0.00035 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
- Disposed & clean rubbish out project site lot 1.00 0.00025 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
- Additional Pit lot 1.00 0.00170 0.0000 0.0000 0.0000 0.0768 0.0000 0.0000 0.0000
- Repair & Touchup existing floor lot 1.00 0.00354 0.0000 0.0000 0.0000 0.1601 0.0000 0.0000 0.0000

B.2 MECHANICAL WORKS LOT 1.00 0.26374 0.0378 0.0457 0.0835

B.2.1 UNDER CONSTRUCTION WORKS


B.2.1.1 TRAINING CENTER BUILDING & HEAD OFFICE WORKS

B.2.1.1.1 WATER SUPPLY WORKS


B.2.1.1.1.1 EQUIPMENT 0.00576 0.0012 0.0000 0.0012
Roof Water Tank Existing Unit 1.00 0.00000 0.2000 0.2000 0.0000 0.0000 0.0000 0.0000

Concrete Foundation for Equipment Lot 1.00 0.00104 0.2000 0.2000 0.1801 0.0002 0.0000 0.0002
Support for Equipment Lot 1.00 0.00041 0.2000 0.2000 0.0715 0.0001 0.0000 0.0001
Painting for Above Lot 1.00 0.00002 0.2000 0.2000 0.0036 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00007 0.2000 0.2000 0.0128 0.0000 0.0000 0.0000
Relocation Cost Lot 1.00 0.00422 0.2000 0.2000 0.7320 0.0008 0.0000 0.0008

B.2.1.1.1.2 PIPING WORKS 0.01340 0.0067 0.0000 0.0067


Water Supply Pipe
Galvanized Steel Pipe Medium Class
GSP-M 32 mm diameter m 98.00 0.00370 49.0000 49.0000 0.2765 0.0019 0.0000 0.0019
GSP-M 25 mm diameter m 24.00 0.00071 12.0000 12.0000 0.0533 0.0004 0.0000 0.0004

Fitting for above Lot 1.00 0.00133 0.5000 0.5000 0.0990 0.0007 0.0000 0.0007
Support For Above Lot 1.00 0.00199 0.5000 0.5000 0.1485 0.0010 0.0000 0.0010
Painting for Above Lot 1.00 0.00039 0.5000 0.5000 0.0289 0.0002 0.0000 0.0002

Gate Valve 10 Kg/Cm2


GV 32 mm diameter Nos 1.00 0.00022 0.5000 0.5000 0.0163 0.0001 0.0000 0.0001

Existing Connection Fee Lot 1.00 0.00123 0.5000 0.5000 0.0922 0.0006 0.0000 0.0006

Miscellaneous Material Lot 1.00 0.00048 0.5000 0.5000 0.0357 0.0002 0.0000 0.0002
Installation Cost Lot 1.00 0.00291 0.5000 0.5000 0.2170 0.0015 0.0000 0.0015
Testing & Commisioning Lot 1.00 0.00029 0.5000 0.5000 0.0217 0.0001 0.0000 0.0001
Insite Transportation Lot 1.00 0.00015 0.5000 0.5000 0.0109 0.0001 0.0000 0.0001

B.2.1.1.2 DRAIN WATER WORKS 0.01110 0.0055 0.0000 0.0055


Drainage Water Pipe
PVC Pipe, 10 Kg/cm² (Class VP) 0.0000
PVC (VP) 100 mm diameter m 30.00 0.00154 15.0000 15.0000 0.1384 0.0008 0.0000 0.0008

Fitting for above Lot 1.00 0.00046 0.5000 0.5000 0.0415 0.0002 0.0000 0.0002
Support For Above Lot 1.00 0.00069 0.5000 0.5000 0.0623 0.0003 0.0000 0.0003
Painting for Above Lot 1.00 0.00003 0.5000 0.5000 0.0031 0.0000 0.0000 0.0000
0.0000
Manhole c/w Cover Lot 1.00 0.00397 0.5000 0.5000 0.3577 0.0020 0.0000 0.0020
900 x 900 mm (Ø 600 mm) 0.0000
0.0000
Excavation & Backfilling Lot 1.00 0.00080 0.5000 0.5000 0.0723 0.0004 0.0000 0.0004
0.0000
Existing Connection Fee Lot 1.00 0.00123 0.5000 0.5000 0.1113 0.0006 0.0000 0.0006
0.0000
Miscellaneous Material Lot 1.00 0.00044 0.5000 0.5000 0.0393 0.0002 0.0000 0.0002
Installation Cost Lot 1.00 0.00168 0.5000 0.5000 0.1513 0.0008 0.0000 0.0008
Testing & Commisioning Lot 1.00 0.00017 0.5000 0.5000 0.0151 0.0001 0.0000 0.0001
Insite Transportation Lot 1.00 0.00008 0.5000 0.5000 0.0076 0.0000 0.0000 0.0000

B.2.1.1.3 FIRE FIGHTING WORKS 0.03758 0.0188 0.0000 0.0188


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 100 mm diameter m 168.00 0.00000 84.0000 84.0000 0.0000 0.0000 0.0000 0.0000
0.0000
Fitting for above Lot 1.00 0.00220 0.5000 0.5000 0.0585 0.0011 0.0000 0.0011
Support For Above Lot 1.00 0.01484 0.5000 0.5000 0.3948 0.0074 0.0000 0.0074
0.0000
Miscellaneous Material Lot 1.00 0.00085 0.5000 0.5000 0.0227 0.0004 0.0000 0.0004
Demolished Cost Lot 1.00 0.00443 0.5000 0.5000 0.1178 0.0022 0.0000 0.0022
Installation Cost Lot 1.00 0.01328 0.5000 0.5000 0.3533 0.0066 0.0000 0.0066
Testing & Commisioning Lot 1.00 0.00133 0.5000 0.5000 0.0353 0.0007 0.0000 0.0007
Insite Transportation Lot 1.00 0.00066 0.5000 0.5000 0.0177 0.0003 0.0000 0.0003

B.2.1.2 EXCAVATOR PAINT FACTORY WORKS

B.2.1.2.1 WATER SUPPLY WORKS


B.2.1.2.1.1 EQUIPMENT 0.00225 0.0011 0.0000 0.0011
Roof Water Tank Existing Unit 1.00 0.00000 0.5000 0.5000 0.0000 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 4
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
Concrete Foundation for Equipment Lot 1.00 0.00035 0.5000 0.5000 0.1535 0.0002 0.0000 0.0002
Support for Equipment Lot 1.00 0.00041 0.5000 0.5000 0.1827 0.0002 0.0000 0.0002
Painting for Above Lot 1.00 0.00002 0.5000 0.5000 0.0091 0.0000 0.0000 0.0000
0.0000
Miscellaneous Material Lot 1.00 0.00004 0.5000 0.5000 0.0173 0.0000 0.0000 0.0000
Relocation Cost Lot 1.00 0.00053 0.5000 0.5000 0.2339 0.0003 0.0000 0.0003
Installation Cost Lot 1.00 0.00079 0.5000 0.5000 0.3508 0.0004 0.0000 0.0004
Testing & Commisioning Lot 1.00 0.00008 0.5000 0.5000 0.0351 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00004 0.5000 0.5000 0.0176 0.0000 0.0000 0.0000
0.0000

B.2.1.2.1.2 PIPING WORKS 0.00757 0.0038 0.0000 0.0038


Water Supply Pipe
Galvanized Steel Pipe Medium Class
GSP-M 20 mm diameter m 112.00 0.00215 56.0000 56.0000 0.2836 0.0011 0.0000 0.0011
0.0000
Fitting for above Lot 1.00 0.00064 0.5000 0.5000 0.0851 0.0003 0.0000 0.0003
Support For Above Lot 1.00 0.00097 0.5000 0.5000 0.1277 0.0005 0.0000 0.0005
Painting for Above Lot 1.00 0.00019 0.5000 0.5000 0.0248 0.0001 0.0000 0.0001
0.0000
Gate Valve 10 Kg/Cm2 0.0000
GV 20 mm diameter Nos 2.00 0.00019 1.0000 1.0000 0.0256 0.0001 0.0000 0.0001
0.0000
Existing Connection Fee Lot 1.00 0.00123 0.5000 0.5000 0.1632 0.0006 0.0000 0.0006
0.0000
Miscellaneous Material Lot 1.00 0.00027 0.5000 0.5000 0.0355 0.0001 0.0000 0.0001
Installation Cost Lot 1.00 0.00167 0.5000 0.5000 0.2213 0.0008 0.0000 0.0008
Testing & Commisioning Lot 1.00 0.00017 0.5000 0.5000 0.0221 0.0001 0.0000 0.0001
Insite Transportation Lot 1.00 0.00008 0.5000 0.5000 0.0111 0.0000 0.0000 0.0000

B.2.1.2.2 DRAIN WATER WORKS 0.09830 0.0007 0.0013 0.0021


Existing Septic Tankat Existing Warehouse Unit 1.00 0.00000 0.2500 0.2500 0.0000 0.0000 0.0000 0.0000

Septic Tank ( Penetration ) Unit 1.00 0.05915 0.0000 0.0000 0.0000 0.6017 0.0000 0.0000 0.0000
Cap. 10 M³/day For Existing Warehouse
Concrete Made

Absortion Well 5 M³ Unit 1.00 0.00947 0.0000 0.0000 0.0000 0.0964 0.0000 0.0000 0.0000

Drainage Water Pipe


PVC Pipe, 10 Kg/cm² (Class VP)
PVC (VP) 100 mm diameter m 60.00 0.00307 6.0000 6.0000 0.0313 0.0003 0.0000 0.0003

Fitting for above Lot 1.00 0.00092 0.1000 0.1000 0.0094 0.0001 0.0000 0.0001
Support For Above Lot 1.00 0.00138 0.1000 0.1000 0.0141 0.0001 0.0000 0.0001
Painting for Above Lot 1.00 0.00007 0.1000 0.1000 0.0007 0.0000 0.0000 0.0000

Manhole c/w Cover Nos 2.00 0.00794 0.0000 0.0000 0.0000 0.0808 0.0000 0.0000 0.0000
900 x 900 mm (Ø 600 mm)

Excavation & Backfilling Lot 1.00 0.00161 0.1000 0.1000 0.0163 0.0002 0.0000 0.0002

Existing Connection Fee Lot 1.00 0.00123 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00081 0.0000 0.1000 0.1000 0.0083 0.0000 0.0001 0.0001
Installation Cost Lot 1.00 0.01008 0.0000 0.1000 0.1000 0.1025 0.0000 0.0010 0.0010
Demolished Cost Lot 1.00 0.00105 0.0000 0.1000 0.1000 0.0107 0.0000 0.0001 0.0001
Testing & Commisioning Lot 1.00 0.00101 0.0000 0.1000 0.1000 0.0103 0.0000 0.0001 0.0001
Insite Transportation Lot 1.00 0.00050 0.0000 0.1000 0.1000 0.0051 0.0000 0.0001 0.0001

B.2.1.2.3 FIRE FIGHTING WORKS 0.02720 0.0000 0.0272 0.0272


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 150 mm diameter m 112.00 0.00000 0.0000 112.0000 112.0000 0.0000 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00220 0.0000 1.0000 1.0000 0.0808 0.0000 0.0022 0.0022
Support For Above Lot 1.00 0.00495 0.0000 1.0000 1.0000 0.1819 0.0000 0.0049 0.0049

Miscellaneous Material Lot 1.00 0.00036 0.0000 1.0000 1.0000 0.0131 0.0000 0.0004 0.0004

Demolished Cost Lot 1.00 0.00443 0.0000 1.0000 1.0000 0.1627 0.0000 0.0044 0.0044
Installation Cost Lot 1.00 0.01328 0.0000 1.0000 1.0000 0.4882 0.0000 0.0133 0.0133
Testing & Commisioning Lot 1.00 0.00133 0.0000 1.0000 1.0000 0.0488 0.0000 0.0013 0.0013
Insite Transportation Lot 1.00 0.00066 0.0000 1.0000 1.0000 0.0244 0.0000 0.0007 0.0007

B.2.1.2.4 HVAC WORKS 0.00451 0.0000 0.0000 0.0000


Outdoor AC at Warehouse Unit 2.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Concrete Foundation for Equipment Lot 1.00 0.00069 0.0000 0.0000 0.0000 0.1535 0.0000 0.0000 0.0000
Support for Equipment Lot 1.00 0.00082 0.0000 0.0000 0.0000 0.1827 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00004 0.0000 0.0000 0.0000 0.0091 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000

Relocation Cost Lot 1.00 0.00105 0.0000 0.0000 0.0000 0.2339 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00158 0.0000 0.0000 0.0000 0.3508 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00016 0.0000 0.0000 0.0000 0.0351 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0175 0.0000 0.0000 0.0000

B.2.1.4 TOUCHUP PAINT BOOTH WORKS

B.2.1.5 ULTRA LARGE FACTORY 2 & TOPCOAT PAINTING BOOTH


WORKS

B.2.1.5.1 WATER SUPPLY WORKS

B.2.1.5.2 DRAIN WATER WORKS

B.2.1.5.3 FIRE FIGHTING WORKS 0.02183 0.0000 0.0000 0.0000


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 150 mm diameter m 90.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00176 0.0000 0.0000 0.0000 0.0806 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00396 0.0000 0.0000 0.0000 0.1813 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00029 0.0000 0.0000 0.0000 0.0131 0.0000 0.0000 0.0000

Demolished Cost Lot 1.00 0.00356 0.0000 0.0000 0.0000 0.1629 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.01067 0.0000 0.0000 0.0000 0.4888 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 5
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
Testing & Commisioning Lot 1.00 0.00107 0.0000 0.0000 0.0000 0.0489 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000

B.2.1.6 OFFICE, CANTEEN & PARKING AREA EXISTING 0.03425 0.0000 0.0171 0.0171

Demolish AC, Ventilation, Sanitary Fixture & : Exhaust Fan Lot 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Accessories at Office Canteen

Demolish Work Lot 1.00 0.03425 0.0000 0.5000 0.5000 1.0000 0.0000 0.0171 0.0171

B.3 ELECTRICAL WORKS LOT 1.00 0.61562 0.0000 0.4736 0.4736

B.3.1 UNDER CONSTRUCTION WORK


B.3.1.1 MV INCOMING 0.01983 0.0000 0.0000 0.0000
MV Cable From Existing MVMDB to Factory Phase 3
MV Cable N2XSEBY 3C - 95 mm2 M 530.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

PVC Conduit 150 mm diameter M 126.00 0.00838 0.0000 0.0000 0.0000 0.4223 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00251 0.0000 0.0000 0.0000 0.1267 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00377 0.0000 0.0000 0.0000 0.1901 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 150 mm diameter M 126.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete Roof 2 M 60.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00076 0.0000 0.0000 0.0000 0.0381 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.00282 0.0000 0.0000 0.0000 0.1421 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00152 0.0000 0.0000 0.0000 0.0765 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000

B.3.1.2 MAIN FEEDER SYSTEM FOR BUILDING FACILITY 0.26550 0.0000 0.2655 0.2655
TRAINING CENTER & OFFICE
Cable NYY 4C - 95 mm2 M 390.00 0.12814 0.0000 390.0000 390.0000 0.4827 0.0000 0.1281 0.1281
NYA 50 mm2 M 390.00 0.01626 0.0000 390.0000 390.0000 0.0613 0.0000 0.0163 0.0163

Termination Cable Lot 1.00 0.00443 0.0000 1.0000 1.0000 0.0167 0.0000 0.0044 0.0044

PVC Conduit 150 mm diameter M 478.00 0.03177 0.0000 478.0000 478.0000 0.1197 0.0000 0.0318 0.0318

Accessories for above Lot 1.00 0.00954 0.0000 1.0000 1.0000 0.0359 0.0000 0.0095 0.0095
Supporting Material Lot 1.00 0.01430 0.0000 1.0000 1.0000 0.0539 0.0000 0.0143 0.0143

Concrete For Sleeve PVC Conduit 150mm diameter M 126.00 0.00000 0.0000 126.0000 126.0000 0.0000 0.0000 0.0000 0.0000

Temporary Stanchion For Cable Set 1.00 0.03846 0.0000 1.0000 1.0000 0.1449 0.0000 0.0385 0.0385

Miscellaneous Material Lot 1.00 0.01215 0.0000 1.0000 1.0000 0.0458 0.0000 0.0121 0.0121
Labour Fee Lot 1.00 0.00924 0.0000 1.0000 1.0000 0.0348 0.0000 0.0092 0.0092
Testing & Commissioning Fee Lot 1.00 0.00092 0.0000 1.0000 1.0000 0.0035 0.0000 0.0009 0.0009
Insite Transportation Lot 1.00 0.00028 0.0000 1.0000 1.0000 0.0010 0.0000 0.0003 0.0003

B.3.1.3 TELEPHONE SYSTEM 0.04586 0.0000 0.0459 0.0459

TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 1.0000 1.0000 0.0144 0.0000 0.0007 0.0007

Supporting Material Lot 1.00 0.00002 0.0000 1.0000 1.0000 0.0004 0.0000 0.0000 0.0000

Cable From TB Existing Office To TB PH - 1


Cable ITC 20 Pr - 0.6 mm2 M 330.00 0.00746 0.0000 330.0000 330.0000 0.1627 0.0000 0.0075 0.0075
ITC 40 Pr - 0.6 mm2 M 288.00 0.01166 0.0000 288.0000 288.0000 0.2542 0.0000 0.0117 0.0117

Termination Cable Lot 1.00 0.00059 0.0000 1.0000 1.0000 0.0128 0.0000 0.0006 0.0006

PVC Conduit HI 25 mm diameter M 618.00 0.00275 0.0000 618.0000 618.0000 0.0600 0.0000 0.0028 0.0028

Accessories for above Lot 1.00 0.00082 0.0000 1.0000 1.0000 0.0179 0.0000 0.0008 0.0008
Supporting Material Lot 1.00 0.00123 0.0000 1.0000 1.0000 0.0269 0.0000 0.0012 0.0012

PVC Conduit 65 mm diameter M 178.00 0.00233 0.0000 178.0000 178.0000 0.0508 0.0000 0.0023 0.0023

Accessories for above Lot 1.00 0.00070 0.0000 1.0000 1.0000 0.0153 0.0000 0.0007 0.0007
Supporting Material Lot 1.00 0.00105 0.0000 1.0000 1.0000 0.0229 0.0000 0.0011 0.0011

Concrete For Sleeve PVC Conduit 150mm diameter M 148.00 0.00000 0.0000 148.0000 148.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00146 0.0000 1.0000 1.0000 0.0319 0.0000 0.0015 0.0015

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 1.0000 1.0000 0.0898 0.0000 0.0041 0.0041
Labour Fee Lot 1.00 0.00974 0.0000 1.0000 1.0000 0.2125 0.0000 0.0097 0.0097
Testing & Commissioning Fee Lot 1.00 0.00097 0.0000 1.0000 1.0000 0.0212 0.0000 0.0010 0.0010
Insite Transportation Lot 1.00 0.00029 0.0000 1.0000 1.0000 0.0064 0.0000 0.0003 0.0003

B.3.1.4 LAN SYSTEM 0.11338 0.0000 0.1134 0.1134

SPLICING BOX Set 1.00 0.00187 0.0000 1.0000 1.0000 0.0165 0.0000 0.0019 0.0019

Cable Fiber Optic 2Pr Single Mode Outdoor type M 677.00 0.03308 0.0000 677.0000 677.0000 0.2917 0.0000 0.0331 0.0331
Fiber Optic 4Pr Single Mode Outdoor type M 349.00 0.03408 0.0000 349.0000 349.0000 0.3006 0.0000 0.0341 0.0341

Termination Cable Lot 1.00 0.00206 0.0000 1.0000 1.0000 0.0182 0.0000 0.0021 0.0021

PVC Conduit HI 25 mm diameter M 1,026.00 0.00457 0.0000 1,026.0000 1,026.0000 0.0403 0.0000 0.0046 0.0046

Accessories for above Lot 1.00 0.00136 0.0000 1.0000 1.0000 0.0120 0.0000 0.0014 0.0014
Supporting Material Lot 1.00 0.00204 0.0000 1.0000 1.0000 0.0180 0.0000 0.0020 0.0020

PVC Conduit 65 mm diameter M 134.00 0.00175 0.0000 134.0000 134.0000 0.0155 0.0000 0.0018 0.0018

Accessories for above Lot 1.00 0.00053 0.0000 1.0000 1.0000 0.0046 0.0000 0.0005 0.0005
Supporting Material Lot 1.00 0.00079 0.0000 1.0000 1.0000 0.0070 0.0000 0.0008 0.0008

Concrete For Sleve PVC Conduit 75 mm diameter M 134.00 0.00000 0.0000 134.0000 134.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete For Cable M 12.00 0.00000 0.0000 12.0000 12.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00401 0.0000 1.0000 1.0000 0.0354 0.0000 0.0040 0.0040

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 1.0000 1.0000 0.0363 0.0000 0.0041 0.0041
Labour Fee Lot 1.00 0.02045 0.0000 1.0000 1.0000 0.1804 0.0000 0.0204 0.0204
Testing & Commissioning Fee Lot 1.00 0.00204 0.0000 1.0000 1.0000 0.0180 0.0000 0.0020 0.0020
Insite Transportation Lot 1.00 0.00061 0.0000 1.0000 1.0000 0.0054 0.0000 0.0006 0.0006
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 6
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

B.3.1.5 PUBLIC ADDRESS SYSTEM 0.01796 0.0000 0.0180 0.0180


TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 1.0000 1.0000 0.0367 0.0000 0.0007 0.0007

Supporting Material Lot 1.00 0.00002 0.0000 1.0000 1.0000 0.0011 0.0000 0.0000 0.0000

Cable From TB-OUTDOOR To TB Existing Office


Cable NYMHY 2C - 1.5mm2 M 287.00 0.00139 0.0000 287.0000 287.0000 0.0776 0.0000 0.0014 0.0014

Termination Cable Lot 1.00 0.00004 0.0000 1.0000 1.0000 0.0024 0.0000 0.0000 0.0000

PVC Conduit HI 25 mm diameter M 287.00 0.00128 0.0000 287.0000 287.0000 0.0712 0.0000 0.0013 0.0013

Accessories for above Lot 1.00 0.00038 0.0000 1.0000 1.0000 0.0212 0.0000 0.0004 0.0004
Supporting Material Lot 1.00 0.00057 0.0000 1.0000 1.0000 0.0318 0.0000 0.0006 0.0006

PVC Conduit 65 mm diameter M 178.00 0.00233 0.0000 178.0000 178.0000 0.1297 0.0000 0.0023 0.0023

Accessories for above Lot 1.00 0.00070 0.0000 1.0000 1.0000 0.0390 0.0000 0.0007 0.0007
Supporting Material Lot 1.00 0.00105 0.0000 1.0000 1.0000 0.0585 0.0000 0.0011 0.0011

Concrete For Sleve PVC Conduit 65 mm diameter M 148.00 0.00000 0.0000 148.0000 148.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00042 0.0000 1.0000 1.0000 0.0234 0.0000 0.0004 0.0004

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 1.0000 1.0000 0.2291 0.0000 0.0041 0.0041
Labour Fee Lot 1.00 0.00442 0.0000 1.0000 1.0000 0.2462 0.0000 0.0044 0.0044
Testing & Commissioning Fee Lot 1.00 0.00044 0.0000 1.0000 1.0000 0.0246 0.0000 0.0004 0.0004
Insite Transportation Lot 1.00 0.00013 0.0000 1.0000 1.0000 0.0074 0.0000 0.0001 0.0001

B.3.1.7 FIRE ALARM SYSTEM 0.10711 0.0000 0.0000 0.0000

FACP 10 Zone Set 1.00 0.00896 0.0000 0.0000 0.0000 0.0836 0.0000 0.0000 0.0000
TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 0.0000 0.0000 0.0062 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00006 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

Cable NYYHY 8C - 1.5 mm2 M 66.00 0.00100 0.0000 0.0000 0.0000 0.0094 0.0000 0.0000 0.0000
NYYHY 30C - 1.5 mm2 M 294.00 0.01617 0.0000 0.0000 0.0000 0.1510 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000

Steel Conduit E 25 mm diameter M 60.00 0.00091 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
E 39 mm diameter M 143.00 0.00393 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00145 0.0000 0.0000 0.0000 0.0135 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00223 0.0000 0.0000 0.0000 0.0208 0.0000 0.0000 0.0000

Painting Material Lot 1.00 0.00025 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000

PVC Conduit 50 mm diameter M 38.00 0.00035 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
75 mm diameter M 148.00 0.00266 0.0000 0.0000 0.0000 0.0248 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00090 0.0000 0.0000 0.0000 0.0084 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00136 0.0000 0.0000 0.0000 0.0127 0.0000 0.0000 0.0000

Excavation & Backfilling M³ 110.00 0.00679 0.0000 0.0000 0.0000 0.0634 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 75 mm diameter M 148.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete For Cable M 38.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00196 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 0.0000 0.0000 0.0384 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.04675 0.0000 0.0000 0.0000 0.4365 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00468 0.0000 0.0000 0.0000 0.0437 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00140 0.0000 0.0000 0.0000 0.0131 0.0000 0.0000 0.0000

B.3.1.8 EXTERNAL LIGHTING SYSTEM 0.01577 0.0000 0.0158 0.0158

U/L COMPONENT FACTORY 2 EXT


Metal Halide 250 W x 1 Street Lighting Set 16.00 0.00000 0.0000 16.0000 16.0000 0.0000 0.0000 0.0000 0.0000
Pole H: 12 m Set 16.00 0.00000 0.0000 16.0000 16.0000 0.0000 0.0000 0.0000 0.0000
Fondation for pole lighting ( H = 12 M ) Set 16.00 0.00000 0.0000 16.0000 16.0000 0.0000 0.0000 0.0000 0.0000

Labour Fee Lot 1.00 0.01396 0.0000 1.0000 1.0000 0.8850 0.0000 0.0140 0.0140
Testing & Commissioning Fee Lot 1.00 0.00140 0.0000 1.0000 1.0000 0.0885 0.0000 0.0014 0.0014
Insite Transportation Lot 1.00 0.00042 0.0000 1.0000 1.0000 0.0265 0.0000 0.0004 0.0004

B.3.1.9 LIGHTNING PROTECTION 0.03021 0.0000 0.0151 0.0151

EF Air Terminal c/ w Connection Sleve Set 1.00 0.00000 0.0000 0.5000 0.5000 0.0000 0.0000 0.0000 0.0000
Earthing Rod Ø 5/8" Set 1.00 0.00137 0.0000 0.5000 0.5000 0.0454 0.0000 0.0007 0.0007
Hand Hole 400 x 400 x 600 c/w cover Set 1.00 0.00173 0.0000 0.5000 0.5000 0.0572 0.0000 0.0009 0.0009
Pole H: 35 m Set 1.00 0.00000 0.0000 0.5000 0.5000 0.0000 0.0000 0.0000 0.0000
Fondation for pole lightning ( H = 35 M ) Set 1.00 0.00790 0.0000 0.5000 0.5000 0.2616 0.0000 0.0040 0.0040
Concrete Block 200x200x45h Set 3.00 0.00002 0.0000 1.5000 1.5000 0.0008 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00041 0.0000 0.5000 0.5000 0.0136 0.0000 0.0002 0.0002

Cable Coaxial 35 mm2 x 2 M 40.00 0.01141 0.0000 20.0000 20.0000 0.3777 0.0000 0.0057 0.0057
Termination Cable Lot 1.00 0.00034 0.0000 0.5000 0.5000 0.0113 0.0000 0.0002 0.0002

PVC Conduit 50 mm diameter M 5.00 0.00005 0.0000 2.5000 2.5000 0.0015 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00001 0.0000 0.5000 0.5000 0.0005 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00002 0.0000 0.5000 0.5000 0.0007 0.0000 0.0000 0.0000

Excavation & Backfilling M³ 12.00 0.00074 0.0000 6.0000 6.0000 0.0245 0.0000 0.0004 0.0004

Miscellaneous Material Lot 1.00 0.00120 0.0000 0.5000 0.5000 0.0397 0.0000 0.0006 0.0006

Government Permit Lot 1.00 0.00247 0.0000 0.5000 0.5000 0.0818 0.0000 0.0012 0.0012
Labour Fee Lot 1.00 0.00223 0.0000 0.5000 0.5000 0.0740 0.0000 0.0011 0.0011
Testing & Commissioning Fee Lot 1.00 0.00022 0.0000 0.5000 0.5000 0.0074 0.0000 0.0001 0.0001
Insite Transportation Lot 1.00 0.00007 0.0000 0.5000 0.5000 0.0022 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 7
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

C. DEMOLITION WORK LOT 1.00 1.40354 1.40354 0.0000 0.0000 0.0000 0.0000 0.4797 0.4797
C. STRUCTURE WORK 0.0000
C.1 WASHING AREA LOT 1.00 0.00875 0.0000 0.0000 0.0000
A Demolish existing slab concrete lot 1.00 0.00719 0.0000 0.0000 0.0000 0.8218 0.0000 0.0000 0.0000
B Disposal of rubbish lot 1.00 0.00156 0.0000 0.0000 0.0000 0.1782 0.0000 0.0000 0.0000

C.2 MAIN GATE AND BOUNDARY WALL LOT 1.00 0.00805 0.0000 0.0000 0.0000
A Demolish existing boundary wall lot 1.00 0.00253 0.0000 0.0000 0.0000 0.3139 0.0000 0.0000 0.0000
B Demolish existing main gate lot 1.00 0.00040 0.0000 0.0000 0.0000 0.0491 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00396 0.0000 0.0000 0.0000 0.4919 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00117 0.0000 0.0000 0.0000 0.1452 0.0000 0.0000 0.0000

C.3 GUARD HOUSE LOT 1.00 0.00424 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.00197 0.0000 0.0000 0.0000 0.4654 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.00093 0.0000 0.0000 0.0000 0.2204 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00062 0.0000 0.0000 0.0000 0.1470 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00071 0.0000 0.0000 0.0000 0.1672 0.0000 0.0000 0.0000

C.4 OFFICE LOT 1.00 0.11102 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.06342 0.0000 0.0000 0.0000 0.5713 0.0000 0.0000 0.0000
B Demolish existing entrance canopy lot 1.00 0.00361 0.0000 0.0000 0.0000 0.0326 0.0000 0.0000 0.0000
C Demolish existing concrete slab lot 1.00 0.03876 0.0000 0.0000 0.0000 0.3491 0.0000 0.0000 0.0000
D Demolish existing pavement lot 1.00 0.00097 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
E Disposal of rubbish lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0383 0.0000 0.0000 0.0000

C.5 CANTEEN LOT 1.00 0.09257 0.0000 0.0926 0.0926


A Demolish existing RC structure lot 1.00 0.05022 0.0000 1.0000 1.0000 0.5425 0.0000 0.0502 0.0502
B Demolish existing entrance canopy lot 1.00 0.00779 0.0000 1.0000 1.0000 0.0841 0.0000 0.0078 0.0078
C Demolish existing concrete slab lot 1.00 0.03069 0.0000 1.0000 1.0000 0.3315 0.0000 0.0307 0.0307
D Demolish existing pavement lot 1.00 0.00068 0.0000 1.0000 1.0000 0.0073 0.0000 0.0007 0.0007
E Disposal of rubbish lot 1.00 0.00319 0.0000 1.0000 1.0000 0.0344 0.0000 0.0032 0.0032

C.6 PARKING & TREE LOT 1.00 0.10770 0.0000 0.1077 0.1077
A Demolish existing pavement lot 1.00 0.00538 0.0000 1.0000 1.0000 0.0499 0.0000 0.0054 0.0054
B Demolish existing concrete slab lot 1.00 0.07494 0.0000 1.0000 1.0000 0.6958 0.0000 0.0749 0.0749
C Demolish existing trees & green space lot 1.00 0.01498 0.0000 1.0000 1.0000 0.1391 0.0000 0.0150 0.0150
D Disposal of rubbish lot 1.00 0.01240 0.0000 1.0000 1.0000 0.1151 0.0000 0.0124 0.0124

C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. LOT 1.00 0.73968 0.0000 0.0226 0.0226
A Demolish existing RC structure lot 1.00 0.31600 0.0000 0.0000 0.0000 0.4272 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.18937 0.0000 0.0000 0.0000 0.2560 0.0000 0.0000 0.0000
C Demolish existing steel plate lot 1.00 0.00478 0.0000 0.3000 0.3000 0.0065 0.0000 0.0014 0.0014
D Demolish existing foundation lot 1.00 0.15113 0.0000 0.0000 0.0000 0.2043 0.0000 0.0000 0.0000
E Demolish existing trees & green space lot 1.00 0.01037 0.0000 0.3000 0.3000 0.0140 0.0000 0.0031 0.0031
F Demolish existing drainage lot 1.00 0.00779 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
G Disposal of rubbish lot 1.00 0.06023 0.0000 0.3000 0.3000 0.0814 0.0000 0.0181 0.0181

C.8 HEXINDO OFFICE LOT 1.00 0.02180 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.00957 0.0000 0.0000 0.0000 0.4387 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.00631 0.0000 0.0000 0.0000 0.2896 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00344 0.0000 0.0000 0.0000 0.1579 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00248 0.0000 0.0000 0.0000 0.1137 0.0000 0.0000 0.0000

C.9 TOUCH UP PAINT BOOTH AREA LOT 1.00 0.05295 0.0000 0.0000 0.0000
A Demolish existing steel wall and door removal lot 1.00 0.01257 0.0000 0.0000 0.0000 0.2374 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.03170 0.0000 0.0000 0.0000 0.5987 0.0000 0.0000 0.0000
C Demolish existing steel plate lot 1.00 0.00478 0.0000 0.0000 0.0000 0.0903 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00390 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000

C.10 STOCK YARD AREA LOT 1.00 0.25679 0.0000 0.2568 0.2568
A Demolish existing concrete slab lot 1.00 0.24294 0.0000 1.0000 1.0000 0.9461 0.0000 0.2429 0.2429
B Demolish existing drainage lot 1.00 0.00141 0.0000 1.0000 1.0000 0.0055 0.0000 0.0014 0.0014
C Disposal of rubbish lot 1.00 0.01244 0.0000 1.0000 1.0000 0.0484 0.0000 0.0124 0.0124

D. BUILDING WORK LOT 1.00 51.06618 51.06618 0.0000 0.0000 0.0000 1.0000 0.0000 1.6439 1.6439
D.1 TRAINING CENTER & HEAD OFFICE 11.16837 0.0000 0.0000 0.0725 0.0725
D.1.1 STRUCTURE WORK 5.06195 0.0000 0.0725 0.0725
D.1.1.1 EARTH WORK 0.24597 0.0000 0.0000 0.0000
A Excavate over site to formation level including cleaning m2 3,502.80 0.01111 0.0000 0.0000 0.0000 0.0452 0.0000 0.0000 0.0000
site of all debris
B Excavation to underground tank m3 415.70 0.00494 0.0000 0.0000 0.0000 0.0201 0.0000 0.0000 0.0000
C Excavation to ground slab m3 1,880.00 0.02233 0.0000 0.0000 0.0000 0.0908 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 894.20 0.01551 0.0000 0.0000 0.0000 0.0630 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 145.00 0.00185 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
F Compacted sub grade m2 3,227.20 0.00588 0.0000 0.0000 0.0000 0.0239 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 591.50 0.00966 0.0000 0.0000 0.0000 0.0393 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 526.00 0.00458 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2 2,834.90 0.07633 0.0000 0.0000 0.0000 0.3103 0.0000 0.0000 0.0000
J Plastic Sheet m2 3,110.50 0.00777 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
K Back fill and compac. w/ Imported Red Soil m3 1,866.30 0.08602 0.0000 0.0000 0.0000 0.3497 0.0000 0.0000 0.0000

D.1.1.2 PILING WORK 0.40894 0.0000 0.0725 0.0725


A Allow for mobilization and demobilization of all pilling plant
and equipment
- Mob & Demob pilling equipment unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0312 0.0000 0.0064 0.0064
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0312 0.0000 0.0064 0.0064
B PC Spun Pile Ø 300 mm , L=15m nos 194.00 0.27526 0.0000 38.8000 38.8000 0.6731 0.0000 0.0551 0.0551
C Driving Pile m 2,910.00 0.08248 0.0000 145.5000 145.5000 0.2017 0.0000 0.0041 0.0041
D Welding Joint nos 194.00 0.01237 0.0000 9.7000 9.7000 0.0303 0.0000 0.0006 0.0006
E Cut off excess pile length at required level & expose nos 194.00 0.00482 0.0000 0.0000 0.0000 0.0118 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0208 0.0000 0.0000 0.0000

D.1.1.3 CONCRETE WORK 1.18616 0.0000 0.0000 0.0000


A Lean concrete T = 50 mm , grade K - 150 concrete m2 526.00 0.01438 0.0000 0.0000 0.0000 0.0121 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 163.10 0.07691 0.0000 0.0000 0.0000 0.0648 0.0000 0.0000 0.0000
C Grade K - 350 concrete to Ground Beam m3 106.30 0.05506 0.0000 0.0000 0.0000 0.0464 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 466.60 0.24169 0.0000 0.0000 0.0000 0.2038 0.0000 0.0000 0.0000
E Ditto, but to Column m3 228.00 0.11810 0.0000 0.0000 0.0000 0.0996 0.0000 0.0000 0.0000
F Ditto, but to Beam 2nd Floor m3 234.40 0.12142 0.0000 0.0000 0.0000 0.1024 0.0000 0.0000 0.0000
G Ditto, but to Slab 2nd Floor m3 298.20 0.15446 0.0000 0.0000 0.0000 0.1302 0.0000 0.0000 0.0000
H Ditto, but to Beam 3rd Floor m3 216.30 0.11204 0.0000 0.0000 0.0000 0.0945 0.0000 0.0000 0.0000
I Ditto, but to Slab 3rd Floor m3 278.30 0.14416 0.0000 0.0000 0.0000 0.1215 0.0000 0.0000 0.0000
J Ditto, but to Roof Beam m3 63.00 0.03263 0.0000 0.0000 0.0000 0.0275 0.0000 0.0000 0.0000
K Ditto, but to Roof Slab m3 0.00 0.00000 -
L Ditto, but to Parapet m3 114.70 0.05941 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
M Ditto, but to Roof Gutter m3 7.20 0.00373 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
N Ditto, but to Corbel m3 3.30 0.00171 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
O Ditto, but to Staircase m3 18.60 0.00963 0.0000 0.0000 0.0000 0.0081 0.0000 0.0000 0.0000
P Ditto, but to Column & Beam Shutter m3 1.80 0.00093 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
Q Ditto, but to Underground Tank m3 30.30 0.01570 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
R Ditto, but to STP m3 46.70 0.02419 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000

D.1.1.4 REINFORCED WORK 1.71596 0.0000 0.0000 0.0000


A HT. Reinforcement to Pile Caps kg 22,270.00 0.12624 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 18,215.00 0.10325 0.0000 0.0000 0.0000 0.0602 0.0000 0.0000 0.0000
C Ditto, but to Column kg 49,544.00 0.28084 0.0000 0.0000 0.0000 0.1637 0.0000 0.0000 0.0000
D Ditto, but to Beam 2nd Floor kg 46,183.00 0.26179 0.0000 0.0000 0.0000 0.1526 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 8
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
E Ditto, but to Slab 2nd Floor kg 30,320.00 0.17187 0.0000 0.0000 0.0000 0.1002 0.0000 0.0000 0.0000
F Ditto, but to Beam 3rd Floor kg 42,680.00 0.24193 0.0000 0.0000 0.0000 0.1410 0.0000 0.0000 0.0000
G Ditto, but to Slab 3rd Floor kg 35,224.00 0.19967 0.0000 0.0000 0.0000 0.1164 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam kg 8,526.00 0.04833 0.0000 0.0000 0.0000 0.0282 0.0000 0.0000 0.0000
I Ditto, but to Roof Slab kg 0.00 0.00000 -
J Ditto, but to Parapet kg 11,060.00 0.06269 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
K Ditto, but to Roof Gutter kg 691.00 0.00392 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
L Ditto, but to Corbel kg 2,088.00 0.01184 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
M Ditto, but to Staircase kg 3,231.00 0.01831 0.0000 0.0000 0.0000 0.0107 0.0000 0.0000 0.0000
N Ditto, but to Column & Beam Shutter kg 540.00 0.00306 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
O Ditto, but to Underground Tank kg 3,910.00 0.02216 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
P Ditto, but to STP kg 5,527.00 0.03133 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000
R Wiremesh #M6 to ground slab (2 layer) m2 2,234.00 0.12874 0.0000 0.0000 0.0000 0.0750 0.0000 0.0000 0.0000

D.1.1.5 FORM WORK 0.87746 0.0000 0.0000 0.0000


A Formwork to Pile Caps m2 370.50 0.02153 0.0000 0.0000 0.0000 0.0245 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 708.60 0.04117 0.0000 0.0000 0.0000 0.0469 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 92.10 0.00535 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
D Ditto, but to Column m2 1,752.60 0.11165 0.0000 0.0000 0.0000 0.1272 0.0000 0.0000 0.0000
E Ditto, but to Beam 2nd Floor m2 1,334.70 0.08502 0.0000 0.0000 0.0000 0.0969 0.0000 0.0000 0.0000
F Ditto, but to Slab 2nd Floor m2 2,244.00 0.14295 0.0000 0.0000 0.0000 0.1629 0.0000 0.0000 0.0000
G Ditto, but to Beam 3rd Floor m2 1,214.20 0.07735 0.0000 0.0000 0.0000 0.0881 0.0000 0.0000 0.0000
H Ditto, but to Slab 3rd Floor m2 2,087.70 0.13299 0.0000 0.0000 0.0000 0.1516 0.0000 0.0000 0.0000
I Ditto, but to Roof Beam m2 463.10 0.02950 0.0000 0.0000 0.0000 0.0336 0.0000 0.0000 0.0000
J Ditto, but to Roof Slab m2 0.00 0.00000 -
K Ditto, but to Parapet m2 1,323.00 0.08428 0.0000 0.0000 0.0000 0.0960 0.0000 0.0000 0.0000
L Ditto, but to Roof Gutter m2 93.30 0.00594 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
M Ditto, but to Corbel m2 27.50 0.00175 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
N Ditto, but to Staircase m2 154.80 0.00986 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
O Ditto, but to Column & Beam Shutter m2 23.30 0.00135 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
P Ditto, but to Underground Tank m2 130.50 0.00831 0.0000 0.0000 0.0000 0.0095 0.0000 0.0000 0.0000
Q Ditto, but to STP m2 288.70 0.01839 0.0000 0.0000 0.0000 0.0210 0.0000 0.0000 0.0000
S Supporting formwork to above m2 9,384.80 0.10006 0.0000 0.0000 0.0000 0.1140 0.0000 0.0000 0.0000

D.1.1.6 STEEL STRUCTURE WORK 0.49464 0.0000 0.0000 0.0000


A Steel trusses of main building included. purlin, bracing, etc.. Kg 25,460.00 0.24912 0.0000 0.0000 0.0000 0.5036 0.0000 0.0000 0.0000
B Steel structure of monitor Kg 200.00 0.00196 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding Kg 13,408.00 0.13120 0.0000 0.0000 0.0000 0.2652 0.0000 0.0000 0.0000
D Steel structure of canopy Kg 6,269.00 0.06134 0.0000 0.0000 0.0000 0.1240 0.0000 0.0000 0.0000
E Steel structure of staircase Kg 1,650.00 0.01614 0.0000 0.0000 0.0000 0.0326 0.0000 0.0000 0.0000
F Finishing paint to steel structure Kg 46,987.00 0.03488 0.0000 0.0000 0.0000 0.0705 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.1.1.7 MISCELLANEOUS WORK 0.13282 0.0000 0.0000 0.0000


A Non Shrinkage grouting, size : 420x420x30mm nos 21.00 0.00067 0.0000 0.0000 0.0000 0.0050 0.0000 0.0000 0.0000
B Expansion joint :
- Sand asphalt fill m 796.00 0.01552 0.0000 0.0000 0.0000 0.1169 0.0000 0.0000 0.0000
- Additional reinforcement kg 4,020.00 0.02279 0.0000 0.0000 0.0000 0.1716 0.0000 0.0000 0.0000
- Dowel rebar kg 2,935.00 0.01664 0.0000 0.0000 0.0000 0.1253 0.0000 0.0000 0.0000
- Flexible pipe m 1,062.00 0.00208 0.0000 0.0000 0.0000 0.0156 0.0000 0.0000 0.0000
C Styrofoam T=25mm to under roof slab m2 1,563.30 0.03323 0.0000 0.0000 0.0000 0.2502 0.0000 0.0000 0.0000
D Sand asphalt fill to expansion joint roof m 1,053.00 0.02054 0.0000 0.0000 0.0000 0.1546 0.0000 0.0000 0.0000
E Waterproofing coating m2 209.20 0.00668 0.0000 0.0000 0.0000 0.0503 0.0000 0.0000 0.0000
F Waterstop m 55.00 0.00487 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000
G Cat Ladder at Ground Water Tank ( U Type ) nos 18.00 0.00485 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
H Cast Iron Man Hole at Ground Water Tank nos 2.00 0.00496 0.0000 0.0000 0.0000 0.0373 0.0000 0.0000 0.0000

D.1.2 FINISHING WORK 6.10642 0.0000 0.0000 0.0000


D.1.2.1 METAL ROOFING & METAL WALL WORK LOT 1.07326 0.0000 0.0000 0.0000

Training Center Roofing


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 850.00 0.07285 0.0000 0.0000 0.0000 0.0679 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 850.00 0.00683 0.0000 0.0000 0.0000 0.0064 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 850.00 0.00545 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 850.00 0.00797 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
E End Close, Boltless U-650 m 91.00 0.00205 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 45.50 0.00103 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 45.50 0.00103 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
H End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 91.00 0.00512 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 39.00 0.00219 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
J Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 45.50 0.00151 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
K PVC Pipe AW Grey Dia. 150mm m 48.00 0.00360 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
L PVC Lbow 450 / 900 , Dia. 150mm pcs 20.00 0.00150 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
M Clamp pipe Sp. 3x42mm , Dia. 150mm pcs 52.00 0.00139 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

Training Center Monitor Roof


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 37.40 0.00281 0.0000 0.0000 0.0000 0.0026 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 37.40 0.00030 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 37.40 0.00024 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 37.40 0.00035 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
E Ridge Cover + Sponge Closer, W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 14.00 0.00094 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
F Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 4.00 0.00023 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
G Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 74.70 0.00600 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
H Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 36.00 0.00146 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 36.00 0.00146 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
J Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 8.00 0.00033 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
K Zinc. Louver H = 800mm m 28.00 0.00570 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000

File Room Roofing


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 507.00 0.03805 0.0000 0.0000 0.0000 0.0354 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 507.00 0.00407 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 507.00 0.00325 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 507.00 0.00476 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
E Ridge Cover + Sponge Closer, W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 20.00 0.00134 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
F Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 52.00 0.00293 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
G End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 39.00 0.00219 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
H Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 39.00 0.00129 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
I PVC Pipe AW Grey Dia. 100mm m 16.00 0.00069 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000
J PVC Lbow 450 / 900 , Dia. 100mm pcs 12.00 0.00051 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
K Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 20.00 0.00032 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000

Wall Finish
A Cladding Corrugated Long Metal Sheet, Thk. 0.40mm m2 1,360.00 0.10233 0.0000 0.0000 0.0000 0.0953 0.0000 0.0000 0.0000
Color Coated
B Roof mesh, Galvanized #3x3" m2 634.00 0.00509 0.0000 0.0000 0.0000 0.0047 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 634.00 0.00406 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 634.00 0.00595 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
E Top flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 140.00 0.00469 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
F Corner flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 68.70 0.00230 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
G End flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 140.00 0.00469 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
H Window & Door flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 185.00 0.00496 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
I PU Sealent m 376.40 0.01560 0.0000 0.0000 0.0000 0.0145 0.0000 0.0000 0.0000
J Cladding Alum. Corrugated Plate, Thk. 0.60mm Color m2 316.00 0.25190 0.0000 0.0000 0.0000 0.2347 0.0000 0.0000 0.0000
( Incld. Sealent & flashing)

carried forward 0.59330

brought forward 0.59330 0.0000 0.0000 0.0000


06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 9
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

METAL ROOFING & METAL WALL WORK

Canopy Finish
A Main Entrance Canopy w/ Color Aluminium Flat batten seam Ls 1.00 0.30935 0.0000 0.0000 0.0000 0.2882 0.0000 0.0000 0.0000
roofing and toplight, size : 13.500 x 11.000mm
B Smoking Canopy w/ Color Aluminium Flat batten seam roofing Ls 1.00 0.07888 0.0000 0.0000 0.0000 0.0735 0.0000 0.0000 0.0000
size : 22.500 x 2.500mm
C Ditto. but to size : 7.000mm (W) x 2.500mm (H) Ls 1.00 0.02892 0.0000 0.0000 0.0000 0.0269 0.0000 0.0000 0.0000
D Entrance Door Canopy w/ Color Aluminium Flat batten seam Ls 1.00 0.01958 0.0000 0.0000 0.0000 0.0182 0.0000 0.0000 0.0000
roofing size : 4.000 x 3.000mm
E Ditto. but to size : 7.000mm (W) x 2.500mm (H) Ls 1.00 0.02429 0.0000 0.0000 0.0000 0.0226 0.0000 0.0000 0.0000
F Ditto. but to size : 4.500mm (W) x 1.000mm (H) Ls 1.00 0.01052 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
G Ditto. but to size : 1.500mm (W) x 1.000mm (H) Ls 2.00 0.00842 0.0000 0.0000 0.0000 0.0078 0.0000 0.0000 0.0000

D.1.2.2 MASONRY WORK LOT 0.58810 0.0000 0.0000 0.0000


A Common brick wall m2 3,180.00 0.21051 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 47.70 0.02012 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 7,632.00 0.04326 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 636.00 0.03695 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 6,360.00 0.27725 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.1.2.3 TILING WORK LOT 0.37630 0.0000 0.0000 0.0000


Floor Finish
A Ceramic Tile 400 x 400 mm m2 191.00 0.01737 0.0000 0.0000 0.0000 0.0462 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 2,102.00 0.17575 0.0000 0.0000 0.0000 0.4670 0.0000 0.0000 0.0000
C Ceramic Tile 200 x 200 mm m2 1,146.00 0.09133 0.0000 0.0000 0.0000 0.2427 0.0000 0.0000 0.0000
D Ceramic Step Nosing m 301.00 0.01310 0.0000 0.0000 0.0000 0.0348 0.0000 0.0000 0.0000
Base Finish
E Ceramic Base H = 100mm m 217.30 0.00465 0.0000 0.0000 0.0000 0.0124 0.0000 0.0000 0.0000
Wall Finish
F Ceramic Tile 200 x 200 mm to brickwall m2 773.10 0.06286 0.0000 0.0000 0.0000 0.1671 0.0000 0.0000 0.0000
G Ceramic Tile 200 x 200 mm to partition wall m2 115.00 0.01123 0.0000 0.0000 0.0000 0.0298 0.0000 0.0000 0.0000

D.1.2.4 DOOR AND WINDOW WORK LOT 0.95350 0.0000 0.0000 0.0000
DOORS
A Motorized steel roll-up shutter (SS -1) nos 1.00 0.02896 0.0000 0.0000 0.0000 0.0304 0.0000 0.0000 0.0000
size : 4.000mm (W) x 6.000mm (H)

B Steel double swinging flush door (SD-1) nos 4.00 0.01806 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
size : 1.700mm (W) x 2.100mm (H)
C Ditto. but to size : 1.600mm (W) x 2.100mm (H) (SD-2) nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
D Steel single swinging flush door (SD-3) nos 3.00 0.00663 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm
E Steel double swinging louver door (SD-4) nos
size : 2.500mm (W) x 2.500mm (H)

F Wooden single swing door w/ vision glass (WD-1) nos 16.00 0.03500 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)
G Wooden double swing door w/ vision glass (WD-2) nos 14.00 0.03864 0.0000 0.0000 0.0000 0.0405 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)
H Ditto. but to size : 1.700mm (W) x 2.100mm (H) (WD-3) nos 5.00 0.01716 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
I Wooden single swing door (WD-4) nos
size : 850mm (W) x 2.100mm (H)
J Ditto. but to size : 600mm (W) x 2.100mm (H) (WD-8) nos 2.00 0.00363 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
K Wooden double swing door (WD-5) nos 1.00 0.00242 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)
L Ditto. but to size : 1.700mm (W) x 2.100mm (H) (WD-6) nos 6.00 0.01777 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
M Double swing glass door w/ Wooden Frame (WD-7) nos 11.00 0.04443 0.0000 0.0000 0.0000 0.0466 0.0000 0.0000 0.0000
size : 1.700mm (W) x 2.100mm (H)
N Wooden single sliding door (WD-9) nos 3.00 0.00727 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)

O Toilet Door w/ HPL Finish nos 18.00 0.03090 0.0000 0.0000 0.0000 0.0324 0.0000 0.0000 0.0000
size : 600mm (W) x 2.000mm (H)

P Automatic Double swing S/S glass door w/ fix glass (STD-1) nos 0.00000
size : 12.920mm (W) x 3.000mm (H)
Q Ditto. but to size : 4.920mm (W) x 3.000mm (H) (STD-2) nos 1.00 0.06429 0.0000 0.0000 0.0000 0.0674 0.0000 0.0000 0.0000

R Alum. single swing door w/ grill & fix window glass (AW-1) nos 1.00 0.08510 0.0000 0.0000 0.0000 0.0892 0.0000 0.0000 0.0000
size : 33.255mm (W) x 3.630mm (H)
S Alum. double swing door w/ fix window glass (AW-9) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
size : 4.000mm (W) x 2.960mm (H)
T Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-11) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
U Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-12) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
V Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-14) nos 1.00 0.01083 0.0000 0.0000 0.0000 0.0114 0.0000 0.0000 0.0000

W Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.11452 0.0000 0.0000 0.0000 0.1201 0.0000 0.0000 0.0000

WINDOWS
A Alum. Fix glass window w/ grill nos 1.00 0.01864 0.0000 0.0000 0.0000 0.0196 0.0000 0.0000 0.0000
size : 7.100mm (W) x 3.450mm (AW -2)
B Ditto. but to size : 45.000mm (W) x 3.350mm (H) (AW-3) nos 1.00 0.11134 0.0000 0.0000 0.0000 0.1168 0.0000 0.0000 0.0000
C Ditto. but to size : 21.600mm (W) x 3.550mm (H) (AW-6) nos 1.00 0.04789 0.0000 0.0000 0.0000 0.0502 0.0000 0.0000 0.0000
D Ditto. but to size : 21.600mm (W) x 1.200mm (H) (AW-7) nos 1.00 0.02497 0.0000 0.0000 0.0000 0.0262 0.0000 0.0000 0.0000
E Ditto. but to size : 15.100mm (W) x 1.200mm (H) (AW-16) nos 1.00 0.01956 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

carried forward 0.77377

brought forward 0.77377 0.0000 0.0000 0.0000

DOOR AND WINDOW WORK


WINDOWS
F Alum. Fix glass window (AW-4) nos 1.00 0.07425 0.0000 0.0000 0.0000 0.0779 0.0000 0.0000 0.0000
size : 11.750mm (W) x 3.010mm
G Ditto. but to size : 9.500mm (W) x 600mm (H) (AW-5) nos 1.00 0.00341 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000 0.0000
H Ditto. but to size : 700mm (W) x 9.550mm (H) (AW-8) nos 1.00 0.00490 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000
I Ditto. but to size : 4.000mm (W) x 600mm (H) (AW-10) nos 4.00 0.00575 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
J Ditto. but to size : 4.000mm (W) x 1.710mm (H) (AW-13) nos 6.00 0.03010 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
K Ditto. but to size : 4.000mm (W) x 520mm (H) (AW-15) nos 6.00 0.00915 0.0000 0.0000 0.0000 0.0096 0.0000 0.0000 0.0000
L Ditto. but to size : 1.600mm (W) x 2.590mm (H) (AW-17) nos 2.00 0.00652 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
M Ditto. but to size : 5.000mm (W) x 2.590mm (H) (AW-18) nos 1.00 0.00978 0.0000 0.0000 0.0000 0.0103 0.0000 0.0000 0.0000
N Ditto. but to size : 5.000mm (W) x 1.710mm (H) (AW-19) nos 3.00 0.01975 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
O Ditto. but to size : 2.500mm (W) x 1.710mm (H) (AW-20) nos 4.00 0.01368 0.0000 0.0000 0.0000 0.0144 0.0000 0.0000 0.0000

P Wooden window w/ fix glass & wooden counter (WW-1) nos 1.00 0.00242 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
size : 700mm (W) x 900mm

D.1.2.5 PAINTING WORK LOT 0.15234 0.0000 0.0000 0.0000


A Weathershield paint to external wall m2 1,212.00 0.02445 0.0000 0.0000 0.0000 0.1605 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 3,200.00 0.03671 0.0000 0.0000 0.0000 0.2410 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 4,335.00 0.04973 0.0000 0.0000 0.0000 0.3264 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 454.00 0.00824 0.0000 0.0000 0.0000 0.0541 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 220.00 0.00148 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 10
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
F Floor Hardener Green Color to Floor m2 760.50 0.03074 0.0000 0.0000 0.0000 0.2018 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 58.50 0.00098 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000

D.1.2.6 INTERIOR FINISHING WORK LOT 2.04985 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 2,531.00 0.00803 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000
B Floor Screeding w/ cement mortar m2 1,712.00 0.04425 0.0000 0.0000 0.0000 0.0216 0.0000 0.0000 0.0000
C PVC Tile 300 x 300mm m2 1,357.00 0.16016 0.0000 0.0000 0.0000 0.0781 0.0000 0.0000 0.0000
D import Carpet Tile 600 x 600 mm m2 355.00 0.11319 0.0000 0.0000 0.0000 0.0552 0.0000 0.0000 0.0000
E Raised Floor H = 100mm m2 1,378.00 0.42059 0.0000 0.0000 0.0000 0.2052 0.0000 0.0000 0.0000

Base Finish
E Wooden Base H = 100mm m 1,331.00 0.08021 0.0000 0.0000 0.0000 0.0391 0.0000 0.0000 0.0000
F Mortar Base w/ AE H = 100mm m 176.00 0.00188 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
G Mortar Base w/ VP H = 100mm m 215.00 0.00274 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

carried forward 0.83105

brought forward 0.83105 0.0000 0.0000 0.0000

INTERIOR FINISHING WORK


Wall Finish
H Drywall Partition Gypsum Board (2side) m2 1,509.00 0.15081 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
I Drywall Partition Gypsum Board (1side) m2 634.00 0.05168 0.0000 0.0000 0.0000 0.0252 0.0000 0.0000 0.0000
J Extra steel chanel to ditto kg 6,429.00 0.06291 0.0000 0.0000 0.0000 0.0307 0.0000 0.0000 0.0000
K Movable Partition (Steel Partition) m2 583.00 0.18829 0.0000 0.0000 0.0000 0.0919 0.0000 0.0000 0.0000
L Low Partition H = 1.800mm m2 48.20 0.01557 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
M Vynil Wall Covering m2 2,529.00 0.24200 0.0000 0.0000 0.0000 0.1181 0.0000 0.0000 0.0000
N Framless Glass Partition m2 29.00 0.02363 0.0000 0.0000 0.0000 0.0115 0.0000 0.0000 0.0000

Ceiling Finish
O Gypsum Board (Flat) T=9mm w/ LGS Frame m2 3,292.00 0.16795 0.0000 0.0000 0.0000 0.0819 0.0000 0.0000 0.0000
P Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 921.00 0.06184 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
Q Gypsum Tile 600 x 600mm T=9mm w/ T-Bar system m2 59.00 0.00284 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
R Drop Ceiling H = 300mm m 261.00 0.01203 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
S Wooden Ceiling W = 150mm, 50mm Thick m2 70.00 0.03348 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
T Extra steel chanel to ditto kg 13,026.00 0.12746 0.0000 0.0000 0.0000 0.0622 0.0000 0.0000 0.0000
U Wooden Curtain Box 150mm Width w/ OP Fin. m 255.00 0.06324 0.0000 0.0000 0.0000 0.0309 0.0000 0.0000 0.0000
V Wooden Light Box 150mm Width w/ OP Fin. m 72.00 0.00893 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
W Acrylic Louver Cover to above m 72.00 0.00434 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
X Skim coat to Exposed Ceiling m2 122.00 0.00182 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000

D.1.2.7 WATERPROOFING WORK LOT 0.26793 0.0000 0.0000 0.0000

A Waterproofing coating m2 209.00 0.00667 0.0000 0.0000 0.0000 0.0249 0.0000 0.0000 0.0000
B Mortar screeding protection to above m2 209.00 0.00540 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
C Waterproofing membrane m2 1,783.00 0.10745 0.0000 0.0000 0.0000 0.4010 0.0000 0.0000 0.0000
D Protection concrete 50 mm to waterproofing membrane m2 1,609.00 0.11922 0.0000 0.0000 0.0000 0.4450 0.0000 0.0000 0.0000
E Protection brick w/ plaster 1 side m2 72.00 0.00791 0.0000 0.0000 0.0000 0.0295 0.0000 0.0000 0.0000
F Groove w/ fill polyurethane sealent (15w x 15d) m 909.00 0.02129 0.0000 0.0000 0.0000 0.0794 0.0000 0.0000 0.0000

D.1.2.8 MISCELLANEOUS WORK LOT 0.64512 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 4.00 0.00128 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 22.00 0.00203 0.0000 0.0000 0.0000 0.0032 0.0000 0.0000 0.0000
C Maintenance steel ladder w/ cage H : 4.000 mm unit 1.00 0.00553 0.0000 0.0000 0.0000 0.0086 0.0000 0.0000 0.0000
D Steel Handrail H = 1000mm w/ OP finish m 143.00 0.05573 0.0000 0.0000 0.0000 0.0864 0.0000 0.0000 0.0000
E Pantry Sink w/ Cabinet unit 2.00 0.03401 0.0000 0.0000 0.0000 0.0527 0.0000 0.0000 0.0000
F S/S Kitchen Sink unit 1.00 0.00319 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
G Kitchen Counter w/ brick + Rc Concrete & SUS pipe rail m 11.00 0.01637 0.0000 0.0000 0.0000 0.0254 0.0000 0.0000 0.0000
H Hand washing w/ Ceramic Tile m 16.00 0.00850 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
I Lavatory concrete table w/ top marble finish
- Size : 2.000mm (L) x 600mm (W) unit 6.00 0.01275 0.0000 0.0000 0.0000 0.0198 0.0000 0.0000 0.0000
- Size : 3.200mm (L) x 600mm (W) unit 3.00 0.01020 0.0000 0.0000 0.0000 0.0158 0.0000 0.0000 0.0000
J Wall mirror at toilet :
- Size : 2.000mm (L) x 1.000mm (H) unit 6.00 0.00808 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
- Size : 3.200mm (L) x 1.000mm (H) unit 3.00 0.00638 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
K Shower screen unit 52.00 0.04606 0.0000 0.0000 0.0000 0.0714 0.0000 0.0000 0.0000
L Receptionist Counter unit 1.00 0.03189 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
M Wooden cassing finish OP to alum. window m 670.00 0.03088 0.0000 0.0000 0.0000 0.0479 0.0000 0.0000 0.0000
N Motorized Projection Screen unit 4.00 0.04960 0.0000 0.0000 0.0000 0.0769 0.0000 0.0000 0.0000
O Vertical Blind m2 536.00 0.10634 0.0000 0.0000 0.0000 0.1648 0.0000 0.0000 0.0000
P Room name plate nos 45.00 0.00877 0.0000 0.0000 0.0000 0.0136 0.0000 0.0000 0.0000
Q Room Name Sheet nos 11.00 0.00214 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
R Movable Partition, size : 6.500 x 3.000mm nos 1.00 0.02267 0.0000 0.0000 0.0000 0.0351 0.0000 0.0000 0.0000
S Picture Rail nos 18.00 0.01913 0.0000 0.0000 0.0000 0.0297 0.0000 0.0000 0.0000
T S/S Insect Net to Ventilation m2 88.00 0.02182 0.0000 0.0000 0.0000 0.0338 0.0000 0.0000 0.0000
U Grating cover 300mm m 64.00 0.03560 0.0000 0.0000 0.0000 0.0552 0.0000 0.0000 0.0000
V Grating cover 600mm m 5.00 0.00478 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
W PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 156.00 0.02930 0.0000 0.0000 0.0000 0.0454 0.0000 0.0000 0.0000
X Cast iron roof drain nos 12.00 0.00298 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
Y Exterior Column Fin. w/ Fluoro Carbon Polymenr Paint lot 1.00 0.00886 0.0000 0.0000 0.0000 0.0137 0.0000 0.0000 0.0000
Z External Company Logo & Sign lot 1.00 0.03189 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
AA Receptionist Company Logo & Sign lot 1.00 0.01771 0.0000 0.0000 0.0000 0.0275 0.0000 0.0000 0.0000
AB Alum Coping for Expantion Joint m 43.00 0.01066 0.0000 0.0000 0.0000 0.0165 0.0000 0.0000 0.0000

D.2 ULTRA LARGE COMPONENT FACT-2 22.34416 0.0000 0.0000 1.5539 1.5539
D.2.1 STRUCTURE WORK 18.61281 0.0000 1.5539 1.5539
D.2.1.1 EARTH WORK 0.33725 0.0000 0.0406 0.0406
A Excavate over site to formation level including cleaning m2 9,851.30 0.03124 0.0000 5,910.7800 5,910.7800 0.0926 0.0000 0.0187 0.0187
site of all debris
B Excavation to ground slab m3 3,278.00 0.03893 0.0000 0.0000 0.0000 0.1154 0.0000 0.0000 0.0000
C Excavation to pile cap & g.beam m3 3,511.60 0.06090 0.0000 0.0000 0.0000 0.1806 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 2,324.20 0.02964 0.0000 0.0000 0.0000 0.0879 0.0000 0.0000 0.0000
E Compacted sub grade m2 9,841.00 0.01793 0.0000 0.0000 0.0000 0.0532 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 4,466.00 0.07293 0.0000 1,339.8000 1,339.8000 0.2163 0.0000 0.0219 0.0219
G T=50mm comp. sand bedding m2 9,841.00 0.08567 0.0000 0.0000 0.0000 0.2540 0.0000 0.0000 0.0000
H T=200mm comp. basecourse m2 -

D.2.1.2 PILING WORK 7.78288 0.0000 1.5132 1.5132


PC SPUN PILE
A Allow for mobilization and demobilization of all 0.00%
pilling plant and equipment
- Mob & Demob pilling equipment unit 4.00 0.05102 0.0000 2.0000 2.0000 0.0066 0.0000 0.0255 0.0255
- Mob & Demob Service Crane unit 2.00 0.02551 0.0000 1.0000 1.0000 0.0033 0.0000 0.0128 0.0128
B PC Spun Pile Ø 300mm , L=30m nos 1,489.00 4.22549 0.0000 297.8000 297.8000 0.5429 0.0000 0.8451 0.8451
C Driving PC Spun Pile Ø 300mm m 44,670.00 1.26605 0.0000 8,040.6000 8,040.6000 0.1627 0.0000 0.2279 0.2279
D Welding Joint PC Spun Pile Ø 300mm nos 2,978.00 0.18991 0.0000 536.0400 536.0400 0.0244 0.0000 0.0342 0.0342
E Cut off excess pile length at required level & expose nos 1,489.00 0.03698 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PC Spun Pile Ø 450mm , L=30m nos 291.00 1.48086 0.0000 58.2000 58.2000 0.1903 0.0000 0.2962 0.2962
G Driving PC Spun Pile Ø 450mm m 8,730.00 0.37114 0.0000 1,571.4000 1,571.4000 0.0477 0.0000 0.0668 0.0668
H Welding Joint PC Spun Pile Ø 450mm nos 291.00 0.02680 0.0000 52.3800 52.3800 0.0034 0.0000 0.0048 0.0048
I Cut off excess pile length at required level & expose nos 291.00 0.00929 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 11
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
reinforcements incl. all necessary excav. Required
J PDA Test nos 6.00 0.02551 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000

BORED PILE
K Mobilization Lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
L Prelimenaries Work Lot 1.00 0.00213 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
M Drilling Work from ground level Ø 400mm m 270.00 0.01722 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
N Grade K - 250 concrete m3 34.00 0.01603 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
O HT. Reinforcement kg 4,021.00 0.02279 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000
P Soil Disposal m 270.00 0.00765 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
Q Demobilization Lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000

D.2.1.3 CONCRETE WORK 2.23570 0.0000 0.0000 0.0000


A Lean concrete T = 50 mm , grade K - 150 concrete m2 9,841.00 0.26896 0.0000 0.0000 0.0000 0.1203 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 466.00 0.21975 0.0000 0.0000 0.0000 0.0983 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 178.40 0.08413 0.0000 0.0000 0.0000 0.0376 0.0000 0.0000 0.0000
D Ditto , but to Drop Panel m3 348.30 0.16424 0.0000 0.0000 0.0000 0.0735 0.0000 0.0000 0.0000
E Ditto , but to Ground Slab m3 2,178.40 1.02725 0.0000 0.0000 0.0000 0.4595 0.0000 0.0000 0.0000
F Ditto, but to Column m3 693.00 0.32679 0.0000 0.0000 0.0000 0.1462 0.0000 0.0000 0.0000
G Ditto, but to Middle Beam m3 104.40 0.04923 0.0000 0.0000 0.0000 0.0220 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam m3 6.70 0.00316 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I Ditto, but to Roof Slab m3 28.20 0.01330 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
J Ditto, but to Parapet m3 6.40 0.00302 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
K Ditto, but to Column & Beam Shutter m3 21.00 0.00990 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
L Ditto, but to Machine Foundation m3 28.40 0.01339 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
M Ditto, but to Gantry Foundation m3 57.10 0.02693 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
N Ditto, but to End Carriage Rail m3 2.20 0.00104 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
O Ditto, but to Corbel m3 52.20 0.02462 0.0000 0.0000 0.0000 0.0110 0.0000 0.0000 0.0000

D.2.1.4 REINFORCED WORK 2.72401 0.0000 0.0000 0.0000


A HT. Reinforcement to Pile Caps kg 37,704.00 0.21372 0.0000 0.0000 0.0000 0.0785 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 35,220.00 0.19964 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel kg 14,524.00 0.08233 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab kg 185,942.00 1.05400 0.0000 0.0000 0.0000 0.3869 0.0000 0.0000 0.0000
E Ditto, but to Column kg 152,120.00 0.86229 0.0000 0.0000 0.0000 0.3166 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam kg 16,522.00 0.09365 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam kg 1,346.00 0.00763 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab kg 2,539.00 0.01439 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
I Ditto, but to Parapet kg 608.00 0.00345 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter kg 6,237.00 0.03535 0.0000 0.0000 0.0000 0.0130 0.0000 0.0000 0.0000
K Ditto, but to Machine Foundation kg 2,602.00 0.01475 0.0000 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000
L Ditto, but to Gantry Foundation kg 4,983.00 0.02825 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
M Ditto, but to End Carriage Rail kg 1,213.00 0.00688 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
N Ditto, but to Corbel kg 18,995.00 0.10767 0.0000 0.0000 0.0000 0.0395 0.0000 0.0000 0.0000

D.2.1.5 FORM WORK 0.60935 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 836.20 0.04858 0.0000 0.0000 0.0000 0.0797 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 1,157.00 0.06722 0.0000 0.0000 0.0000 0.1103 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel m2 1,786.00 0.10377 0.0000 0.0000 0.0000 0.1703 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m2 277.80 0.01614 0.0000 0.0000 0.0000 0.0265 0.0000 0.0000 0.0000
E Ditto, but to Column m2 3,311.90 0.21098 0.0000 0.0000 0.0000 0.3462 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m2 863.10 0.05498 0.0000 0.0000 0.0000 0.0902 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m2 66.80 0.00426 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab m2 197.80 0.01260 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
I Ditto, but to Parapet m2 75.50 0.00481 0.0000 0.0000 0.0000 0.0079 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter m2 96.30 0.00613 0.0000 0.0000 0.0000 0.0101 0.0000 0.0000 0.0000
K Ditto, but to Machine Foundation m2 26.20 0.00152 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
L Ditto, but to Gantry Foundation m2 146.20 0.00849 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
M Ditto, but to End Carriage Rail m2 8.50 0.00049 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
N Ditto, but to Corbel m2 270.60 0.01724 0.0000 0.0000 0.0000 0.0283 0.0000 0.0000 0.0000
O Supporting formwork to above m2 4,889.20 0.05213 0.0000 0.0000 0.0000 0.0855 0.0000 0.0000 0.0000

D.2.1.6 STEEL STRUCTURE WORK 4.84123 0.0000 0.0000 0.0000

A Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 278,627.40 2.72632 0.0000 0.0000 0.0000 0.5631 0.0000 0.0000 0.0000

B Steel structure of metal fascia Kg 3,784.40 0.03703 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding Kg 22,944.20 0.22451 0.0000 0.0000 0.0000 0.0464 0.0000 0.0000 0.0000
D Steel structure of canopy Kg 10,098.80 0.09882 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000
E Steel structure of gantry corbel Kg 159,187.40 1.55762 0.0000 0.0000 0.0000 0.3217 0.0000 0.0000 0.0000
F Steel structure of staircase Kg 4,885.40 0.04780 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
G Finishing paint to steel structure Kg 200,900.20 0.14913 0.0000 0.0000 0.0000 0.0308 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.2.1.7 MISCELLANEOUS WORK 0.08239 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 76.00 0.00243 0.0000 0.0000 0.0000 0.0294 0.0000 0.0000 0.0000
B Sand asphalt fill to expansion joint roof m 218.00 0.00425 0.0000 0.0000 0.0000 0.0516 0.0000 0.0000 0.0000
C Styrofoam T=25mm to under roof slab m2 187.00 0.00398 0.0000 0.0000 0.0000 0.0482 0.0000 0.0000 0.0000
D Expansion joint to existing slab :
- Sand asphalt fill m 110.00 0.00215 0.0000 0.0000 0.0000 0.0260 0.0000 0.0000 0.0000
- Dowel rebar kg 402.00 0.00228 0.0000 0.0000 0.0000 0.0277 0.0000 0.0000 0.0000
- Flexible pipe m 145.00 0.00028 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
E Machine Foundation Work :
- Support D10 @300 kg 36.00 0.00020 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
- Bending Plate 9mm Thick kg 1,174.00 0.01149 0.0000 0.0000 0.0000 0.1394 0.0000 0.0000 0.0000
F - Base Adjuster L 50x50x5 kg 88.00 0.00086 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
- Edge L 60x60x6 kg
Gantry Rail Foundation Work :
G - Embeded Bar D12 @300 kg 2,039.00 0.01995 0.0000 0.0000 0.0000 0.2421 0.0000 0.0000 0.0000
- Base Adjuster L 50x50x5 kg 2,766.00 0.02706 0.0000 0.0000 0.0000 0.3285 0.0000 0.0000 0.0000
End Carriage Rail Work :
- Base Adjuster L 50x50x5 kg 763.00 0.00747 0.0000 0.0000 0.0000 0.0906 0.0000 0.0000 0.0000

D.2.2 FINISHING WORK 3.73135 0.0000 0.0000 0.0000

D.2.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 1.78077 0.0000 0.0000 0.0000

Metal Roofing Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 6,175.00 0.52921 0.0000 0.0000 0.0000 0.2972 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 0.00 0.00000 -
C Aluminium foil single sided m2 0.00 0.00000 -
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00 0.00000 -
E End Close, Boltless U-650 m 556.00 0.01253 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 278.00 0.00627 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 278.00 0.00627 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
H Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 75.00 0.00503 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 140.00 0.00788 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
J Expantion Cover W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 70.00 0.00394 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
K Monitor Nagare Flashing. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 912.00 0.05133 0.0000 0.0000 0.0000 0.0288 0.0000 0.0000 0.0000
L End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 131.00 0.00737 0.0000 0.0000 0.0000 0.0041 0.0000 0.0000 0.0000
M Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 278.00 0.00923 0.0000 0.0000 0.0000 0.0052 0.0000 0.0000 0.0000
N Eaves FRP Gutter , Grey Thk 2.0mm , W=1.100mm m 245.00 0.05054 0.0000 0.0000 0.0000 0.0284 0.0000 0.0000 0.0000
O Gutter Bracket Steel Angle 30x30x30x3 mm, W=1.300mm pcs 378.00 0.01316 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
P PVC Pipe AW Grey Dia. 200mm m 612.00 0.08198 0.0000 0.0000 0.0000 0.0460 0.0000 0.0000 0.0000
Q PVC Lbow 450 / 900 , Dia. 200mm pcs 144.00 0.01929 0.0000 0.0000 0.0000 0.0108 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 12
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
R Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 648.00 0.02086 0.0000 0.0000 0.0000 0.0117 0.0000 0.0000 0.0000

Monitor Roof
A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 2,784.00 0.23859 0.0000 0.0000 0.0000 0.1340 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 0.00 0.00000 -
C Aluminium foil single sided m2 0.00 0.00000 -
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00 0.00000 -
E End Close, Boltless U-650 m 384.00 0.00865 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 96.00 0.00216 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 192.00 0.00433 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
H Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 48.00 0.00322 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 928.00 0.05223 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
J End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 96.00 0.00540 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
K Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 192.00 0.00637 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000 0.0000
L Monitor Wall FRP Type U-527 (27mm) Clear/Natural Thk. 2,0mm m2 547.00 0.10258 0.0000 0.0000 0.0000 0.0576 0.0000 0.0000 0.0000
M Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 320.00 0.02572 0.0000 0.0000 0.0000 0.0144 0.0000 0.0000 0.0000
N Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 245.00 0.00997 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
O End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 245.00 0.00997 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
P Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 3.00 0.00012 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 3,841.50 0.30874 0.0000 0.0000 0.0000 0.1734 0.0000 0.0000 0.0000
B FRP Cladding Type U527 (27mm) Clear/Natural, Thk. 1,5mm m 528.80 0.07790 0.0000 0.0000 0.0000 0.0437 0.0000 0.0000 0.0000
C End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 246.00 0.01001 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
D Window, Shutter & Open flashing W=457mm, Zincalume m 283.00 0.01152 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
Thk 0.4mm -
E Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 33.00 0.00134 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
F Wall Expansion Cover W=457mm, Zincalume Colour Thk 0.40mm m 33.00 0.00134 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 336.00 0.02521 0.0000 0.0000 0.0000 0.0142 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 240.00 0.01351 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
C Steel Hollow 40x20x2,3mm + Zinchromate m 336.00 0.00991 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
D Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 84.00 0.01575 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
E Gutter Bracket Sp 3x42mm W=1.200mm pcs 178.00 0.00573 0.0000 0.0000 0.0000 0.0032 0.0000 0.0000 0.0000
F PVC Pipe AW Grey Dia. 100mm m 80.00 0.00343 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
G PVC Lbow 450 / 900 , Dia. 100mm pcs 18.00 0.00077 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000
H Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 88.00 0.00141 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

D.2.2.2 MASONRY WORK 0.17348 0.0000 0.0000 0.0000

A Common brick wall m2 938.00 0.06210 0.0000 0.0000 0.0000 0.0349 0.0000 0.0000 0.0000
B Ventilation block wall m2 0.00000 -
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 14.10 0.00595 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
- HT. Reinforcement kg 2,251.00 0.01276 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Timber formwork m2 187.60 0.01090 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 1,876.00 0.08178 0.0000 0.0000 0.0000 0.0459 0.0000 0.0000 0.0000
w/ instant mortar

D.2.2.3 TILING WORK 0.02202 0.0000 0.0000 0.0000

Floor Finish
A Ceramic Tile 200 x 200 mm m2 180.00 0.01435 0.0000 0.0000 0.0000 0.6514 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 12.00 0.00100 0.0000 0.0000 0.0000 0.0456 0.0000 0.0000 0.0000
Base Finish
C Ceramic Base H = 100mm m 49.00 0.00105 0.0000 0.0000 0.0000 0.0476 0.0000 0.0000 0.0000
Wall Finish
D Ceramic Tile 200 x 200 mm m2 69.20 0.00563 0.0000 0.0000 0.0000 0.2555 0.0000 0.0000 0.0000

D.2.2.4 DOOR AND WINDOW WORK 0.94775 0.0000 0.0000 0.0000

DOORS
A Steel double hanging sliding door w/ FRP Panel (SD-1) nos 3.00 0.42090 0.0000 0.0000 0.0000 0.4441 0.0000 0.0000 0.0000
size : 10.000mm (W) x 10.000mm (H)
B Ditto. but to size : 8.000mm (W) x 8.000mm (H) (SD-2) nos 2.00 0.17958 0.0000 0.0000 0.0000 0.1895 0.0000 0.0000 0.0000
C Ditto. but to size : 5.000mm (W) x 6.000mm (H) (SD-3) nos 4.00 0.16836 0.0000 0.0000 0.0000 0.1776 0.0000 0.0000 0.0000

D Steel double swinging flush door w/ Louver (SD-4) nos 2.00 0.01037 0.0000 0.0000 0.0000 0.0109 0.0000 0.0000 0.0000
size : 1.800mm (W) x 2.100mm (H)
E Ditto. but to size : 1.800mm (W) x 2.500mm (H) (SD-5) nos 1.00 0.00617 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
F Steel single swinging flush door (SD-6) nos 4.00 0.00883 0.0000 0.0000 0.0000 0.0093 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm
G Steel single swinging flush mesh door (SD-7) nos 3.00 0.00707 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
size : 800mm (W) x 2.000mm
H Ditto. but to size : 600mm (W) x 2.100mm (H) nos 2.00 0.00412 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
I Steel double swinging flush mesh door (SD-8) nos 1.00 0.00465 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.000mm (H)

I Wooden double swing door w/ vision glass (WD-1) nos 2.00 0.00687 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.100mm (H)
J Wooden single swing door w/ vision glass (WD-2) nos 1.00 0.00219 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)
K Wooden single swing door (WD-3) nos 3.00 0.00586 0.0000 0.0000 0.0000 0.0062 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)

L Toilet booth nos 4.00 0.00525 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
size : 600mm (W) x 2.000mm (H)

carried forward 0.83022

brought forward 0.83022 0.0000 0.0000 0.0000

DOOR AND WINDOW WORK

DOORS
M Alum. single swing door w/ vision glass (AD-1) nos 1.00 0.00265 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm (H)

N Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.03259 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000

WINDOWS
A Aluminium top hinge window (AW-1) nos 47.00 0.05047 0.0000 0.0000 0.0000 0.0533 0.0000 0.0000 0.0000
size : 800mm (W) x 900mm
B Ditto. but to size : 1.800mm (W) x 900mm (H) (AW-5) nos 1.00 0.00268 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
C Aluminium top hinge + fix glass window (AW-3) nos 7.00 0.01468 0.0000 0.0000 0.0000 0.0155 0.0000 0.0000 0.0000
size : 1.700mm (W) x 900mm
D Aluminium bouevenlight window (AW-4) nos 5.00 0.00176 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
size : 1.200mm (W) x 400mm
E Aluminium top hinge + jalousie window (AW-6) nos 2.00 0.00478 0.0000 0.0000 0.0000 0.0050 0.0000 0.0000 0.0000
size : 1.000mm (W) x 1.100mm

F Steel Louver, size : 1.000mm (W) x 1.100mm (H) (LW-1) nos 8.00 0.00791 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000

D.2.2.5 PAINTING WORK 0.41606 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 1,152.00 0.02324 0.0000 0.0000 0.0000 0.0559 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 1,556.00 0.01785 0.0000 0.0000 0.0000 0.0429 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 13
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
C Ditto , but to ceiling m2 374.00 0.00429 0.0000 0.0000 0.0000 0.0103 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 1,193.00 0.02166 0.0000 0.0000 0.0000 0.0520 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 692.00 0.00467 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 8,418.00 0.34027 0.0000 0.0000 0.0000 0.8178 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 243.00 0.00408 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000

D.2.2.6 INTERIOR FINISHING WORK 0.05144 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 8,661.00 0.02747 0.0000 0.0000 0.0000 0.5340 0.0000 0.0000 0.0000

Base Finish
B Wooden Base H = 100mm m 2.00 0.00012 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
C Mortar Base w/ AE H = 100mm m 83.00 0.00088 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
D Mortar Base w/ Epoxy Paint H=100mm m 38.40 0.00476 0.0000 0.0000 0.0000 0.0926 0.0000 0.0000 0.0000

Ceiling Finish
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 158.00 0.00806 0.0000 0.0000 0.0000 0.1567 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 28.00 0.00188 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 558.00 0.00546 0.0000 0.0000 0.0000 0.1061 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 188.00 0.00280 0.0000 0.0000 0.0000 0.0545 0.0000 0.0000 0.0000

D.2.2.7 WATERPROOFING WORK 0.04040 0.0000 0.0000 0.0000

A Waterproofing membrane m2 208.00 0.01106 0.0000 0.0000 0.0000 0.2737 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 188.00 0.01147 0.0000 0.0000 0.0000 0.2838 0.0000 0.0000 0.0000
C Protection brick w/ plaster 1 side m2 26.30 0.00268 0.0000 0.0000 0.0000 0.0663 0.0000 0.0000 0.0000
D Groove w/ fill polyurethane sealent (15w x 15d) m 649.00 0.01520 0.0000 0.0000 0.0000 0.3761 0.0000 0.0000 0.0000

D.2.2.8 MISCELLANEOUS WORK 0.29942 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 36.00 0.01148 0.0000 0.0000 0.0000 0.0383 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 162.00 0.01498 0.0000 0.0000 0.0000 0.0500 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 18.500 mm unit 1.00 0.02551 0.0000 0.0000 0.0000 0.0852 0.0000 0.0000 0.0000
D S/S Insect Net to Ventilation m2 176.10 0.04367 0.0000 0.0000 0.0000 0.1459 0.0000 0.0000 0.0000
E Lavatory concrete table w/ top marble finish
- Size : 2.400mm (L) x 600mm (W) unit 1.00 0.00255 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
F Wall mirror at toilet :
- Size : 2.400mm (L) x 1.000mm (H) unit 1.00 0.00163 0.0000 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000
G Mesh Fence Wall H = 2.200mm m2 115.20 0.12897 0.0000 0.0000 0.0000 0.4307 0.0000 0.0000 0.0000
H Cast iron roof drain nos 3.00 0.00074 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
I PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 21.00 0.00394 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
J Room name plate nos 7.00 0.00211 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
K Wooden Casing to aluminium window m 212.20 0.00978 0.0000 0.0000 0.0000 0.0327 0.0000 0.0000 0.0000
L Steel Handrail H = 1000mm w/ OP finish m 105.00 0.04092 0.0000 0.0000 0.0000 0.1367 0.0000 0.0000 0.0000
M Steel Ladder L = 9.000mm nos 1.00 0.00957 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
N Glass Block, size : 200mm (W) x 200mm (H) nos 53.00 0.00357 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000

D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH 3.01658 0.0000 0.0175 0.0175

D.3.1 STRUCTURE WORK 2.02902 0.0000 0.0175 0.0175

D.3.1.1 EARTH WORK LOT 1.00 0.07503 0.0000 0.0047 0.0047

A Excavate over site to formation level including cleaning m2 1,483.10 0.00470 0.0000 1,483.1000 1,483.1000 0.0627 0.0000 0.0047 0.0047
site of all debris
B Excavation to underground tank m3
C Excavation to ground slab m3 530.00 0.00629 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 1,277.30 0.02215 0.0000 0.0000 0.0000 0.2952 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 908.00 0.01158 0.0000 0.0000 0.0000 0.1544 0.0000 0.0000 0.0000
F Compacted sub grade m2 1,483.10 0.00270 0.0000 0.0000 0.0000 0.0360 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 899.20 0.01468 0.0000 0.0000 0.0000 0.1957 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 1,483.10 0.01291 0.0000 0.0000 0.0000 0.1721 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2

D.3.1.2 PILING WORK LOT 1.00 0.58263 0.0000 0.0128 0.0128

A Allow for mobilization and demobilization of all


pilling plant and equipment
- Mob & Demob pilling equipment unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0219 0.0000 0.0064 0.0064
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0219 0.0000 0.0064 0.0064
B PC Spun Pile Ø 300mm , L=30m nos 82.00 0.23270 0.0000 0.0000 0.0000 0.3994 0.0000 0.0000 0.0000
C Driving PC Spun Pile Ø 300mm m 2,460.00 0.06972 0.0000 0.0000 0.0000 0.1197 0.0000 0.0000 0.0000
D Welding Joint PC Spun Pile Ø 300mm nos 164.00 0.01046 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 82.00 0.00204 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PC Spun Pile Ø 350mm , L=30m nos 50.00 0.17803 0.0000 0.0000 0.0000 0.3056 0.0000 0.0000 0.0000
G Driving PC Spun Pile Ø 350mm m 1,500.00 0.04788 0.0000 0.0000 0.0000 0.0822 0.0000 0.0000 0.0000
H Welding Joint PC Spun Pile Ø 350mm nos 100.00 0.00638 0.0000 0.0000 0.0000 0.0109 0.0000 0.0000 0.0000
I Cut off excess pile length at required level & expose nos 50.00 0.00142 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
J PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0146 0.0000 0.0000 0.0000

D.3.1.3 CONCRETE WORK LOT 1.00 0.34177 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 1,483.10 0.04053 0.0000 0.0000 0.0000 0.1186 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 38.00 0.01792 0.0000 0.0000 0.0000 0.0524 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 36.80 0.01735 0.0000 0.0000 0.0000 0.0508 0.0000 0.0000 0.0000
D Ditto , but to Drop Panel m3 30.40 0.01434 0.0000 0.0000 0.0000 0.0419 0.0000 0.0000 0.0000
E Ditto , but to Ground Slab m3 344.30 0.16236 0.0000 0.0000 0.0000 0.4751 0.0000 0.0000 0.0000
F Ditto, but to Column m3 77.50 0.03655 0.0000 0.0000 0.0000 0.1069 0.0000 0.0000 0.0000
G Ditto, but to Middle Beam m3 6.40 0.00302 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam m3 26.70 0.01259 0.0000 0.0000 0.0000 0.0368 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter m3 -
J Ditto, but to Pit m3 78.70 0.03711 0.0000 0.0000 0.0000 0.1086 0.0000 0.0000 0.0000

D.3.1.4 REINFORCED WORK 0.50742 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 4,830.00 0.02738 0.0000 0.0000 0.0000 0.0540 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 6,966.00 0.03949 0.0000 0.0000 0.0000 0.0778 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel kg 950.00 0.00539 0.0000 0.0000 0.0000 0.0106 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab kg 44,455.00 0.25199 0.0000 0.0000 0.0000 0.4966 0.0000 0.0000 0.0000
E Ditto, but to Column kg 19,771.00 0.11207 0.0000 0.0000 0.0000 0.2209 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam kg 1,146.00 0.00650 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam kg 2,994.00 0.01697 0.0000 0.0000 0.0000 0.0334 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter kg
I Ditto, but to Pit kg 8,405.00 0.04764 0.0000 0.0000 0.0000 0.0939 0.0000 0.0000 0.0000

D.3.1.5 FORM WORK LOT 1.00 0.14620 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 173.50 0.01008 0.0000 0.0000 0.0000 0.0689 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 245.00 0.01423 0.0000 0.0000 0.0000 0.0974 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel m2 104.60 0.00608 0.0000 0.0000 0.0000 0.0416 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m2 290.70 0.01689 0.0000 0.0000 0.0000 0.1155 0.0000 0.0000 0.0000
E Ditto, but to Column m2 622.60 0.03966 0.0000 0.0000 0.0000 0.2713 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m2 72.00 0.00459 0.0000 0.0000 0.0000 0.0314 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m2 222.00 0.01414 0.0000 0.0000 0.0000 0.0967 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter m2
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 14
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
I Ditto, but to Pit m2 413.60 0.02635 0.0000 0.0000 0.0000 0.1802 0.0000 0.0000 0.0000
J Supporting formwork to above m2 1,330.20 0.01418 0.0000 0.0000 0.0000 0.0970 0.0000 0.0000 0.0000

D.3.1.6 STEEL STRUCTURE WORK LOT 1.00 0.35324 0.0000 0.0000 0.0000

A Steel trusses of main building included. purlin, bracing, etc..

B Steel structure of metal fascia Kg 13,820.60 0.13523 0.0000 0.0000 0.0000 0.3828 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding
D Steel structure of canopy Kg 609.20 0.00596 0.0000 0.0000 0.0000 0.0169 0.0000 0.0000 0.0000
E Finishing paint to steel structure Kg 7,801.80 0.07634 0.0000 0.0000 0.0000 0.2161 0.0000 0.0000 0.0000
(synthetic enamel 60 micron) Kg 12,298.10 0.12033 0.0000 0.0000 0.0000 0.3407 0.0000 0.0000 0.0000
Kg 20,709.10 0.01537 0.0000 0.0000 0.0000 0.0435 0.0000 0.0000 0.0000

D.3.1.7 MISCELLANEOUS WORK LOT 1.00 0.02273 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 16.00 0.00051 0.0000 0.0000 0.0000 0.0225 0.0000 0.0000 0.0000
B Waterproofing coating to Pit m3 262.00 0.00836 0.0000 0.0000 0.0000 0.3679 0.0000 0.0000 0.0000
C Waterstop m 47.00 0.00416 0.0000 0.0000 0.0000 0.1832 0.0000 0.0000 0.0000
D Cat Ladder at Ground Water Tank ( U Type ) nos 36.00 0.00969 0.0000 0.0000 0.0000 0.4264 0.0000 0.0000 0.0000

D.3.2 FINISHING WORK 0.98757 0.0000 0.0000 0.0000

D.3.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 0.42084 0.0000 0.0000 0.0000

A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 1,144.00 0.09804 0.0000 0.0000 0.0000 0.2330 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 1,144.00 0.00919 0.0000 0.0000 0.0000 0.0218 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 1,144.00 0.00733 0.0000 0.0000 0.0000 0.0174 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 1,144.00 0.01073 0.0000 0.0000 0.0000 0.0255 0.0000 0.0000 0.0000
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 130.00 0.02124 0.0000 0.0000 0.0000 0.0505 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 140.00 0.00316 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 70.00 0.00158 0.0000 0.0000 0.0000 0.0037 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 70.00 0.00158 0.0000 0.0000 0.0000 0.0037 0.0000 0.0000 0.0000
I High Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 55.00 0.00369 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
J End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 15.00 0.00084 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
K Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 50.00 0.00281 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
L Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 70.00 0.00232 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
M FRP Flashing. W=305mm , zincalume Thk 0.5mm (Tct) m 260.00 0.01058 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
N Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 70.00 0.00563 0.0000 0.0000 0.0000 0.0134 0.0000 0.0000 0.0000
O Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 70.00 0.00285 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
P End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 70.00 0.00285 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
Q Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 4.00 0.00016 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000
R Eaves FRP Gutter , Grey Thk 3.0mm , W=1.050mm m 55.00 0.01090 0.0000 0.0000 0.0000 0.0259 0.0000 0.0000 0.0000
S Gutter Bracket SP 3x42 mm, W=1.250mm pcs 86.00 0.00288 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
T PVC Pipe AW Grey Dia. 150mm m 90.00 0.00675 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
U PVC Lbow 450 / 900 , Dia. 150mm pcs 24.00 0.00180 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000
V Clamp pipe Sp. 3x42mm , Dia. 150mm pcs 96.00 0.00257 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
W Eaves FRP Gutter , Grey Thk 3.0mm , W=650mm m 15.00 0.00185 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
X Gutter Bracket SP 3x42 mm, W=850mm pcs 24.00 0.00055 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
Y PVC Pipe AW Grey Dia. 100mm m 8.00 0.00034 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
Z PVC Lbow 450 / 900 , Dia. 100mm pcs 8.00 0.00034 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
AA Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 10.00 0.00019 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 1,811.00 0.14555 0.0000 0.0000 0.0000 0.3459 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 120.00 0.00488 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 138.00 0.00562 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 65.00 0.00264 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 400.00 0.03002 0.0000 0.0000 0.0000 0.0713 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 120.00 0.00675 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 40.00 0.00750 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 82.00 0.00264 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 30.00 0.00129 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 16.00 0.00069 0.0000 0.0000 0.0000 0.0016 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 32.00 0.00051 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000

D.3.2.2 MASONRY WORK LOT 1.00 0.04568 0.0000 0.0000 0.0000

A Common brick wall m2 247.00 0.01635 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B Ventilation block wall m2 -
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 3.70 0.00156 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 593.00 0.00336 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 49.40 0.00287 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 494.00 0.02154 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.3.2.3 TILING WORK LOT 1.00 0.00356 0.0000 0.0000 0.0000


Floor Finish
A Ceramic Tile 200 x 200 mm m2 14.10 0.00112 0.0000 0.0000 0.0000 0.3156 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 6.00 0.00050 0.0000 0.0000 0.0000 0.1409 0.0000 0.0000 0.0000
Wall Finish
C Ceramic Tile 200 x 200 mm m2 23.80 0.00194 0.0000 0.0000 0.0000 0.5435 0.0000 0.0000 0.0000

D.3.2.4 DOOR AND WINDOW WORK LOT 1.00 0.33186 0.0000 0.0000 0.0000

DOORS
A Motorized steel roll-up shutter (SS -1) nos 2.00 0.09249 0.0000 0.0000 0.0000 0.2787 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)
B Ditto. but to size : 10.000mm (W) x 7.200mm (H) (SS-2) nos 2.00 0.17326 0.0000 0.0000 0.0000 0.5221 0.0000 0.0000 0.0000

C Steel single swinging flush door (SD-1) nos 3.00 0.00663 0.0000 0.0000 0.0000 0.0200 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm
D Steel double swinging flush door (SD-2) nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.000mm (H)

E Wooden single swing door w/ vision glass (WD-1) nos 1.00 0.00219 0.0000 0.0000 0.0000 0.0066 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm (H)
F Ditto. but to size : 800mm (W) x 2.100mm (H) (WD-3) nos 1.00 0.00195 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
G Wooden double swing door w/ vision glass (WD-2) nos 1.00 0.00276 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)

H Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.00922 0.0000 0.0000 0.0000 0.0278 0.0000 0.0000 0.0000

WINDOWS
A Aluminium top hinge + fix glass window (AW-1) nos 2.00 0.00367 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
size : 1.700mm (W) x 900mm
B Aluminium Louver (AG-1) nos 4.00 0.03375 0.0000 0.0000 0.0000 0.1017 0.0000 0.0000 0.0000
size : 2.700mm (W) x 2.800mm
C Ditto. but to size : 1.700mm (W) x 900mm (H) (AG-2) nos 1.00 0.00171 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000

D.3.2.5 PAINTING WORK LOT 1.00 0.06056 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 185.00 0.00373 0.0000 0.0000 0.0000 0.0616 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 15
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Acrylic Emulsion Paint (AEP) to internal wall m2 312.00 0.00358 0.0000 0.0000 0.0000 0.0591 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 20.00 0.00023 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 482.00 0.00875 0.0000 0.0000 0.0000 0.1445 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 23.00 0.00016 0.0000 0.0000 0.0000 0.0026 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 1,080.00 0.04366 0.0000 0.0000 0.0000 0.7209 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 27.00 0.00045 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000

D.3.2.6 INTERIOR FINISHING WORK LOT 1.00 0.00805 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 1,107.00 0.00351 0.0000 0.0000 0.0000 0.4362 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 24.00 0.00026 0.0000 0.0000 0.0000 0.0318 0.0000 0.0000 0.0000
C Mortar Base w/ Epoxy Paint H=100mm m 14.60 0.00019 0.0000 0.0000 0.0000 0.0231 0.0000 0.0000 0.0000

Wall Finish
D Drywall Partition Gypsum Board (1side) m2 21.50 0.00175 0.0000 0.0000 0.0000 0.2177 0.0000 0.0000 0.0000
E Extra steel chanel to ditto kg 64.50 0.00063 0.0000 0.0000 0.0000 0.0784 0.0000 0.0000 0.0000

Ceiling Finish
F Gypsum Board (Flat) T=9mm w/ LGS Frame m2 14.10 0.00072 0.0000 0.0000 0.0000 0.0894 0.0000 0.0000 0.0000
G Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 6.00 0.00040 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
H Extra steel chanel to ditto kg 60.30 0.00059 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000

D.3.2.7 WATERPROOFING WORK LOT 1.00 0.00068 0.0000 0.0000 0.0000

A Groove w/ fill polyurethane sealent (15w x 15d) m 29.00 0.00068 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.3.2.8 MISCELLANEOUS WORK LOT 1.00 0.11634 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 16.00 0.00510 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 20.00 0.00185 0.0000 0.0000 0.0000 0.0159 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 18.500 mm unit 1.00 0.02551 0.0000 0.0000 0.0000 0.2193 0.0000 0.0000 0.0000
D S/S Insect Net to Ventilation m2 31.80 0.00789 0.0000 0.0000 0.0000 0.0678 0.0000 0.0000 0.0000
E Room name plate nos 3.00 0.00090 0.0000 0.0000 0.0000 0.0078 0.0000 0.0000 0.0000
F Wooden Casing to aluminium window m 10.40 0.00048 0.0000 0.0000 0.0000 0.0041 0.0000 0.0000 0.0000
G Grating cover 600mm m 54.00 0.07461 0.0000 0.0000 0.0000 0.6413 0.0000 0.0000 0.0000

D.4 EXCAVATOR PAINT FACTORY 13.53542 0.0000 0.0000 0.0000

D.4.1 STRUCTURE WORK LOT 1.00 8.63500 0.0000 0.0000 0.0000

D.4.1.1 EARTH WORK LOT 1.00 0.70617 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 9,400.00 0.02981 0.0000 0.0000 0.0000 0.0422 0.0000 0.0000 0.0000
site of all debris
B Excavation to ground slab m3 6,516.70 0.07740 0.0000 0.0000 0.0000 0.1096 0.0000 0.0000 0.0000
C Excavation to pile cap & g.beam m3 1,952.00 0.03385 0.0000 0.0000 0.0000 0.0479 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 662.00 0.00844 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
E Compacted sub grade m2 9,997.00 0.01821 0.0000 0.0000 0.0000 0.0258 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 7,806.00 0.12748 0.0000 0.0000 0.0000 0.1805 0.0000 0.0000 0.0000
G T=50mm comp. sand bedding m2 2,499.00 0.02175 0.0000 0.0000 0.0000 0.0308 0.0000 0.0000 0.0000
H T=150mm comp. basecourse m2 182.10 0.00375 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2 7,498.00 0.20189 0.0000 0.0000 0.0000 0.2859 0.0000 0.0000 0.0000
J Plastic Sheet m2 7,498.00 0.01872 0.0000 0.0000 0.0000 0.0265 0.0000 0.0000 0.0000
K Back fill and compac. w/ Imported Red Soil m3 3,577.00 0.16486 0.0000 0.0000 0.0000 0.2335 0.0000 0.0000 0.0000

D.4.1.2 PILING WORK LOT 1.00 0.71149 0.0000 0.0000 0.0000

DRIVING PILE WORK


A Allow for mobilization and demobilization of all
pilling plant and equipment
- Mob & Demob pilling equipment unit 2.00 0.02551 0.0000 0.0000 0.0000 0.0359 0.0000 0.0000 0.0000
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.0000 0.0000 0.0179 0.0000 0.0000 0.0000
B PC Spun Pile Ø 300 mm , L=16m nos 228.00 0.34507 0.0000 0.0000 0.0000 0.4850 0.0000 0.0000 0.0000
C Driving Pile m 3,648.00 0.10339 0.0000 0.0000 0.0000 0.1453 0.0000 0.0000 0.0000
D Welding Joint nos 228.00 0.01454 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 228.00 0.00566 0.0000 0.0000 0.0000 0.0080 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

PRESS PILE WORK


G Allow for mobilization and demobilization of all unit 1.00 0.00921 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
pilling plant and equipment
H PC Square Pile 250x250 mm , L=20m (Assume) nos 59.00 0.12709 0.0000 0.0000 0.0000 0.1786 0.0000 0.0000 0.0000
I Driving Pile w/ Jacking system m 1,180.00 0.04603 0.0000 0.0000 0.0000 0.0647 0.0000 0.0000 0.0000
J Welding Joint nos 59.00 0.00376 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
K Cut off excess pile length at required level & expose nos 59.00 0.00147 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
L PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

D.4.1.3 CONCRETE WORK LOT 1.00 1.45725 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 2,245.70 0.06138 0.0000 0.0000 0.0000 0.0421 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 184.50 0.08700 0.0000 0.0000 0.0000 0.0597 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 93.20 0.04395 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 1,784.00 0.84127 0.0000 0.0000 0.0000 0.5773 0.0000 0.0000 0.0000
E Ditto, but to Column m3 213.40 0.10063 0.0000 0.0000 0.0000 0.0691 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m3 28.30 0.01335 0.0000 0.0000 0.0000 0.0092 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m3 77.70 0.03664 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab m3 4.50 0.00212 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I Ditto, but to Parapet m3 2.20 0.00104 0.0000 0.0000 0.0000 0.0007 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter m3 17.50 0.00825 0.0000 0.0000 0.0000 0.0057 0.0000 0.0000 0.0000
K Ditto, but to Pit m3 514.80 0.24276 0.0000 0.0000 0.0000 0.1666 0.0000 0.0000 0.0000
L Ditto, but to Recovery Slab m3 40.00 0.01886 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000

D.4.1.4 REINFORCED WORK LOT 1.00 1.83951 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 23,354.00 0.13238 0.0000 0.0000 0.0000 0.0720 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 13,402.00 0.07597 0.0000 0.0000 0.0000 0.0413 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab Kg 3,595.00 0.02038 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
D Ditto, but to Column kg 50,640.00 0.28705 0.0000 0.0000 0.0000 0.1560 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam kg 3,780.00 0.02143 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam kg 10,733.00 0.06084 0.0000 0.0000 0.0000 0.0331 0.0000 0.0000 0.0000
G Ditto, but to Roof Slab kg 556.00 0.00315 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
H Ditto, but to Parapet kg 254.00 0.00144 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter kg 5,274.00 0.02990 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
J Ditto, but to Pit kg 82,360.00 0.46685 0.0000 0.0000 0.0000 0.2538 0.0000 0.0000 0.0000
K Ditto, but to Recovery Slab kg 3,595.00 0.02038 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
L Wiremesh #M8 to ground slab (2 layer) m2 8,721.00 0.71974 0.0000 0.0000 0.0000 0.3913 0.0000 0.0000 0.0000

D.4.1.5 FORM WORK LOT 1.00 0.32842 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 688.50 0.04000 0.0000 0.0000 0.0000 0.1218 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 621.10 0.03609 0.0000 0.0000 0.0000 0.1099 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 16
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
C Ditto , but to Ground Slab m2 165.40 0.00961 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
D Ditto, but to Column m2 1,658.00 0.09633 0.0000 0.0000 0.0000 0.2933 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam m2 228.30 0.01454 0.0000 0.0000 0.0000 0.0443 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam m2 607.20 0.03868 0.0000 0.0000 0.0000 0.1178 0.0000 0.0000 0.0000
G Ditto, but to Roof Slab m2 33.30 0.00212 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
H Ditto, but to Parapet m2 25.30 0.00161 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter m2 231.40 0.01474 0.0000 0.0000 0.0000 0.0449 0.0000 0.0000 0.0000
J Ditto, but to Pit m2 605.30 0.03856 0.0000 0.0000 0.0000 0.1174 0.0000 0.0000 0.0000
K Ditto, but to Recovery Slab m2 0.00000
L Supporting formwork to above m2 3,388.80 0.03613 0.0000 0.0000 0.0000 0.1100 0.0000 0.0000 0.0000

D.4.1.6 STEEL STRUCTURE WORK LOT 1.00 3.53723 0.0000 0.0000 0.0000

A Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 317,897.90 3.11058 0.0000 0.0000 0.0000 0.8794 0.0000 0.0000 0.0000
B Steel structure of metal fascia Kg 0.00 0.00000
C Steel structure of metal wall cladding Kg 15,889.90 0.15548 0.0000 0.0000 0.0000 0.0440 0.0000 0.0000 0.0000
D Steel structure of gutter support Kg 7,497.20 0.07336 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
E Steel structure of add. metal wall Kg 18,441.70 0.18045 0.0000 0.0000 0.0000 0.0510 0.0000 0.0000 0.0000
F Finishing paint to steel structure Kg 23,387.10 0.01736 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.4.1.7 MISCELLANEOUS WORK LOT 1.00 0.05494 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 51.00 0.00163 0.0000 0.0000 0.0000 0.0296 0.0000 0.0000 0.0000
B Expansion joint to existing slab :
- Sand asphalt fill m 1,240.00 0.02418 0.0000 0.0000 0.0000 0.4402 0.0000 0.0000 0.0000
- Dowel rebar kg 4,568.00 0.02589 0.0000 0.0000 0.0000 0.4713 0.0000 0.0000 0.0000
- Flexible pipe m 1,654.00 0.00324 0.0000 0.0000 0.0000 0.0589 0.0000 0.0000 0.0000

D.4.2 FINISHING WORK 4.90042 0.0000 0.0000 0.0000

D.4.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 2.35276 0.0000 0.0000 0.0000

Metal Roofing Excavator Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 7,956.00 0.68184 0.0000 0.0000 0.0000 0.2898 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 7,956.00 0.06389 0.0000 0.0000 0.0000 0.0272 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 7,956.00 0.05100 0.0000 0.0000 0.0000 0.0217 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 546.00 0.08920 0.0000 0.0000 0.0000 0.0379 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 348.00 0.00784 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 250.00 0.00563 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 151.00 0.00340 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 87.00 0.00583 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
J End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 76.00 0.00428 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
K Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 193.00 0.01086 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
L Nagare Flashing. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 148.00 0.00833 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
M Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 158.00 0.00525 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
N FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 1,092.00 0.04444 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
O Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
P Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
Q End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
R Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
S Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 181.00 0.04073 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
T Gutter Bracket SP 3x42 mm, W=1.400mm pcs 280.00 0.01051 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
U PVC Pipe AW Grey Dia. 200mm m 185.00 0.02478 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
V PVC Lbow 450 / 900 , Dia. 200mm pcs 58.00 0.00777 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
W Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 203.00 0.00653 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
X Eaves FRP Gutter , Grey Thk 3.0mm , W=600mm m 68.00 0.00729 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
Y Gutter Bracket SP 3x42 mm, W=800mm pcs 105.00 0.00225 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
Z PVC Pipe AW Grey Dia. 100mm m 18.00 0.00077 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
AA PVC Lbow 450 / 900 , Dia. 100mm pcs 16.00 0.00069 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
AB Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 20.00 0.00038 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 2,723.00 0.21885 0.0000 0.0000 0.0000 0.0930 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 366.30 0.01491 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 266.80 0.01086 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 48.00 0.00195 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

Utility & Plant Room Roofing


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 1,037.00 0.07782 0.0000 0.0000 0.0000 0.0331 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 146.00 0.00822 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 82.00 0.01538 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 165.00 0.00531 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 80.00 0.00343 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 48.00 0.00206 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 90.00 0.00145 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 338.00 0.02536 0.0000 0.0000 0.0000 0.0108 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 75.00 0.00422 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 23.00 0.00431 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 46.00 0.00148 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 10.00 0.00043 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 4.00 0.00017 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 10.00 0.00016 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000

carried forward 1.47985

brought forward 1.47985 0.0000 0.0000 0.0000

METAL ROOFING & METAL WALL WORK

Roof -1 Area
A Roofing Corrugated Steel Sheet Thk. 0,5mm (Tct), H=30mm U750 m2 1,746.00 0.11794 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 1,746.00 0.01402 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 1,746.00 0.01119 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 192.00 0.03137 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 360.00 0.00811 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 180.00 0.00406 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 158.00 0.00356 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 180.00 0.01013 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000
J Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 158.00 0.00525 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
K FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 384.00 0.01563 0.0000 0.0000 0.0000 0.0066 0.0000 0.0000 0.0000
L Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
M Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
N End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
O Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
P Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 158.00 0.02963 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000
Q Gutter Bracket Sp 3x42mm W=1.200mm pcs 246.00 0.00792 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
R PVC Pipe AW Grey Dia. 100mm m 135.00 0.00578 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
S PVC Lbow 450 / 900 , Dia. 100mm pcs 60.00 0.00257 0.0000 0.0000 0.0000 0.0011 0.0000 0.0000 0.0000
T Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 135.00 0.00217 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000

Roof - 2 Area
A Roofing Zinc Alume SF-750 (55mm), Thk. 0,5mm (Tct) m2 3,651.00 0.30575 0.0000 0.0000 0.0000 0.1300 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 17
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Roof mesh, Galvanized #3x3" m2 3,651.00 0.02932 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 3,651.00 0.02341 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00000 -
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 295.00 0.04820 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 320.00 0.00721 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 160.00 0.00361 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 160.00 0.00361 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 95.00 0.00637 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
J Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 60.00 0.00338 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
K Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 160.00 0.00531 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
L FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 590.00 0.02401 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
M Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
N Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
O End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
P Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
Q Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 160.00 0.03601 0.0000 0.0000 0.0000 0.0153 0.0000 0.0000 0.0000
R Gutter Bracket SP 3x42 mm, W=1.400mm pcs 250.00 0.00938 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000
S PVC Pipe AW Grey Dia. 200mm m 130.00 0.01741 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
T PVC Lbow 450 / 900 , Dia. 200mm pcs 40.00 0.00536 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
U Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 130.00 0.00418 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000

New Down Metal Wall


A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 777.50 0.06249 0.0000 0.0000 0.0000 0.0266 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 190.00 0.00773 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
C Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000

D.4.2.2 MASONRY WORK LOT 1.00 0.51955 0.0000 0.0000 0.0000

A Common brick wall m2 2,809.40 0.18598 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B Ventilation block wall m2 0.00000
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 42.10 0.01776 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 6,743.00 0.03822 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 561.90 0.03265 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 5,618.80 0.24494 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.4.2.3 TILING WORK LOT 1.00 0.01146 0.0000 0.0000 0.0000

Floor Finish
A Ceramic Tile 200 x 200 mm m2 21.00 0.00167 0.0000 0.0000 0.0000 0.1460 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 74.00 0.00619 0.0000 0.0000 0.0000 0.5397 0.0000 0.0000 0.0000
Wall Finish
C Ceramic Tile 200 x 200 mm m2 44.30 0.00360 0.0000 0.0000 0.0000 0.3143 0.0000 0.0000 0.0000

D.4.2.4 DOOR AND WINDOW WORK LOT 1.00 0.93405 0.0000 0.0000 0.0000

DOORS
A Motorized steel roll-up shutter (SS -1) nos 5.00 0.23122 0.0000 0.0000 0.0000 0.2475 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)
B Ditto. but to size : 6.000mm (W) x 5.000mm (H) (SD-3) nos 1.00 0.04046 0.0000 0.0000 0.0000 0.0433 0.0000 0.0000 0.0000

C High speed shutter (HSS -1) nos 1.00 0.17649 0.0000 0.0000 0.0000 0.1890 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)

D Steel double hanging sliding door w/ FRP Panel (SD-1) nos 3.00 0.25225 0.0000 0.0000 0.0000 0.2701 0.0000 0.0000 0.0000
size : 10.000mm (W) x 6.000mm (H)
E Steel double swinging flush louver door (SD-3) nos 4.00 0.03247 0.0000 0.0000 0.0000 0.0348 0.0000 0.0000 0.0000
size : 1.800mm (W) x 2.500mm (H)
F Steel single swinging flush door (SD-6) nos 4.00 0.00883 0.0000 0.0000 0.0000 0.0095 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm

G Wooden double swing door (WD-1) nos 2.00 0.00687 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.100mm (H)
H Wooden single swing door w/ vision glass (WD-2) nos 7.00 0.01366 0.0000 0.0000 0.0000 0.0146 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)

I Toilet booth nos 0.00000


size : 600mm (W) x 2.000mm (H)

J Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.02448 0.0000 0.0000 0.0000 0.0262 0.0000 0.0000 0.0000

WINDOWS
A Aluminium Louver (AG-1) nos 4.00 0.14731 0.0000 0.0000 0.0000 0.1577 0.0000 0.0000 0.0000
size : 20.000mm (W) x 1.650mm

D.4.2.5 PAINTING WORK LOT 1.00 0.23823 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 1,460.00 0.02946 0.0000 0.0000 0.0000 0.1237 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 3,923.00 0.04500 0.0000 0.0000 0.0000 0.1889 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 202.50 0.00232 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 950.20 0.01725 0.0000 0.0000 0.0000 0.0724 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 373.00 0.00252 0.0000 0.0000 0.0000 0.0106 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 0.00 0.00000 -
G Floor Hardener Natural Color to Floor m2 8,432.00 0.14168 0.0000 0.0000 0.0000 0.5947 0.0000 0.0000 0.0000

D.4.2.6 INTERIOR FINISHING WORK LOT 1.00 0.04468 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 8,432.00 0.02674 0.0000 0.0000 0.0000 0.5985 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 208.00 0.00222 0.0000 0.0000 0.0000 0.0496 0.0000 0.0000 0.0000
C Mortar Base w/ Epoxy Paint H=100mm m 49.00 0.00062 0.0000 0.0000 0.0000 0.0140 0.0000 0.0000 0.0000

Wall Finish
D Styrene Resin Board T=25mm m2 0.00000 -

Ceiling Finish
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 73.50 0.00375 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 21.00 0.00141 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 283.50 0.00277 0.0000 0.0000 0.0000 0.0621 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 108.00 0.00161 0.0000 0.0000 0.0000 0.0360 0.0000 0.0000 0.0000
I Styrene Resin Board T=25mm m2 54.00 0.00555 0.0000 0.0000 0.0000 0.1242 0.0000 0.0000 0.0000

D.4.2.7 WATERPROOFING WORK LOT 1.00 0.01696 0.0000 0.0000 0.0000

A Waterproofing membrane m2 63.00 0.00380 0.0000 0.0000 0.0000 0.2238 0.0000 0.0000 0.0000
B Protection concrete 50 mm to waterproofing membrane m2 54.00 0.00400 0.0000 0.0000 0.0000 0.2359 0.0000 0.0000 0.0000
C Protection brick w/ plaster 1 side m2 12.00 0.00132 0.0000 0.0000 0.0000 0.0777 0.0000 0.0000 0.0000
D Groove w/ fill polyurethane sealent (15w x 15d) m 335.00 0.00784 0.0000 0.0000 0.0000 0.4625 0.0000 0.0000 0.0000

D.4.2.8 MISCELLANEOUS WORK LOT 1.00 0.78272 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 36.00 0.01148 0.0000 0.0000 0.0000 0.0147 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 83.00 0.00767 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 16.000 mm unit 1.00 0.02211 0.0000 0.0000 0.0000 0.0282 0.0000 0.0000 0.0000
D Insect Net to Ventilation m2 132.00 0.03274 0.0000 0.0000 0.0000 0.0418 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 18
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
E Lavatory concrete table w/ top marble finish
- Size : 2.000mm (L) x 600mm (W) unit 1.00 0.00213 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
F Wall mirror at toilet :
- Size : 2.000mm (L) x 1.000mm (H) unit 1.00 0.00135 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
G Toilet Partition w/ Door m2 12.00 0.01190 0.0000 0.0000 0.0000 0.0152 0.0000 0.0000 0.0000
H Room name plate nos 8.00 0.00241 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
I Steel Grating W = 4.000mm m2 588.00 0.68744 0.0000 0.0000 0.0000 0.8783 0.0000 0.0000 0.0000
J PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 16.00 0.00300 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
K Cast iron roof drain nos 2.00 0.00050 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

D.5 TOUCHUP PAINT BOOTH 0.73952 0.0000 0.0000 0.0000

D.5.1 STRUCTURE WORK LOT 1.00 0.54630 0.0000 0.0000 0.0000 0.0000

D.5.1.1 EARTH WORK LOT 1.00 0.01521 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 330.00 0.00105 0.0000 0.0000 0.0000 0.0688 0.0000 0.0000 0.0000
site of all debris
B Excavation to pit m3 84.10 0.00100 0.0000 0.0000 0.0000 0.0657 0.0000 0.0000 0.0000
C Excavation to ground slab m3 244.40 0.00290 0.0000 0.0000 0.0000 0.1908 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 35.00 0.00061 0.0000 0.0000 0.0000 0.0399 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 83.80 0.00107 0.0000 0.0000 0.0000 0.0703 0.0000 0.0000 0.0000
F Compacted sub grade m2 362.30 0.00066 0.0000 0.0000 0.0000 0.0434 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 279.80 0.00457 0.0000 0.0000 0.0000 0.3004 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 339.70 0.00296 0.0000 0.0000 0.0000 0.1944 0.0000 0.0000 0.0000
I T=100mm comp. sand bedding m2 22.60 0.00040 0.0000 0.0000 0.0000 0.0264 0.0000 0.0000 0.0000
J T=250mm comp. basecourse m2

D.5.1.2 PILING WORK LOT 1.00 0.06592 0.0000 0.0000 0.0000

A PC Spun Pile Ø 300mm , L=16m nos 30.00 0.04540 0.0000 0.0000 0.0000 0.6888 0.0000 0.0000 0.0000
B Driving PC Spun Pile Ø 300mm m 480.00 0.01360 0.0000 0.0000 0.0000 0.2064 0.0000 0.0000 0.0000
C Welding Joint PC Spun Pile Ø 300mm nos 30.00 0.00191 0.0000 0.0000 0.0000 0.0290 0.0000 0.0000 0.0000
D Cut off excess pile length at required level & expose nos 30.00 0.00074 0.0000 0.0000 0.0000 0.0113 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
E PDA Test nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0645 0.0000 0.0000 0.0000

D.5.1.3 CONCRETE WORK LOT 1.00 0.10945 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 362.30 0.00990 0.0000 0.0000 0.0000 0.0905 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 4.10 0.00193 0.0000 0.0000 0.0000 0.0177 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 7.40 0.00349 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 82.70 0.03900 0.0000 0.0000 0.0000 0.3563 0.0000 0.0000 0.0000
E Ditto, but to Column m3 15.10 0.00712 0.0000 0.0000 0.0000 0.0651 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m3 7.40 0.00349 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m3 4.00 0.00189 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter m3 4.40 0.00207 0.0000 0.0000 0.0000 0.0190 0.0000 0.0000 0.0000
I Ditto, but to Pit m3 86.00 0.04055 0.0000 0.0000 0.0000 0.3705 0.0000 0.0000 0.0000

D.5.1.4 REINFORCED WORK LOT 1.00 0.13468 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 594.00 0.00337 0.0000 0.0000 0.0000 0.0250 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 1,072.00 0.00608 0.0000 0.0000 0.0000 0.0451 0.0000 0.0000 0.0000
C Ditto, but to Column kg 4,062.00 0.02303 0.0000 0.0000 0.0000 0.1710 0.0000 0.0000 0.0000
D Ditto, but to Middle Beam kg 1,049.00 0.00595 0.0000 0.0000 0.0000 0.0442 0.0000 0.0000 0.0000
E Ditto, but to Roof Beam kg 552.00 0.00313 0.0000 0.0000 0.0000 0.0232 0.0000 0.0000 0.0000
F Ditto, but to Column & Beam Shutter kg 1,292.00 0.00732 0.0000 0.0000 0.0000 0.0544 0.0000 0.0000 0.0000
G Ditto, but to Pit kg 10,319.00 0.05849 0.0000 0.0000 0.0000 0.4343 0.0000 0.0000 0.0000
H Wiremesh #M8 to ground slab (2 layer) m2 331.00 0.02732 0.0000 0.0000 0.0000 0.2028 0.0000 0.0000 0.0000

D.5.1.5 FORM WORK LOT 1.00 0.05795 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 21.90 0.00127 0.0000 0.0000 0.0000 0.0220 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 49.00 0.00285 0.0000 0.0000 0.0000 0.0491 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 26.00 0.00151 0.0000 0.0000 0.0000 0.0261 0.0000 0.0000 0.0000
D Ditto, but to Column m2 133.80 0.00852 0.0000 0.0000 0.0000 0.1471 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam m2 61.50 0.00392 0.0000 0.0000 0.0000 0.0676 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam m2 33.60 0.00214 0.0000 0.0000 0.0000 0.0369 0.0000 0.0000 0.0000
G Ditto, but to Column & Beam Shutter m2 57.60 0.00367 0.0000 0.0000 0.0000 0.0633 0.0000 0.0000 0.0000
H Ditto, but to Pit m2 451.00 0.02620 0.0000 0.0000 0.0000 0.4522 0.0000 0.0000 0.0000
I Supporting formwork to above m2 737.50 0.00786 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000

D.5.1.6 STEEL STRUCTURE WORK LOT 1.00 0.13929 0.0000 0.0000 0.0000

A Steel trusses of main building included. purlin, bracing, etc.. Kg 9,979.00 0.09764 0.0000 0.0000 0.0000 0.7010 0.0000 0.0000 0.0000

B Steel structure of metal wall cladding Kg 2,610.00 0.02554 0.0000 0.0000 0.0000 0.1833 0.0000 0.0000 0.0000
C Finishing paint to steel structure Kg 2,610.00 0.00194 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)
D Relocation & Re-install Steel Plate Lot 1.00 0.01417 0.0000 0.0000 0.0000 0.1017 0.0000 0.0000 0.0000

D.5.1.7 MISCELLANEOUS WORK LOT 1.00 0.02380 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 6.00 0.00019 0.0000 0.0000 0.0000 0.0080 0.0000 0.0000 0.0000
B Waterproofing coating to Ground water tank m2 168.30 0.00537 0.0000 0.0000 0.0000 0.2257 0.0000 0.0000 0.0000
C Waterstop m 135.00 0.01196 0.0000 0.0000 0.0000 0.5025 0.0000 0.0000 0.0000
D Expansion joint to existing slab :
- Sand asphalt fill m 20.50 0.00040 0.0000 0.0000 0.0000 0.0168 0.0000 0.0000 0.0000
- Dowel rebar kg 76.00 0.00043 0.0000 0.0000 0.0000 0.0181 0.0000 0.0000 0.0000
- Flexible pipe m 27.00 0.00005 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
E Edge Protector L 50x50x5 kg 95.00 0.00093 0.0000 0.0000 0.0000 0.0391 0.0000 0.0000 0.0000
F Chemical Anchor to extension joint nos 36.00 0.00447 0.0000 0.0000 0.0000 0.1876 0.0000 0.0000 0.0000

D.5.2 FINISHING WORK LOT 1.00 0.19323 0.0000 0.0000 0.0000

D.5.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 0.08387 0.0000 0.0000 0.0000

Metal Roofing Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 256.00 0.02194 0.0000 0.0000 0.0000 0.2616 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 256.00 0.00206 0.0000 0.0000 0.0000 0.0245 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 256.00 0.00164 0.0000 0.0000 0.0000 0.0196 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 22.00 0.00359 0.0000 0.0000 0.0000 0.0429 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 50.00 0.00113 0.0000 0.0000 0.0000 0.0134 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 25.00 0.00056 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 25.00 0.00056 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 13.00 0.00087 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
J Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 22.00 0.00124 0.0000 0.0000 0.0000 0.0148 0.0000 0.0000 0.0000
K Expansion Cover W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 22.00 0.00124 0.0000 0.0000 0.0000 0.0148 0.0000 0.0000 0.0000
L Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 25.00 0.00083 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
M FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 43.00 0.00175 0.0000 0.0000 0.0000 0.0209 0.0000 0.0000 0.0000
N Eaves Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 25.00 0.00469 0.0000 0.0000 0.0000 0.0559 0.0000 0.0000 0.0000
O Gutter Bracket Sp 3x42mm W=1.200mm pcs 40.00 0.00129 0.0000 0.0000 0.0000 0.0154 0.0000 0.0000 0.0000
P PVC Pipe AW Grey Dia. 150mm m 26.00 0.00195 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
Q PVC Lbow 450 / 900 , Dia. 150mm pcs 8.00 0.00060 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
R Clamp pipe Sp. 3x30mm , Dia. 150mm pcs 26.00 0.00070 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000

Metal Wall
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 19
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 404.00 0.03247 0.0000 0.0000 0.0000 0.3872 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 35.00 0.00142 0.0000 0.0000 0.0000 0.0170 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 40.00 0.00163 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
E Wall Expansion Cover W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000

D.5.2.2 MASONRY WORK LOT 1.00 0.00673 0.0000 0.0000 0.0000

A Common brick wall m2 35.00 0.00232 0.0000 0.0000 0.0000 0.3441 0.0000 0.0000 0.0000
B Ventilation block wall m2
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 0.70 0.00030 0.0000 0.0000 0.0000 0.0438 0.0000 0.0000 0.0000
- HT. Reinforcement kg 112.00 0.00063 0.0000 0.0000 0.0000 0.0943 0.0000 0.0000 0.0000
- Timber formwork m2 7.50 0.00044 0.0000 0.0000 0.0000 0.0647 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 70.00 0.00305 0.0000 0.0000 0.0000 0.4531 0.0000 0.0000 0.0000
w/ instant mortar

D.5.2.3 TILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

D.5.2.4 DOOR AND WINDOW WORK LOT 1.00 0.02267 0.0000 0.0000 0.0000

DOORS
A Relocation & Re-install Motorized steel roll-up shutter
size : 6.000mm (W) x 8.000mm (H) nos 2.00 0.02126 0.0000 0.0000 0.0000 0.9375 0.0000 0.0000 0.0000
B Ditto, but to Steel single door
nos 1.00 0.00142 0.0000 0.0000 0.0000 0.0625 0.0000 0.0000 0.0000

D.5.2.5 PAINTING WORK LOT 1.00 0.02494 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 35.00 0.00071 0.0000 0.0000 0.0000 0.0283 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 44.00 0.00050 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 202.00 0.00367 0.0000 0.0000 0.0000 0.1470 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 26.00 0.00018 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 492.00 0.01989 0.0000 0.0000 0.0000 0.7974 0.0000 0.0000 0.0000

D.5.2.6 INTERIOR FINISHING WORK LOT 1.00 0.00207 0.0000 0.0000 0.0000
Floor Finish
A Steel trowel finish m2 492.00 0.00156 0.0000 0.0000 0.0000 0.0626 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 48.00 0.00051 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

D.5.2.7 WATERPROOFING WORK LOT 1.00 0.00023 0.0000 0.0000 0.0000

A Groove w/ fill polyurethane sealent (15w x 15d) m 10.00 0.00023 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.5.2.8 MISCELLANEOUS WORK LOT 1.00 0.05270 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 8.00 0.00255 0.0000 0.0000 0.0000 0.0484 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 6.00 0.00055 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
C Steel Grating W = 1.000mm m 40.00 0.04960 0.0000 0.0000 0.0000 0.9411 0.0000 0.0000 0.0000

D.6 WASHING AREA 0.26212 0.0000 0.0000 0.0000

D.6.1 STRUCTURE WORK LOT 1.00 0.26212 0.0000 0.0000 0.0000

D.6.1.1 EARTH WORK LOT 1.00 0.00974 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 180.00 0.00057 0.0000 0.0000 0.0000 0.0586 0.0000 0.0000 0.0000
site of all debris
B Excavation to pit m3 185.30 0.00220 0.0000 0.0000 0.0000 0.2259 0.0000 0.0000 0.0000
C Excavation to ground slab m3 41.40 0.00049 0.0000 0.0000 0.0000 0.0505 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 68.50 0.00087 0.0000 0.0000 0.0000 0.0897 0.0000 0.0000 0.0000
E Compacted sub grade m2 113.60 0.00021 0.0000 0.0000 0.0000 0.0212 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 116.90 0.00191 0.0000 0.0000 0.0000 0.1959 0.0000 0.0000 0.0000
G T=50mm comp. sand bedding m2 49.60 0.00043 0.0000 0.0000 0.0000 0.0443 0.0000 0.0000 0.0000
H T=200mm comp. basecourse m2 113.60 0.00306 0.0000 0.0000 0.0000 0.3139 0.0000 0.0000 0.0000

D.6.1.2 PILING WORK LOT 1.00 0.00000

D.6.1.3 CONCRETE WORK LOT 1.00 0.02484 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 49.60 0.00136 0.0000 0.0000 0.0000 0.0546 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pit m3 36.30 0.01712 0.0000 0.0000 0.0000 0.6891 0.0000 0.0000 0.0000
C Ditto , but to RC Dike m3 13.50 0.00637 0.0000 0.0000 0.0000 0.2563 0.0000 0.0000 0.0000

D.6.1.4 REINFORCED WORK LOT 1.00 0.02346 0.0000 0.0000 0.0000

A HT. Reinforcement to Pit kg 3,921.00 0.02223 0.0000 0.0000 0.0000 0.9473 0.0000 0.0000 0.0000
B Ditto , but to RC Dike Kg 218.00 0.00124 0.0000 0.0000 0.0000 0.0527 0.0000 0.0000 0.0000

D.6.1.5 FORM WORK LOT 1.00 0.01655 0.0000 0.0000 0.0000

A Formwork to Pit m2 216.70 0.01259 0.0000 0.0000 0.0000 0.7607 0.0000 0.0000 0.0000
B Ditto , but to RC Dike m2 24.00 0.00139 0.0000 0.0000 0.0000 0.0842 0.0000 0.0000 0.0000
E Supporting formwork to above m2 240.70 0.00257 0.0000 0.0000 0.0000 0.1551 0.0000 0.0000 0.0000

D.6.1.6 STEEL STRUCTURE WORK LOT 1.00 0.06485 0.0000 0.0000 0.0000

A Steel Plate T=19mm m2 64.00 0.06485 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.6.1.7 MISCELLANEOUS WORK LOT 1.00 0.12268 0.0000 0.0000 0.0000

A Waterproofing coating anti acid to Pit m2 189.30 0.08718 0.0000 0.0000 0.0000 0.7107 0.0000 0.0000 0.0000
B Waterstop m 22.00 0.00273 0.0000 0.0000 0.0000 0.0222 0.0000 0.0000 0.0000
C Steel Angle L.40.40.5 w/ Galvanish Fin. m 80.00 0.00539 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000
D Pit Cover w/ Checker Plate Galvaized Fin. m2 15.10 0.01498 0.0000 0.0000 0.0000 0.1221 0.0000 0.0000 0.0000
E Steel Galv. Guard Rail, size : 1.900mm x 1.100mm (H) nos 4.00 0.00453 0.0000 0.0000 0.0000 0.0370 0.0000 0.0000 0.0000
F Steel Galv. Guard Rail, size : 2.600mm x 1.100mm (H) nos 2.00 0.00312 0.0000 0.0000 0.0000 0.0254 0.0000 0.0000 0.0000
G Steel Guard Post H = 1.100mm w/ S.S chain & hock nos 2.00 0.00475 0.0000 0.0000 0.0000 0.0387 0.0000 0.0000 0.0000

E. MECHANICAL WORK LOT 1.00 12.03803 12.03803 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
E.1 TRAINING CENTER & HEAD OFFICE
E.2 ULTRA LARGE COMPONENT FACT-2
E.3 ULTRA LARGE TOPCOAT PAINTING BOOTH
E.4 EXCAVATOR PAINT FACTORY
E.5 TOUCHUP PAINT BOOTH
E.6 WASHING AREA

F. ELECTRICAL WORK LOT 1.00 14.64834 14.64834 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
F.1 TRAINING CENTER & HEAD OFFICE
F.2 ULTRA LARGE COMPONENT FACT-2
F.3 ULTRA LARGE TOPCOAT PAINTING BOOTH
F.4 EXCAVATOR PAINT FACTORY
F.5 TOUCHUP PAINT BOOTH
F.6 WASHING AREA

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 20
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
G. EXTERNAL WORK LOT 1.00 11.33154 11.33154 0.0000 0.0000 0.0000 1.0000 3.0580 0.0000 3.0580
0.0000
G.1 CIVIL WORK LOT 1.00 9.57299 3.0580 0.0000 3.0580

G.1.1 TRAINING CENTER & HEAD OFFICE AREA LOT 1.00 0.98023 0.0000 0.0000 0.0000

G.1.1.1 PAVING WORK LOT 1.00 0.69379 0.0000 0.0000 0.0000

A Asphalt Pavement
- Excavation Soil m3 1,600.90 0.01901 0.0000 0.0000 0.0000 0.0274 0.0000 0.0000 0.0000
- Disposed excavated material m3 1,600.90 0.02614 0.0000 0.0000 0.0000 0.0377 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 3,335.20 0.00608 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 3,335.20 0.06864 0.0000 0.0000 0.0000 0.0989 0.0000 0.0000 0.0000
- T=250mm Limestone m2 3,335.20 0.09228 0.0000 0.0000 0.0000 0.1330 0.0000 0.0000 0.0000
- Prime coat m2 3,335.20 0.01846 0.0000 0.0000 0.0000 0.0266 0.0000 0.0000 0.0000
- ATB 50 mm thick m3 3,335.20 0.22034 0.0000 0.0000 0.0000 0.3176 0.0000 0.0000 0.0000
- Wearing course 30mm thick m2 3,335.20 0.14337 0.0000 0.0000 0.0000 0.2066 0.0000 0.0000 0.0000
- Teack Coat m2 3,335.20 0.01238 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000

B Paving Block
- Excavate over site to formation level including m2 467.00 0.00148 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
cleaning site of all debris (D=100mm)
- Excavation Work m3 121.42 0.00211 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
- Disposal Soil m3 121.42 0.00198 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000
- Comp. Sub grade m2 467.00 0.00085 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
- T=150mm Base course m2 467.00 0.00961 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
- Compacted sand bed T=50mm m2 467.00 0.00407 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
- Paving Block 60mm thick m2 467.00 0.02152 0.0000 0.0000 0.0000 0.0310 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 492.00 0.04402 0.0000 0.0000 0.0000 0.0635 0.0000 0.0000 0.0000

D Boundary Concrete Curb m 18.00 0.00145 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000

G.1.1.2 DRAINAGE WORK LOT 1.00 0.24656 0.0000 0.0000 0.0000


A Open Drainage
- Excavation Soil m3 607.00 0.01053 0.0000 0.0000 0.0000 0.0427 0.0000 0.0000 0.0000
- Disposed excavated material m3 272.00 0.00444 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 335.00 0.00427 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 258.80 0.00047 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 258.80 0.00533 0.0000 0.0000 0.0000 0.0216 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 258.80 0.00707 0.0000 0.0000 0.0000 0.0287 0.0000 0.0000 0.0000
- River stone m3 224.00 0.07142 0.0000 0.0000 0.0000 0.2897 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 569.30 0.01471 0.0000 0.0000 0.0000 0.0597 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 20.70 0.00976 0.0000 0.0000 0.0000 0.0396 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,970.00 0.01117 0.0000 0.0000 0.0000 0.0453 0.0000 0.0000 0.0000
- Formwork m2 207.00 0.01203 0.0000 0.0000 0.0000 0.0488 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 344.90 0.00598 0.0000 0.0000 0.0000 0.0243 0.0000 0.0000 0.0000
- Disposed excavated material m3 153.30 0.00250 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 191.60 0.00244 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 87.60 0.00016 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

carried forward 0.16229

brought forward 0.16229 0.0000 0.0000 0.0000

B RC Culvert
- Sub base course 150mm thick m2 87.60 0.00180 0.0000 0.0000 0.0000 0.0073 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 87.60 0.00239 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 52.60 0.02480 0.0000 0.0000 0.0000 0.1006 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 6,307.00 0.03575 0.0000 0.0000 0.0000 0.1450 0.0000 0.0000 0.0000
- Formwork m2 335.80 0.01951 0.0000 0.0000 0.0000 0.0791 0.0000 0.0000 0.0000

G.1.1.3 LANDSCAPE WORK LOT 1.00 0.01296 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 1,178.00 0.00874 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 1,178.00 0.00421 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.1.4 MISCELLANEOUS WORK LOT 1.00 0.02693 0.0000 0.0000 0.0000

A Parking Line (White Paint) m 433.00 0.00567 0.0000 0.0000 0.0000 0.2105 0.0000 0.0000 0.0000
B Repair & Touchup existing Flag Pole lot 1.00 0.01063 0.0000 0.0000 0.0000 0.3947 0.0000 0.0000 0.0000
C Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 0.3947 0.0000 0.0000 0.0000

G.1.2 EXCAVATOR PAINT FACTORY AREA LOT 1.00 0.82498 0.0000 0.0000 0.0000

G.1.2.1 PAVING WORK LOT 1.00 0.38305 0.0000 0.0000 0.0000

A RC Pavement
- Excavation Soil m3 682.65 0.00811 0.0000 0.0000 0.0000 0.0212 0.0000 0.0000 0.0000
- Disposed excavated material m3 682.65 0.01115 0.0000 0.0000 0.0000 0.0291 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 1,517.00 0.00276 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Sub base course 200mm thick m2 1,517.00 0.04085 0.0000 0.0000 0.0000 0.1066 0.0000 0.0000 0.0000
- T=250mm Limestone m2 1,517.00 0.04197 0.0000 0.0000 0.0000 0.1096 0.0000 0.0000 0.0000
- PE Sheet Damp Proof Membrane m2 1,517.00 0.00379 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
- Concrete grade K-250 , T=200mm m3 303.40 0.14307 0.0000 0.0000 0.0000 0.3735 0.0000 0.0000 0.0000
- Wiremesh #M10 ( Single ) m2 1,517.00 0.09572 0.0000 0.0000 0.0000 0.2499 0.0000 0.0000 0.0000
- Formwork m2 79.00 0.00459 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
- Steel Trowel finish m2 1,517.00 0.00481 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000
B Construction Joint filled w/ asphalt fill
- Sand Asphlat Fill m 316.00 0.00616 0.0000 0.0000 0.0000 0.0161 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 1,948.00 0.01104 0.0000 0.0000 0.0000 0.0288 0.0000 0.0000 0.0000
- Dowel bar kg 1,164.00 0.00660 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
- Flexible hose m 421.00 0.00091 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 17.00 0.00152 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000

G.1.2.2 DRAINAGE WORK LOT 1.00 0.42044 0.0000 0.0000 0.0000

A Open Drainage
- Excavation Soil m3 424.00 0.00735 0.0000 0.0000 0.0000 0.0175 0.0000 0.0000 0.0000
- Disposed excavated material m3 190.00 0.00310 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 234.00 0.00298 0.0000 0.0000 0.0000 0.0071 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 180.80 0.00033 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 180.80 0.00372 0.0000 0.0000 0.0000 0.0089 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 180.80 0.00494 0.0000 0.0000 0.0000 0.0118 0.0000 0.0000 0.0000
- River stone m3 156.70 0.04996 0.0000 0.0000 0.0000 0.1188 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 397.70 0.01028 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 14.50 0.00684 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,376.00 0.00780 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
- Formwork m2 144.60 0.00840 0.0000 0.0000 0.0000 0.0200 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 1,139.00 0.01975 0.0000 0.0000 0.0000 0.0470 0.0000 0.0000 0.0000
- Disposed excavated material m3 506.00 0.00826 0.0000 0.0000 0.0000 0.0197 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 21
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Back fill part return and compaction m3 633.00 0.00807 0.0000 0.0000 0.0000 0.0192 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 289.20 0.00053 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 289.20 0.00595 0.0000 0.0000 0.0000 0.0142 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 289.20 0.00790 0.0000 0.0000 0.0000 0.0188 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 173.50 0.08182 0.0000 0.0000 0.0000 0.1946 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 20,822.00 0.11803 0.0000 0.0000 0.0000 0.2807 0.0000 0.0000 0.0000
- Formwork m2 1,108.60 0.06441 0.0000 0.0000 0.0000 0.1532 0.0000 0.0000 0.0000

G.1.2.3 LANDSCAPE WORK LOT 1.00 0.00377 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 343.00 0.00255 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 343.00 0.00123 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.2.4 MISCELLANEOUS WORK LOT 1.00 0.01771 0.0000 0.0000 0.0000

A Repair & Touchup existing external work lot 1.00 0.01771 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

G.1.3 ULTRA LARGE COMPONENT FACTORY-2 AREA LOT 1.00 1.70938 0.0000 0.0000 0.0000

G.1.3.1 PAVING WORK LOT 1.00 1.22001 0.0000 0.0000 0.0000

A RC Pavement
- Excavation Soil m3 2,163.60 0.02570 0.0000 0.0000 0.0000 0.0211 0.0000 0.0000 0.0000
- Disposed excavated material m3 2,163.60 0.03533 0.0000 0.0000 0.0000 0.0290 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 4,808.00 0.00876 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Sub base course 200mm thick m2 4,808.00 0.12946 0.0000 0.0000 0.0000 0.1061 0.0000 0.0000 0.0000
- T=250mm Limestone m2 4,808.00 0.13303 0.0000 0.0000 0.0000 0.1090 0.0000 0.0000 0.0000
- PE Sheet Damp Proof Membrane m2 4,808.00 0.01200 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
- Concrete grade K-250 , T=200mm m3 961.60 0.45345 0.0000 0.0000 0.0000 0.3717 0.0000 0.0000 0.0000
- Wiremesh #M10 ( Single ) m2 4,808.00 0.30336 0.0000 0.0000 0.0000 0.2487 0.0000 0.0000 0.0000
- Formwork m2 250.00 0.01453 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000
- Steel Trowel finish m2 4,808.00 0.01525 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
B Construction Joint filled w/ asphalt fill
- Sand Asphlat Fill m 534.00 0.01041 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 8,080.00 0.04580 0.0000 0.0000 0.0000 0.0375 0.0000 0.0000 0.0000
- Dowel bar kg 3,721.00 0.02109 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Flexible hose m 715.00 0.00154 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 115.00 0.01029 0.0000 0.0000 0.0000 0.0084 0.0000 0.0000 0.0000

G.1.3.2 DRAINAGE WORK LOT 1.00 0.46890 0.0000 0.0000 0.0000

A Open Drainage
- Excavation Soil m3 482.00 0.00836 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000
- Disposed excavated material m3 216.00 0.00353 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 266.00 0.00339 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 205.50 0.00037 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 205.50 0.00423 0.0000 0.0000 0.0000 0.0090 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 205.50 0.00562 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
- River stone m3 178.00 0.05676 0.0000 0.0000 0.0000 0.1210 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 452.00 0.01168 0.0000 0.0000 0.0000 0.0249 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 16.50 0.00778 0.0000 0.0000 0.0000 0.0166 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,564.00 0.00887 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
- Formwork m2 165.00 0.00959 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 1,262.00 0.02189 0.0000 0.0000 0.0000 0.0467 0.0000 0.0000 0.0000
- Disposed excavated material m3 561.00 0.00916 0.0000 0.0000 0.0000 0.0195 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 701.00 0.00894 0.0000 0.0000 0.0000 0.0191 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 320.40 0.00058 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 320.40 0.00659 0.0000 0.0000 0.0000 0.0141 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 320.40 0.00876 0.0000 0.0000 0.0000 0.0187 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 192.30 0.09068 0.0000 0.0000 0.0000 0.1934 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 23,069.00 0.13077 0.0000 0.0000 0.0000 0.2789 0.0000 0.0000 0.0000
- Formwork m2 1,228.20 0.07136 0.0000 0.0000 0.0000 0.1522 0.0000 0.0000 0.0000

G.1.3.3 LANDSCAPE WORK LOT 1.00 0.00984 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 895.00 0.00664 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 895.00 0.00320 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.3.4 MISCELLANEOUS WORK LOT 1.00 0.01063 0.0000 0.0000 0.0000

A Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

G.1.4 TOUCHUP PAINT BOOTH AREA LOT 1.00 0.19330 0.0000 0.0000 0.0000

G.1.4.1 DRAINAGE WORK LOT 1.00 0.19330 0.0000 0.0000 0.0000

A RC Culvert
- Excavation Soil m3 699.30 0.01213 0.0000 0.0000 0.0000 0.0627 0.0000 0.0000 0.0000
- Disposed excavated material m3 310.80 0.00508 0.0000 0.0000 0.0000 0.0263 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 388.50 0.00495 0.0000 0.0000 0.0000 0.0256 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 177.60 0.00032 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 177.60 0.00366 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 177.60 0.00485 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 106.60 0.05027 0.0000 0.0000 0.0000 0.2601 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 12,787.00 0.07248 0.0000 0.0000 0.0000 0.3750 0.0000 0.0000 0.0000
- Formwork m2 680.80 0.03956 0.0000 0.0000 0.0000 0.2046 0.0000 0.0000 0.0000

G.1.5 MAIN GATE AND FENCE LOT 1.00 0.33456 0.0000 0.0000 0.0000

G.1.5.1 MAIN GATE

A Automatic Steel Main Gate size. 12.000mm (W) x 2.000mm (H) unit 2.00 0.14586 0.0000 0.0000 0.0000 0.4360 0.0000 0.0000 0.0000
B Foundation to Main Gate unit 2.00 0.05385 0.0000 0.0000 0.0000 0.1610 0.0000 0.0000 0.0000
C Steel Man Door, size : 1.200mm (W) x 2.000mm (H) unit 1.00 0.00461 0.0000 0.0000 0.0000 0.0138 0.0000 0.0000 0.0000
D Steel Grid Fence H = 2.000mm m 22.00 0.01169 0.0000 0.0000 0.0000 0.0349 0.0000 0.0000 0.0000

G.1.5.2 FENCE

RC Wall Fence
A Earth Work
- Excavation Soil m3 33.80 0.00059 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
- Disposed excavated material m3 9.30 0.00015 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 24.50 0.00031 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 38.50 0.00007 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
- T=50mm comp. sand bedding m2 38.50 0.00034 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
B Strauss Pile
- Mob and Demob equipment and transport lot 1.00 0.00248 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
- Drilling Ø200 - 2m nos 50.00 0.00531 0.0000 0.0000 0.0000 0.0159 0.0000 0.0000 0.0000
- Concrete K-250 m3 3.20 0.00151 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
- H.T. Reinforcement kg 684.00 0.00388 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
- Disposal of pre-bored earth nos 50.00 0.00248 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
C Reinforced Concrete Work
- Lean concrete T = 100mm, grade K-150 concrete m2 38.50 0.00105 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
- Concrete grade K-250, to Sloof m3 4.60 0.00217 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 22
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Ditto , but to RC Wall m3 21.60 0.01019 0.0000 0.0000 0.0000 0.0304 0.0000 0.0000 0.0000
- Ditto , but to Planter Box m3 3.00 0.00141 0.0000 0.0000 0.0000 0.0042 0.0000 0.0000 0.0000
- HT. Reinforcement to Sloof kg 1,020.00 0.00578 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Ditto , but to RC Wall kg 2,784.00 0.01578 0.0000 0.0000 0.0000 0.0472 0.0000 0.0000 0.0000
- Ditto , but to Planter Box kg 478.00 0.00271 0.0000 0.0000 0.0000 0.0081 0.0000 0.0000 0.0000
- Formwork to Sloof m2 61.60 0.00358 0.0000 0.0000 0.0000 0.0107 0.0000 0.0000 0.0000
- Ditto , but to RC Wall m2 287.30 0.01669 0.0000 0.0000 0.0000 0.0499 0.0000 0.0000 0.0000
- Ditto , but to Planter Box m2 39.50 0.00230 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
- Supporting formwork to above m2 326.80 0.00348 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
F Miscellaneous Work
- Textured Spray Paint Fin. m2 458.00 0.01786 0.0000 0.0000 0.0000 0.0534 0.0000 0.0000 0.0000
- Company Logo & Signane nos 2.00 0.00779 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
- Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 0.0318 0.0000 0.0000 0.0000

G.1.6 GUARD HOUSE - 1 LOT 1.00 0.14741 0.0000 0.0000 0.0000

G.1.6.1 STRUCTURE WORK LOT 1.00 0.07973 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.00242 0.0000 0.0000 0.0000

A Manual Excavation to foundation & grade beam m3 29.70 0.00052 0.0000 0.0000 0.0000 0.2127 0.0000 0.0000 0.0000
B Back fill part return and compaction m3 8.60 0.00011 0.0000 0.0000 0.0000 0.0453 0.0000 0.0000 0.0000
C Compacted sub grade m2 77.00 0.00014 0.0000 0.0000 0.0000 0.0579 0.0000 0.0000 0.0000
D Dispose excavated material (out project site) m3 21.10 0.00034 0.0000 0.0000 0.0000 0.1423 0.0000 0.0000 0.0000
E T=50mm comp.sand bedding m2 23.00 0.00020 0.0000 0.0000 0.0000 0.0827 0.0000 0.0000 0.0000
F T=150mm comp. basecourse m2 54.00 0.00111 0.0000 0.0000 0.0000 0.4590 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.02147 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 23.00 0.00063 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Ground Beam m3 5.10 0.00240 0.0000 0.0000 0.0000 0.1120 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m3 6.80 0.00321 0.0000 0.0000 0.0000 0.1493 0.0000 0.0000 0.0000
D Ditto , but to Column m3 2.10 0.00099 0.0000 0.0000 0.0000 0.0461 0.0000 0.0000 0.0000
E Ditto , but to to Roof Beam m3 7.10 0.00335 0.0000 0.0000 0.0000 0.1559 0.0000 0.0000 0.0000
F Ditto , but to to Roof Slab m3 6.80 0.00321 0.0000 0.0000 0.0000 0.1493 0.0000 0.0000 0.0000
G Ditto , but to to Parapet m3 4.30 0.00203 0.0000 0.0000 0.0000 0.0944 0.0000 0.0000 0.0000
H Ditto , but to to Canopy m3 10.00 0.00472 0.0000 0.0000 0.0000 0.2196 0.0000 0.0000 0.0000
I Ditto , but to to RC Bench m3 2.00 0.00094 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000

IV REINFORCED WORK LOT 1.00 0.02876 0.0000 0.0000 0.0000

A HT. Reinforcement to Ground Beam kg 718.00 0.00407 0.0000 0.0000 0.0000 0.1415 0.0000 0.0000 0.0000
B Ditto , but to Column kg 325.00 0.00184 0.0000 0.0000 0.0000 0.0641 0.0000 0.0000 0.0000
C Ditto , but to to Roof Beam kg 1,097.00 0.00622 0.0000 0.0000 0.0000 0.2162 0.0000 0.0000 0.0000
D Ditto , but to to Roof Slab kg 745.00 0.00422 0.0000 0.0000 0.0000 0.1468 0.0000 0.0000 0.0000
E Ditto , but to to Parapet kg 621.00 0.00352 0.0000 0.0000 0.0000 0.1224 0.0000 0.0000 0.0000
F Ditto , but to to Canopy kg 1,049.00 0.00595 0.0000 0.0000 0.0000 0.2068 0.0000 0.0000 0.0000
G Ditto , but to to RC Bench kg 244.00 0.00138 0.0000 0.0000 0.0000 0.0481 0.0000 0.0000 0.0000
H Wiremesh #M6 to ground slab (1 layer) m2 54.00 0.00156 0.0000 0.0000 0.0000 0.0541 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.02707 0.0000 0.0000 0.0000

A Timber formwork to Ground Beam m2 40.80 0.00237 0.0000 0.0000 0.0000 0.0876 0.0000 0.0000 0.0000
B Ditto , but to Ground Slab m2 5.30 0.00031 0.0000 0.0000 0.0000 0.0114 0.0000 0.0000 0.0000
C Ditto , but to Column m2 32.50 0.00189 0.0000 0.0000 0.0000 0.0697 0.0000 0.0000 0.0000
D Ditto , but to to Roof Beam m2 56.30 0.00359 0.0000 0.0000 0.0000 0.1325 0.0000 0.0000 0.0000
E Ditto , but to to Roof Slab m2 59.30 0.00378 0.0000 0.0000 0.0000 0.1395 0.0000 0.0000 0.0000
F Ditto , but to to Parapet m2 61.80 0.00394 0.0000 0.0000 0.0000 0.1454 0.0000 0.0000 0.0000
G Ditto , but to to Canopy m2 101.50 0.00647 0.0000 0.0000 0.0000 0.2388 0.0000 0.0000 0.0000
H Ditto , but to to RC Bench m2 19.10 0.00122 0.0000 0.0000 0.0000 0.0449 0.0000 0.0000 0.0000
J Supporting formwork m2 330.50 0.00352 0.0000 0.0000 0.0000 0.1302 0.0000 0.0000 0.0000

G.1.6.2 FINISHING WORK LOT 1.00 0.06769 0.0000 0.0000 0.0000

I DOOR and WINDOW WORK LOT 1.00 0.00574 0.0000 0.0000 0.0000

DOORS
A Wooden single swing door (WD-1) unit 2.00 0.00411 0.0000 0.0000 0.0000 0.7159 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)

B Hardware and Ironmongery lot 1.00 0.00117 0.0000 0.0000 0.0000 0.2042 0.0000 0.0000 0.0000

C Aluminium Fix Glass Window (AW-1) unit 1.00 0.00046 0.0000 0.0000 0.0000 0.0799 0.0000 0.0000 0.0000
size : 1.250 x 450 mm

II MASONRY WORK LOT 1.00 0.02072 0.0000 0.0000 0.0000

A Common brick wall m2 112.00 0.00741 0.0000 0.0000 0.0000 0.3578 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 1.70 0.00072 0.0000 0.0000 0.0000 0.0346 0.0000 0.0000 0.0000
- HT. Reinforcement kg 269.00 0.00152 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 22.40 0.00130 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 224.00 0.00976 0.0000 0.0000 0.0000 0.4712 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.00785 0.0000 0.0000 0.0000

A Texured spray paint to external wall m2 135.50 0.00529 0.0000 0.0000 0.0000 0.6733 0.0000 0.0000 0.0000
B Emulsion paint to internal wall m2 99.00 0.00120 0.0000 0.0000 0.0000 0.1523 0.0000 0.0000 0.0000
C Emulsion paint to ceiling m2 100.00 0.00121 0.0000 0.0000 0.0000 0.1539 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 8.40 0.00016 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

IV INTERIOR FINISHING WORK LOT 1.00 0.01275 0.0000 0.0000 0.0000

FLOOR FINISHING
A Ceramic tile , 200x200mm w/ bed mortar m2 7.40 0.00059 0.0000 0.0000 0.0000 0.0462 0.0000 0.0000 0.0000
B Ceramic tile , 300x300mm w/ bed mortar m2 46.60 0.00390 0.0000 0.0000 0.0000 0.3055 0.0000 0.0000 0.0000
WALL FINISHING
C Ceramic tile , 200mm x 200mm m2 24.70 0.00201 0.0000 0.0000 0.0000 0.1575 0.0000 0.0000 0.0000
D Ceramic base H=100mm m2 52.10 0.00111 0.0000 0.0000 0.0000 0.0874 0.0000 0.0000 0.0000
CEILING FINISH
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 46.60 0.00238 0.0000 0.0000 0.0000 0.1864 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 7.40 0.00050 0.0000 0.0000 0.0000 0.0390 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 162.00 0.00159 0.0000 0.0000 0.0000 0.1243 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 46.00 0.00069 0.0000 0.0000 0.0000 0.0538 0.0000 0.0000 0.0000

V WATERPROOFING WORK LOT 1.00 0.00859 0.0000 0.0000 0.0000

A Waterproofing membrane to roof m2 67.00 0.00356 0.0000 0.0000 0.0000 0.4149 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 54.00 0.00329 0.0000 0.0000 0.0000 0.3836 0.0000 0.0000 0.0000
C Brick protection w/ plastering finish m2 17.00 0.00173 0.0000 0.0000 0.0000 0.2016 0.0000 0.0000 0.0000

VI MISCELLANEOUS WORK LOT 1.00 0.01203 0.0000 0.0000 0.0000

A Lavatory concrete table w/ ceramic tile nos 1.00 0.00113 0.0000 0.0000 0.0000 0.0942 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 23
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Pantry concrete table w/ ceramic tile & S/S Sink nos 1.00 0.00248 0.0000 0.0000 0.0000 0.2061 0.0000 0.0000 0.0000
C Toilet partition w/ Door m2 3.70 0.00367 0.0000 0.0000 0.0000 0.3050 0.0000 0.0000 0.0000
D PVC Down Spout Ø 100mm w/ Elbow & Clamp Pipe m 20.00 0.00376 0.0000 0.0000 0.0000 0.3122 0.0000 0.0000 0.0000
E Cast iron roof drain nos 4.00 0.00099 0.0000 0.0000 0.0000 0.0824 0.0000 0.0000 0.0000

G.1.7 GUARD HOUSE - 2 LOT 1.00 0.02012 0.0000 0.0000 0.0000

G.1.7.1 STRUCTURE WORK LOT 1.00 0.01395 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.00024 0.0000 0.0000 0.0000

A Manual Excavation to foundation & grade beam m3 3.60 0.00006 0.0000 0.0000 0.0000 0.2573 0.0000 0.0000 0.0000
B Back fill part return and compaction m3 1.70 0.00002 0.0000 0.0000 0.0000 0.0894 0.0000 0.0000 0.0000
C Compacted sub grade m2 7.60 0.00001 0.0000 0.0000 0.0000 0.0571 0.0000 0.0000 0.0000
D Dispose excavated material (out project site) m3 1.90 0.00003 0.0000 0.0000 0.0000 0.1279 0.0000 0.0000 0.0000
E T=50mm comp.sand bedding m2 3.60 0.00003 0.0000 0.0000 0.0000 0.1291 0.0000 0.0000 0.0000
F T=150mm comp. basecourse m2 4.00 0.00008 0.0000 0.0000 0.0000 0.3393 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.00382 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 3.60 0.00010 0.0000 0.0000 0.0000 0.0257 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Ground Beam m3 0.80 0.00038 0.0000 0.0000 0.0000 0.0987 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m3 0.50 0.00024 0.0000 0.0000 0.0000 0.0617 0.0000 0.0000 0.0000
D Ditto , but to Column m3 1.10 0.00052 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000
E Ditto , but to to Roof Beam m3 0.80 0.00038 0.0000 0.0000 0.0000 0.0987 0.0000 0.0000 0.0000
F Ditto , but to to Roof Slab m3 1.10 0.00052 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000
G Ditto , but to to Parapet m3 1.60 0.00075 0.0000 0.0000 0.0000 0.1973 0.0000 0.0000 0.0000
H Ditto , but to to Canopy m3 2.00 0.00094 0.0000 0.0000 0.0000 0.2467 0.0000 0.0000 0.0000
I Ditto , but to to RC Bench m3

IV REINFORCED WORK LOT 1.00 0.00502 0.0000 0.0000 0.0000

A HT. Reinforcement to Ground Beam kg 128.00 0.00073 0.0000 0.0000 0.0000 0.1446 0.0000 0.0000 0.0000
B Ditto , but to Column kg 163.00 0.00092 0.0000 0.0000 0.0000 0.1841 0.0000 0.0000 0.0000
C Ditto , but to to Roof Beam kg 132.00 0.00075 0.0000 0.0000 0.0000 0.1491 0.0000 0.0000 0.0000
D Ditto , but to to Roof Slab kg 98.00 0.00056 0.0000 0.0000 0.0000 0.1107 0.0000 0.0000 0.0000
E Ditto , but to to Parapet kg 163.00 0.00092 0.0000 0.0000 0.0000 0.1841 0.0000 0.0000 0.0000
F Ditto , but to to Canopy kg 181.00 0.00103 0.0000 0.0000 0.0000 0.2044 0.0000 0.0000 0.0000
G Ditto , but to to RC Bench kg 0.00000 -
H Wiremesh #M6 to ground slab (1 layer) m2 4.00 0.00012 0.0000 0.0000 0.0000 0.0230 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.00487 0.0000 0.0000 0.0000

A Timber formwork to Ground Beam m2 6.40 0.00037 0.0000 0.0000 0.0000 0.0764 0.0000 0.0000 0.0000
B Ditto , but to Ground Slab m2 1.00 0.00006 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000
C Ditto , but to Column m2 14.60 0.00085 0.0000 0.0000 0.0000 0.1742 0.0000 0.0000 0.0000
D Ditto , but to to Roof Beam m2 6.00 0.00038 0.0000 0.0000 0.0000 0.0785 0.0000 0.0000 0.0000
E Ditto , but to to Roof Slab m2 4.40 0.00028 0.0000 0.0000 0.0000 0.0576 0.0000 0.0000 0.0000
F Ditto , but to to Parapet m2 15.00 0.00096 0.0000 0.0000 0.0000 0.1962 0.0000 0.0000 0.0000
G Ditto , but to to Canopy m2 20.80 0.00133 0.0000 0.0000 0.0000 0.2721 0.0000 0.0000 0.0000
H Ditto , but to to RC Bench m2 0.00000
J Supporting formwork m2 60.80 0.00065 0.0000 0.0000 0.0000 0.1331 0.0000 0.0000 0.0000

G.1.7.2 FINISHING WORK LOT 1.00 0.00616 0.0000 0.0000 0.0000

I DOOR and WINDOW WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

II MASONRY WORK LOT 1.00 0.00208 0.0000 0.0000 0.0000

A Common brick wall m2 11.00 0.00073 0.0000 0.0000 0.0000 0.3509 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 0.20 0.00008 0.0000 0.0000 0.0000 0.0406 0.0000 0.0000 0.0000
- HT. Reinforcement kg 29.00 0.00016 0.0000 0.0000 0.0000 0.0792 0.0000 0.0000 0.0000
- Timber formwork m2 2.40 0.00014 0.0000 0.0000 0.0000 0.0672 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 22.00 0.00096 0.0000 0.0000 0.0000 0.4621 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.00110 0.0000 0.0000 0.0000

A Texured spray paint to external wall m2 20.30 0.00079 0.0000 0.0000 0.0000 0.7184 0.0000 0.0000 0.0000
B Emulsion paint to internal wall m2 16.70 0.00020 0.0000 0.0000 0.0000 0.1830 0.0000 0.0000 0.0000
C Emulsion paint to ceiling m2 9.00 0.00011 0.0000 0.0000 0.0000 0.0986 0.0000 0.0000 0.0000

IV INTERIOR FINISHING WORK LOT 1.00 0.00089 0.0000 0.0000 0.0000

FLOOR FINISHING
A Ceramic tile , 300x300mm w/ bed mortar m2 4.00 0.00033 0.0000 0.0000 0.0000 0.3763 0.0000 0.0000 0.0000
WALL FINISHING
B Ceramic base H=100mm m2 7.40 0.00016 0.0000 0.0000 0.0000 0.1781 0.0000 0.0000 0.0000
CEILING FINISH
C Gypsum Board (Flat) T=9mm w/ LGS Frame m2 4.00 0.00020 0.0000 0.0000 0.0000 0.2296 0.0000 0.0000 0.0000
D Extra steel chanel to ditto kg 12.00 0.00012 0.0000 0.0000 0.0000 0.1321 0.0000 0.0000 0.0000
E Skim coat to Exposed Ceiling m2 5.00 0.00007 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000

V WATERPROOFING WORK LOT 1.00 0.00091 0.0000 0.0000 0.0000

A Waterproofing membrane to roof m2 6.40 0.00034 0.0000 0.0000 0.0000 0.3739 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 4.00 0.00024 0.0000 0.0000 0.0000 0.2681 0.0000 0.0000 0.0000
C Brick protection w/ plastering finish m2 3.20 0.00033 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000

VI MISCELLANEOUS WORK LOT 1.00 0.00119 0.0000 0.0000 0.0000

A PVC Down Spout Ø 100mm w/ Elbow & Clamp Pipe m 5.00 0.00094 0.0000 0.0000 0.0000 0.7911 0.0000 0.0000 0.0000
B Cast iron roof drain nos 1.00 0.00025 0.0000 0.0000 0.0000 0.2089 0.0000 0.0000 0.0000

G.1.8 RC PAVEMENT & DRAINAGE AREA - A LOT 1.00 5.36302 3.0580 0.0000 3.0580

G.1.7.1 PAVING WORK LOT 1.00 5.04700 3.0264 0.0000 3.0264

A RC Pavement
- Excavation Soil m3 8,950.50 0.10630 8,950.50 - 8,950.5000 0.0211 0.1063 0.0000 0.1063
- Disposed excavated material m3 8,950.50 0.14617 8,950.50 - 8,950.5000 0.0290 0.1462 0.0000 0.1462
- Pre compacted subgrade m2 19,890.00 0.03624 19,890.00 - 19,890.0000 0.0072 0.0362 0.0000 0.0362
- Sub base course 200mm thick m2 19,890.00 0.53554 19,890.00 - 19,890.0000 0.1061 0.5355 0.0000 0.5355
- T=250mm Limestone m2 19,890.00 0.55031 19,890.00 - 19,890.0000 0.1090 0.5503 0.0000 0.5503
- PE Sheet Damp Proof Membrane m2 19,890.00 0.04966 9,945.00 - 9,945.0000 0.0098 0.0248 0.0000 0.0248
- Concrete grade K-250 , T=200mm m3 3,978.00 1.87587 1,989.00 - 1,989.0000 0.3717 0.9379 0.0000 0.9379
- Wiremesh #M10 ( Single ) m2 19,890.00 1.25497 9,945.00 - 9,945.0000 0.2487 0.6275 0.0000 0.6275
- Formwork m2 1,034.20 0.06009 517.10 - 517.1000 0.0119 0.0300 0.0000 0.0300
- Steel Trowel finish m2 19,890.00 0.06308 9,945.00 - 9,945.0000 0.0125 0.0315 0.0000 0.0315
B Construction Joint filled w/ asphalt fill - -
- Sand Asphlat Fill m 2,209.10 0.04308 - - 0.0000 0.0085 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 33,426.10 0.18947 - - 0.0000 0.0375 0.0000 0.0000 0.0000
- Dowel bar kg 15,393.40 0.08726 - - 0.0000 0.0173 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 24
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Flexible hose m 2,957.90 0.00639 - - 0.0000 0.0013 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 475.70 0.04257 - - 0.0000 0.0084 0.0000 0.0000 0.0000

G.1.7.2 DRAINAGE WORK LOT 1.00 0.31602 0.0316 0.0000 0.0316

A Open Drainage
- Excavation Soil m3 1,267.60 0.02198 126.76 126.7600 0.0696 0.0022 0.0000 0.0022
- Disposed excavated material m3 568.00 0.00928 56.80 56.8000 0.0294 0.0009 0.0000 0.0009
- Back fill part return and compaction m3 699.50 0.00892 69.95 69.9500 0.0282 0.0009 0.0000 0.0009
- Pre compacted subgrade m2 540.40 0.00098 54.04 54.0400 0.0031 0.0001 0.0000 0.0001
- Sub base course 150mm thick m2 540.40 0.01112 54.04 54.0400 0.0352 0.0011 0.0000 0.0011
- Lean concrete T = 100mm, grade K-150 concrete m2 540.40 0.01477 54.04 54.0400 0.0467 0.0015 0.0000 0.0015
- River stone m3 468.10 0.14925 46.81 46.8100 0.4723 0.0149 0.0000 0.0149
- Mortar Plestering to above (Siar) m2 1,188.70 0.03072 118.87 118.8700 0.0972 0.0031 0.0000 0.0031
- RC Protection, size : 150 x 200mm m3 43.40 0.02047 4.34 4.3400 0.0648 0.0020 0.0000 0.0020
- HT. Reinforcement to above kg 4,113.10 0.02331 411.31 411.3100 0.0738 0.0023 0.0000 0.0023
- Formwork m2 433.90 0.02521 43.39 43.3900 0.0798 0.0025 0.0000 0.0025

G.2 MECHANICAL WORK LOT 1.00 0.02254 0.0000 0.0000 0.0000 0.0713 0.0000 0.0000 0.0000

G.3 ELECTRICAL WORK LOT 1.00 1.73600 0.0000 0.0000 0.0000 5.4933 0.0000 0.0000 0.0000

H. MOTOR CYCLE PARKING LOT 1.00 2.28928 2.28928 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
0.0000
H.1 CIVIL WORK LOT 1.00 2.05759 0.0000 0.0000 0.0000

H.1.1 PAVING WORK & DRAINAGE WORK LOT 1.00 0.23619 0.0000 0.0000 0.0000

A Modification External Road & Drainage lot 1.00 0.23619 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

H.1.2 MOTORCYCLE PARKING AREA ( E, F, G & H ) LOT 1.00 0.42140 0.0000 0.0000 0.0000

A Foundation Work
Earth Work
- - Excavation m3 312.80 0.00542 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
- - Backfill m3 0.00 0.00000 -
- - Disposal m3 312.80 0.00511 0.0000 0.0000 0.0000 0.0121 0.0000 0.0000 0.0000
- - Comp. sub grade m2 693.50 0.00126 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
- - Comp. Macadam T = 150mm m2 693.50 0.01427 0.0000 0.0000 0.0000 0.0339 0.0000 0.0000 0.0000
Concrete Work
- Lean concrete T = 50 mm , grade K - 150 concrete m2 693.50 0.01895 0.0000 0.0000 0.0000 0.0450 0.0000 0.0000 0.0000
- Grade K - 250 concrete to Slab m3 173.50 0.08182 0.0000 0.0000 0.0000 0.1942 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal m3 3.50 0.00165 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000
- Timber formwork to Slab m2 105.30 0.00612 0.0000 0.0000 0.0000 0.0145 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal m2 34.10 0.00217 0.0000 0.0000 0.0000 0.0052 0.0000 0.0000 0.0000
- Supporting formwork m2 34.10 0.00036 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
- HT. Reinforcement to Slab kg 5,060.00 0.02868 0.0000 0.0000 0.0000 0.0681 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal kg 517.50 0.00293 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000

B Steel Structure
- Stl Roofing c/w stl. Truss , purlin, sagrod & bracing kg 13,870.20 0.13572 0.0000 0.0000 0.0000 0.3221 0.0000 0.0000 0.0000
- Zinchromate paint 35 µ to steel structure kg 13,870.20 0.01030 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000

C Metal Roof
- Roofing Boltless U-527 ( 27mm), Zinc Alume Thk 0,50mm (Tmt) m2 813.00 0.06101 0.0000 0.0000 0.0000 0.1448 0.0000 0.0000 0.0000
- Gable Flashing W=610mm, Zinc Alume Thk 0.50mm (Tmt) m 166.00 0.00934 0.0000 0.0000 0.0000 0.0222 0.0000 0.0000 0.0000
- FRP Gutter, Grey Thk 2.0mm , W=750mm m 166.00 0.02089 0.0000 0.0000 0.0000 0.0496 0.0000 0.0000 0.0000
- Gutter Bracket Sp 3x30mm W=100mm pcs 332.00 0.00889 0.0000 0.0000 0.0000 0.0211 0.0000 0.0000 0.0000
- PVC Pipe AW Grey Dia. 100mm m 78.00 0.00293 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
- PVC Lbow 450 / 900 , Dia. 100mm pcs 62.00 0.00233 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
- Clamp pipe Sp. 3x30mm , Dia. 100mm pcs 93.00 0.00124 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000

H.1.3 MOTORCYCLE PARKING BUILDING ( C & D ) LOT 1.00 1.35208 0.0000 0.0000 0.0000

H.1.3.1 STRUCTURE WORK LOT 1.00 0.99685 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.04041 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 1,043.10 0.00331 0.0000 0.0000 0.0000 0.0819 0.0000 0.0000 0.0000
B site of all debris
C Excavation to ground slab m3 156.40 0.00186 0.0000 0.0000 0.0000 0.0460 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 170.80 0.00296 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 132.00 0.00168 0.0000 0.0000 0.0000 0.0417 0.0000 0.0000 0.0000
F Compacted sub grade m2 1,156.70 0.00211 0.0000 0.0000 0.0000 0.0522 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 195.30 0.00319 0.0000 0.0000 0.0000 0.0789 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 114.10 0.00099 0.0000 0.0000 0.0000 0.0246 0.0000 0.0000 0.0000
I T=150mm comp. basecourse m2 1,053.20 0.02168 0.0000 0.0000 0.0000 0.5364 0.0000 0.0000 0.0000
J Plastic Sheet m2 1,053.20 0.00263 0.0000 0.0000 0.0000 0.0651 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.12653 0.0000 0.0000 0.0000

A Allow for mobilization and demobilization of all unit 1.00 0.00921 0.0000 0.0000 0.0000 0.0728 0.0000 0.0000 0.0000
pilling plant and equipment
B PC Square Pile 250x250 mm , L=20m (Assume) nos 36.00 0.07754 0.0000 0.0000 0.0000 0.6128 0.0000 0.0000 0.0000
C Driving Pile w/ Jacking system m 720.00 0.02808 0.0000 0.0000 0.0000 0.2219 0.0000 0.0000 0.0000
D Welding Joint nos 36.00 0.00230 0.0000 0.0000 0.0000 0.0181 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 36.00 0.00089 0.0000 0.0000 0.0000 0.0071 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0672 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.23536 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 114.10 0.00312 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Foundation m3 16.30 0.00769 0.0000 0.0000 0.0000 0.0327 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 15.90 0.00750 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 156.40 0.07375 0.0000 0.0000 0.0000 0.3134 0.0000 0.0000 0.0000
E Ditto , but to Column m3 19.80 0.00934 0.0000 0.0000 0.0000 0.0397 0.0000 0.0000 0.0000
F Ditto , but to RC Wall m3 71.90 0.03391 0.0000 0.0000 0.0000 0.1441 0.0000 0.0000 0.0000
G Ditto , but to 2nd Fl Beam m3 51.00 0.02405 0.0000 0.0000 0.0000 0.1022 0.0000 0.0000 0.0000
H Ditto , but to 2nd Fl Slab m3 81.90 0.03862 0.0000 0.0000 0.0000 0.1641 0.0000 0.0000 0.0000
I Ditto , but to Roof Beam m3 35.40 0.01669 0.0000 0.0000 0.0000 0.0709 0.0000 0.0000 0.0000
J Ditto , but to Ramp m3 37.90 0.01787 0.0000 0.0000 0.0000 0.0759 0.0000 0.0000 0.0000
K Ditto , but to Staircase m3 6.00 0.00283 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

IV REINFORCED WORK LOT 1.00 0.29413 0.0000 0.0000 0.0000

A HT. Reinforcement to Foundation kg 2,056.20 0.01166 0.0000 0.0000 0.0000 0.0396 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam kg 1,711.20 0.00970 0.0000 0.0000 0.0000 0.0330 0.0000 0.0000 0.0000
C Ditto , but to Column kg 4,373.50 0.02479 0.0000 0.0000 0.0000 0.0843 0.0000 0.0000 0.0000
D Ditto , but to RC Wall kg 7,736.10 0.04385 0.0000 0.0000 0.0000 0.1491 0.0000 0.0000 0.0000
E Ditto , but to 2nd Fl Beam kg 7,086.30 0.04017 0.0000 0.0000 0.0000 0.1366 0.0000 0.0000 0.0000
F Ditto , but to 2nd Fl Slab kg 8,789.50 0.04982 0.0000 0.0000 0.0000 0.1694 0.0000 0.0000 0.0000
G Ditto , but to Roof Beam kg 3,821.50 0.02166 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
H Ditto , but to Ramp kg 4,462.00 0.02529 0.0000 0.0000 0.0000 0.0860 0.0000 0.0000 0.0000
I Ditto , but to Staircase kg 1,211.00 0.00686 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
J Wiremesh #M6 to ground slab (2 layer) m2 1,043.10 0.06032 0.0000 0.0000 0.0000 0.2051 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.21384 0.0000 0.0000 0.0000


06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 25
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

A Timber formwork to Foundation m2 67.20 0.00390 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 126.70 0.00736 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 58.00 0.00337 0.0000 0.0000 0.0000 0.0158 0.0000 0.0000 0.0000
D Ditto , but to Column m2 246.40 0.01570 0.0000 0.0000 0.0000 0.0734 0.0000 0.0000 0.0000
E Ditto , but to RC Wall m2 958.00 0.06103 0.0000 0.0000 0.0000 0.2854 0.0000 0.0000 0.0000
F Ditto , but to 2nd Fl Beam m2 275.40 0.01754 0.0000 0.0000 0.0000 0.0820 0.0000 0.0000 0.0000
G Ditto , but to 2nd Fl Slab m2 676.40 0.04309 0.0000 0.0000 0.0000 0.2015 0.0000 0.0000 0.0000
H Ditto , but to Roof Beam m2 374.30 0.02384 0.0000 0.0000 0.0000 0.1115 0.0000 0.0000 0.0000
I Ditto , but to Ramp m2 123.80 0.00789 0.0000 0.0000 0.0000 0.0369 0.0000 0.0000 0.0000
J Ditto , but to Staircase m2 24.40 0.00155 0.0000 0.0000 0.0000 0.0073 0.0000 0.0000 0.0000
K Supporting formwork m2 2,678.70 0.02856 0.0000 0.0000 0.0000 0.1336 0.0000 0.0000 0.0000

VI STEEL STRUCTURE WORK LOT 1.00 0.06634 0.0000 0.0000 0.0000

Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 6,302.00 0.06166 0.0000 0.0000 0.0000 0.9295 0.0000 0.0000 0.0000

Finishing paint to steel structure Kg 6,302.00 0.00468 0.0000 0.0000 0.0000 0.0705 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

VII MISCELLANEOUS WORK LOT 1.00 0.02024 0.0000 0.0000 0.0000

Non Shrinkage grouting, size : 420x420x30mm nos 29.00 0.00093 0.0000 0.0000 0.0000 0.0457 0.0000 0.0000 0.0000
Expansion joint to existing slab :
- Sand asphalt fill m 246.40 0.00481 0.0000 0.0000 0.0000 0.2374 0.0000 0.0000 0.0000
- Dowel rebar kg 907.40 0.00514 0.0000 0.0000 0.0000 0.2542 0.0000 0.0000 0.0000
- Add. Rebbar kg 1,538.70 0.00872 0.0000 0.0000 0.0000 0.4310 0.0000 0.0000 0.0000
- Flexible pipe m 327.80 0.00064 0.0000 0.0000 0.0000 0.0317 0.0000 0.0000 0.0000

H.1.3.2 FINISHING WORK LOT 1.00 0.35523 0.0000 0.0000 0.0000

I METAL ROOFING WORK LOT 1.00 0.19542 0.0000 0.0000 0.0000

Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 908.00 0.07782 0.0000 0.0000 0.0000 0.3982 0.0000 0.0000 0.0000
Roof mesh, Galvanized #3x3" m2 908.00 0.00729 0.0000 0.0000 0.0000 0.0373 0.0000 0.0000 0.0000
Aluminium foil single sided m2 908.00 0.00582 0.0000 0.0000 0.0000 0.0298 0.0000 0.0000 0.0000
Glasswool 16 kgs/m3, Thk 25mm m2 908.00 0.00852 0.0000 0.0000 0.0000 0.0436 0.0000 0.0000 0.0000
End Close, Boltless U-650 m 242.00 0.00545 0.0000 0.0000 0.0000 0.0279 0.0000 0.0000 0.0000
Appron Boltless U-650 m 121.00 0.00273 0.0000 0.0000 0.0000 0.0140 0.0000 0.0000 0.0000
Eaves Close Boltless U-650 m 111.00 0.00250 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 61.00 0.00409 0.0000 0.0000 0.0000 0.0209 0.0000 0.0000 0.0000
End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 76.00 0.00428 0.0000 0.0000 0.0000 0.0219 0.0000 0.0000 0.0000
Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 47.00 0.00265 0.0000 0.0000 0.0000 0.0135 0.0000 0.0000 0.0000
Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 111.00 0.00369 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 111.00 0.02498 0.0000 0.0000 0.0000 0.1278 0.0000 0.0000 0.0000
Gutter Bracket SP 3x42 mm, W=1.400mm pcs 226.00 0.00848 0.0000 0.0000 0.0000 0.0434 0.0000 0.0000 0.0000
PVC Pipe AW Grey Dia. 200mm m 162.00 0.02170 0.0000 0.0000 0.0000 0.1110 0.0000 0.0000 0.0000
PVC Lbow 450 / 900 , Dia. 200mm pcs 72.00 0.00964 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 180.00 0.00579 0.0000 0.0000 0.0000 0.0296 0.0000 0.0000 0.0000

II MASONRY WORK LOT 1.00 0.05691 0.0000 0.0000 0.0000

A Common brick wall m2 307.00 0.02032 0.0000 0.0000 0.0000 0.3571 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 4.60 0.00194 0.0000 0.0000 0.0000 0.0341 0.0000 0.0000 0.0000
- HT. Reinforcement kg 760.00 0.00431 0.0000 0.0000 0.0000 0.0757 0.0000 0.0000 0.0000
- Timber formwork m2 61.40 0.00357 0.0000 0.0000 0.0000 0.0627 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 614.00 0.02677 0.0000 0.0000 0.0000 0.4704 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.05528 0.0000 0.0000 0.0000

A Textured paint to external wall m2 560.00 0.02184 0.0000 0.0000 0.0000 0.3951 0.0000 0.0000 0.0000
B Emulsion paint to wall m2 834.00 0.01007 0.0000 0.0000 0.0000 0.1822 0.0000 0.0000 0.0000
C Parking Line (White Paint) m 1,785.00 0.02337 0.0000 0.0000 0.0000 0.4227 0.0000 0.0000 0.0000

IV MISCELLANEOUS WORK LOT 1.00 0.04762 0.0000 0.0000 0.0000

A Steel troweled fin. m2 1,604.00 0.00509 0.0000 0.0000 0.0000 0.1068 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 131.00 0.01211 0.0000 0.0000 0.0000 0.2543 0.0000 0.0000 0.0000
C Steel Handrail H = 1000mm w/ OP finish m 33.50 0.01306 0.0000 0.0000 0.0000 0.2742 0.0000 0.0000 0.0000
D Groove line to Ramp m2 140.00 0.01736 0.0000 0.0000 0.0000 0.3647 0.0000 0.0000 0.0000

H.1.4 MISCELLANEOUS WORK LOT 1.00 0.04791 0.0000 0.0000 0.0000

A Parking Line (White Paint) m 905.00 0.01185 0.0000 0.0000 0.0000 0.2473 0.0000 0.0000 0.0000
B Weathershield paint to column m2 30.00 0.00064 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
C Repair & Touchup existing external work lot 1.00 0.03543 0.0000 0.0000 0.0000 0.7394 0.0000 0.0000 0.0000

H.2 MECHANICAL WORK LOT 1.00 0.07171 0.0000 0.0000 0.0000 1.4968 0.0000 0.0000 0.0000

H.3 ELECTRICAL WORK LOT 1.00 0.15997 0.0000 0.0000 0.0000 3.3388 0.0000 0.0000 0.0000

I. CRANE WORK LOT 1.00 1.38228 1.38228 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

I.1 TRAINING CENTER & HEAD OFFICE LOT 1.00 0.07294 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 4,592.00 0.04493 0.0000 0.0000 0.0000 0.6160 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 4,592.00 0.00341 0.0000 0.0000 0.0000 0.0467 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Crane Rail, square bar 45 x 45mm m 78.00 0.02183 0.0000 0.0000 0.0000 0.2993 0.0000 0.0000 0.0000

D Installation cost Lot 1.00 0.00276 0.0000 0.0000 0.0000 0.0379 0.0000 0.0000 0.0000

I.2 ULTRA LARGE COMPONENT FACT-2 LOT 1.00 1.01253 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 48,039.60 0.47006 0.0000 0.0000 0.0000 0.4642 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 48,039.60 0.03566 0.0000 0.0000 0.0000 0.0352 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Hoist Crane Rail, square bar 60 x 60mm m 612.00 0.18685 0.0000 0.0000 0.0000 0.1845 0.0000 0.0000 0.0000
D Gantry Crane Rail, square bar 50 x 50mm (upper) m 612.00 0.15865 0.0000 0.0000 0.0000 0.1567 0.0000 0.0000 0.0000
E Gantry Crane Rail, H - 100 x 100 x 6 x 8 (lower) m 612.00 0.09626 0.0000 0.0000 0.0000 0.0951 0.0000 0.0000 0.0000

F Installation cost Lot 1.00 0.06505 0.0000 0.0000 0.0000 0.0642 0.0000 0.0000 0.0000

I.3 EXCAVATOR PAINT FACTORY LOT 1.00 0.29682 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 22,811.00 0.22320 0.0000 0.0000 0.0000 0.7520 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 22,811.00 0.01693 0.0000 0.0000 0.0000 0.0570 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Crane Rail, square bar 50 x 50mm m 160.00 0.05102 0.0000 0.0000 0.0000 0.1719 0.0000 0.0000 0.0000

D Installation cost Lot 1.00 0.00567 0.0000 0.0000 0.0000 0.0191 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 26
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 04 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
J. SOIL INVESTIGATION WORK LOT 1.00 0.08557 0.08557 0.0000 0.0000 0.0000 0.0000 0.0856 0.0856

1 Mob & Demobilization Tools & Equipment (2 Rigs) lot 1.00 0.01063 0.0000 1.0000 1.0000 0.1242 0.0000 0.0106 0.0106

2 Moving and Setting drilling machine at each location Locs. 6.00 0.00128 0.0000 6.0000 6.0000 0.0149 0.0000 0.0013 0.0013

3 Drilling in soil formantions, 6 location @ 30 m m 180.00 0.03399 0.0000 180.0000 180.0000 0.3972 0.0000 0.0340 0.0340
( Rotary wash boring, incld. Undisturbed Soil
Sampling & SPT )

4 Laboratory Test lot 1.00 0.00886 0.0000 1.0000 1.0000 0.1035 0.0000 0.0089 0.0089

5 Site Supervision and Reporting lot 1.00 0.03082 0.0000 1.0000 1.0000 0.3602 0.0000 0.0308 0.0308

TOTAL ( A ~ J ) 100.00000 100.00000 137,320.0909 3.5470 2.7283 6.2754

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 27
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

NO. WORK ITEM

A. TEMPORARY WORK

B. TEMPORARY ME WORK
B.1
B.1.1
B.1.2

B.2

B.3

C. DEMOLITION WORK
C. STRUCTURE WORK
C.1 WASHING AREA
C.2 MAIN GATE AND BOUNDARY WALL
C.3 GUARD HOUSE
C.4 OFFICE
C.5 CANTEEN
C.6 PARKING & TREE
C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT.
C.8 HEXINDO OFFICE
C.9 TOUCH UP PAINT BOOTH AREA
C.10 STOCK YARD AREA

D. BUILDING WORK

D.1 TRAINING CENTER & HEAD OFFICE


D.1.1
D.1.1.1
D.1.1.2
D.1.1.3
D.1.1.4
D.1.1.5
D.1.1.6
D.1.1.7

D.1.2
D.1.2.1
D.1.2.2
D.1.2.3
D.1.2.4
D.1.2.5
D.1.2.6
D.1.2.7
D.1.2.8

D.2 ULTRA LARGE COMPONENT FACT-2


D.2.1
D.2.1.1
D.2.1.2
D.2.1.3
D.2.1.4
D.2.1.5
D.2.1.6
D.2.1.7

D.2.2
D.2.2.1
D.2.2.2
D.2.2.3
D.2.2.4
D.2.2.5
D.2.2.6
D.2.2.7
D.2.2.8

D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH


D.3.1
D.3.1.1
D.3.1.2
D.3.1.3
D.3.1.4
D.3.1.5
D.3.1.6
D.3.1.7

D.3.2
D.3.2.1
D.3.2.2
D.3.2.3
D.3.2.4
D.3.2.5
D.3.2.6
D.3.2.7
D.3.2.8

D.4 EXCAVATOR PAINT FACTORY


D.4.1
D.4.1.1
D.4.1.2
D.4.1.3
D.4.1.4
D.4.1.5
D.4.1.6
D.4.1.7

D.4.2
D.4.2.1
D.4.2.2
D.4.2.3
D.4.2.4
D.4.2.5
D.4.2.6
D.4.2.7
D.4.2.8

D.5 TOUCHUP PAINT BOOTH


D.5.1
D.5.1.1
D.5.1.2
D.5.1.3
D.5.1.4
D.5.1.5
D.5.1.6
D.5.1.7

D.5.2
D.5.2.1
D.5.2.2
D.5.2.3
D.5.2.4
D.5.2.5
D.5.2.6
D.5.2.7
D.5.2.8

D.6 WASHING AREA


D.6.1
D.6.1.1
D.6.1.2
D.6.1.3
D.6.1.4
D.6.1.5
D.6.1.6
D.6.1.7

E. MECHANICAL WORK

F. ELECTRICAL WORK

G. EXTERNAL WORK

G.1
G.1.1
G.1.1.1
G.1.1.2
G.1.1.3
G.1.1.4

G.1.2
G.1.2.1
G.1.2.2
G.1.2.3
G.1.2.4

G.1.3
G.1.3.1
G.1.3.2
G.1.3.3
G.1.3.4

G.1.4
G.1.4.1

G.1.5

G.1.6
G.1.6.1
I
II
III
IV
V

G.1.6.2
I
II
III
IV
V
VI

G.1.7
G.1.7.1
I
II
III
IV
V

G.1.7.2
I
II
III
IV
V
VI

G.1.8
G.1.7.1
G.1.7.2

G.2

G.3

H. MOTOR CYCLE PARKING

H.1
H.1.1

H.1.2

H.1.3
H.1.3.1
I
II
III
IV
V
VI
VII

H.1.3.2
I
II
III
IV

H.1.4

H.2
H.3

I. CRANE WORK
I.1
I.2
I.3

J. SOIL INVESTIGATION WORK

TOTAL
TUNG FACTORY EXPANSION PROJECT
Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

WORK ITEM WEIGHT

TEMPORARY WORK 4.7622

TEMPORARY ME WORK
CIVIL WORKS
CABLE CONECTION WORK 0.0916
RENOVATION EXISTING GENSET ROOM 0.0221

MECHANICAL WORKS 0.2637

ELECTRICAL WORKS 0.6156

DEMOLITION WORK
STRUCTURE WORK
WASHING AREA 0.0087
MAIN GATE AND BOUNDARY WALL 0.0081
GUARD HOUSE 0.0042
OFFICE 0.1110
CANTEEN 0.0926
PARKING & TREE 0.1077
PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. 0.7397
HEXINDO OFFICE 0.0218
TOUCH UP PAINT BOOTH AREA 0.0529
STOCK YARD AREA 0.2568

BUILDING WORK

TRAINING CENTER & HEAD OFFICE


STRUCTURE WORK
EARTH WORK 0.2460
PILING WORK 0.4089
CONCRETE WORK 1.1862
REINFORCED WORK 1.7160
FORM WORK 0.8775
STEEL STRUCTURE WORK 0.4946
MISCELLANEOUS WORK 0.1328

FINISHING WORK
METAL ROOFING & METAL WALL WORK 1.0733
MASONRY WORK 0.5881
TILING WORK 0.3763
DOOR AND WINDOW WORK 0.9535
PAINTING WORK 0.1523
INTERIOR FINISHING WORK 2.0499
WATERPROOFING WORK 0.2679
MISCELLANEOUS WORK 0.6451

ULTRA LARGE COMPONENT FACT-2


STRUCTURE WORK
EARTH WORK 0.3373
PILING WORK 7.7829
CONCRETE WORK 2.2357
REINFORCED WORK 2.7240
FORM WORK 0.6094
STEEL STRUCTURE WORK 4.8412
MISCELLANEOUS WORK 0.0824

FINISHING WORK
METAL ROOFING & METAL WALL WORK 1.7808
MASONRY WORK 0.1735
TILING WORK 0.0220
DOOR AND WINDOW WORK 0.9477
PAINTING WORK 0.4161
INTERIOR FINISHING WORK 0.0514
WATERPROOFING WORK 0.0404
MISCELLANEOUS WORK 0.2994

ULTRA LARGE TOPCOAT PAINTING BOOTH


STRUCTURE WORK
EARTH WORK 0.0750
PILING WORK 0.5826
CONCRETE WORK 0.3418
REINFORCED WORK 0.5074
FORM WORK 0.1462
STEEL STRUCTURE WORK 0.3532
MISCELLANEOUS WORK 0.0227

FINISHING WORK
METAL ROOFING & METAL WALL WORK 0.4208
MASONRY WORK 0.0457
TILING WORK 0.0036
DOOR AND WINDOW WORK 0.3319
PAINTING WORK 0.0606
INTERIOR FINISHING WORK 0.0080
WATERPROOFING WORK 0.0007
MISCELLANEOUS WORK 0.1163

EXCAVATOR PAINT FACTORY


STRUCTURE WORK
EARTH WORK 0.7062
PILING WORK 0.7115
CONCRETE WORK 1.4572
REINFORCED WORK 1.8395
FORM WORK 0.3284
STEEL STRUCTURE WORK 3.5372
MISCELLANEOUS WORK 0.0549

FINISHING WORK
METAL ROOFING & METAL WALL WORK 2.3528
MASONRY WORK 0.5196
TILING WORK 0.0115
DOOR AND WINDOW WORK 0.9341
PAINTING WORK 0.2382
INTERIOR FINISHING WORK 0.0447
WATERPROOFING WORK 0.0170
MISCELLANEOUS WORK 0.7827

TOUCHUP PAINT BOOTH


STRUCTURE WORK
EARTH WORK 0.0152
PILING WORK 0.0659
CONCRETE WORK 0.1094
REINFORCED WORK 0.1347
FORM WORK 0.0579
STEEL STRUCTURE WORK 0.1393
MISCELLANEOUS WORK 0.0238

FINISHING WORK
METAL ROOFING & METAL WALL WORK 0.0839
MASONRY WORK 0.0067
TILING WORK 0.0000
DOOR AND WINDOW WORK 0.0227
PAINTING WORK 0.0249
INTERIOR FINISHING WORK 0.0021
WATERPROOFING WORK 0.0002
MISCELLANEOUS WORK 0.0527

WASHING AREA
STRUCTURE WORK
EARTH WORK 0.0097
PILING WORK 0.0000
CONCRETE WORK 0.0248
REINFORCED WORK 0.0235
FORM WORK 0.0166
STEEL STRUCTURE WORK 0.0648
MISCELLANEOUS WORK 0.1227

MECHANICAL WORK 12.0380

ELECTRICAL WORK 14.6483

EXTERNAL WORK

CIVIL WORK
TRAINING CENTER & HEAD OFFICE AREA
PAVING WORK 0.6938
DRAINAGE WORK 0.2466
LANDSCAPE WORK 0.0130
MISCELLANEOUS WORK 0.0269

EXCAVATOR PAINT FACTORY AREA


PAVING WORK 0.3830
DRAINAGE WORK 0.4204
LANDSCAPE WORK 0.0038
MISCELLANEOUS WORK 0.0177

ULTRA LARGE COMPONENT FACTORY-2 AREA


PAVING WORK 1.2200
DRAINAGE WORK 0.4689
LANDSCAPE WORK 0.0098
MISCELLANEOUS WORK 0.0106

TOUCHUP PAINT BOOTH AREA


DRAINAGE WORK 0.1933

MAIN GATE AND FENCE 0.3346

GUARD HOUSE - 1
STRUCTURE WORK
EARTH WORK 0.0024
PILING WORK 0.0000
CONCRETE WORK 0.0215
REINFORCED WORK 0.0288
FORMWORK 0.0271

FINISHING WORK
DOOR and WINDOW WORK 0.0057
MASONRY WORK 0.0207
PAINTING WORK 0.0078
INTERIOR FINISHING WORK 0.0128
WATERPROOFING WORK 0.0086
MISCELLANEOUS WORK 0.0120

GUARD HOUSE - 2
STRUCTURE WORK
EARTH WORK 0.0002
PILING WORK 0.0000
CONCRETE WORK 0.0038
REINFORCED WORK 0.0050
FORMWORK 0.0049

FINISHING WORK
DOOR and WINDOW WORK 0.0000
MASONRY WORK 0.0021
PAINTING WORK 0.0011
INTERIOR FINISHING WORK 0.0009
WATERPROOFING WORK 0.0009
MISCELLANEOUS WORK 0.0012

RC PAVEMENT & DRAINAGE AREA - A


PAVING WORK 5.0470
DRAINAGE WORK 0.3160

MECHANICAL WORK 0.0225

ELECTRICAL WORK 1.7360

MOTOR CYCLE PARKING

CIVIL WORK
PAVING WORK & DRAINAGE WORK 0.2362

MOTORCYCLE PARKING AREA ( E, F, G & H ) 0.4214

MOTORCYCLE PARKING BUILDING ( C & D )


STRUCTURE WORK
EARTH WORK 0.0404
PILING WORK 0.1265
CONCRETE WORK 0.2354
REINFORCED WORK 0.2941
FORMWORK 0.2138
STEEL STRUCTURE WORK 0.0663
MISCELLANEOUS WORK 0.0202

FINISHING WORK
METAL ROOFING WORK 0.1954
MASONRY WORK 0.0569
PAINTING WORK 0.0553
MISCELLANEOUS WORK 0.0476

MISCELLANEOUS WORK 0.0479

MECHANICAL WORK 0.0717


ELECTRICAL WORK 0.1600

CRANE WORK
TRAINING CENTER & HEAD OFFICE 0.0729
ULTRA LARGE COMPONENT FACT-2 1.0125
EXCAVATOR PAINT FACTORY 0.2968

SOIL INVESTIGATION WORK 0.0856

TOTAL 100.0000
Minggu ke - 04 ( May '2011)

PROGRESS
UP TO
WEIGHT
THIS WEEK

0.0909 0.4329

0.2000 0.0183
0.0000 0.0000

0.3165 0.0835

0.7693 0.4736

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
1.0000 0.0926
1.0000 0.1077
0.0306 0.0226
0.0000 0.0000
0.0000 0.0000
1.0000 0.2568
0.0000 0.0000
0.1774 0.0725
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.1205 0.0406
0.1944 1.5132
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0627 0.0047
0.0219 0.0128
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000

0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000

0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.5996 3.0264
0.1000 0.0316

0.0000 0.0000

0.0000 0.0000

0.0000 0.0000

0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

0.0000 0.0000

0.0000 0.0000
0.0000 0.0000

0.0000 0.0000
0.0000 0.0000
0.0000 0.0000

1.0000 0.0856

6.2754
MONTHLY PROGRESS REPORT
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

PERIODE : 1 / Maret / 2011 ~ 31 / Maret / 2011

PROGRESS
WEIGHT
NO DESCRIPTION UP TO LAST TOTAL UP TO % PROGRESS

(%) MONTH THIS MONTH CUMMULATIVE

(A) (B) (C) (F) (G)=(E)+(F) (H)=(G)/(C)x100

A. TEMPORARY WORK 4.76218 0.0000 0.4329 9.0909

B. TEMPORARY ME WORK 0.99306 0.0000 0.5754 128.5767


B.1 CIVIL WORKS
B.1.1 CABLE CONECTION WORK 0.09158 0.0000 0.0183 20.0000
B.1.2 RENOVATION EXISTING GENSET ROOM 0.02213 0.0000 0.0000 0.0000

B.2 MECHANICAL WORKS 0.26374 0.0000 0.0835 31.6498

B.3 ELECTRICAL WORKS 0.61562 0.0000 0.4736 76.9269

C. DEMOLITION WORK 1.40354 0.0000 0.4797 303.0573


C. STRUCTURE WORK
C.1 WASHING AREA 0.00875 0.0000 0.0000 0.0000
C.2 MAIN GATE AND BOUNDARY WALL 0.00805 0.0000 0.0000 0.0000
C.3 GUARD HOUSE 0.00424 0.0000 0.0000 0.0000
C.4 OFFICE 0.11102 0.0000 0.0000 0.0000
C.5 CANTEEN 0.09257 0.0000 0.0926 100.0000
C.6 PARKING & TREE 0.10770 0.0000 0.1077 100.0000
C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. 0.73968 0.0000 0.0226 3.0573
C.8 HEXINDO OFFICE 0.02180 0.0000 0.0000 0.0000
C.9 TOUCH UP PAINT BOOTH AREA 0.05295 0.0000 0.0000 0.0000
C.10 STOCK YARD AREA 0.25679 0.0000 0.2568 100.0000

D. BUILDING WORK

D.1 TRAINING CENTER & HEAD OFFICE 11.16837 0.0000 0.0725 17.7408
D.1.1 STRUCTURE WORK
D.1.1.1 EARTH WORK 0.24597 0.0000 0.0000 0.0000
D.1.1.2 PILING WORK 0.40894 0.0000 0.0725 17.7408
D.1.1.3 CONCRETE WORK 1.18616 0.0000 0.0000 0.0000
D.1.1.4 REINFORCED WORK 1.71596 0.0000 0.0000 0.0000
D.1.1.5 FORM WORK 0.87746 0.0000 0.0000 0.0000
D.1.1.6 STEEL STRUCTURE WORK 0.49464 0.0000 0.0000 0.0000
D.1.1.7 MISCELLANEOUS WORK 0.13282 0.0000 0.0000 0.0000

D.1.2 FINISHING WORK


D.1.2.1 METAL ROOFING & METAL WALL WORK 1.07326 0.0000 0.0000 0.0000
D.1.2.2 MASONRY WORK 0.58810 0.0000 0.0000 0.0000
D.1.2.3 TILING WORK 0.37630 0.0000 0.0000 0.0000
D.1.2.4 DOOR AND WINDOW WORK 0.95350 0.0000 0.0000 0.0000
D.1.2.5 PAINTING WORK 0.15234 0.0000 0.0000 0.0000
D.1.2.6 INTERIOR FINISHING WORK 2.04985 0.0000 0.0000 0.0000
D.1.2.7 WATERPROOFING WORK 0.26793 0.0000 0.0000 0.0000
D.1.2.8 MISCELLANEOUS WORK 0.64512 0.0000 0.0000 0.0000

D.2 ULTRA LARGE COMPONENT FACT-2 22.34416 0.0000 1.5539 31.4895


D.2.1 STRUCTURE WORK
D.2.1.1 EARTH WORK 0.33725 0.0000 0.0406 12.0464
D.2.1.2 PILING WORK 7.78288 0.0000 1.5132 19.4431
D.2.1.3 CONCRETE WORK 2.23570 0.0000 0.0000 0.0000
D.2.1.4 REINFORCED WORK 2.72401 0.0000 0.0000 0.0000
D.2.1.5 FORM WORK 0.60935 0.0000 0.0000 0.0000
D.2.1.6 STEEL STRUCTURE WORK 4.84123 0.0000 0.0000 0.0000
D.2.1.7 MISCELLANEOUS WORK 0.08239 0.0000 0.0000 0.0000

D.2.2 FINISHING WORK


D.2.2.1 METAL ROOFING & METAL WALL WORK 1.78077 0.0000 0.0000 0.0000
D.2.2.2 MASONRY WORK 0.17348 0.0000 0.0000 0.0000
D.2.2.3 TILING WORK 0.02202 0.0000 0.0000 0.0000
D.2.2.4 DOOR AND WINDOW WORK 0.94775 0.0000 0.0000 0.0000
D.2.2.5 PAINTING WORK 0.41606 0.0000 0.0000 0.0000
D.2.2.6 INTERIOR FINISHING WORK 0.05144 0.0000 0.0000 0.0000
D.2.2.7 WATERPROOFING WORK 0.04040 0.0000 0.0000 0.0000
D.2.2.8 MISCELLANEOUS WORK 0.29942 0.0000 0.0000 0.0000

D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH 3.01658 0.0000 0.0175 8.4585
D.3.1 STRUCTURE WORK
D.3.1.1 EARTH WORK 0.07503 0.0000 0.0047 6.2694
D.3.1.2 PILING WORK 0.58263 0.0000 0.0128 2.1891
D.3.1.3 CONCRETE WORK 0.34177 0.0000 0.0000 0.0000
D.3.1.4 REINFORCED WORK 0.50742 0.0000 0.0000 0.0000
D.3.1.5 FORM WORK 0.14620 0.0000 0.0000 0.0000
D.3.1.6 STEEL STRUCTURE WORK 0.35324 0.0000 0.0000 0.0000
D.3.1.7 MISCELLANEOUS WORK 0.02273 0.0000 0.0000 0.0000

D.3.2 FINISHING WORK


D.2.2.1 METAL ROOFING & METAL WALL WORK 0.42084 0.0000 0.0000 0.0000
D.2.2.2 MASONRY WORK 0.04568 0.0000 0.0000 0.0000
D.2.2.3 TILING WORK 0.00356 0.0000 0.0000 0.0000
D.2.2.4 DOOR AND WINDOW WORK 0.33186 0.0000 0.0000 0.0000
D.2.2.5 PAINTING WORK 0.06056 0.0000 0.0000 0.0000
D.2.2.6 INTERIOR FINISHING WORK 0.00805 0.0000 0.0000 0.0000
D.2.2.7 WATERPROOFING WORK 0.00068 0.0000 0.0000 0.0000
D.2.2.8 MISCELLANEOUS WORK 0.11634 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 49
PROGRESS
WEIGHT
NO DESCRIPTION UP TO LAST TOTAL UP TO % PROGRESS

(%) MONTH THIS MONTH CUMMULATIVE

(A) (B) (C) (F) (G)=(E)+(F) (H)=(G)/(C)x100

D.4 EXCAVATOR PAINT FACTORY 13.53542 0.0000 0.0000 0.0000


D.4.1 STRUCTURE WORK
D.4.1.1 EARTH WORK 0.70617 0.0000 0.0000 0.0000
D.4.1.2 PILING WORK 0.71149 0.0000 0.0000 0.0000
D.4.1.3 CONCRETE WORK 1.45725 0.0000 0.0000 0.0000
D.4.1.4 REINFORCED WORK 1.83951 0.0000 0.0000 0.0000
D.4.1.5 FORM WORK 0.32842 0.0000 0.0000 0.0000
D.4.1.6 STEEL STRUCTURE WORK 3.53723 0.0000 0.0000 0.0000
D.4.1.7 MISCELLANEOUS WORK 0.05494 0.0000 0.0000 0.0000

D.4.2 FINISHING WORK


D.4.2.1 METAL ROOFING & METAL WALL WORK 2.35276 0.0000 0.0000 0.0000
D.4.2.2 MASONRY WORK 0.51955 0.0000 0.0000 0.0000
D.4.2.3 TILING WORK 0.01146 0.0000 0.0000 0.0000
D.4.2.4 DOOR AND WINDOW WORK 0.93405 0.0000 0.0000 0.0000
D.4.2.5 PAINTING WORK 0.23823 0.0000 0.0000 0.0000
D.4.2.6 INTERIOR FINISHING WORK 0.04468 0.0000 0.0000 0.0000
D.4.2.7 WATERPROOFING WORK 0.01696 0.0000 0.0000 0.0000
D.4.2.8 MISCELLANEOUS WORK 0.78272 0.0000 0.0000 0.0000

D.5 TOUCHUP PAINT BOOTH 0.73952 0.0000 0.0000 0.0000


D.5.1 STRUCTURE WORK
D.5.1.1 EARTH WORK 0.01521 0.0000 0.0000 0.0000
D.5.1.2 PILING WORK 0.06592 0.0000 0.0000 0.0000
D.5.1.3 CONCRETE WORK 0.10945 0.0000 0.0000 0.0000
D.5.1.4 REINFORCED WORK 0.13468 0.0000 0.0000 0.0000
D.5.1.5 FORM WORK 0.05795 0.0000 0.0000 0.0000
D.5.1.6 STEEL STRUCTURE WORK 0.13929 0.0000 0.0000 0.0000
D.5.1.7 MISCELLANEOUS WORK 0.02380 0.0000 0.0000 0.0000

D.5.2 FINISHING WORK


D.5.2.1 METAL ROOFING & METAL WALL WORK 0.08387 0.0000 0.0000 0.0000
D.5.2.2 MASONRY WORK 0.00673 0.0000 0.0000 0.0000
D.5.2.3 TILING WORK 0.00000 0.0000 0.0000 0.0000
D.5.2.4 DOOR AND WINDOW WORK 0.02267 0.0000 0.0000 0.0000
D.5.2.5 PAINTING WORK 0.02494 0.0000 0.0000 0.0000
D.5.2.6 INTERIOR FINISHING WORK 0.00207 0.0000 0.0000 0.0000
D.5.2.7 WATERPROOFING WORK 0.00023 0.0000 0.0000 0.0000
D.5.2.8 MISCELLANEOUS WORK 0.05270 0.0000 0.0000 0.0000

D.6 WASHING AREA 0.26212 0.0000 0.0000 0.0000


D.6.1 STRUCTURE WORK
D.6.1.1 EARTH WORK 0.00974 0.0000 0.0000 0.0000
D.6.1.2 PILING WORK 0.00000 0.0000 0.0000 0.0000
D.6.1.3 CONCRETE WORK 0.02484 0.0000 0.0000 0.0000
D.6.1.4 REINFORCED WORK 0.02346 0.0000 0.0000 0.0000
D.6.1.5 FORM WORK 0.01655 0.0000 0.0000 0.0000
D.6.1.6 STEEL STRUCTURE WORK 0.06485 0.0000 0.0000 0.0000
D.6.1.7 MISCELLANEOUS WORK 0.12268 0.0000 0.0000 0.0000

E. MECHANICAL WORK 12.03803 0.0000 0.0000 0.0000

F. ELECTRICAL WORK 14.64834 0.0000 0.0000 0.0000

G. EXTERNAL WORK

G.1 CIVIL WORK 9.57299 0.0000 3.0580 69.9642

G.1.1 TRAINING CENTER & HEAD OFFICE AREA 0.98023 0.0000 0.0000 0.0000
G.1.1.1 PAVING WORK 0.69379 0.0000 0.0000 0.0000
G.1.1.2 DRAINAGE WORK 0.24656 0.0000 0.0000 0.0000
G.1.1.3 LANDSCAPE WORK 0.01296 0.0000 0.0000 0.0000
G.1.1.4 MISCELLANEOUS WORK 0.02693 0.0000 0.0000 0.0000

G.1.2 EXCAVATOR PAINT FACTORY AREA 0.82498 0.0000 0.0000 0.0000


G.1.2.1 PAVING WORK 0.38305 0.0000 0.0000 0.0000
G.1.2.2 DRAINAGE WORK 0.42044 0.0000 0.0000 0.0000
G.1.2.3 LANDSCAPE WORK 0.00377 0.0000 0.0000 0.0000
G.1.2.4 MISCELLANEOUS WORK 0.01771 0.0000 0.0000 0.0000

G.1.3 ULTRA LARGE COMPONENT FACTORY-2 AREA 1.70938 0.0000 0.0000 0.0000
G.1.3.1 PAVING WORK 1.22001 0.0000 0.0000 0.0000
G.1.3.2 DRAINAGE WORK 0.46890 0.0000 0.0000 0.0000
G.1.3.3 LANDSCAPE WORK 0.00984 0.0000 0.0000 0.0000
G.1.3.4 MISCELLANEOUS WORK 0.01063 0.0000 0.0000 0.0000

G.1.4 TOUCHUP PAINT BOOTH AREA 0.19330 0.0000 0.0000 0.0000


G.1.4.1 DRAINAGE WORK 0.19330 0.0000 0.0000 0.0000

G.1.5 MAIN GATE AND FENCE 0.33456 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 50
PROGRESS
WEIGHT
NO DESCRIPTION UP TO LAST TOTAL UP TO % PROGRESS

(%) MONTH THIS MONTH CUMMULATIVE

(A) (B) (C) (F) (G)=(E)+(F) (H)=(G)/(C)x100

G.1.6 GUARD HOUSE - 1 0.14741 0.0000 0.0000 0.0000


G.1.6.1 STRUCTURE WORK
I EARTH WORK 0.00242 0.0000 0.0000 0.0000
II PILING WORK 0.00000 0.0000 0.0000 0.0000
III CONCRETE WORK 0.02147 0.0000 0.0000 0.0000
IV REINFORCED WORK 0.02876 0.0000 0.0000 0.0000
V FORMWORK 0.02707 0.0000 0.0000 0.0000

G.1.6.2 FINISHING WORK


I DOOR and WINDOW WORK 0.00574 0.0000 0.0000 0.0000
II MASONRY WORK 0.02072 0.0000 0.0000 0.0000
III PAINTING WORK 0.00785 0.0000 0.0000 0.0000
IV INTERIOR FINISHING WORK 0.01275 0.0000 0.0000 0.0000
V WATERPROOFING WORK 0.00859 0.0000 0.0000 0.0000
VI MISCELLANEOUS WORK 0.01203 0.0000 0.0000 0.0000

G.1.7 GUARD HOUSE - 2 0.02012 0.0000 0.0000 0.0000


G.1.7.1 STRUCTURE WORK
I EARTH WORK 0.00024 0.0000 0.0000 0.0000
II PILING WORK 0.00000 0.0000 0.0000 0.0000
III CONCRETE WORK 0.00382 0.0000 0.0000 0.0000
IV REINFORCED WORK 0.00502 0.0000 0.0000 0.0000
V FORMWORK 0.00487 0.0000 0.0000 0.0000

G.1.7.2 FINISHING WORK


I DOOR and WINDOW WORK 0.00000 0.0000 0.0000 0.0000
II MASONRY WORK 0.00208 0.0000 0.0000 0.0000
III PAINTING WORK 0.00110 0.0000 0.0000 0.0000
IV INTERIOR FINISHING WORK 0.00089 0.0000 0.0000 0.0000
V WATERPROOFING WORK 0.00091 0.0000 0.0000 0.0000
VI MISCELLANEOUS WORK 0.00119 0.0000 0.0000 0.0000

G.1.8 RC PAVEMENT & DRAINAGE AREA - A 5.36302 0.0000 3.0580 69.9642


G.1.7.1 PAVING WORK 5.04700 0.0000 3.0264 59.9642
G.1.7.2 DRAINAGE WORK 0.31602 0.0000 0.0316 10.0000

G.2 MECHANICAL WORK 0.02254 0.0000 0.0000 0.0000

G.3 ELECTRICAL WORK 1.73600 0.0000 0.0000 0.0000

H. MOTOR CYCLE PARKING

H.1 CIVIL WORK 2.05759 0.0000 0.0000 0.0000

H.1.1 PAVING WORK & DRAINAGE WORK 0.23619 0.0000 0.0000 0.0000

H.1.2 MOTORCYCLE PARKING AREA ( E, F, G & H ) 0.42140 0.0000 0.0000 0.0000

H.1.3 MOTORCYCLE PARKING BUILDING ( C & D ) 1.35208 0.0000 0.0000 0.0000


H.1.3.1 STRUCTURE WORK
I EARTH WORK 0.04041 0.0000 0.0000 0.0000
II PILING WORK 0.12653 0.0000 0.0000 0.0000
III CONCRETE WORK 0.23536 0.0000 0.0000 0.0000
IV REINFORCED WORK 0.29413 0.0000 0.0000 0.0000
V FORMWORK 0.21384 0.0000 0.0000 0.0000
VI STEEL STRUCTURE WORK 0.06634 0.0000 0.0000 0.0000
VII MISCELLANEOUS WORK 0.02024 0.0000 0.0000 0.0000

H.1.3.2 FINISHING WORK


I METAL ROOFING WORK 0.19542 0.0000 0.0000 0.0000
II MASONRY WORK 0.05691 0.0000 0.0000 0.0000
III PAINTING WORK 0.05528 0.0000 0.0000 0.0000
IV MISCELLANEOUS WORK 0.04762 0.0000 0.0000 0.0000

H.1.4 MISCELLANEOUS WORK 0.04791 0.0000 0.0000 0.0000

H.2 MECHANICAL WORK 0.07171 0.0000 0.0000 0.0000

H.3 ELECTRICAL WORK 0.15997 0.0000 0.0000 0.0000

I. CRANE WORK 1.38228 0.0000 0.0000 0.0000

I.1 TRAINING CENTER & HEAD OFFICE 0.07294 0.0000 0.0000 0.0000
I.2 ULTRA LARGE COMPONENT FACT-2 1.01253 0.0000 0.0000 0.0000
I.3 EXCAVATOR PAINT FACTORY 0.29682 0.0000 0.0000 0.0000

J. SOIL INVESTIGATION WORK 0.08557 0.0000 0.0856 100.0000

TOTAL 100.00000 0.00000 6.2754

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 51
PT. HCMI CIBITUNG EXTENSION PROJECT
PROGRESS OF PROJECT
Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12
PLANNED 0 0.000 5.390 11.477 18.770 26.002 38.500 61.827 83.423 93.170 96.402 98.644 100.000 100.000
ACTUAL 0 0.00 6.28

DEVIATION (5.39) (5.20) (18.77) (26.00) (38.50) (61.83) (83.42) (93.17) (96.40) (98.64) (100.00) (100.00) -
Average 5.390 6.086 7.293 7.232 12.498 23.326 21.596 9.747 3.232 2.242 1.356 0.000
Actual - Planned 0.000 0.885
WEEKLY PROGRESS QUANTITY REPORT

PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT


LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

A. TEMPORARY WORK LOT 1.00 4.76218 4.76218 0.0000 1.4287 1.4287 1.0000 0.0000 6.8035 6.8035

B. TEMPORARY ME WORK LOT 1.00 0.99306 0.99306 1.0000 0.0000 0.0048 0.0048
B.1 CIVIL WORKS LOT 1.00 0.11371 0.0000 0.0006 0.0006
B.1.1 CABLE CONECTION WORK LOT 1.00 0.09158 0.0000 0.0006 0.0006
A Chipping & Repair Road for :
- HV. Cable Route lot 1.00 0.00749 0.0000 0.0022 0.0022 0.0818 0.0000 0.0000 0.0000
- Feeder Cable Route lot 1.00 0.01582 0.0000 0.0047 0.0047 0.1727 0.0000 0.0001 0.0001
- Fire Alarm Cable Route lot 1.00 0.03413 0.0000 0.0102 0.0102 0.3727 0.0000 0.0003 0.0003
- Telephone System Cable Route lot 1.00 0.01415 0.0000 0.0042 0.0042 0.1545 0.0000 0.0001 0.0001
- Sound System Cable Route lot 1.00 0.01415 0.0000 0.0042 0.0042 0.1545 0.0000 0.0001 0.0001
- Cable Fiber Optic & Data lot 1.00 0.00583 0.0000 0.0017 0.0017 0.0636 0.0000 0.0000 0.0000

B.1.2 RENOVATION EXISTING GENSET ROOM LOT 1.00 0.02213 0.0000 0.0000 0.0000
A Additional Louver for Ventilation
- Demolish existing wall lot 1.00 0.00045 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
- Disposed & clean rubbish out project site lot 1.00 0.00035 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
- Steel Louver, size : 4.250mm (W) x 1.600mm (H) nos 2.00 0.01318 0.0000 0.0000 0.0000 0.5956 0.0000 0.0000 0.0000
- Oil Paint Fin. to Steel Louver lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0240 0.0000 0.0000 0.0000
- Repair & Touchup existing wall lot 1.00 0.00177 0.0000 0.0000 0.0000 0.0801 0.0000 0.0000 0.0000

B Extension Pit
- Demolish existing slab lot 1.00 0.00035 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
- Disposed & clean rubbish out project site lot 1.00 0.00025 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
- Additional Pit lot 1.00 0.00170 0.0000 0.0000 0.0000 0.0768 0.0000 0.0000 0.0000
- Repair & Touchup existing floor lot 1.00 0.00354 0.0000 0.0000 0.0000 0.1601 0.0000 0.0000 0.0000

B.2 MECHANICAL WORKS LOT 1.00 0.26374 0.0000 0.0013 0.0013

B.2.1 UNDER CONSTRUCTION WORKS


B.2.1.1 TRAINING CENTER BUILDING & HEAD OFFICE WORKS

B.2.1.1.1 WATER SUPPLY WORKS


B.2.1.1.1.1 EQUIPMENT 0.00576 0.0000 0.0000 0.0000
Roof Water Tank Existing Unit 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Concrete Foundation for Equipment Lot 1.00 0.00104 0.0000 0.0010 0.0010 0.1801 0.0000 0.0000 0.0000
Support for Equipment Lot 1.00 0.00041 0.0000 0.0004 0.0004 0.0715 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00002 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00007 0.0000 0.0001 0.0001 0.0128 0.0000 0.0000 0.0000
Relocation Cost Lot 1.00 0.00422 0.0000 0.0042 0.0042 0.7320 0.0000 0.0000 0.0000

B.2.1.1.1.2 PIPING WORKS 0.01340 0.0000 0.0000 0.0000


Water Supply Pipe
Galvanized Steel Pipe Medium Class
GSP-M 32 mm diameter m 98.00 0.00370 0.0000 0.0037 0.0037 0.2765 0.0000 0.0000 0.0000
GSP-M 25 mm diameter m 24.00 0.00071 0.0000 0.0007 0.0007 0.0533 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00133 0.0000 0.0013 0.0013 0.0990 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00199 0.0000 0.0020 0.0020 0.1485 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00039 0.0000 0.0004 0.0004 0.0289 0.0000 0.0000 0.0000

Gate Valve 10 Kg/Cm2


GV 32 mm diameter Nos 1.00 0.00022 0.0000 0.0002 0.0002 0.0163 0.0000 0.0000 0.0000

Existing Connection Fee Lot 1.00 0.00123 0.0000 0.0012 0.0012 0.0922 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00048 0.0000 0.0005 0.0005 0.0357 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00291 0.0000 0.0029 0.0029 0.2170 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00029 0.0000 0.0003 0.0003 0.0217 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00015 0.0000 0.0001 0.0001 0.0109 0.0000 0.0000 0.0000

B.2.1.1.2 DRAIN WATER WORKS 0.01110 0.0000 0.0000 0.0000


Drainage Water Pipe
PVC Pipe, 10 Kg/cm² (Class VP)
PVC (VP) 100 mm diameter m 30.00 0.00154 0.0000 0.0015 0.0015 0.1384 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00046 0.0000 0.0005 0.0005 0.0415 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00069 0.0000 0.0007 0.0007 0.0623 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00003 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000

Manhole c/w Cover Lot 1.00 0.00397 0.0000 0.0040 0.0040 0.3577 0.0000 0.0000 0.0000
900 x 900 mm (Ø 600 mm)

Excavation & Backfilling Lot 1.00 0.00080 0.0000 0.0008 0.0008 0.0723 0.0000 0.0000 0.0000

Existing Connection Fee Lot 1.00 0.00123 0.0000 0.0012 0.0012 0.1113 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00044 0.0000 0.0004 0.0004 0.0393 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00168 0.0000 0.0017 0.0017 0.1513 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00017 0.0000 0.0002 0.0002 0.0151 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0001 0.0001 0.0076 0.0000 0.0000 0.0000

B.2.1.1.3 FIRE FIGHTING WORKS 0.03758 0.0000 0.0004 0.0004


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 100 mm diameter m 168.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00220 0.0000 0.0022 0.0022 0.0585 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.01484 0.0000 0.0148 0.0148 0.3948 0.0000 0.0002 0.0002

Miscellaneous Material Lot 1.00 0.00085 0.0000 0.0009 0.0009 0.0227 0.0000 0.0000 0.0000
Demolished Cost Lot 1.00 0.00443 0.0000 0.0044 0.0044 0.1178 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.01328 0.0000 0.0133 0.0133 0.3533 0.0000 0.0002 0.0002
Testing & Commisioning Lot 1.00 0.00133 0.0000 0.0013 0.0013 0.0353 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00066 0.0000 0.0007 0.0007 0.0177 0.0000 0.0000 0.0000

B.2.1.2 EXCAVATOR PAINT FACTORY WORKS

B.2.1.2.1 WATER SUPPLY WORKS


B.2.1.2.1.1 EQUIPMENT 0.00225 0.0000 0.0000 0.0000
Roof Water Tank Existing Unit 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 53
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
Concrete Foundation for Equipment Lot 1.00 0.00035 0.0000 0.0003 0.0003 0.1535 0.0000 0.0000 0.0000
Support for Equipment Lot 1.00 0.00041 0.0000 0.0004 0.0004 0.1827 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00002 0.0000 0.0000 0.0000 0.0091 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00004 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
Relocation Cost Lot 1.00 0.00053 0.0000 0.0005 0.0005 0.2339 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00079 0.0000 0.0008 0.0008 0.3508 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00008 0.0000 0.0001 0.0001 0.0351 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00004 0.0000 0.0000 0.0000 0.0176 0.0000 0.0000 0.0000

B.2.1.2.1.2 PIPING WORKS 0.00757 0.0000 0.0000 0.0000


Water Supply Pipe
Galvanized Steel Pipe Medium Class
GSP-M 20 mm diameter m 112.00 0.00215 0.0000 0.0021 0.0021 0.2836 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00064 0.0000 0.0006 0.0006 0.0851 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00097 0.0000 0.0010 0.0010 0.1277 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00019 0.0000 0.0002 0.0002 0.0248 0.0000 0.0000 0.0000

Gate Valve 10 Kg/Cm2


GV 20 mm diameter Nos 2.00 0.00019 0.0000 0.0002 0.0002 0.0256 0.0000 0.0000 0.0000

Existing Connection Fee Lot 1.00 0.00123 0.0000 0.0012 0.0012 0.1632 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00027 0.0000 0.0003 0.0003 0.0355 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00167 0.0000 0.0017 0.0017 0.2213 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00017 0.0000 0.0002 0.0002 0.0221 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0001 0.0001 0.0111 0.0000 0.0000 0.0000

B.2.1.2.2 DRAIN WATER WORKS 0.09830 0.0000 0.0000 0.0000


Existing Septic Tankat Existing Warehouse Unit 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Septic Tank ( Penetration ) Unit 1.00 0.05915 0.0000 0.0000 0.0000 0.6017 0.0000 0.0000 0.0000
Cap. 10 M³/day For Existing Warehouse
Concrete Made

Absortion Well 5 M³ Unit 1.00 0.00947 0.0000 0.0000 0.0000 0.0964 0.0000 0.0000 0.0000

Drainage Water Pipe


PVC Pipe, 10 Kg/cm² (Class VP)
PVC (VP) 100 mm diameter m 60.00 0.00307 0.0000 0.0003 0.0003 0.0313 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00092 0.0000 0.0001 0.0001 0.0094 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00138 0.0000 0.0001 0.0001 0.0141 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00007 0.0000 0.0000 0.0000 0.0007 0.0000 0.0000 0.0000

Manhole c/w Cover Nos 2.00 0.00794 0.0000 0.0000 0.0000 0.0808 0.0000 0.0000 0.0000
900 x 900 mm (Ø 600 mm)

Excavation & Backfilling Lot 1.00 0.00161 0.0000 0.0011 0.0011 0.0163 0.0000 0.0000 0.0000

Existing Connection Fee Lot 1.00 0.00123 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00081 0.0000 0.0001 0.0001 0.0083 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.01008 0.0000 0.0010 0.0010 0.1025 0.0000 0.0000 0.0000
Demolished Cost Lot 1.00 0.00105 0.0000 0.0001 0.0001 0.0107 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00101 0.0000 0.0001 0.0001 0.0103 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00050 0.0000 0.0001 0.0001 0.0051 0.0000 0.0000 0.0000

B.2.1.2.3 FIRE FIGHTING WORKS 0.02720 0.0000 0.0002 0.0002


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 150 mm diameter m 112.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00220 0.0000 0.0022 0.0022 0.0808 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00495 0.0000 0.0049 0.0049 0.1819 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00036 0.0000 0.0004 0.0004 0.0131 0.0000 0.0000 0.0000

Demolished Cost Lot 1.00 0.00443 0.0000 0.0044 0.0044 0.1627 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.01328 0.0000 0.0133 0.0133 0.4882 0.0000 0.0002 0.0002
Testing & Commisioning Lot 1.00 0.00133 0.0000 0.0013 0.0013 0.0488 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00066 0.0000 0.0007 0.0007 0.0244 0.0000 0.0000 0.0000

B.2.1.2.4 HVAC WORKS 0.00451 0.0000 0.0000 0.0000


Outdoor AC at Warehouse Unit 2.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Concrete Foundation for Equipment Lot 1.00 0.00069 0.0000 0.0000 0.0000 0.1535 0.0000 0.0000 0.0000
Support for Equipment Lot 1.00 0.00082 0.0000 0.0000 0.0000 0.1827 0.0000 0.0000 0.0000
Painting for Above Lot 1.00 0.00004 0.0000 0.0000 0.0000 0.0091 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000

Relocation Cost Lot 1.00 0.00105 0.0000 0.0000 0.0000 0.2339 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.00158 0.0000 0.0000 0.0000 0.3508 0.0000 0.0000 0.0000
Testing & Commisioning Lot 1.00 0.00016 0.0000 0.0000 0.0000 0.0351 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0175 0.0000 0.0000 0.0000

B.2.1.4 TOUCHUP PAINT BOOTH WORKS

B.2.1.5 ULTRA LARGE FACTORY 2 & TOPCOAT PAINTING BOOTH


WORKS

B.2.1.5.1 WATER SUPPLY WORKS

B.2.1.5.2 DRAIN WATER WORKS

B.2.1.5.3 FIRE FIGHTING WORKS 0.02183 0.0000 0.0000 0.0000


Fire Hydrant Pipe
Black Steel Pipe Medium Class
BSP-M 150 mm diameter m 90.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Fitting for above Lot 1.00 0.00176 0.0000 0.0000 0.0000 0.0806 0.0000 0.0000 0.0000
Support For Above Lot 1.00 0.00396 0.0000 0.0000 0.0000 0.1813 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00029 0.0000 0.0000 0.0000 0.0131 0.0000 0.0000 0.0000

Demolished Cost Lot 1.00 0.00356 0.0000 0.0000 0.0000 0.1629 0.0000 0.0000 0.0000
Installation Cost Lot 1.00 0.01067 0.0000 0.0000 0.0000 0.4888 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 54
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
Testing & Commisioning Lot 1.00 0.00107 0.0000 0.0000 0.0000 0.0489 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000

B.2.1.6 OFFICE, CANTEEN & PARKING AREA EXISTING 0.03425 0.0000 0.0006 0.0006

Demolish AC, Ventilation, Sanitary Fixture & : Exhaust Fan Lot 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Accessories at Office Canteen

Demolish Work Lot 1.00 0.03425 0.0000 0.0171 0.0171 1.0000 0.0000 0.0006 0.0006

B.3 ELECTRICAL WORKS LOT 1.00 0.61562 0.0000 0.0029 0.0029

B.3.1 UNDER CONSTRUCTION WORK


B.3.1.1 MV INCOMING 0.01983 0.0000 0.0000 0.0000
MV Cable From Existing MVMDB to Factory Phase 3
MV Cable N2XSEBY 3C - 95 mm2 M 530.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

PVC Conduit 150 mm diameter M 126.00 0.00838 0.0000 0.0000 0.0000 0.4223 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00251 0.0000 0.0000 0.0000 0.1267 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00377 0.0000 0.0000 0.0000 0.1901 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 150 mm diameter M 126.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete Roof 2 M 60.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00076 0.0000 0.0000 0.0000 0.0381 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.00282 0.0000 0.0000 0.0000 0.1421 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00152 0.0000 0.0000 0.0000 0.0765 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00008 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000

B.3.1.2 MAIN FEEDER SYSTEM FOR BUILDING FACILITY 0.26550 0.0000 0.0021 0.0021
TRAINING CENTER & OFFICE
Cable NYY 4C - 95 mm2 M 390.00 0.12814 0.0000 0.1281 0.1281 0.4827 0.0000 0.0000 0.0000
NYA 50 mm2 M 390.00 0.01626 0.0000 0.0163 0.0163 0.0613 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00443 0.0000 0.0044 0.0044 0.0167 0.0000 0.0000 0.0000

PVC Conduit 150 mm diameter M 478.00 0.03177 0.0000 0.0318 0.0318 0.1197 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00954 0.0000 0.0095 0.0095 0.0359 0.0000 0.0001 0.0001
Supporting Material Lot 1.00 0.01430 0.0000 0.0143 0.0143 0.0539 0.0000 0.0002 0.0002

Concrete For Sleeve PVC Conduit 150mm diameter M 126.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Temporary Stanchion For Cable Set 1.00 0.03846 0.0000 0.0385 0.0385 0.1449 0.0000 0.0015 0.0015

Miscellaneous Material Lot 1.00 0.01215 0.0000 0.0121 0.0121 0.0458 0.0000 0.0001 0.0001
Labour Fee Lot 1.00 0.00924 0.0000 0.0092 0.0092 0.0348 0.0000 0.0001 0.0001
Testing & Commissioning Fee Lot 1.00 0.00092 0.0000 0.0009 0.0009 0.0035 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00028 0.0000 0.0003 0.0003 0.0010 0.0000 0.0000 0.0000

B.3.1.3 TELEPHONE SYSTEM 0.04586 0.0000 0.0001 0.0001

TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 0.0007 0.0007 0.0144 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00002 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000

Cable From TB Existing Office To TB PH - 1


Cable ITC 20 Pr - 0.6 mm2 M 330.00 0.00746 0.0000 0.0075 0.0075 0.1627 0.0000 0.0000 0.0000
ITC 40 Pr - 0.6 mm2 M 288.00 0.01166 0.0000 0.0117 0.0117 0.2542 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00059 0.0000 0.0006 0.0006 0.0128 0.0000 0.0000 0.0000

PVC Conduit HI 25 mm diameter M 618.00 0.00275 0.0000 0.0028 0.0028 0.0600 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00082 0.0000 0.0008 0.0008 0.0179 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00123 0.0000 0.0012 0.0012 0.0269 0.0000 0.0000 0.0000

PVC Conduit 65 mm diameter M 178.00 0.00233 0.0000 0.0023 0.0023 0.0508 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00070 0.0000 0.0007 0.0007 0.0153 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00105 0.0000 0.0011 0.0011 0.0229 0.0000 0.0000 0.0000

Concrete For Sleeve PVC Conduit 150mm diameter M 148.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00146 0.0000 0.0015 0.0015 0.0319 0.0000 0.0000 0.0000

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 0.0041 0.0041 0.0898 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.00974 0.0000 0.0097 0.0097 0.2125 0.0000 0.0001 0.0001
Testing & Commissioning Fee Lot 1.00 0.00097 0.0000 0.0010 0.0010 0.0212 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00029 0.0000 0.0003 0.0003 0.0064 0.0000 0.0000 0.0000

B.3.1.4 LAN SYSTEM 0.11338 0.0000 0.0005 0.0005

SPLICING BOX Set 1.00 0.00187 0.0000 0.0019 0.0019 0.0165 0.0000 0.0000 0.0000

Cable Fiber Optic 2Pr Single Mode Outdoor type M 677.00 0.03308 0.0000 0.0331 0.0331 0.2917 0.0000 0.0000 0.0000
Fiber Optic 4Pr Single Mode Outdoor type M 349.00 0.03408 0.0000 0.0341 0.0341 0.3006 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00206 0.0000 0.0021 0.0021 0.0182 0.0000 0.0000 0.0000

PVC Conduit HI 25 mm diameter M 1,026.00 0.00457 0.0000 0.0046 0.0046 0.0403 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00136 0.0000 0.0014 0.0014 0.0120 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00204 0.0000 0.0020 0.0020 0.0180 0.0000 0.0000 0.0000

PVC Conduit 65 mm diameter M 134.00 0.00175 0.0000 0.0018 0.0018 0.0155 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00053 0.0000 0.0005 0.0005 0.0046 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00079 0.0000 0.0008 0.0008 0.0070 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 75 mm diameter M 134.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete For Cable M 12.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00401 0.0000 0.0040 0.0040 0.0354 0.0000 0.0000 0.0000

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 0.0041 0.0041 0.0363 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.02045 0.0000 0.0204 0.0204 0.1804 0.0000 0.0004 0.0004
Testing & Commissioning Fee Lot 1.00 0.00204 0.0000 0.0020 0.0020 0.0180 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00061 0.0000 0.0006 0.0006 0.0054 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 55
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

B.3.1.5 PUBLIC ADDRESS SYSTEM 0.01796 0.0000 0.0000 0.0000


TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 0.0007 0.0007 0.0367 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00002 0.0000 0.0000 0.0000 0.0011 0.0000 0.0000 0.0000

Cable From TB-OUTDOOR To TB Existing Office


Cable NYMHY 2C - 1.5mm2 M 287.00 0.00139 0.0000 0.0014 0.0014 0.0776 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00004 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000

PVC Conduit HI 25 mm diameter M 287.00 0.00128 0.0000 0.0013 0.0013 0.0712 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00038 0.0000 0.0004 0.0004 0.0212 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00057 0.0000 0.0006 0.0006 0.0318 0.0000 0.0000 0.0000

PVC Conduit 65 mm diameter M 178.00 0.00233 0.0000 0.0023 0.0023 0.1297 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00070 0.0000 0.0007 0.0007 0.0390 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00105 0.0000 0.0011 0.0011 0.0585 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 65 mm diameter M 148.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00042 0.0000 0.0004 0.0004 0.0234 0.0000 0.0000 0.0000

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 0.0041 0.0041 0.2291 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.00442 0.0000 0.0044 0.0044 0.2462 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00044 0.0000 0.0004 0.0004 0.0246 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00013 0.0000 0.0001 0.0001 0.0074 0.0000 0.0000 0.0000

B.3.1.7 FIRE ALARM SYSTEM 0.10711 0.0000 0.0000 0.0000

FACP 10 Zone Set 1.00 0.00896 0.0000 0.0000 0.0000 0.0836 0.0000 0.0000 0.0000
TB-OUTDOOR FACTORY PH-1 Set 1.00 0.00066 0.0000 0.0000 0.0000 0.0062 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00006 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

Cable NYYHY 8C - 1.5 mm2 M 66.00 0.00100 0.0000 0.0000 0.0000 0.0094 0.0000 0.0000 0.0000
NYYHY 30C - 1.5 mm2 M 294.00 0.01617 0.0000 0.0000 0.0000 0.1510 0.0000 0.0000 0.0000

Termination Cable Lot 1.00 0.00053 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000

Steel Conduit E 25 mm diameter M 60.00 0.00091 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
E 39 mm diameter M 143.00 0.00393 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00145 0.0000 0.0000 0.0000 0.0135 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00223 0.0000 0.0000 0.0000 0.0208 0.0000 0.0000 0.0000

Painting Material Lot 1.00 0.00025 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000

PVC Conduit 50 mm diameter M 38.00 0.00035 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
75 mm diameter M 148.00 0.00266 0.0000 0.0000 0.0000 0.0248 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00090 0.0000 0.0000 0.0000 0.0084 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00136 0.0000 0.0000 0.0000 0.0127 0.0000 0.0000 0.0000

Excavation & Backfilling M³ 110.00 0.00679 0.0000 0.0000 0.0000 0.0634 0.0000 0.0000 0.0000

Concrete For Sleve PVC Conduit 75 mm diameter M 148.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Chipping Concrete For Cable M 38.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00196 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000

Demolish Work For Office & Canteen Lot 1.00 0.00412 0.0000 0.0000 0.0000 0.0384 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.04675 0.0000 0.0000 0.0000 0.4365 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00468 0.0000 0.0000 0.0000 0.0437 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00140 0.0000 0.0000 0.0000 0.0131 0.0000 0.0000 0.0000

B.3.1.8 EXTERNAL LIGHTING SYSTEM 0.01577 0.0000 0.0002 0.0002

U/L COMPONENT FACTORY 2 EXT


Metal Halide 250 W x 1 Street Lighting Set 16.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Pole H: 12 m Set 16.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Fondation for pole lighting ( H = 12 M ) Set 16.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Labour Fee Lot 1.00 0.01396 0.0000 0.0140 0.0140 0.8850 0.0000 0.0002 0.0002
Testing & Commissioning Fee Lot 1.00 0.00140 0.0000 0.0014 0.0014 0.0885 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00042 0.0000 0.0004 0.0004 0.0265 0.0000 0.0000 0.0000

B.3.1.9 LIGHTNING PROTECTION 0.03021 0.0000 0.0000 0.0000

EF Air Terminal c/ w Connection Sleve Set 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Earthing Rod Ø 5/8" Set 1.00 0.00137 0.0000 0.0007 0.0007 0.0454 0.0000 0.0000 0.0000
Hand Hole 400 x 400 x 600 c/w cover Set 1.00 0.00173 0.0000 0.0009 0.0009 0.0572 0.0000 0.0000 0.0000
Pole H: 35 m Set 1.00 0.00000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Fondation for pole lightning ( H = 35 M ) Set 1.00 0.00790 0.0000 0.0040 0.0040 0.2616 0.0000 0.0000 0.0000
Concrete Block 200x200x45h Set 3.00 0.00002 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

Supporting Material Lot 1.00 0.00041 0.0000 0.0002 0.0002 0.0136 0.0000 0.0000 0.0000

Cable Coaxial 35 mm2 x 2 M 40.00 0.01141 0.0000 0.0057 0.0057 0.3777 0.0000 0.0000 0.0000
Termination Cable Lot 1.00 0.00034 0.0000 0.0002 0.0002 0.0113 0.0000 0.0000 0.0000

PVC Conduit 50 mm diameter M 5.00 0.00005 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000

Accessories for above Lot 1.00 0.00001 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
Supporting Material Lot 1.00 0.00002 0.0000 0.0000 0.0000 0.0007 0.0000 0.0000 0.0000

Excavation & Backfilling M³ 12.00 0.00074 0.0000 0.0004 0.0004 0.0245 0.0000 0.0000 0.0000

Miscellaneous Material Lot 1.00 0.00120 0.0000 0.0006 0.0006 0.0397 0.0000 0.0000 0.0000

Government Permit Lot 1.00 0.00247 0.0000 0.0012 0.0012 0.0818 0.0000 0.0000 0.0000
Labour Fee Lot 1.00 0.00223 0.0000 0.0011 0.0011 0.0740 0.0000 0.0000 0.0000
Testing & Commissioning Fee Lot 1.00 0.00022 0.0000 0.0001 0.0001 0.0074 0.0000 0.0000 0.0000
Insite Transportation Lot 1.00 0.00007 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 56
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

C. DEMOLITION WORK LOT 1.00 1.40354 1.40354 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
C. STRUCTURE WORK
C.1 WASHING AREA LOT 1.00 0.00875 0.0000 0.0000 0.0000
A Demolish existing slab concrete lot 1.00 0.00719 0.0000 0.0000 0.0000 0.8218 0.0000 0.0000 0.0000
B Disposal of rubbish lot 1.00 0.00156 0.0000 0.0000 0.0000 0.1782 0.0000 0.0000 0.0000

C.2 MAIN GATE AND BOUNDARY WALL LOT 1.00 0.00805 0.0000 0.0000 0.0000
A Demolish existing boundary wall lot 1.00 0.00253 0.0000 0.0000 0.0000 0.3139 0.0000 0.0000 0.0000
B Demolish existing main gate lot 1.00 0.00040 0.0000 0.0000 0.0000 0.0491 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00396 0.0000 0.0000 0.0000 0.4919 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00117 0.0000 0.0000 0.0000 0.1452 0.0000 0.0000 0.0000

C.3 GUARD HOUSE LOT 1.00 0.00424 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.00197 0.0000 0.0000 0.0000 0.4654 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.00093 0.0000 0.0000 0.0000 0.2204 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00062 0.0000 0.0000 0.0000 0.1470 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00071 0.0000 0.0000 0.0000 0.1672 0.0000 0.0000 0.0000

C.4 OFFICE LOT 1.00 0.11102 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.06342 0.0000 0.0000 0.0000 0.5713 0.0000 0.0000 0.0000
B Demolish existing entrance canopy lot 1.00 0.00361 0.0000 0.0000 0.0000 0.0326 0.0000 0.0000 0.0000
C Demolish existing concrete slab lot 1.00 0.03876 0.0000 0.0000 0.0000 0.3491 0.0000 0.0000 0.0000
D Demolish existing pavement lot 1.00 0.00097 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
E Disposal of rubbish lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0383 0.0000 0.0000 0.0000

C.5 CANTEEN LOT 1.00 0.09257 0.0000 0.0035 0.0035


A Demolish existing RC structure lot 1.00 0.05022 0.0000 0.0502 0.0502 0.5425 0.0000 0.0025 0.0025
B Demolish existing entrance canopy lot 1.00 0.00779 0.0000 0.0078 0.0078 0.0841 0.0000 0.0001 0.0001
C Demolish existing concrete slab lot 1.00 0.03069 0.0000 0.0307 0.0307 0.3315 0.0000 0.0009 0.0009
D Demolish existing pavement lot 1.00 0.00068 0.0000 0.0007 0.0007 0.0073 0.0000 0.0000 0.0000
E Disposal of rubbish lot 1.00 0.00319 0.0000 0.0032 0.0032 0.0344 0.0000 0.0000 0.0000

C.6 PARKING & TREE LOT 1.00 0.10770 0.0000 0.0060 0.0060
A Demolish existing pavement lot 1.00 0.00538 0.0000 0.0054 0.0054 0.0499 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.07494 0.0000 0.0749 0.0749 0.6958 0.0000 0.0056 0.0056
C Demolish existing trees & green space lot 1.00 0.01498 0.0000 0.0150 0.0150 0.1391 0.0000 0.0002 0.0002
D Disposal of rubbish lot 1.00 0.01240 0.0000 0.0124 0.0124 0.1151 0.0000 0.0002 0.0002

C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. LOT 1.00 0.73968 0.0000 0.0011 0.0011
A Demolish existing RC structure lot 1.00 0.31600 0.0000 0.0000 0.0000 0.4272 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.18937 0.0000 0.0000 0.0000 0.2560 0.0000 0.0000 0.0000
C Demolish existing steel plate lot 1.00 0.00478 0.0000 0.0014 0.0014 0.0065 0.0000 0.0000 0.0000
D Demolish existing foundation lot 1.00 0.15113 0.0000 0.0000 0.0000 0.2043 0.0000 0.0000 0.0000
E Demolish existing trees & green space lot 1.00 0.01037 0.0000 0.0031 0.0031 0.0140 0.0000 0.0000 0.0000
F Demolish existing drainage lot 1.00 0.00779 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
G Disposal of rubbish lot 1.00 0.06023 0.0000 0.0181 0.0181 0.0814 0.0000 0.0011 0.0011

C.8 HEXINDO OFFICE LOT 1.00 0.02180 0.0000 0.0000 0.0000


A Demolish existing RC structure lot 1.00 0.00957 0.0000 0.0000 0.0000 0.4387 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.00631 0.0000 0.0000 0.0000 0.2896 0.0000 0.0000 0.0000
C Demolish existing foundation lot 1.00 0.00344 0.0000 0.0000 0.0000 0.1579 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00248 0.0000 0.0000 0.0000 0.1137 0.0000 0.0000 0.0000

C.9 TOUCH UP PAINT BOOTH AREA LOT 1.00 0.05295 0.0000 0.0000 0.0000
A Demolish existing steel wall and door removal lot 1.00 0.01257 0.0000 0.0000 0.0000 0.2374 0.0000 0.0000 0.0000
B Demolish existing concrete slab lot 1.00 0.03170 0.0000 0.0000 0.0000 0.5987 0.0000 0.0000 0.0000
C Demolish existing steel plate lot 1.00 0.00478 0.0000 0.0000 0.0000 0.0903 0.0000 0.0000 0.0000
D Disposal of rubbish lot 1.00 0.00390 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000

C.10 STOCK YARD AREA LOT 1.00 0.25679 0.0000 0.0592 0.0592
A Demolish existing concrete slab lot 1.00 0.24294 0.0000 0.2429 0.2429 0.9461 0.0000 0.0590 0.0590
B Demolish existing drainage lot 1.00 0.00141 0.0000 0.0014 0.0014 0.0055 0.0000 0.0000 0.0000
C Disposal of rubbish lot 1.00 0.01244 0.0000 0.0124 0.0124 0.0484 0.0000 0.0002 0.0002

D. BUILDING WORK LOT 1.00 51.06618 51.06618 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
D.1 TRAINING CENTER & HEAD OFFICE 11.16837 0.0000 0.0000 0.0000
D.1.1 STRUCTURE WORK 5.06195 0.0000 0.0000 0.0000
D.1.1.1 EARTH WORK 0.24597 0.0000 0.0000 0.0000
A Excavate over site to formation level including cleaning m2 3,502.80 0.01111 0.0000 0.0000 0.0000 0.0452 0.0000 0.0000 0.0000
site of all debris
B Excavation to underground tank m3 415.70 0.00494 0.0000 0.0000 0.0000 0.0201 0.0000 0.0000 0.0000
C Excavation to ground slab m3 1,880.00 0.02233 0.0000 0.0000 0.0000 0.0908 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 894.20 0.01551 0.0000 0.0000 0.0000 0.0630 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 145.00 0.00185 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
F Compacted sub grade m2 3,227.20 0.00588 0.0000 0.0000 0.0000 0.0239 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 591.50 0.00966 0.0000 0.0000 0.0000 0.0393 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 526.00 0.00458 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2 2,834.90 0.07633 0.0000 0.0000 0.0000 0.3103 0.0000 0.0000 0.0000
J Plastic Sheet m2 3,110.50 0.00777 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
K Back fill and compac. w/ Imported Red Soil m3 1,866.30 0.08602 0.0000 0.0000 0.0000 0.3497 0.0000 0.0000 0.0000

D.1.1.2 PILING WORK 0.40894 0.0000 0.0000 0.0000


A Allow for mobilization and demobilization of all pilling plant
and equipment
- Mob & Demob pilling equipment unit 1.00 0.01275 0.0000 0.0000 0.0000 0.0312 0.0000 0.0000 0.0000
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.0000 0.0000 0.0312 0.0000 0.0000 0.0000
B PC Spun Pile Ø 300 mm , L=15m nos 194.00 0.27526 0.0000 0.0000 0.0000 0.6731 0.0000 0.0000 0.0000
C Driving Pile m 2,910.00 0.08248 0.0000 0.0000 0.0000 0.2017 0.0000 0.0000 0.0000
D Welding Joint nos 194.00 0.01237 0.0000 0.0000 0.0000 0.0303 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 194.00 0.00482 0.0000 0.0000 0.0000 0.0118 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0208 0.0000 0.0000 0.0000

D.1.1.3 CONCRETE WORK 1.18616 0.0000 0.0000 0.0000


A Lean concrete T = 50 mm , grade K - 150 concrete m2 526.00 0.01438 0.0000 0.0000 0.0000 0.0121 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 163.10 0.07691 0.0000 0.0000 0.0000 0.0648 0.0000 0.0000 0.0000
C Grade K - 350 concrete to Ground Beam m3 106.30 0.05506 0.0000 0.0000 0.0000 0.0464 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 466.60 0.24169 0.0000 0.0000 0.0000 0.2038 0.0000 0.0000 0.0000
E Ditto, but to Column m3 228.00 0.11810 0.0000 0.0000 0.0000 0.0996 0.0000 0.0000 0.0000
F Ditto, but to Beam 2nd Floor m3 234.40 0.12142 0.0000 0.0000 0.0000 0.1024 0.0000 0.0000 0.0000
G Ditto, but to Slab 2nd Floor m3 298.20 0.15446 0.0000 0.0000 0.0000 0.1302 0.0000 0.0000 0.0000
H Ditto, but to Beam 3rd Floor m3 216.30 0.11204 0.0000 0.0000 0.0000 0.0945 0.0000 0.0000 0.0000
I Ditto, but to Slab 3rd Floor m3 278.30 0.14416 0.0000 0.0000 0.0000 0.1215 0.0000 0.0000 0.0000
J Ditto, but to Roof Beam m3 63.00 0.03263 0.0000 0.0000 0.0000 0.0275 0.0000 0.0000 0.0000
K Ditto, but to Roof Slab m3 0.00 0.00000 -
L Ditto, but to Parapet m3 114.70 0.05941 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
M Ditto, but to Roof Gutter m3 7.20 0.00373 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
N Ditto, but to Corbel m3 3.30 0.00171 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
O Ditto, but to Staircase m3 18.60 0.00963 0.0000 0.0000 0.0000 0.0081 0.0000 0.0000 0.0000
P Ditto, but to Column & Beam Shutter m3 1.80 0.00093 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
Q Ditto, but to Underground Tank m3 30.30 0.01570 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
R Ditto, but to STP m3 46.70 0.02419 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000

D.1.1.4 REINFORCED WORK 1.71596 0.0000 0.0000 0.0000


A HT. Reinforcement to Pile Caps kg 22,270.00 0.12624 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 18,215.00 0.10325 0.0000 0.0000 0.0000 0.0602 0.0000 0.0000 0.0000
C Ditto, but to Column kg 49,544.00 0.28084 0.0000 0.0000 0.0000 0.1637 0.0000 0.0000 0.0000
D Ditto, but to Beam 2nd Floor kg 46,183.00 0.26179 0.0000 0.0000 0.0000 0.1526 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 57
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
E Ditto, but to Slab 2nd Floor kg 30,320.00 0.17187 0.0000 0.0000 0.0000 0.1002 0.0000 0.0000 0.0000
F Ditto, but to Beam 3rd Floor kg 42,680.00 0.24193 0.0000 0.0000 0.0000 0.1410 0.0000 0.0000 0.0000
G Ditto, but to Slab 3rd Floor kg 35,224.00 0.19967 0.0000 0.0000 0.0000 0.1164 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam kg 8,526.00 0.04833 0.0000 0.0000 0.0000 0.0282 0.0000 0.0000 0.0000
I Ditto, but to Roof Slab kg 0.00 0.00000 -
J Ditto, but to Parapet kg 11,060.00 0.06269 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
K Ditto, but to Roof Gutter kg 691.00 0.00392 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
L Ditto, but to Corbel kg 2,088.00 0.01184 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
M Ditto, but to Staircase kg 3,231.00 0.01831 0.0000 0.0000 0.0000 0.0107 0.0000 0.0000 0.0000
N Ditto, but to Column & Beam Shutter kg 540.00 0.00306 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
O Ditto, but to Underground Tank kg 3,910.00 0.02216 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
P Ditto, but to STP kg 5,527.00 0.03133 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000
R Wiremesh #M6 to ground slab (2 layer) m2 2,234.00 0.12874 0.0000 0.0000 0.0000 0.0750 0.0000 0.0000 0.0000

D.1.1.5 FORM WORK 0.87746 0.0000 0.0000 0.0000


A Formwork to Pile Caps m2 370.50 0.02153 0.0000 0.0000 0.0000 0.0245 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 708.60 0.04117 0.0000 0.0000 0.0000 0.0469 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 92.10 0.00535 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
D Ditto, but to Column m2 1,752.60 0.11165 0.0000 0.0000 0.0000 0.1272 0.0000 0.0000 0.0000
E Ditto, but to Beam 2nd Floor m2 1,334.70 0.08502 0.0000 0.0000 0.0000 0.0969 0.0000 0.0000 0.0000
F Ditto, but to Slab 2nd Floor m2 2,244.00 0.14295 0.0000 0.0000 0.0000 0.1629 0.0000 0.0000 0.0000
G Ditto, but to Beam 3rd Floor m2 1,214.20 0.07735 0.0000 0.0000 0.0000 0.0881 0.0000 0.0000 0.0000
H Ditto, but to Slab 3rd Floor m2 2,087.70 0.13299 0.0000 0.0000 0.0000 0.1516 0.0000 0.0000 0.0000
I Ditto, but to Roof Beam m2 463.10 0.02950 0.0000 0.0000 0.0000 0.0336 0.0000 0.0000 0.0000
J Ditto, but to Roof Slab m2 0.00 0.00000 -
K Ditto, but to Parapet m2 1,323.00 0.08428 0.0000 0.0000 0.0000 0.0960 0.0000 0.0000 0.0000
L Ditto, but to Roof Gutter m2 93.30 0.00594 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
M Ditto, but to Corbel m2 27.50 0.00175 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
N Ditto, but to Staircase m2 154.80 0.00986 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
O Ditto, but to Column & Beam Shutter m2 23.30 0.00135 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
P Ditto, but to Underground Tank m2 130.50 0.00831 0.0000 0.0000 0.0000 0.0095 0.0000 0.0000 0.0000
Q Ditto, but to STP m2 288.70 0.01839 0.0000 0.0000 0.0000 0.0210 0.0000 0.0000 0.0000
S Supporting formwork to above m2 9,384.80 0.10006 0.0000 0.0000 0.0000 0.1140 0.0000 0.0000 0.0000

D.1.1.6 STEEL STRUCTURE WORK 0.49464 0.0000 0.0000 0.0000


A Steel trusses of main building included. purlin, bracing, etc.. Kg 25,460.00 0.24912 0.0000 0.0000 0.0000 0.5036 0.0000 0.0000 0.0000
B Steel structure of monitor Kg 200.00 0.00196 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding Kg 13,408.00 0.13120 0.0000 0.0000 0.0000 0.2652 0.0000 0.0000 0.0000
D Steel structure of canopy Kg 6,269.00 0.06134 0.0000 0.0000 0.0000 0.1240 0.0000 0.0000 0.0000
E Steel structure of staircase Kg 1,650.00 0.01614 0.0000 0.0000 0.0000 0.0326 0.0000 0.0000 0.0000
F Finishing paint to steel structure Kg 46,987.00 0.03488 0.0000 0.0000 0.0000 0.0705 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.1.1.7 MISCELLANEOUS WORK 0.13282 0.0000 0.0000 0.0000


A Non Shrinkage grouting, size : 420x420x30mm nos 21.00 0.00067 0.0000 0.0000 0.0000 0.0050 0.0000 0.0000 0.0000
B Expansion joint :
- Sand asphalt fill m 796.00 0.01552 0.0000 0.0000 0.0000 0.1169 0.0000 0.0000 0.0000
- Additional reinforcement kg 4,020.00 0.02279 0.0000 0.0000 0.0000 0.1716 0.0000 0.0000 0.0000
- Dowel rebar kg 2,935.00 0.01664 0.0000 0.0000 0.0000 0.1253 0.0000 0.0000 0.0000
- Flexible pipe m 1,062.00 0.00208 0.0000 0.0000 0.0000 0.0156 0.0000 0.0000 0.0000
C Styrofoam T=25mm to under roof slab m2 1,563.30 0.03323 0.0000 0.0000 0.0000 0.2502 0.0000 0.0000 0.0000
D Sand asphalt fill to expansion joint roof m 1,053.00 0.02054 0.0000 0.0000 0.0000 0.1546 0.0000 0.0000 0.0000
E Waterproofing coating m2 209.20 0.00668 0.0000 0.0000 0.0000 0.0503 0.0000 0.0000 0.0000
F Waterstop m 55.00 0.00487 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000
G Cat Ladder at Ground Water Tank ( U Type ) nos 18.00 0.00485 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
H Cast Iron Man Hole at Ground Water Tank nos 2.00 0.00496 0.0000 0.0000 0.0000 0.0373 0.0000 0.0000 0.0000

D.1.2 FINISHING WORK 6.10642 0.0000 0.0000 0.0000


D.1.2.1 METAL ROOFING & METAL WALL WORK LOT 1.07326 0.0000 0.0000 0.0000

Training Center Roofing


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 850.00 0.07285 0.0000 0.0000 0.0000 0.0679 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 850.00 0.00683 0.0000 0.0000 0.0000 0.0064 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 850.00 0.00545 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 850.00 0.00797 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
E End Close, Boltless U-650 m 91.00 0.00205 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 45.50 0.00103 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 45.50 0.00103 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
H End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 91.00 0.00512 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 39.00 0.00219 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
J Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 45.50 0.00151 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
K PVC Pipe AW Grey Dia. 150mm m 48.00 0.00360 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
L PVC Lbow 450 / 900 , Dia. 150mm pcs 20.00 0.00150 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
M Clamp pipe Sp. 3x42mm , Dia. 150mm pcs 52.00 0.00139 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

Training Center Monitor Roof


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 37.40 0.00281 0.0000 0.0000 0.0000 0.0026 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 37.40 0.00030 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 37.40 0.00024 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 37.40 0.00035 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
E Ridge Cover + Sponge Closer, W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 14.00 0.00094 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
F Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 4.00 0.00023 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
G Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 74.70 0.00600 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
H Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 36.00 0.00146 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 36.00 0.00146 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
J Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 8.00 0.00033 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
K Zinc. Louver H = 800mm m 28.00 0.00570 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000

File Room Roofing


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 507.00 0.03805 0.0000 0.0000 0.0000 0.0354 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 507.00 0.00407 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 507.00 0.00325 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 507.00 0.00476 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
E Ridge Cover + Sponge Closer, W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 20.00 0.00134 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
F Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 52.00 0.00293 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
G End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 39.00 0.00219 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
H Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 39.00 0.00129 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
I PVC Pipe AW Grey Dia. 100mm m 16.00 0.00069 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000
J PVC Lbow 450 / 900 , Dia. 100mm pcs 12.00 0.00051 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
K Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 20.00 0.00032 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000

Wall Finish
A Cladding Corrugated Long Metal Sheet, Thk. 0.40mm m2 1,360.00 0.10233 0.0000 0.0000 0.0000 0.0953 0.0000 0.0000 0.0000
Color Coated
B Roof mesh, Galvanized #3x3" m2 634.00 0.00509 0.0000 0.0000 0.0000 0.0047 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 634.00 0.00406 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 634.00 0.00595 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
E Top flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 140.00 0.00469 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
F Corner flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 68.70 0.00230 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
G End flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 140.00 0.00469 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
H Window & Door flashing Corrug. Long Metal Sheet Colour Thk 0.40mm m 185.00 0.00496 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
I PU Sealent m 376.40 0.01560 0.0000 0.0000 0.0000 0.0145 0.0000 0.0000 0.0000
J Cladding Alum. Corrugated Plate, Thk. 0.60mm Color m2 316.00 0.25190 0.0000 0.0000 0.0000 0.2347 0.0000 0.0000 0.0000
( Incld. Sealent & flashing)

carried forward 0.59330

brought forward 0.59330 0.0000 0.0000 0.0000


06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 58
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

METAL ROOFING & METAL WALL WORK

Canopy Finish
A Main Entrance Canopy w/ Color Aluminium Flat batten seam Ls 1.00 0.30935 0.0000 0.0000 0.0000 0.2882 0.0000 0.0000 0.0000
roofing and toplight, size : 13.500 x 11.000mm
B Smoking Canopy w/ Color Aluminium Flat batten seam roofing Ls 1.00 0.07888 0.0000 0.0000 0.0000 0.0735 0.0000 0.0000 0.0000
size : 22.500 x 2.500mm
C Ditto. but to size : 7.000mm (W) x 2.500mm (H) Ls 1.00 0.02892 0.0000 0.0000 0.0000 0.0269 0.0000 0.0000 0.0000
D Entrance Door Canopy w/ Color Aluminium Flat batten seam Ls 1.00 0.01958 0.0000 0.0000 0.0000 0.0182 0.0000 0.0000 0.0000
roofing size : 4.000 x 3.000mm
E Ditto. but to size : 7.000mm (W) x 2.500mm (H) Ls 1.00 0.02429 0.0000 0.0000 0.0000 0.0226 0.0000 0.0000 0.0000
F Ditto. but to size : 4.500mm (W) x 1.000mm (H) Ls 1.00 0.01052 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
G Ditto. but to size : 1.500mm (W) x 1.000mm (H) Ls 2.00 0.00842 0.0000 0.0000 0.0000 0.0078 0.0000 0.0000 0.0000

D.1.2.2 MASONRY WORK LOT 0.58810 0.0000 0.0000 0.0000


A Common brick wall m2 3,180.00 0.21051 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 47.70 0.02012 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 7,632.00 0.04326 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 636.00 0.03695 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 6,360.00 0.27725 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.1.2.3 TILING WORK LOT 0.37630 0.0000 0.0000 0.0000


Floor Finish
A Ceramic Tile 400 x 400 mm m2 191.00 0.01737 0.0000 0.0000 0.0000 0.0462 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 2,102.00 0.17575 0.0000 0.0000 0.0000 0.4670 0.0000 0.0000 0.0000
C Ceramic Tile 200 x 200 mm m2 1,146.00 0.09133 0.0000 0.0000 0.0000 0.2427 0.0000 0.0000 0.0000
D Ceramic Step Nosing m 301.00 0.01310 0.0000 0.0000 0.0000 0.0348 0.0000 0.0000 0.0000
Base Finish
E Ceramic Base H = 100mm m 217.30 0.00465 0.0000 0.0000 0.0000 0.0124 0.0000 0.0000 0.0000
Wall Finish
F Ceramic Tile 200 x 200 mm to brickwall m2 773.10 0.06286 0.0000 0.0000 0.0000 0.1671 0.0000 0.0000 0.0000
G Ceramic Tile 200 x 200 mm to partition wall m2 115.00 0.01123 0.0000 0.0000 0.0000 0.0298 0.0000 0.0000 0.0000

D.1.2.4 DOOR AND WINDOW WORK LOT 0.95350 0.0000 0.0000 0.0000
DOORS
A Motorized steel roll-up shutter (SS -1) nos 1.00 0.02896 0.0000 0.0000 0.0000 0.0304 0.0000 0.0000 0.0000
size : 4.000mm (W) x 6.000mm (H)

B Steel double swinging flush door (SD-1) nos 4.00 0.01806 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
size : 1.700mm (W) x 2.100mm (H)
C Ditto. but to size : 1.600mm (W) x 2.100mm (H) (SD-2) nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
D Steel single swinging flush door (SD-3) nos 3.00 0.00663 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm
E Steel double swinging louver door (SD-4) nos
size : 2.500mm (W) x 2.500mm (H)

F Wooden single swing door w/ vision glass (WD-1) nos 16.00 0.03500 0.0000 0.0000 0.0000 0.0367 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)
G Wooden double swing door w/ vision glass (WD-2) nos 14.00 0.03864 0.0000 0.0000 0.0000 0.0405 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)
H Ditto. but to size : 1.700mm (W) x 2.100mm (H) (WD-3) nos 5.00 0.01716 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
I Wooden single swing door (WD-4) nos
size : 850mm (W) x 2.100mm (H)
J Ditto. but to size : 600mm (W) x 2.100mm (H) (WD-8) nos 2.00 0.00363 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
K Wooden double swing door (WD-5) nos 1.00 0.00242 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)
L Ditto. but to size : 1.700mm (W) x 2.100mm (H) (WD-6) nos 6.00 0.01777 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
M Double swing glass door w/ Wooden Frame (WD-7) nos 11.00 0.04443 0.0000 0.0000 0.0000 0.0466 0.0000 0.0000 0.0000
size : 1.700mm (W) x 2.100mm (H)
N Wooden single sliding door (WD-9) nos 3.00 0.00727 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)

O Toilet Door w/ HPL Finish nos 18.00 0.03090 0.0000 0.0000 0.0000 0.0324 0.0000 0.0000 0.0000
size : 600mm (W) x 2.000mm (H)

P Automatic Double swing S/S glass door w/ fix glass (STD-1) nos 0.00000
size : 12.920mm (W) x 3.000mm (H)
Q Ditto. but to size : 4.920mm (W) x 3.000mm (H) (STD-2) nos 1.00 0.06429 0.0000 0.0000 0.0000 0.0674 0.0000 0.0000 0.0000

R Alum. single swing door w/ grill & fix window glass (AW-1) nos 1.00 0.08510 0.0000 0.0000 0.0000 0.0892 0.0000 0.0000 0.0000
size : 33.255mm (W) x 3.630mm (H)
S Alum. double swing door w/ fix window glass (AW-9) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
size : 4.000mm (W) x 2.960mm (H)
T Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-11) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
U Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-12) nos 1.00 0.00718 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
V Ditto. but to size : 4.000mm (W) x 2.960mm (H) (AW-14) nos 1.00 0.01083 0.0000 0.0000 0.0000 0.0114 0.0000 0.0000 0.0000

W Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.11452 0.0000 0.0000 0.0000 0.1201 0.0000 0.0000 0.0000

WINDOWS
A Alum. Fix glass window w/ grill nos 1.00 0.01864 0.0000 0.0000 0.0000 0.0196 0.0000 0.0000 0.0000
size : 7.100mm (W) x 3.450mm (AW -2)
B Ditto. but to size : 45.000mm (W) x 3.350mm (H) (AW-3) nos 1.00 0.11134 0.0000 0.0000 0.0000 0.1168 0.0000 0.0000 0.0000
C Ditto. but to size : 21.600mm (W) x 3.550mm (H) (AW-6) nos 1.00 0.04789 0.0000 0.0000 0.0000 0.0502 0.0000 0.0000 0.0000
D Ditto. but to size : 21.600mm (W) x 1.200mm (H) (AW-7) nos 1.00 0.02497 0.0000 0.0000 0.0000 0.0262 0.0000 0.0000 0.0000
E Ditto. but to size : 15.100mm (W) x 1.200mm (H) (AW-16) nos 1.00 0.01956 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

carried forward 0.77377

brought forward 0.77377 0.0000 0.0000 0.0000

DOOR AND WINDOW WORK


WINDOWS
F Alum. Fix glass window (AW-4) nos 1.00 0.07425 0.0000 0.0000 0.0000 0.0779 0.0000 0.0000 0.0000
size : 11.750mm (W) x 3.010mm
G Ditto. but to size : 9.500mm (W) x 600mm (H) (AW-5) nos 1.00 0.00341 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000 0.0000
H Ditto. but to size : 700mm (W) x 9.550mm (H) (AW-8) nos 1.00 0.00490 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000
I Ditto. but to size : 4.000mm (W) x 600mm (H) (AW-10) nos 4.00 0.00575 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
J Ditto. but to size : 4.000mm (W) x 1.710mm (H) (AW-13) nos 6.00 0.03010 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
K Ditto. but to size : 4.000mm (W) x 520mm (H) (AW-15) nos 6.00 0.00915 0.0000 0.0000 0.0000 0.0096 0.0000 0.0000 0.0000
L Ditto. but to size : 1.600mm (W) x 2.590mm (H) (AW-17) nos 2.00 0.00652 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
M Ditto. but to size : 5.000mm (W) x 2.590mm (H) (AW-18) nos 1.00 0.00978 0.0000 0.0000 0.0000 0.0103 0.0000 0.0000 0.0000
N Ditto. but to size : 5.000mm (W) x 1.710mm (H) (AW-19) nos 3.00 0.01975 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
O Ditto. but to size : 2.500mm (W) x 1.710mm (H) (AW-20) nos 4.00 0.01368 0.0000 0.0000 0.0000 0.0144 0.0000 0.0000 0.0000

P Wooden window w/ fix glass & wooden counter (WW-1) nos 1.00 0.00242 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
size : 700mm (W) x 900mm

D.1.2.5 PAINTING WORK LOT 0.15234 0.0000 0.0000 0.0000


A Weathershield paint to external wall m2 1,212.00 0.02445 0.0000 0.0000 0.0000 0.1605 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 3,200.00 0.03671 0.0000 0.0000 0.0000 0.2410 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 4,335.00 0.04973 0.0000 0.0000 0.0000 0.3264 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 454.00 0.00824 0.0000 0.0000 0.0000 0.0541 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 220.00 0.00148 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 59
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
F Floor Hardener Green Color to Floor m2 760.50 0.03074 0.0000 0.0000 0.0000 0.2018 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 58.50 0.00098 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000

D.1.2.6 INTERIOR FINISHING WORK LOT 2.04985 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 2,531.00 0.00803 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000
B Floor Screeding w/ cement mortar m2 1,712.00 0.04425 0.0000 0.0000 0.0000 0.0216 0.0000 0.0000 0.0000
C PVC Tile 300 x 300mm m2 1,357.00 0.16016 0.0000 0.0000 0.0000 0.0781 0.0000 0.0000 0.0000
D import Carpet Tile 600 x 600 mm m2 355.00 0.11319 0.0000 0.0000 0.0000 0.0552 0.0000 0.0000 0.0000
E Raised Floor H = 100mm m2 1,378.00 0.42059 0.0000 0.0000 0.0000 0.2052 0.0000 0.0000 0.0000

Base Finish
E Wooden Base H = 100mm m 1,331.00 0.08021 0.0000 0.0000 0.0000 0.0391 0.0000 0.0000 0.0000
F Mortar Base w/ AE H = 100mm m 176.00 0.00188 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
G Mortar Base w/ VP H = 100mm m 215.00 0.00274 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

carried forward 0.83105

brought forward 0.83105 0.0000 0.0000 0.0000

INTERIOR FINISHING WORK


Wall Finish
H Drywall Partition Gypsum Board (2side) m2 1,509.00 0.15081 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
I Drywall Partition Gypsum Board (1side) m2 634.00 0.05168 0.0000 0.0000 0.0000 0.0252 0.0000 0.0000 0.0000
J Extra steel chanel to ditto kg 6,429.00 0.06291 0.0000 0.0000 0.0000 0.0307 0.0000 0.0000 0.0000
K Movable Partition (Steel Partition) m2 583.00 0.18829 0.0000 0.0000 0.0000 0.0919 0.0000 0.0000 0.0000
L Low Partition H = 1.800mm m2 48.20 0.01557 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
M Vynil Wall Covering m2 2,529.00 0.24200 0.0000 0.0000 0.0000 0.1181 0.0000 0.0000 0.0000
N Framless Glass Partition m2 29.00 0.02363 0.0000 0.0000 0.0000 0.0115 0.0000 0.0000 0.0000

Ceiling Finish
O Gypsum Board (Flat) T=9mm w/ LGS Frame m2 3,292.00 0.16795 0.0000 0.0000 0.0000 0.0819 0.0000 0.0000 0.0000
P Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 921.00 0.06184 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
Q Gypsum Tile 600 x 600mm T=9mm w/ T-Bar system m2 59.00 0.00284 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
R Drop Ceiling H = 300mm m 261.00 0.01203 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
S Wooden Ceiling W = 150mm, 50mm Thick m2 70.00 0.03348 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
T Extra steel chanel to ditto kg 13,026.00 0.12746 0.0000 0.0000 0.0000 0.0622 0.0000 0.0000 0.0000
U Wooden Curtain Box 150mm Width w/ OP Fin. m 255.00 0.06324 0.0000 0.0000 0.0000 0.0309 0.0000 0.0000 0.0000
V Wooden Light Box 150mm Width w/ OP Fin. m 72.00 0.00893 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
W Acrylic Louver Cover to above m 72.00 0.00434 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
X Skim coat to Exposed Ceiling m2 122.00 0.00182 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000

D.1.2.7 WATERPROOFING WORK LOT 0.26793 0.0000 0.0000 0.0000

A Waterproofing coating m2 209.00 0.00667 0.0000 0.0000 0.0000 0.0249 0.0000 0.0000 0.0000
B Mortar screeding protection to above m2 209.00 0.00540 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
C Waterproofing membrane m2 1,783.00 0.10745 0.0000 0.0000 0.0000 0.4010 0.0000 0.0000 0.0000
D Protection concrete 50 mm to waterproofing membrane m2 1,609.00 0.11922 0.0000 0.0000 0.0000 0.4450 0.0000 0.0000 0.0000
E Protection brick w/ plaster 1 side m2 72.00 0.00791 0.0000 0.0000 0.0000 0.0295 0.0000 0.0000 0.0000
F Groove w/ fill polyurethane sealent (15w x 15d) m 909.00 0.02129 0.0000 0.0000 0.0000 0.0794 0.0000 0.0000 0.0000

D.1.2.8 MISCELLANEOUS WORK LOT 0.64512 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 4.00 0.00128 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 22.00 0.00203 0.0000 0.0000 0.0000 0.0032 0.0000 0.0000 0.0000
C Maintenance steel ladder w/ cage H : 4.000 mm unit 1.00 0.00553 0.0000 0.0000 0.0000 0.0086 0.0000 0.0000 0.0000
D Steel Handrail H = 1000mm w/ OP finish m 143.00 0.05573 0.0000 0.0000 0.0000 0.0864 0.0000 0.0000 0.0000
E Pantry Sink w/ Cabinet unit 2.00 0.03401 0.0000 0.0000 0.0000 0.0527 0.0000 0.0000 0.0000
F S/S Kitchen Sink unit 1.00 0.00319 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
G Kitchen Counter w/ brick + Rc Concrete & SUS pipe rail m 11.00 0.01637 0.0000 0.0000 0.0000 0.0254 0.0000 0.0000 0.0000
H Hand washing w/ Ceramic Tile m 16.00 0.00850 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
I Lavatory concrete table w/ top marble finish
- Size : 2.000mm (L) x 600mm (W) unit 6.00 0.01275 0.0000 0.0000 0.0000 0.0198 0.0000 0.0000 0.0000
- Size : 3.200mm (L) x 600mm (W) unit 3.00 0.01020 0.0000 0.0000 0.0000 0.0158 0.0000 0.0000 0.0000
J Wall mirror at toilet :
- Size : 2.000mm (L) x 1.000mm (H) unit 6.00 0.00808 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
- Size : 3.200mm (L) x 1.000mm (H) unit 3.00 0.00638 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
K Shower screen unit 52.00 0.04606 0.0000 0.0000 0.0000 0.0714 0.0000 0.0000 0.0000
L Receptionist Counter unit 1.00 0.03189 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
M Wooden cassing finish OP to alum. window m 670.00 0.03088 0.0000 0.0000 0.0000 0.0479 0.0000 0.0000 0.0000
N Motorized Projection Screen unit 4.00 0.04960 0.0000 0.0000 0.0000 0.0769 0.0000 0.0000 0.0000
O Vertical Blind m2 536.00 0.10634 0.0000 0.0000 0.0000 0.1648 0.0000 0.0000 0.0000
P Room name plate nos 45.00 0.00877 0.0000 0.0000 0.0000 0.0136 0.0000 0.0000 0.0000
Q Room Name Sheet nos 11.00 0.00214 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
R Movable Partition, size : 6.500 x 3.000mm nos 1.00 0.02267 0.0000 0.0000 0.0000 0.0351 0.0000 0.0000 0.0000
S Picture Rail nos 18.00 0.01913 0.0000 0.0000 0.0000 0.0297 0.0000 0.0000 0.0000
T S/S Insect Net to Ventilation m2 88.00 0.02182 0.0000 0.0000 0.0000 0.0338 0.0000 0.0000 0.0000
U Grating cover 300mm m 64.00 0.03560 0.0000 0.0000 0.0000 0.0552 0.0000 0.0000 0.0000
V Grating cover 600mm m 5.00 0.00478 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
W PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 156.00 0.02930 0.0000 0.0000 0.0000 0.0454 0.0000 0.0000 0.0000
X Cast iron roof drain nos 12.00 0.00298 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
Y Exterior Column Fin. w/ Fluoro Carbon Polymenr Paint lot 1.00 0.00886 0.0000 0.0000 0.0000 0.0137 0.0000 0.0000 0.0000
Z External Company Logo & Sign lot 1.00 0.03189 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
AA Receptionist Company Logo & Sign lot 1.00 0.01771 0.0000 0.0000 0.0000 0.0275 0.0000 0.0000 0.0000
AB Alum Coping for Expantion Joint m 43.00 0.01066 0.0000 0.0000 0.0000 0.0165 0.0000 0.0000 0.0000

D.2 ULTRA LARGE COMPONENT FACT-2 22.34416 0.0000 0.2130 0.2130


D.2.1 STRUCTURE WORK 18.61281 0.0000 0.2130 0.2130
D.2.1.1 EARTH WORK 0.33725 0.0000 0.0000 0.0000
A Excavate over site to formation level including cleaning m2 9,851.30 0.03124 0.0000 0.0187 0.0187 0.0926 0.0000 0.0000 0.0000
site of all debris
B Excavation to ground slab m3 3,278.00 0.03893 0.0000 0.0000 0.0000 0.1154 0.0000 0.0000 0.0000
C Excavation to pile cap & g.beam m3 3,511.60 0.06090 0.0000 0.0000 0.0000 0.1806 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 2,324.20 0.02964 0.0000 0.0000 0.0000 0.0879 0.0000 0.0000 0.0000
E Compacted sub grade m2 9,841.00 0.01793 0.0000 0.0000 0.0000 0.0532 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 4,466.00 0.07293 0.0000 0.0219 0.0219 0.2163 0.0000 0.0000 0.0000
G T=50mm comp. sand bedding m2 9,841.00 0.08567 0.0000 0.0000 0.0000 0.2540 0.0000 0.0000 0.0000
H T=200mm comp. basecourse m2 -

D.2.1.2 PILING WORK 7.78288 0.0000 0.2130 0.2130


PC SPUN PILE
A Allow for mobilization and demobilization of all
pilling plant and equipment
- Mob & Demob pilling equipment unit 4.00 0.05102 0.0000 0.0255 0.0255 0.0066 0.0000 0.0003 0.0003
- Mob & Demob Service Crane unit 2.00 0.02551 0.0000 0.0128 0.0128 0.0033 0.0000 0.0002 0.0002
B PC Spun Pile Ø 300mm , L=30m nos 1,489.00 4.22549 0.0000 2.5353 2.5353 0.5429 0.0000 0.0072 0.0072
C Driving PC Spun Pile Ø 300mm m 44,670.00 1.26605 0.0000 3,087.0000 3,087.0000 0.1627 0.0000 0.0875 0.0875
D Welding Joint PC Spun Pile Ø 300mm nos 2,978.00 0.18991 0.0000 205.8000 205.8000 0.0244 0.0000 0.0131 0.0131
E Cut off excess pile length at required level & expose nos 1,489.00 0.03698 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PC Spun Pile Ø 450mm , L=30m nos 291.00 1.48086 0.0000 0.8885 0.8885 0.1903 0.0000 0.0045 0.0045
G Driving PC Spun Pile Ø 450mm m 8,730.00 0.37114 0.0000 2,058.0000 2,058.0000 0.0477 0.0000 0.0875 0.0875
H Welding Joint PC Spun Pile Ø 450mm nos 291.00 0.02680 0.0000 137.2000 137.2000 0.0034 0.0000 0.0126 0.0126
I Cut off excess pile length at required level & expose nos 291.00 0.00929 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 60
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
reinforcements incl. all necessary excav. Required
J PDA Test nos 6.00 0.02551 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000

BORED PILE
K Mobilization Lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
L Prelimenaries Work Lot 1.00 0.00213 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
M Drilling Work from ground level Ø 400mm m 270.00 0.01722 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
N Grade K - 250 concrete m3 34.00 0.01603 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
O HT. Reinforcement kg 4,021.00 0.02279 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000
P Soil Disposal m 270.00 0.00765 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
Q Demobilization Lot 1.00 0.00425 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000

D.2.1.3 CONCRETE WORK 2.23570 0.0000 0.0000 0.0000


A Lean concrete T = 50 mm , grade K - 150 concrete m2 9,841.00 0.26896 0.0000 0.0000 0.0000 0.1203 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 466.00 0.21975 0.0000 0.0000 0.0000 0.0983 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 178.40 0.08413 0.0000 0.0000 0.0000 0.0376 0.0000 0.0000 0.0000
D Ditto , but to Drop Panel m3 348.30 0.16424 0.0000 0.0000 0.0000 0.0735 0.0000 0.0000 0.0000
E Ditto , but to Ground Slab m3 2,178.40 1.02725 0.0000 0.0000 0.0000 0.4595 0.0000 0.0000 0.0000
F Ditto, but to Column m3 693.00 0.32679 0.0000 0.0000 0.0000 0.1462 0.0000 0.0000 0.0000
G Ditto, but to Middle Beam m3 104.40 0.04923 0.0000 0.0000 0.0000 0.0220 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam m3 6.70 0.00316 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I Ditto, but to Roof Slab m3 28.20 0.01330 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
J Ditto, but to Parapet m3 6.40 0.00302 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
K Ditto, but to Column & Beam Shutter m3 21.00 0.00990 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
L Ditto, but to Machine Foundation m3 28.40 0.01339 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
M Ditto, but to Gantry Foundation m3 57.10 0.02693 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
N Ditto, but to End Carriage Rail m3 2.20 0.00104 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
O Ditto, but to Corbel m3 52.20 0.02462 0.0000 0.0000 0.0000 0.0110 0.0000 0.0000 0.0000

D.2.1.4 REINFORCED WORK 2.72401 0.0000 0.0000 0.0000


A HT. Reinforcement to Pile Caps kg 37,704.00 0.21372 0.0000 0.0000 0.0000 0.0785 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 35,220.00 0.19964 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel kg 14,524.00 0.08233 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab kg 185,942.00 1.05400 0.0000 0.0000 0.0000 0.3869 0.0000 0.0000 0.0000
E Ditto, but to Column kg 152,120.00 0.86229 0.0000 0.0000 0.0000 0.3166 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam kg 16,522.00 0.09365 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam kg 1,346.00 0.00763 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab kg 2,539.00 0.01439 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
I Ditto, but to Parapet kg 608.00 0.00345 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter kg 6,237.00 0.03535 0.0000 0.0000 0.0000 0.0130 0.0000 0.0000 0.0000
K Ditto, but to Machine Foundation kg 2,602.00 0.01475 0.0000 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000
L Ditto, but to Gantry Foundation kg 4,983.00 0.02825 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
M Ditto, but to End Carriage Rail kg 1,213.00 0.00688 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
N Ditto, but to Corbel kg 18,995.00 0.10767 0.0000 0.0000 0.0000 0.0395 0.0000 0.0000 0.0000

D.2.1.5 FORM WORK 0.60935 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 836.20 0.04858 0.0000 0.0000 0.0000 0.0797 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 1,157.00 0.06722 0.0000 0.0000 0.0000 0.1103 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel m2 1,786.00 0.10377 0.0000 0.0000 0.0000 0.1703 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m2 277.80 0.01614 0.0000 0.0000 0.0000 0.0265 0.0000 0.0000 0.0000
E Ditto, but to Column m2 3,311.90 0.21098 0.0000 0.0000 0.0000 0.3462 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m2 863.10 0.05498 0.0000 0.0000 0.0000 0.0902 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m2 66.80 0.00426 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab m2 197.80 0.01260 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
I Ditto, but to Parapet m2 75.50 0.00481 0.0000 0.0000 0.0000 0.0079 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter m2 96.30 0.00613 0.0000 0.0000 0.0000 0.0101 0.0000 0.0000 0.0000
K Ditto, but to Machine Foundation m2 26.20 0.00152 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
L Ditto, but to Gantry Foundation m2 146.20 0.00849 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
M Ditto, but to End Carriage Rail m2 8.50 0.00049 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
N Ditto, but to Corbel m2 270.60 0.01724 0.0000 0.0000 0.0000 0.0283 0.0000 0.0000 0.0000
O Supporting formwork to above m2 4,889.20 0.05213 0.0000 0.0000 0.0000 0.0855 0.0000 0.0000 0.0000

D.2.1.6 STEEL STRUCTURE WORK 4.84123 0.0000 0.0000 0.0000

A Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 278,627.40 2.72632 0.0000 0.0000 0.0000 0.5631 0.0000 0.0000 0.0000

B Steel structure of metal fascia Kg 3,784.40 0.03703 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding Kg 22,944.20 0.22451 0.0000 0.0000 0.0000 0.0464 0.0000 0.0000 0.0000
D Steel structure of canopy Kg 10,098.80 0.09882 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000
E Steel structure of gantry corbel Kg 159,187.40 1.55762 0.0000 0.0000 0.0000 0.3217 0.0000 0.0000 0.0000
F Steel structure of staircase Kg 4,885.40 0.04780 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
G Finishing paint to steel structure Kg 200,900.20 0.14913 0.0000 0.0000 0.0000 0.0308 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.2.1.7 MISCELLANEOUS WORK 0.08239 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 76.00 0.00243 0.0000 0.0000 0.0000 0.0294 0.0000 0.0000 0.0000
B Sand asphalt fill to expansion joint roof m 218.00 0.00425 0.0000 0.0000 0.0000 0.0516 0.0000 0.0000 0.0000
C Styrofoam T=25mm to under roof slab m2 187.00 0.00398 0.0000 0.0000 0.0000 0.0482 0.0000 0.0000 0.0000
D Expansion joint to existing slab :
- Sand asphalt fill m 110.00 0.00215 0.0000 0.0000 0.0000 0.0260 0.0000 0.0000 0.0000
- Dowel rebar kg 402.00 0.00228 0.0000 0.0000 0.0000 0.0277 0.0000 0.0000 0.0000
- Flexible pipe m 145.00 0.00028 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
E Machine Foundation Work :
- Support D10 @300 kg 36.00 0.00020 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
- Bending Plate 9mm Thick kg 1,174.00 0.01149 0.0000 0.0000 0.0000 0.1394 0.0000 0.0000 0.0000
F - Base Adjuster L 50x50x5 kg 88.00 0.00086 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
- Edge L 60x60x6 kg
Gantry Rail Foundation Work :
G - Embeded Bar D12 @300 kg 2,039.00 0.01995 0.0000 0.0000 0.0000 0.2421 0.0000 0.0000 0.0000
- Base Adjuster L 50x50x5 kg 2,766.00 0.02706 0.0000 0.0000 0.0000 0.3285 0.0000 0.0000 0.0000
End Carriage Rail Work :
- Base Adjuster L 50x50x5 kg 763.00 0.00747 0.0000 0.0000 0.0000 0.0906 0.0000 0.0000 0.0000

D.2.2 FINISHING WORK 3.73135 0.0000 0.0000 0.0000

D.2.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 1.78077 0.0000 0.0000 0.0000

Metal Roofing Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 6,175.00 0.52921 0.0000 0.0000 0.0000 0.2972 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 0.00 0.00000 -
C Aluminium foil single sided m2 0.00 0.00000 -
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00 0.00000 -
E End Close, Boltless U-650 m 556.00 0.01253 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 278.00 0.00627 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 278.00 0.00627 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
H Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 75.00 0.00503 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 140.00 0.00788 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
J Expantion Cover W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 70.00 0.00394 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
K Monitor Nagare Flashing. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 912.00 0.05133 0.0000 0.0000 0.0000 0.0288 0.0000 0.0000 0.0000
L End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 131.00 0.00737 0.0000 0.0000 0.0000 0.0041 0.0000 0.0000 0.0000
M Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 278.00 0.00923 0.0000 0.0000 0.0000 0.0052 0.0000 0.0000 0.0000
N Eaves FRP Gutter , Grey Thk 2.0mm , W=1.100mm m 245.00 0.05054 0.0000 0.0000 0.0000 0.0284 0.0000 0.0000 0.0000
O Gutter Bracket Steel Angle 30x30x30x3 mm, W=1.300mm pcs 378.00 0.01316 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
P PVC Pipe AW Grey Dia. 200mm m 612.00 0.08198 0.0000 0.0000 0.0000 0.0460 0.0000 0.0000 0.0000
Q PVC Lbow 450 / 900 , Dia. 200mm pcs 144.00 0.01929 0.0000 0.0000 0.0000 0.0108 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 61
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
R Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 648.00 0.02086 0.0000 0.0000 0.0000 0.0117 0.0000 0.0000 0.0000

Monitor Roof
A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 2,784.00 0.23859 0.0000 0.0000 0.0000 0.1340 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 0.00 0.00000 -
C Aluminium foil single sided m2 0.00 0.00000 -
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00 0.00000 -
E End Close, Boltless U-650 m 384.00 0.00865 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
F Appron Boltless U-650 m 96.00 0.00216 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
G Eaves Close Boltless U-650 m 192.00 0.00433 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
H Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 48.00 0.00322 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
I Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 928.00 0.05223 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
J End Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 96.00 0.00540 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
K Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 192.00 0.00637 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000 0.0000
L Monitor Wall FRP Type U-527 (27mm) Clear/Natural Thk. 2,0mm m2 547.00 0.10258 0.0000 0.0000 0.0000 0.0576 0.0000 0.0000 0.0000
M Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 320.00 0.02572 0.0000 0.0000 0.0000 0.0144 0.0000 0.0000 0.0000
N Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 245.00 0.00997 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
O End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 245.00 0.00997 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
P Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 3.00 0.00012 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 3,841.50 0.30874 0.0000 0.0000 0.0000 0.1734 0.0000 0.0000 0.0000
B FRP Cladding Type U527 (27mm) Clear/Natural, Thk. 1,5mm m 528.80 0.07790 0.0000 0.0000 0.0000 0.0437 0.0000 0.0000 0.0000
C End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 246.00 0.01001 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
D Window, Shutter & Open flashing W=457mm, Zincalume m 283.00 0.01152 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
Thk 0.4mm -
E Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 33.00 0.00134 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
F Wall Expansion Cover W=457mm, Zincalume Colour Thk 0.40mm m 33.00 0.00134 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 336.00 0.02521 0.0000 0.0000 0.0000 0.0142 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 240.00 0.01351 0.0000 0.0000 0.0000 0.0076 0.0000 0.0000 0.0000
C Steel Hollow 40x20x2,3mm + Zinchromate m 336.00 0.00991 0.0000 0.0000 0.0000 0.0056 0.0000 0.0000 0.0000
D Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 84.00 0.01575 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
E Gutter Bracket Sp 3x42mm W=1.200mm pcs 178.00 0.00573 0.0000 0.0000 0.0000 0.0032 0.0000 0.0000 0.0000
F PVC Pipe AW Grey Dia. 100mm m 80.00 0.00343 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
G PVC Lbow 450 / 900 , Dia. 100mm pcs 18.00 0.00077 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000
H Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 88.00 0.00141 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

D.2.2.2 MASONRY WORK 0.17348 0.0000 0.0000 0.0000

A Common brick wall m2 938.00 0.06210 0.0000 0.0000 0.0000 0.0349 0.0000 0.0000 0.0000
B Ventilation block wall m2 0.00000 -
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 14.10 0.00595 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
- HT. Reinforcement kg 2,251.00 0.01276 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Timber formwork m2 187.60 0.01090 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 1,876.00 0.08178 0.0000 0.0000 0.0000 0.0459 0.0000 0.0000 0.0000
w/ instant mortar

D.2.2.3 TILING WORK 0.02202 0.0000 0.0000 0.0000

Floor Finish
A Ceramic Tile 200 x 200 mm m2 180.00 0.01435 0.0000 0.0000 0.0000 0.6514 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 12.00 0.00100 0.0000 0.0000 0.0000 0.0456 0.0000 0.0000 0.0000
Base Finish
C Ceramic Base H = 100mm m 49.00 0.00105 0.0000 0.0000 0.0000 0.0476 0.0000 0.0000 0.0000
Wall Finish
D Ceramic Tile 200 x 200 mm m2 69.20 0.00563 0.0000 0.0000 0.0000 0.2555 0.0000 0.0000 0.0000

D.2.2.4 DOOR AND WINDOW WORK 0.94775 0.0000 0.0000 0.0000

DOORS
A Steel double hanging sliding door w/ FRP Panel (SD-1) nos 3.00 0.42090 0.0000 0.0000 0.0000 0.4441 0.0000 0.0000 0.0000
size : 10.000mm (W) x 10.000mm (H)
B Ditto. but to size : 8.000mm (W) x 8.000mm (H) (SD-2) nos 2.00 0.17958 0.0000 0.0000 0.0000 0.1895 0.0000 0.0000 0.0000
C Ditto. but to size : 5.000mm (W) x 6.000mm (H) (SD-3) nos 4.00 0.16836 0.0000 0.0000 0.0000 0.1776 0.0000 0.0000 0.0000

D Steel double swinging flush door w/ Louver (SD-4) nos 2.00 0.01037 0.0000 0.0000 0.0000 0.0109 0.0000 0.0000 0.0000
size : 1.800mm (W) x 2.100mm (H)
E Ditto. but to size : 1.800mm (W) x 2.500mm (H) (SD-5) nos 1.00 0.00617 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
F Steel single swinging flush door (SD-6) nos 4.00 0.00883 0.0000 0.0000 0.0000 0.0093 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm
G Steel single swinging flush mesh door (SD-7) nos 3.00 0.00707 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
size : 800mm (W) x 2.000mm
H Ditto. but to size : 600mm (W) x 2.100mm (H) nos 2.00 0.00412 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
I Steel double swinging flush mesh door (SD-8) nos 1.00 0.00465 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.000mm (H)

I Wooden double swing door w/ vision glass (WD-1) nos 2.00 0.00687 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.100mm (H)
J Wooden single swing door w/ vision glass (WD-2) nos 1.00 0.00219 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)
K Wooden single swing door (WD-3) nos 3.00 0.00586 0.0000 0.0000 0.0000 0.0062 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)

L Toilet booth nos 4.00 0.00525 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
size : 600mm (W) x 2.000mm (H)

carried forward 0.83022

brought forward 0.83022 0.0000 0.0000 0.0000

DOOR AND WINDOW WORK

DOORS
M Alum. single swing door w/ vision glass (AD-1) nos 1.00 0.00265 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm (H)

N Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.03259 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000

WINDOWS
A Aluminium top hinge window (AW-1) nos 47.00 0.05047 0.0000 0.0000 0.0000 0.0533 0.0000 0.0000 0.0000
size : 800mm (W) x 900mm
B Ditto. but to size : 1.800mm (W) x 900mm (H) (AW-5) nos 1.00 0.00268 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
C Aluminium top hinge + fix glass window (AW-3) nos 7.00 0.01468 0.0000 0.0000 0.0000 0.0155 0.0000 0.0000 0.0000
size : 1.700mm (W) x 900mm
D Aluminium bouevenlight window (AW-4) nos 5.00 0.00176 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
size : 1.200mm (W) x 400mm
E Aluminium top hinge + jalousie window (AW-6) nos 2.00 0.00478 0.0000 0.0000 0.0000 0.0050 0.0000 0.0000 0.0000
size : 1.000mm (W) x 1.100mm

F Steel Louver, size : 1.000mm (W) x 1.100mm (H) (LW-1) nos 8.00 0.00791 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000

D.2.2.5 PAINTING WORK 0.41606 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 1,152.00 0.02324 0.0000 0.0000 0.0000 0.0559 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 1,556.00 0.01785 0.0000 0.0000 0.0000 0.0429 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 62
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
C Ditto , but to ceiling m2 374.00 0.00429 0.0000 0.0000 0.0000 0.0103 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 1,193.00 0.02166 0.0000 0.0000 0.0000 0.0520 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 692.00 0.00467 0.0000 0.0000 0.0000 0.0112 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 8,418.00 0.34027 0.0000 0.0000 0.0000 0.8178 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 243.00 0.00408 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000

D.2.2.6 INTERIOR FINISHING WORK 0.05144 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 8,661.00 0.02747 0.0000 0.0000 0.0000 0.5340 0.0000 0.0000 0.0000

Base Finish
B Wooden Base H = 100mm m 2.00 0.00012 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
C Mortar Base w/ AE H = 100mm m 83.00 0.00088 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
D Mortar Base w/ Epoxy Paint H=100mm m 38.40 0.00476 0.0000 0.0000 0.0000 0.0926 0.0000 0.0000 0.0000

Ceiling Finish
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 158.00 0.00806 0.0000 0.0000 0.0000 0.1567 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 28.00 0.00188 0.0000 0.0000 0.0000 0.0365 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 558.00 0.00546 0.0000 0.0000 0.0000 0.1061 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 188.00 0.00280 0.0000 0.0000 0.0000 0.0545 0.0000 0.0000 0.0000

D.2.2.7 WATERPROOFING WORK 0.04040 0.0000 0.0000 0.0000

A Waterproofing membrane m2 208.00 0.01106 0.0000 0.0000 0.0000 0.2737 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 188.00 0.01147 0.0000 0.0000 0.0000 0.2838 0.0000 0.0000 0.0000
C Protection brick w/ plaster 1 side m2 26.30 0.00268 0.0000 0.0000 0.0000 0.0663 0.0000 0.0000 0.0000
D Groove w/ fill polyurethane sealent (15w x 15d) m 649.00 0.01520 0.0000 0.0000 0.0000 0.3761 0.0000 0.0000 0.0000

D.2.2.8 MISCELLANEOUS WORK 0.29942 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 36.00 0.01148 0.0000 0.0000 0.0000 0.0383 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 162.00 0.01498 0.0000 0.0000 0.0000 0.0500 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 18.500 mm unit 1.00 0.02551 0.0000 0.0000 0.0000 0.0852 0.0000 0.0000 0.0000
D S/S Insect Net to Ventilation m2 176.10 0.04367 0.0000 0.0000 0.0000 0.1459 0.0000 0.0000 0.0000
E Lavatory concrete table w/ top marble finish
- Size : 2.400mm (L) x 600mm (W) unit 1.00 0.00255 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
F Wall mirror at toilet :
- Size : 2.400mm (L) x 1.000mm (H) unit 1.00 0.00163 0.0000 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000
G Mesh Fence Wall H = 2.200mm m2 115.20 0.12897 0.0000 0.0000 0.0000 0.4307 0.0000 0.0000 0.0000
H Cast iron roof drain nos 3.00 0.00074 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
I PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 21.00 0.00394 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
J Room name plate nos 7.00 0.00211 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
K Wooden Casing to aluminium window m 212.20 0.00978 0.0000 0.0000 0.0000 0.0327 0.0000 0.0000 0.0000
L Steel Handrail H = 1000mm w/ OP finish m 105.00 0.04092 0.0000 0.0000 0.0000 0.1367 0.0000 0.0000 0.0000
M Steel Ladder L = 9.000mm nos 1.00 0.00957 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
N Glass Block, size : 200mm (W) x 200mm (H) nos 53.00 0.00357 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000

D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH 3.01658 0.0000 0.2502 0.2502

D.3.1 STRUCTURE WORK 2.02902 0.0000 0.2502 0.2502

D.3.1.1 EARTH WORK LOT 1.00 0.07503 0.0000 0.0047 0.0047

A Excavate over site to formation level including cleaning m2 1,483.10 0.00470 0.0000 1,483.1000 1,483.1000 0.0627 0.0000 0.0047 0.0047
site of all debris
B Excavation to underground tank m3
C Excavation to ground slab m3 530.00 0.00629 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 1,277.30 0.02215 0.0000 0.0000 0.0000 0.2952 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 908.00 0.01158 0.0000 0.0000 0.0000 0.1544 0.0000 0.0000 0.0000
F Compacted sub grade m2 1,483.10 0.00270 0.0000 0.0000 0.0000 0.0360 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 899.20 0.01468 0.0000 0.0000 0.0000 0.1957 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 1,483.10 0.01291 0.0000 0.0000 0.0000 0.1721 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2

D.3.1.2 PILING WORK LOT 1.00 0.58263 0.0000 0.2455 0.2455

A Allow for mobilization and demobilization of all


pilling plant and equipment
- Mob & Demob pilling equipment unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0219 0.0000 0.0064 0.0064
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.5000 0.5000 0.0219 0.0000 0.0064 0.0064
B PC Spun Pile Ø 300mm , L=30m nos 82.00 0.23270 0.0000 82.0000 82.0000 0.3994 0.0000 0.2327 0.2327
C Driving PC Spun Pile Ø 300mm m 2,460.00 0.06972 0.0000 0.0000 0.0000 0.1197 0.0000 0.0000 0.0000
D Welding Joint PC Spun Pile Ø 300mm nos 164.00 0.01046 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 82.00 0.00204 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PC Spun Pile Ø 350mm , L=30m nos 50.00 0.17803 0.0000 0.0000 0.0000 0.3056 0.0000 0.0000 0.0000
G Driving PC Spun Pile Ø 350mm m 1,500.00 0.04788 0.0000 0.0000 0.0000 0.0822 0.0000 0.0000 0.0000
H Welding Joint PC Spun Pile Ø 350mm nos 100.00 0.00638 0.0000 0.0000 0.0000 0.0109 0.0000 0.0000 0.0000
I Cut off excess pile length at required level & expose nos 50.00 0.00142 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
J PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0146 0.0000 0.0000 0.0000

D.3.1.3 CONCRETE WORK LOT 1.00 0.34177 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 1,483.10 0.04053 0.0000 0.0000 0.0000 0.1186 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 38.00 0.01792 0.0000 0.0000 0.0000 0.0524 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 36.80 0.01735 0.0000 0.0000 0.0000 0.0508 0.0000 0.0000 0.0000
D Ditto , but to Drop Panel m3 30.40 0.01434 0.0000 0.0000 0.0000 0.0419 0.0000 0.0000 0.0000
E Ditto , but to Ground Slab m3 344.30 0.16236 0.0000 0.0000 0.0000 0.4751 0.0000 0.0000 0.0000
F Ditto, but to Column m3 77.50 0.03655 0.0000 0.0000 0.0000 0.1069 0.0000 0.0000 0.0000
G Ditto, but to Middle Beam m3 6.40 0.00302 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
H Ditto, but to Roof Beam m3 26.70 0.01259 0.0000 0.0000 0.0000 0.0368 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter m3 -
J Ditto, but to Pit m3 78.70 0.03711 0.0000 0.0000 0.0000 0.1086 0.0000 0.0000 0.0000

D.3.1.4 REINFORCED WORK 0.50742 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 4,830.00 0.02738 0.0000 0.0000 0.0000 0.0540 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 6,966.00 0.03949 0.0000 0.0000 0.0000 0.0778 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel kg 950.00 0.00539 0.0000 0.0000 0.0000 0.0106 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab kg 44,455.00 0.25199 0.0000 0.0000 0.0000 0.4966 0.0000 0.0000 0.0000
E Ditto, but to Column kg 19,771.00 0.11207 0.0000 0.0000 0.0000 0.2209 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam kg 1,146.00 0.00650 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam kg 2,994.00 0.01697 0.0000 0.0000 0.0000 0.0334 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter kg
I Ditto, but to Pit kg 8,405.00 0.04764 0.0000 0.0000 0.0000 0.0939 0.0000 0.0000 0.0000

D.3.1.5 FORM WORK LOT 1.00 0.14620 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 173.50 0.01008 0.0000 0.0000 0.0000 0.0689 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 245.00 0.01423 0.0000 0.0000 0.0000 0.0974 0.0000 0.0000 0.0000
C Ditto , but to Drop Panel m2 104.60 0.00608 0.0000 0.0000 0.0000 0.0416 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m2 290.70 0.01689 0.0000 0.0000 0.0000 0.1155 0.0000 0.0000 0.0000
E Ditto, but to Column m2 622.60 0.03966 0.0000 0.0000 0.0000 0.2713 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m2 72.00 0.00459 0.0000 0.0000 0.0000 0.0314 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m2 222.00 0.01414 0.0000 0.0000 0.0000 0.0967 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter m2
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 63
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
I Ditto, but to Pit m2 413.60 0.02635 0.0000 0.0000 0.0000 0.1802 0.0000 0.0000 0.0000
J Supporting formwork to above m2 1,330.20 0.01418 0.0000 0.0000 0.0000 0.0970 0.0000 0.0000 0.0000

D.3.1.6 STEEL STRUCTURE WORK LOT 1.00 0.35324 0.0000 0.0000 0.0000

A Steel trusses of main building included. purlin, bracing, etc..

B Steel structure of metal fascia Kg 13,820.60 0.13523 0.0000 0.0000 0.0000 0.3828 0.0000 0.0000 0.0000
C Steel structure of metal wall cladding
D Steel structure of canopy Kg 609.20 0.00596 0.0000 0.0000 0.0000 0.0169 0.0000 0.0000 0.0000
E Finishing paint to steel structure Kg 7,801.80 0.07634 0.0000 0.0000 0.0000 0.2161 0.0000 0.0000 0.0000
(synthetic enamel 60 micron) Kg 12,298.10 0.12033 0.0000 0.0000 0.0000 0.3407 0.0000 0.0000 0.0000
Kg 20,709.10 0.01537 0.0000 0.0000 0.0000 0.0435 0.0000 0.0000 0.0000

D.3.1.7 MISCELLANEOUS WORK LOT 1.00 0.02273 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 16.00 0.00051 0.0000 0.0000 0.0000 0.0225 0.0000 0.0000 0.0000
B Waterproofing coating to Pit m3 262.00 0.00836 0.0000 0.0000 0.0000 0.3679 0.0000 0.0000 0.0000
C Waterstop m 47.00 0.00416 0.0000 0.0000 0.0000 0.1832 0.0000 0.0000 0.0000
D Cat Ladder at Ground Water Tank ( U Type ) nos 36.00 0.00969 0.0000 0.0000 0.0000 0.4264 0.0000 0.0000 0.0000

D.3.2 FINISHING WORK 0.98757 0.0000 0.0000 0.0000

D.3.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 0.42084 0.0000 0.0000 0.0000

A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 1,144.00 0.09804 0.0000 0.0000 0.0000 0.2330 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 1,144.00 0.00919 0.0000 0.0000 0.0000 0.0218 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 1,144.00 0.00733 0.0000 0.0000 0.0000 0.0174 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 1,144.00 0.01073 0.0000 0.0000 0.0000 0.0255 0.0000 0.0000 0.0000
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 130.00 0.02124 0.0000 0.0000 0.0000 0.0505 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 140.00 0.00316 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 70.00 0.00158 0.0000 0.0000 0.0000 0.0037 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 70.00 0.00158 0.0000 0.0000 0.0000 0.0037 0.0000 0.0000 0.0000
I High Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 55.00 0.00369 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
J End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 15.00 0.00084 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000
K Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 50.00 0.00281 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
L Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 70.00 0.00232 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
M FRP Flashing. W=305mm , zincalume Thk 0.5mm (Tct) m 260.00 0.01058 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
N Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 70.00 0.00563 0.0000 0.0000 0.0000 0.0134 0.0000 0.0000 0.0000
O Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 70.00 0.00285 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
P End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 70.00 0.00285 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
Q Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 4.00 0.00016 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000
R Eaves FRP Gutter , Grey Thk 3.0mm , W=1.050mm m 55.00 0.01090 0.0000 0.0000 0.0000 0.0259 0.0000 0.0000 0.0000
S Gutter Bracket SP 3x42 mm, W=1.250mm pcs 86.00 0.00288 0.0000 0.0000 0.0000 0.0068 0.0000 0.0000 0.0000
T PVC Pipe AW Grey Dia. 150mm m 90.00 0.00675 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
U PVC Lbow 450 / 900 , Dia. 150mm pcs 24.00 0.00180 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000
V Clamp pipe Sp. 3x42mm , Dia. 150mm pcs 96.00 0.00257 0.0000 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000
W Eaves FRP Gutter , Grey Thk 3.0mm , W=650mm m 15.00 0.00185 0.0000 0.0000 0.0000 0.0044 0.0000 0.0000 0.0000
X Gutter Bracket SP 3x42 mm, W=850mm pcs 24.00 0.00055 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
Y PVC Pipe AW Grey Dia. 100mm m 8.00 0.00034 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
Z PVC Lbow 450 / 900 , Dia. 100mm pcs 8.00 0.00034 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
AA Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 10.00 0.00019 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 1,811.00 0.14555 0.0000 0.0000 0.0000 0.3459 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 120.00 0.00488 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 138.00 0.00562 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 65.00 0.00264 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 400.00 0.03002 0.0000 0.0000 0.0000 0.0713 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 120.00 0.00675 0.0000 0.0000 0.0000 0.0160 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 40.00 0.00750 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 82.00 0.00264 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 30.00 0.00129 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 16.00 0.00069 0.0000 0.0000 0.0000 0.0016 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 32.00 0.00051 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000

D.3.2.2 MASONRY WORK LOT 1.00 0.04568 0.0000 0.0000 0.0000

A Common brick wall m2 247.00 0.01635 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B Ventilation block wall m2 -
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 3.70 0.00156 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 593.00 0.00336 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 49.40 0.00287 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 494.00 0.02154 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.3.2.3 TILING WORK LOT 1.00 0.00356 0.0000 0.0000 0.0000


Floor Finish
A Ceramic Tile 200 x 200 mm m2 14.10 0.00112 0.0000 0.0000 0.0000 0.3156 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 6.00 0.00050 0.0000 0.0000 0.0000 0.1409 0.0000 0.0000 0.0000
Wall Finish
C Ceramic Tile 200 x 200 mm m2 23.80 0.00194 0.0000 0.0000 0.0000 0.5435 0.0000 0.0000 0.0000

D.3.2.4 DOOR AND WINDOW WORK LOT 1.00 0.33186 0.0000 0.0000 0.0000

DOORS
A Motorized steel roll-up shutter (SS -1) nos 2.00 0.09249 0.0000 0.0000 0.0000 0.2787 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)
B Ditto. but to size : 10.000mm (W) x 7.200mm (H) (SS-2) nos 2.00 0.17326 0.0000 0.0000 0.0000 0.5221 0.0000 0.0000 0.0000

C Steel single swinging flush door (SD-1) nos 3.00 0.00663 0.0000 0.0000 0.0000 0.0200 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm
D Steel double swinging flush door (SD-2) nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.000mm (H)

E Wooden single swing door w/ vision glass (WD-1) nos 1.00 0.00219 0.0000 0.0000 0.0000 0.0066 0.0000 0.0000 0.0000
size : 800mm (W) x 2.100mm (H)
F Ditto. but to size : 800mm (W) x 2.100mm (H) (WD-3) nos 1.00 0.00195 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
G Wooden double swing door w/ vision glass (WD-2) nos 1.00 0.00276 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000
size : 1.150mm (W) x 2.100mm (H)

H Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.00922 0.0000 0.0000 0.0000 0.0278 0.0000 0.0000 0.0000

WINDOWS
A Aluminium top hinge + fix glass window (AW-1) nos 2.00 0.00367 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
size : 1.700mm (W) x 900mm
B Aluminium Louver (AG-1) nos 4.00 0.03375 0.0000 0.0000 0.0000 0.1017 0.0000 0.0000 0.0000
size : 2.700mm (W) x 2.800mm
C Ditto. but to size : 1.700mm (W) x 900mm (H) (AG-2) nos 1.00 0.00171 0.0000 0.0000 0.0000 0.0051 0.0000 0.0000 0.0000

D.3.2.5 PAINTING WORK LOT 1.00 0.06056 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 185.00 0.00373 0.0000 0.0000 0.0000 0.0616 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 64
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Acrylic Emulsion Paint (AEP) to internal wall m2 312.00 0.00358 0.0000 0.0000 0.0000 0.0591 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 20.00 0.00023 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 482.00 0.00875 0.0000 0.0000 0.0000 0.1445 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 23.00 0.00016 0.0000 0.0000 0.0000 0.0026 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 1,080.00 0.04366 0.0000 0.0000 0.0000 0.7209 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 27.00 0.00045 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000

D.3.2.6 INTERIOR FINISHING WORK LOT 1.00 0.00805 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 1,107.00 0.00351 0.0000 0.0000 0.0000 0.4362 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 24.00 0.00026 0.0000 0.0000 0.0000 0.0318 0.0000 0.0000 0.0000
C Mortar Base w/ Epoxy Paint H=100mm m 14.60 0.00019 0.0000 0.0000 0.0000 0.0231 0.0000 0.0000 0.0000

Wall Finish
D Drywall Partition Gypsum Board (1side) m2 21.50 0.00175 0.0000 0.0000 0.0000 0.2177 0.0000 0.0000 0.0000
E Extra steel chanel to ditto kg 64.50 0.00063 0.0000 0.0000 0.0000 0.0784 0.0000 0.0000 0.0000

Ceiling Finish
F Gypsum Board (Flat) T=9mm w/ LGS Frame m2 14.10 0.00072 0.0000 0.0000 0.0000 0.0894 0.0000 0.0000 0.0000
G Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 6.00 0.00040 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
H Extra steel chanel to ditto kg 60.30 0.00059 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000

D.3.2.7 WATERPROOFING WORK LOT 1.00 0.00068 0.0000 0.0000 0.0000

A Groove w/ fill polyurethane sealent (15w x 15d) m 29.00 0.00068 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.3.2.8 MISCELLANEOUS WORK LOT 1.00 0.11634 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 16.00 0.00510 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 20.00 0.00185 0.0000 0.0000 0.0000 0.0159 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 18.500 mm unit 1.00 0.02551 0.0000 0.0000 0.0000 0.2193 0.0000 0.0000 0.0000
D S/S Insect Net to Ventilation m2 31.80 0.00789 0.0000 0.0000 0.0000 0.0678 0.0000 0.0000 0.0000
E Room name plate nos 3.00 0.00090 0.0000 0.0000 0.0000 0.0078 0.0000 0.0000 0.0000
F Wooden Casing to aluminium window m 10.40 0.00048 0.0000 0.0000 0.0000 0.0041 0.0000 0.0000 0.0000
G Grating cover 600mm m 54.00 0.07461 0.0000 0.0000 0.0000 0.6413 0.0000 0.0000 0.0000

D.4 EXCAVATOR PAINT FACTORY 13.53542 0.0000 0.0000 0.0000

D.4.1 STRUCTURE WORK LOT 1.00 8.63500 0.0000 0.0000 0.0000

D.4.1.1 EARTH WORK LOT 1.00 0.70617 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 9,400.00 0.02981 0.0000 0.0000 0.0000 0.0422 0.0000 0.0000 0.0000
site of all debris
B Excavation to ground slab m3 6,516.70 0.07740 0.0000 0.0000 0.0000 0.1096 0.0000 0.0000 0.0000
C Excavation to pile cap & g.beam m3 1,952.00 0.03385 0.0000 0.0000 0.0000 0.0479 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 662.00 0.00844 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
E Compacted sub grade m2 9,997.00 0.01821 0.0000 0.0000 0.0000 0.0258 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 7,806.00 0.12748 0.0000 0.0000 0.0000 0.1805 0.0000 0.0000 0.0000
G T=50mm comp. sand bedding m2 2,499.00 0.02175 0.0000 0.0000 0.0000 0.0308 0.0000 0.0000 0.0000
H T=150mm comp. basecourse m2 182.10 0.00375 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
I T=200mm comp. basecourse m2 7,498.00 0.20189 0.0000 0.0000 0.0000 0.2859 0.0000 0.0000 0.0000
J Plastic Sheet m2 7,498.00 0.01872 0.0000 0.0000 0.0000 0.0265 0.0000 0.0000 0.0000
K Back fill and compac. w/ Imported Red Soil m3 3,577.00 0.16486 0.0000 0.0000 0.0000 0.2335 0.0000 0.0000 0.0000

D.4.1.2 PILING WORK LOT 1.00 0.71149 0.0000 0.0000 0.0000

DRIVING PILE WORK


A Allow for mobilization and demobilization of all
pilling plant and equipment
- Mob & Demob pilling equipment unit 2.00 0.02551 0.0000 0.0000 0.0000 0.0359 0.0000 0.0000 0.0000
- Mob & Demob Service Crane unit 1.00 0.01275 0.0000 0.0000 0.0000 0.0179 0.0000 0.0000 0.0000
B PC Spun Pile Ø 300 mm , L=16m nos 228.00 0.34507 0.0000 0.0000 0.0000 0.4850 0.0000 0.0000 0.0000
C Driving Pile m 3,648.00 0.10339 0.0000 0.0000 0.0000 0.1453 0.0000 0.0000 0.0000
D Welding Joint nos 228.00 0.01454 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 228.00 0.00566 0.0000 0.0000 0.0000 0.0080 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

PRESS PILE WORK


G Allow for mobilization and demobilization of all unit 1.00 0.00921 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
pilling plant and equipment
H PC Square Pile 250x250 mm , L=20m (Assume) nos 59.00 0.12709 0.0000 0.0000 0.0000 0.1786 0.0000 0.0000 0.0000
I Driving Pile w/ Jacking system m 1,180.00 0.04603 0.0000 0.0000 0.0000 0.0647 0.0000 0.0000 0.0000
J Welding Joint nos 59.00 0.00376 0.0000 0.0000 0.0000 0.0053 0.0000 0.0000 0.0000
K Cut off excess pile length at required level & expose nos 59.00 0.00147 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
L PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

D.4.1.3 CONCRETE WORK LOT 1.00 1.45725 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 2,245.70 0.06138 0.0000 0.0000 0.0000 0.0421 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 184.50 0.08700 0.0000 0.0000 0.0000 0.0597 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 93.20 0.04395 0.0000 0.0000 0.0000 0.0302 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 1,784.00 0.84127 0.0000 0.0000 0.0000 0.5773 0.0000 0.0000 0.0000
E Ditto, but to Column m3 213.40 0.10063 0.0000 0.0000 0.0000 0.0691 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m3 28.30 0.01335 0.0000 0.0000 0.0000 0.0092 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m3 77.70 0.03664 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
H Ditto, but to Roof Slab m3 4.50 0.00212 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I Ditto, but to Parapet m3 2.20 0.00104 0.0000 0.0000 0.0000 0.0007 0.0000 0.0000 0.0000
J Ditto, but to Column & Beam Shutter m3 17.50 0.00825 0.0000 0.0000 0.0000 0.0057 0.0000 0.0000 0.0000
K Ditto, but to Pit m3 514.80 0.24276 0.0000 0.0000 0.0000 0.1666 0.0000 0.0000 0.0000
L Ditto, but to Recovery Slab m3 40.00 0.01886 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000

D.4.1.4 REINFORCED WORK LOT 1.00 1.83951 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 23,354.00 0.13238 0.0000 0.0000 0.0000 0.0720 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 13,402.00 0.07597 0.0000 0.0000 0.0000 0.0413 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab Kg 3,595.00 0.02038 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
D Ditto, but to Column kg 50,640.00 0.28705 0.0000 0.0000 0.0000 0.1560 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam kg 3,780.00 0.02143 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam kg 10,733.00 0.06084 0.0000 0.0000 0.0000 0.0331 0.0000 0.0000 0.0000
G Ditto, but to Roof Slab kg 556.00 0.00315 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
H Ditto, but to Parapet kg 254.00 0.00144 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter kg 5,274.00 0.02990 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
J Ditto, but to Pit kg 82,360.00 0.46685 0.0000 0.0000 0.0000 0.2538 0.0000 0.0000 0.0000
K Ditto, but to Recovery Slab kg 3,595.00 0.02038 0.0000 0.0000 0.0000 0.0111 0.0000 0.0000 0.0000
L Wiremesh #M8 to ground slab (2 layer) m2 8,721.00 0.71974 0.0000 0.0000 0.0000 0.3913 0.0000 0.0000 0.0000

D.4.1.5 FORM WORK LOT 1.00 0.32842 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 688.50 0.04000 0.0000 0.0000 0.0000 0.1218 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 621.10 0.03609 0.0000 0.0000 0.0000 0.1099 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 65
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
C Ditto , but to Ground Slab m2 165.40 0.00961 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
D Ditto, but to Column m2 1,658.00 0.09633 0.0000 0.0000 0.0000 0.2933 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam m2 228.30 0.01454 0.0000 0.0000 0.0000 0.0443 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam m2 607.20 0.03868 0.0000 0.0000 0.0000 0.1178 0.0000 0.0000 0.0000
G Ditto, but to Roof Slab m2 33.30 0.00212 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
H Ditto, but to Parapet m2 25.30 0.00161 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
I Ditto, but to Column & Beam Shutter m2 231.40 0.01474 0.0000 0.0000 0.0000 0.0449 0.0000 0.0000 0.0000
J Ditto, but to Pit m2 605.30 0.03856 0.0000 0.0000 0.0000 0.1174 0.0000 0.0000 0.0000
K Ditto, but to Recovery Slab m2 0.00000
L Supporting formwork to above m2 3,388.80 0.03613 0.0000 0.0000 0.0000 0.1100 0.0000 0.0000 0.0000

D.4.1.6 STEEL STRUCTURE WORK LOT 1.00 3.53723 0.0000 0.0000 0.0000

A Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 317,897.90 3.11058 0.0000 0.0000 0.0000 0.8794 0.0000 0.0000 0.0000
B Steel structure of metal fascia Kg 0.00 0.00000
C Steel structure of metal wall cladding Kg 15,889.90 0.15548 0.0000 0.0000 0.0000 0.0440 0.0000 0.0000 0.0000
D Steel structure of gutter support Kg 7,497.20 0.07336 0.0000 0.0000 0.0000 0.0207 0.0000 0.0000 0.0000
E Steel structure of add. metal wall Kg 18,441.70 0.18045 0.0000 0.0000 0.0000 0.0510 0.0000 0.0000 0.0000
F Finishing paint to steel structure Kg 23,387.10 0.01736 0.0000 0.0000 0.0000 0.0049 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

D.4.1.7 MISCELLANEOUS WORK LOT 1.00 0.05494 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 51.00 0.00163 0.0000 0.0000 0.0000 0.0296 0.0000 0.0000 0.0000
B Expansion joint to existing slab :
- Sand asphalt fill m 1,240.00 0.02418 0.0000 0.0000 0.0000 0.4402 0.0000 0.0000 0.0000
- Dowel rebar kg 4,568.00 0.02589 0.0000 0.0000 0.0000 0.4713 0.0000 0.0000 0.0000
- Flexible pipe m 1,654.00 0.00324 0.0000 0.0000 0.0000 0.0589 0.0000 0.0000 0.0000

D.4.2 FINISHING WORK 4.90042 0.0000 0.0000 0.0000

D.4.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 2.35276 0.0000 0.0000 0.0000

Metal Roofing Excavator Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 7,956.00 0.68184 0.0000 0.0000 0.0000 0.2898 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 7,956.00 0.06389 0.0000 0.0000 0.0000 0.0272 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 7,956.00 0.05100 0.0000 0.0000 0.0000 0.0217 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 546.00 0.08920 0.0000 0.0000 0.0000 0.0379 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 348.00 0.00784 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 250.00 0.00563 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 151.00 0.00340 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 87.00 0.00583 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
J End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 76.00 0.00428 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
K Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 193.00 0.01086 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
L Nagare Flashing. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 148.00 0.00833 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
M Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 158.00 0.00525 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
N FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 1,092.00 0.04444 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
O Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
P Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
Q End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
R Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
S Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 181.00 0.04073 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
T Gutter Bracket SP 3x42 mm, W=1.400mm pcs 280.00 0.01051 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
U PVC Pipe AW Grey Dia. 200mm m 185.00 0.02478 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
V PVC Lbow 450 / 900 , Dia. 200mm pcs 58.00 0.00777 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
W Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 203.00 0.00653 0.0000 0.0000 0.0000 0.0028 0.0000 0.0000 0.0000
X Eaves FRP Gutter , Grey Thk 3.0mm , W=600mm m 68.00 0.00729 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
Y Gutter Bracket SP 3x42 mm, W=800mm pcs 105.00 0.00225 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
Z PVC Pipe AW Grey Dia. 100mm m 18.00 0.00077 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
AA PVC Lbow 450 / 900 , Dia. 100mm pcs 16.00 0.00069 0.0000 0.0000 0.0000 0.0003 0.0000 0.0000 0.0000
AB Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 20.00 0.00038 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000

Metal Wall
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 2,723.00 0.21885 0.0000 0.0000 0.0000 0.0930 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 366.30 0.01491 0.0000 0.0000 0.0000 0.0063 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 266.80 0.01086 0.0000 0.0000 0.0000 0.0046 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 48.00 0.00195 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000

Utility & Plant Room Roofing


A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 1,037.00 0.07782 0.0000 0.0000 0.0000 0.0331 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 146.00 0.00822 0.0000 0.0000 0.0000 0.0035 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 82.00 0.01538 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 165.00 0.00531 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 80.00 0.00343 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 48.00 0.00206 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 90.00 0.00145 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

Canopy
A Roofing Boltless U-527 (27mm), Zinc Alume Thk. 0,50mm (Tct) m2 338.00 0.02536 0.0000 0.0000 0.0000 0.0108 0.0000 0.0000 0.0000
B Gable Flashing. W=610mm, Zinc. Alume Thk. 0,50mm (Tct) m 75.00 0.00422 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
C Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 23.00 0.00431 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
D Gutter Bracket Sp 3x42mm W=1.200mm pcs 46.00 0.00148 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000
E PVC Pipe AW Grey Dia. 100mm m 10.00 0.00043 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
F PVC Lbow 450 / 900 , Dia. 100mm pcs 4.00 0.00017 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000
G Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 10.00 0.00016 0.0000 0.0000 0.0000 0.0001 0.0000 0.0000 0.0000

carried forward 1.47985

brought forward 1.47985 0.0000 0.0000 0.0000

METAL ROOFING & METAL WALL WORK

Roof -1 Area
A Roofing Corrugated Steel Sheet Thk. 0,5mm (Tct), H=30mm U750 m2 1,746.00 0.11794 0.0000 0.0000 0.0000 0.0501 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 1,746.00 0.01402 0.0000 0.0000 0.0000 0.0060 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 1,746.00 0.01119 0.0000 0.0000 0.0000 0.0048 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 192.00 0.03137 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 360.00 0.00811 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 180.00 0.00406 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 158.00 0.00356 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 180.00 0.01013 0.0000 0.0000 0.0000 0.0043 0.0000 0.0000 0.0000
J Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 158.00 0.00525 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
K FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 384.00 0.01563 0.0000 0.0000 0.0000 0.0066 0.0000 0.0000 0.0000
L Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
M Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
N End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
O Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
P Valley Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 158.00 0.02963 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000
Q Gutter Bracket Sp 3x42mm W=1.200mm pcs 246.00 0.00792 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000 0.0000
R PVC Pipe AW Grey Dia. 100mm m 135.00 0.00578 0.0000 0.0000 0.0000 0.0025 0.0000 0.0000 0.0000
S PVC Lbow 450 / 900 , Dia. 100mm pcs 60.00 0.00257 0.0000 0.0000 0.0000 0.0011 0.0000 0.0000 0.0000
T Clamp pipe Sp. 3x42mm , Dia. 100mm pcs 135.00 0.00217 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000

Roof - 2 Area
A Roofing Zinc Alume SF-750 (55mm), Thk. 0,5mm (Tct) m2 3,651.00 0.30575 0.0000 0.0000 0.0000 0.1300 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 66
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Roof mesh, Galvanized #3x3" m2 3,651.00 0.02932 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 3,651.00 0.02341 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2 0.00000 -
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 295.00 0.04820 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 320.00 0.00721 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 160.00 0.00361 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 160.00 0.00361 0.0000 0.0000 0.0000 0.0015 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 95.00 0.00637 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
J Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 60.00 0.00338 0.0000 0.0000 0.0000 0.0014 0.0000 0.0000 0.0000
K Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 160.00 0.00531 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
L FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 590.00 0.02401 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
M Metal Fascia U-527 ( 27mm), Zinc Alume Colour Thk 0,40mm (Tct) m2 0.00 0.00000 -
N Copping Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
O End Fascia flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
P Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 0.00 0.00000 -
Q Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 160.00 0.03601 0.0000 0.0000 0.0000 0.0153 0.0000 0.0000 0.0000
R Gutter Bracket SP 3x42 mm, W=1.400mm pcs 250.00 0.00938 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000
S PVC Pipe AW Grey Dia. 200mm m 130.00 0.01741 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
T PVC Lbow 450 / 900 , Dia. 200mm pcs 40.00 0.00536 0.0000 0.0000 0.0000 0.0023 0.0000 0.0000 0.0000
U Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 130.00 0.00418 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000

New Down Metal Wall


A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 777.50 0.06249 0.0000 0.0000 0.0000 0.0266 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 190.00 0.00773 0.0000 0.0000 0.0000 0.0033 0.0000 0.0000 0.0000
C Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0004 0.0000 0.0000 0.0000

D.4.2.2 MASONRY WORK LOT 1.00 0.51955 0.0000 0.0000 0.0000

A Common brick wall m2 2,809.40 0.18598 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000
B Ventilation block wall m2 0.00000
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 42.10 0.01776 0.0000 0.0000 0.0000 0.0342 0.0000 0.0000 0.0000
- HT. Reinforcement kg 6,743.00 0.03822 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 561.90 0.03265 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 5,618.80 0.24494 0.0000 0.0000 0.0000 0.4714 0.0000 0.0000 0.0000
w/ instant mortar

D.4.2.3 TILING WORK LOT 1.00 0.01146 0.0000 0.0000 0.0000

Floor Finish
A Ceramic Tile 200 x 200 mm m2 21.00 0.00167 0.0000 0.0000 0.0000 0.1460 0.0000 0.0000 0.0000
B Ceramic Tile 300 x 300 mm m2 74.00 0.00619 0.0000 0.0000 0.0000 0.5397 0.0000 0.0000 0.0000
Wall Finish
C Ceramic Tile 200 x 200 mm m2 44.30 0.00360 0.0000 0.0000 0.0000 0.3143 0.0000 0.0000 0.0000

D.4.2.4 DOOR AND WINDOW WORK LOT 1.00 0.93405 0.0000 0.0000 0.0000

DOORS
A Motorized steel roll-up shutter (SS -1) nos 5.00 0.23122 0.0000 0.0000 0.0000 0.2475 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)
B Ditto. but to size : 6.000mm (W) x 5.000mm (H) (SD-3) nos 1.00 0.04046 0.0000 0.0000 0.0000 0.0433 0.0000 0.0000 0.0000

C High speed shutter (HSS -1) nos 1.00 0.17649 0.0000 0.0000 0.0000 0.1890 0.0000 0.0000 0.0000
size : 6.000mm (W) x 6.000mm (H)

D Steel double hanging sliding door w/ FRP Panel (SD-1) nos 3.00 0.25225 0.0000 0.0000 0.0000 0.2701 0.0000 0.0000 0.0000
size : 10.000mm (W) x 6.000mm (H)
E Steel double swinging flush louver door (SD-3) nos 4.00 0.03247 0.0000 0.0000 0.0000 0.0348 0.0000 0.0000 0.0000
size : 1.800mm (W) x 2.500mm (H)
F Steel single swinging flush door (SD-6) nos 4.00 0.00883 0.0000 0.0000 0.0000 0.0095 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm

G Wooden double swing door (WD-1) nos 2.00 0.00687 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
size : 1.600mm (W) x 2.100mm (H)
H Wooden single swing door w/ vision glass (WD-2) nos 7.00 0.01366 0.0000 0.0000 0.0000 0.0146 0.0000 0.0000 0.0000
size : 900mm (W) x 2.100mm (H)

I Toilet booth nos 0.00000


size : 600mm (W) x 2.000mm (H)

J Hardware and ironmongery ( Goal or Equal ) lot 1.00 0.02448 0.0000 0.0000 0.0000 0.0262 0.0000 0.0000 0.0000

WINDOWS
A Aluminium Louver (AG-1) nos 4.00 0.14731 0.0000 0.0000 0.0000 0.1577 0.0000 0.0000 0.0000
size : 20.000mm (W) x 1.650mm

D.4.2.5 PAINTING WORK LOT 1.00 0.23823 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 1,460.00 0.02946 0.0000 0.0000 0.0000 0.1237 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 3,923.00 0.04500 0.0000 0.0000 0.0000 0.1889 0.0000 0.0000 0.0000
C Ditto , but to ceiling m2 202.50 0.00232 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 950.20 0.01725 0.0000 0.0000 0.0000 0.0724 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 373.00 0.00252 0.0000 0.0000 0.0000 0.0106 0.0000 0.0000 0.0000
F Floor Hardener Green Color to Floor m2 0.00 0.00000 -
G Floor Hardener Natural Color to Floor m2 8,432.00 0.14168 0.0000 0.0000 0.0000 0.5947 0.0000 0.0000 0.0000

D.4.2.6 INTERIOR FINISHING WORK LOT 1.00 0.04468 0.0000 0.0000 0.0000

Floor Finish
A Steel trowel finish m2 8,432.00 0.02674 0.0000 0.0000 0.0000 0.5985 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 208.00 0.00222 0.0000 0.0000 0.0000 0.0496 0.0000 0.0000 0.0000
C Mortar Base w/ Epoxy Paint H=100mm m 49.00 0.00062 0.0000 0.0000 0.0000 0.0140 0.0000 0.0000 0.0000

Wall Finish
D Styrene Resin Board T=25mm m2 0.00000 -

Ceiling Finish
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 73.50 0.00375 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 21.00 0.00141 0.0000 0.0000 0.0000 0.0316 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 283.50 0.00277 0.0000 0.0000 0.0000 0.0621 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 108.00 0.00161 0.0000 0.0000 0.0000 0.0360 0.0000 0.0000 0.0000
I Styrene Resin Board T=25mm m2 54.00 0.00555 0.0000 0.0000 0.0000 0.1242 0.0000 0.0000 0.0000

D.4.2.7 WATERPROOFING WORK LOT 1.00 0.01696 0.0000 0.0000 0.0000

A Waterproofing membrane m2 63.00 0.00380 0.0000 0.0000 0.0000 0.2238 0.0000 0.0000 0.0000
B Protection concrete 50 mm to waterproofing membrane m2 54.00 0.00400 0.0000 0.0000 0.0000 0.2359 0.0000 0.0000 0.0000
C Protection brick w/ plaster 1 side m2 12.00 0.00132 0.0000 0.0000 0.0000 0.0777 0.0000 0.0000 0.0000
D Groove w/ fill polyurethane sealent (15w x 15d) m 335.00 0.00784 0.0000 0.0000 0.0000 0.4625 0.0000 0.0000 0.0000

D.4.2.8 MISCELLANEOUS WORK LOT 1.00 0.78272 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 36.00 0.01148 0.0000 0.0000 0.0000 0.0147 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 83.00 0.00767 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
C Maintenance S.S ladder w/ cage H : 16.000 mm unit 1.00 0.02211 0.0000 0.0000 0.0000 0.0282 0.0000 0.0000 0.0000
D Insect Net to Ventilation m2 132.00 0.03274 0.0000 0.0000 0.0000 0.0418 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 67
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
E Lavatory concrete table w/ top marble finish
- Size : 2.000mm (L) x 600mm (W) unit 1.00 0.00213 0.0000 0.0000 0.0000 0.0027 0.0000 0.0000 0.0000
F Wall mirror at toilet :
- Size : 2.000mm (L) x 1.000mm (H) unit 1.00 0.00135 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
G Toilet Partition w/ Door m2 12.00 0.01190 0.0000 0.0000 0.0000 0.0152 0.0000 0.0000 0.0000
H Room name plate nos 8.00 0.00241 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
I Steel Grating W = 4.000mm m2 588.00 0.68744 0.0000 0.0000 0.0000 0.8783 0.0000 0.0000 0.0000
J PVC Down Spout Ø 150mm w/ Elbow & Clamp Pipe m 16.00 0.00300 0.0000 0.0000 0.0000 0.0038 0.0000 0.0000 0.0000
K Cast iron roof drain nos 2.00 0.00050 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

D.5 TOUCHUP PAINT BOOTH 0.73952 0.0000 0.0000 0.0000

D.5.1 STRUCTURE WORK LOT 1.00 0.54630 0.0000 0.0000 0.0000

D.5.1.1 EARTH WORK LOT 1.00 0.01521 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 330.00 0.00105 0.0000 0.0000 0.0000 0.0688 0.0000 0.0000 0.0000
site of all debris
B Excavation to pit m3 84.10 0.00100 0.0000 0.0000 0.0000 0.0657 0.0000 0.0000 0.0000
C Excavation to ground slab m3 244.40 0.00290 0.0000 0.0000 0.0000 0.1908 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 35.00 0.00061 0.0000 0.0000 0.0000 0.0399 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 83.80 0.00107 0.0000 0.0000 0.0000 0.0703 0.0000 0.0000 0.0000
F Compacted sub grade m2 362.30 0.00066 0.0000 0.0000 0.0000 0.0434 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 279.80 0.00457 0.0000 0.0000 0.0000 0.3004 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 339.70 0.00296 0.0000 0.0000 0.0000 0.1944 0.0000 0.0000 0.0000
I T=100mm comp. sand bedding m2 22.60 0.00040 0.0000 0.0000 0.0000 0.0264 0.0000 0.0000 0.0000
J T=250mm comp. basecourse m2

D.5.1.2 PILING WORK LOT 1.00 0.06592 0.0000 0.0000 0.0000

A PC Spun Pile Ø 300mm , L=16m nos 30.00 0.04540 0.0000 0.0000 0.0000 0.6888 0.0000 0.0000 0.0000
B Driving PC Spun Pile Ø 300mm m 480.00 0.01360 0.0000 0.0000 0.0000 0.2064 0.0000 0.0000 0.0000
C Welding Joint PC Spun Pile Ø 300mm nos 30.00 0.00191 0.0000 0.0000 0.0000 0.0290 0.0000 0.0000 0.0000
D Cut off excess pile length at required level & expose nos 30.00 0.00074 0.0000 0.0000 0.0000 0.0113 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
E PDA Test nos 1.00 0.00425 0.0000 0.0000 0.0000 0.0645 0.0000 0.0000 0.0000

D.5.1.3 CONCRETE WORK LOT 1.00 0.10945 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 362.30 0.00990 0.0000 0.0000 0.0000 0.0905 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pile Caps m3 4.10 0.00193 0.0000 0.0000 0.0000 0.0177 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 7.40 0.00349 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 82.70 0.03900 0.0000 0.0000 0.0000 0.3563 0.0000 0.0000 0.0000
E Ditto, but to Column m3 15.10 0.00712 0.0000 0.0000 0.0000 0.0651 0.0000 0.0000 0.0000
F Ditto, but to Middle Beam m3 7.40 0.00349 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
G Ditto, but to Roof Beam m3 4.00 0.00189 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
H Ditto, but to Column & Beam Shutter m3 4.40 0.00207 0.0000 0.0000 0.0000 0.0190 0.0000 0.0000 0.0000
I Ditto, but to Pit m3 86.00 0.04055 0.0000 0.0000 0.0000 0.3705 0.0000 0.0000 0.0000

D.5.1.4 REINFORCED WORK LOT 1.00 0.13468 0.0000 0.0000 0.0000

A HT. Reinforcement to Pile Caps kg 594.00 0.00337 0.0000 0.0000 0.0000 0.0250 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam Kg 1,072.00 0.00608 0.0000 0.0000 0.0000 0.0451 0.0000 0.0000 0.0000
C Ditto, but to Column kg 4,062.00 0.02303 0.0000 0.0000 0.0000 0.1710 0.0000 0.0000 0.0000
D Ditto, but to Middle Beam kg 1,049.00 0.00595 0.0000 0.0000 0.0000 0.0442 0.0000 0.0000 0.0000
E Ditto, but to Roof Beam kg 552.00 0.00313 0.0000 0.0000 0.0000 0.0232 0.0000 0.0000 0.0000
F Ditto, but to Column & Beam Shutter kg 1,292.00 0.00732 0.0000 0.0000 0.0000 0.0544 0.0000 0.0000 0.0000
G Ditto, but to Pit kg 10,319.00 0.05849 0.0000 0.0000 0.0000 0.4343 0.0000 0.0000 0.0000
H Wiremesh #M8 to ground slab (2 layer) m2 331.00 0.02732 0.0000 0.0000 0.0000 0.2028 0.0000 0.0000 0.0000

D.5.1.5 FORM WORK LOT 1.00 0.05795 0.0000 0.0000 0.0000

A Formwork to Pile Caps m2 21.90 0.00127 0.0000 0.0000 0.0000 0.0220 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 49.00 0.00285 0.0000 0.0000 0.0000 0.0491 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 26.00 0.00151 0.0000 0.0000 0.0000 0.0261 0.0000 0.0000 0.0000
D Ditto, but to Column m2 133.80 0.00852 0.0000 0.0000 0.0000 0.1471 0.0000 0.0000 0.0000
E Ditto, but to Middle Beam m2 61.50 0.00392 0.0000 0.0000 0.0000 0.0676 0.0000 0.0000 0.0000
F Ditto, but to Roof Beam m2 33.60 0.00214 0.0000 0.0000 0.0000 0.0369 0.0000 0.0000 0.0000
G Ditto, but to Column & Beam Shutter m2 57.60 0.00367 0.0000 0.0000 0.0000 0.0633 0.0000 0.0000 0.0000
H Ditto, but to Pit m2 451.00 0.02620 0.0000 0.0000 0.0000 0.4522 0.0000 0.0000 0.0000
I Supporting formwork to above m2 737.50 0.00786 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000

D.5.1.6 STEEL STRUCTURE WORK LOT 1.00 0.13929 0.0000 0.0000 0.0000

A Steel trusses of main building included. purlin, bracing, etc.. Kg 9,979.00 0.09764 0.0000 0.0000 0.0000 0.7010 0.0000 0.0000 0.0000

B Steel structure of metal wall cladding Kg 2,610.00 0.02554 0.0000 0.0000 0.0000 0.1833 0.0000 0.0000 0.0000
C Finishing paint to steel structure Kg 2,610.00 0.00194 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)
D Relocation & Re-install Steel Plate Lot 1.00 0.01417 0.0000 0.0000 0.0000 0.1017 0.0000 0.0000 0.0000

D.5.1.7 MISCELLANEOUS WORK LOT 1.00 0.02380 0.0000 0.0000 0.0000

A Non Shrinkage grouting, size : 420x420x30mm nos 6.00 0.00019 0.0000 0.0000 0.0000 0.0080 0.0000 0.0000 0.0000
B Waterproofing coating to Ground water tank m2 168.30 0.00537 0.0000 0.0000 0.0000 0.2257 0.0000 0.0000 0.0000
C Waterstop m 135.00 0.01196 0.0000 0.0000 0.0000 0.5025 0.0000 0.0000 0.0000
D Expansion joint to existing slab :
- Sand asphalt fill m 20.50 0.00040 0.0000 0.0000 0.0000 0.0168 0.0000 0.0000 0.0000
- Dowel rebar kg 76.00 0.00043 0.0000 0.0000 0.0000 0.0181 0.0000 0.0000 0.0000
- Flexible pipe m 27.00 0.00005 0.0000 0.0000 0.0000 0.0022 0.0000 0.0000 0.0000
E Edge Protector L 50x50x5 kg 95.00 0.00093 0.0000 0.0000 0.0000 0.0391 0.0000 0.0000 0.0000
F Chemical Anchor to extension joint nos 36.00 0.00447 0.0000 0.0000 0.0000 0.1876 0.0000 0.0000 0.0000

D.5.2 FINISHING WORK LOT 1.00 0.19323 0.0000 0.0000 0.0000

D.5.2.1 METAL ROOFING & METAL WALL WORK LOT 1.00 0.08387 0.0000 0.0000 0.0000

Metal Roofing Factory


A Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 256.00 0.02194 0.0000 0.0000 0.0000 0.2616 0.0000 0.0000 0.0000
B Roof mesh, Galvanized #3x3" m2 256.00 0.00206 0.0000 0.0000 0.0000 0.0245 0.0000 0.0000 0.0000
C Aluminium foil single sided m2 256.00 0.00164 0.0000 0.0000 0.0000 0.0196 0.0000 0.0000 0.0000
D Glasswool 16 kgs/m3, Thk 25mm m2
E FRP Roofing Bottless U-650 (100mm ) clear, t : 2mm m 22.00 0.00359 0.0000 0.0000 0.0000 0.0429 0.0000 0.0000 0.0000
F End Close, Boltless U-650 m 50.00 0.00113 0.0000 0.0000 0.0000 0.0134 0.0000 0.0000 0.0000
G Appron Boltless U-650 m 25.00 0.00056 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
H Eaves Close Boltless U-650 m 25.00 0.00056 0.0000 0.0000 0.0000 0.0067 0.0000 0.0000 0.0000
I Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 13.00 0.00087 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
J Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 22.00 0.00124 0.0000 0.0000 0.0000 0.0148 0.0000 0.0000 0.0000
K Expansion Cover W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 22.00 0.00124 0.0000 0.0000 0.0000 0.0148 0.0000 0.0000 0.0000
L Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 25.00 0.00083 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
M FRP Flashing W=305mm , zincalume Thk 0.5mm (Tct) m 43.00 0.00175 0.0000 0.0000 0.0000 0.0209 0.0000 0.0000 0.0000
N Eaves Gutter, FRP Grey Thk 2.0mm , W=1.000mm m 25.00 0.00469 0.0000 0.0000 0.0000 0.0559 0.0000 0.0000 0.0000
O Gutter Bracket Sp 3x42mm W=1.200mm pcs 40.00 0.00129 0.0000 0.0000 0.0000 0.0154 0.0000 0.0000 0.0000
P PVC Pipe AW Grey Dia. 150mm m 26.00 0.00195 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
Q PVC Lbow 450 / 900 , Dia. 150mm pcs 8.00 0.00060 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
R Clamp pipe Sp. 3x30mm , Dia. 150mm pcs 26.00 0.00070 0.0000 0.0000 0.0000 0.0083 0.0000 0.0000 0.0000

Metal Wall
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 68
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
A Metal Wall Type U527 (27mm), Zinc Alum Colour Thk. 0,40mm (Tct) m2 404.00 0.03247 0.0000 0.0000 0.0000 0.3872 0.0000 0.0000 0.0000
B End Wall Flashing W=457mm, Zincalume Colour Thk 0.40mm m 35.00 0.00142 0.0000 0.0000 0.0000 0.0170 0.0000 0.0000 0.0000
C Window, Shutter & Open flashing W=457mm, Zincalume m 40.00 0.00163 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000 0.0000
Thk 0.4mm
D Corner flashing W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
E Wall Expansion Cover W=457mm, Zincalume Colour Thk 0.40mm m 21.00 0.00085 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000

D.5.2.2 MASONRY WORK LOT 1.00 0.00673 0.0000 0.0000 0.0000

A Common brick wall m2 35.00 0.00232 0.0000 0.0000 0.0000 0.3441 0.0000 0.0000 0.0000
B Ventilation block wall m2
C The following in lintel / stiffener :
- Grade K - 175 concrete m3 0.70 0.00030 0.0000 0.0000 0.0000 0.0438 0.0000 0.0000 0.0000
- HT. Reinforcement kg 112.00 0.00063 0.0000 0.0000 0.0000 0.0943 0.0000 0.0000 0.0000
- Timber formwork m2 7.50 0.00044 0.0000 0.0000 0.0000 0.0647 0.0000 0.0000 0.0000
D Plastering 25mm on common brick walls with float & rendered m2 70.00 0.00305 0.0000 0.0000 0.0000 0.4531 0.0000 0.0000 0.0000
w/ instant mortar

D.5.2.3 TILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

D.5.2.4 DOOR AND WINDOW WORK LOT 1.00 0.02267 0.0000 0.0000 0.0000

DOORS
A Relocation & Re-install Motorized steel roll-up shutter
size : 6.000mm (W) x 8.000mm (H) nos 2.00 0.02126 0.0000 0.0000 0.0000 0.9375 0.0000 0.0000 0.0000
B Ditto, but to Steel single door
nos 1.00 0.00142 0.0000 0.0000 0.0000 0.0625 0.0000 0.0000 0.0000

D.5.2.5 PAINTING WORK LOT 1.00 0.02494 0.0000 0.0000 0.0000

A Weathershield paint to external wall m2 35.00 0.00071 0.0000 0.0000 0.0000 0.0283 0.0000 0.0000 0.0000
B Acrylic Emulsion Paint (AEP) to internal wall m2 44.00 0.00050 0.0000 0.0000 0.0000 0.0202 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 202.00 0.00367 0.0000 0.0000 0.0000 0.1470 0.0000 0.0000 0.0000
E Ditto, but to PVC pipe m 26.00 0.00018 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000
G Floor Hardener Natural Color to Floor m2 492.00 0.01989 0.0000 0.0000 0.0000 0.7974 0.0000 0.0000 0.0000

D.5.2.6 INTERIOR FINISHING WORK LOT 1.00 0.00207 0.0000 0.0000 0.0000
Floor Finish
A Steel trowel finish m2 492.00 0.00156 0.0000 0.0000 0.0000 0.0626 0.0000 0.0000 0.0000

Base Finish
B Mortar Base w/ AE H = 100mm m 48.00 0.00051 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

D.5.2.7 WATERPROOFING WORK LOT 1.00 0.00023 0.0000 0.0000 0.0000

A Groove w/ fill polyurethane sealent (15w x 15d) m 10.00 0.00023 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.5.2.8 MISCELLANEOUS WORK LOT 1.00 0.05270 0.0000 0.0000 0.0000

A Guard post steel pipe Dia.100, H=1200 mm (H) nos 8.00 0.00255 0.0000 0.0000 0.0000 0.0484 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 6.00 0.00055 0.0000 0.0000 0.0000 0.0105 0.0000 0.0000 0.0000
C Steel Grating W = 1.000mm m 40.00 0.04960 0.0000 0.0000 0.0000 0.9411 0.0000 0.0000 0.0000

D.6 WASHING AREA 0.26212 0.0000 0.0000 0.0000

D.6.1 STRUCTURE WORK LOT 1.00 0.26212 0.0000 0.0000 0.0000

D.6.1.1 EARTH WORK LOT 1.00 0.00974 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 180.00 0.00057 0.0000 0.0000 0.0000 0.0586 0.0000 0.0000 0.0000
site of all debris
B Excavation to pit m3 185.30 0.00220 0.0000 0.0000 0.0000 0.2259 0.0000 0.0000 0.0000
C Excavation to ground slab m3 41.40 0.00049 0.0000 0.0000 0.0000 0.0505 0.0000 0.0000 0.0000
D Back fill part return and compaction m3 68.50 0.00087 0.0000 0.0000 0.0000 0.0897 0.0000 0.0000 0.0000
E Compacted sub grade m2 113.60 0.00021 0.0000 0.0000 0.0000 0.0212 0.0000 0.0000 0.0000
F Dispose excavated material (out project site) m3 116.90 0.00191 0.0000 0.0000 0.0000 0.1959 0.0000 0.0000 0.0000
G T=50mm comp. sand bedding m2 49.60 0.00043 0.0000 0.0000 0.0000 0.0443 0.0000 0.0000 0.0000
H T=200mm comp. basecourse m2 113.60 0.00306 0.0000 0.0000 0.0000 0.3139 0.0000 0.0000 0.0000

D.6.1.2 PILING WORK LOT 1.00 0.00000

D.6.1.3 CONCRETE WORK LOT 1.00 0.02484 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm , grade K - 150 concrete m2 49.60 0.00136 0.0000 0.0000 0.0000 0.0546 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Pit m3 36.30 0.01712 0.0000 0.0000 0.0000 0.6891 0.0000 0.0000 0.0000
C Ditto , but to RC Dike m3 13.50 0.00637 0.0000 0.0000 0.0000 0.2563 0.0000 0.0000 0.0000

D.6.1.4 REINFORCED WORK LOT 1.00 0.02346 0.0000 0.0000 0.0000

A HT. Reinforcement to Pit kg 3,921.00 0.02223 0.0000 0.0000 0.0000 0.9473 0.0000 0.0000 0.0000
B Ditto , but to RC Dike Kg 218.00 0.00124 0.0000 0.0000 0.0000 0.0527 0.0000 0.0000 0.0000

D.6.1.5 FORM WORK LOT 1.00 0.01655 0.0000 0.0000 0.0000

A Formwork to Pit m2 216.70 0.01259 0.0000 0.0000 0.0000 0.7607 0.0000 0.0000 0.0000
B Ditto , but to RC Dike m2 24.00 0.00139 0.0000 0.0000 0.0000 0.0842 0.0000 0.0000 0.0000
E Supporting formwork to above m2 240.70 0.00257 0.0000 0.0000 0.0000 0.1551 0.0000 0.0000 0.0000

D.6.1.6 STEEL STRUCTURE WORK LOT 1.00 0.06485 0.0000 0.0000 0.0000

A Steel Plate T=19mm m2 64.00 0.06485 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

D.6.1.7 MISCELLANEOUS WORK LOT 1.00 0.12268 0.0000 0.0000 0.0000

A Waterproofing coating anti acid to Pit m2 189.30 0.08718 0.0000 0.0000 0.0000 0.7107 0.0000 0.0000 0.0000
B Waterstop m 22.00 0.00273 0.0000 0.0000 0.0000 0.0222 0.0000 0.0000 0.0000
C Steel Angle L.40.40.5 w/ Galvanish Fin. m 80.00 0.00539 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000
D Pit Cover w/ Checker Plate Galvaized Fin. m2 15.10 0.01498 0.0000 0.0000 0.0000 0.1221 0.0000 0.0000 0.0000
E Steel Galv. Guard Rail, size : 1.900mm x 1.100mm (H) nos 4.00 0.00453 0.0000 0.0000 0.0000 0.0370 0.0000 0.0000 0.0000
F Steel Galv. Guard Rail, size : 2.600mm x 1.100mm (H) nos 2.00 0.00312 0.0000 0.0000 0.0000 0.0254 0.0000 0.0000 0.0000
G Steel Guard Post H = 1.100mm w/ S.S chain & hock nos 2.00 0.00475 0.0000 0.0000 0.0000 0.0387 0.0000 0.0000 0.0000

E. MECHANICAL WORK LOT 1.00 12.03803 12.03803 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
E.1 TRAINING CENTER & HEAD OFFICE
E.2 ULTRA LARGE COMPONENT FACT-2
E.3 ULTRA LARGE TOPCOAT PAINTING BOOTH
E.4 EXCAVATOR PAINT FACTORY
E.5 TOUCHUP PAINT BOOTH
E.6 WASHING AREA

F. ELECTRICAL WORK LOT 1.00 14.64834 14.64834 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000
F.1 TRAINING CENTER & HEAD OFFICE
F.2 ULTRA LARGE COMPONENT FACT-2
F.3 ULTRA LARGE TOPCOAT PAINTING BOOTH
F.4 EXCAVATOR PAINT FACTORY
F.5 TOUCHUP PAINT BOOTH
F.6 WASHING AREA

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 69
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
G. EXTERNAL WORK LOT 1.00 11.33154 11.33154 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

G.1 CIVIL WORK LOT 1.00 9.57299 0.0000 0.0011 0.0011

G.1.1 TRAINING CENTER & HEAD OFFICE AREA LOT 1.00 0.98023 0.0000 0.0000 0.0000

G.1.1.1 PAVING WORK LOT 1.00 0.69379 0.0000 0.0000 0.0000

A Asphalt Pavement
- Excavation Soil m3 1,600.90 0.01901 0.0000 0.0000 0.0000 0.0274 0.0000 0.0000 0.0000
- Disposed excavated material m3 1,600.90 0.02614 0.0000 0.0000 0.0000 0.0377 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 3,335.20 0.00608 0.0000 0.0000 0.0000 0.0088 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 3,335.20 0.06864 0.0000 0.0000 0.0000 0.0989 0.0000 0.0000 0.0000
- T=250mm Limestone m2 3,335.20 0.09228 0.0000 0.0000 0.0000 0.1330 0.0000 0.0000 0.0000
- Prime coat m2 3,335.20 0.01846 0.0000 0.0000 0.0000 0.0266 0.0000 0.0000 0.0000
- ATB 50 mm thick m3 3,335.20 0.22034 0.0000 0.0000 0.0000 0.3176 0.0000 0.0000 0.0000
- Wearing course 30mm thick m2 3,335.20 0.14337 0.0000 0.0000 0.0000 0.2066 0.0000 0.0000 0.0000
- Teack Coat m2 3,335.20 0.01238 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000

B Paving Block
- Excavate over site to formation level including m2 467.00 0.00148 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000
cleaning site of all debris (D=100mm)
- Excavation Work m3 121.42 0.00211 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
- Disposal Soil m3 121.42 0.00198 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000
- Comp. Sub grade m2 467.00 0.00085 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
- T=150mm Base course m2 467.00 0.00961 0.0000 0.0000 0.0000 0.0139 0.0000 0.0000 0.0000
- Compacted sand bed T=50mm m2 467.00 0.00407 0.0000 0.0000 0.0000 0.0059 0.0000 0.0000 0.0000
- Paving Block 60mm thick m2 467.00 0.02152 0.0000 0.0000 0.0000 0.0310 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 492.00 0.04402 0.0000 0.0000 0.0000 0.0635 0.0000 0.0000 0.0000

D Boundary Concrete Curb m 18.00 0.00145 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000 0.0000

G.1.1.2 DRAINAGE WORK LOT 1.00 0.24656 0.0000 0.0000 0.0000


A Open Drainage
- Excavation Soil m3 607.00 0.01053 0.0000 0.0000 0.0000 0.0427 0.0000 0.0000 0.0000
- Disposed excavated material m3 272.00 0.00444 0.0000 0.0000 0.0000 0.0180 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 335.00 0.00427 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 258.80 0.00047 0.0000 0.0000 0.0000 0.0019 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 258.80 0.00533 0.0000 0.0000 0.0000 0.0216 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 258.80 0.00707 0.0000 0.0000 0.0000 0.0287 0.0000 0.0000 0.0000
- River stone m3 224.00 0.07142 0.0000 0.0000 0.0000 0.2897 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 569.30 0.01471 0.0000 0.0000 0.0000 0.0597 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 20.70 0.00976 0.0000 0.0000 0.0000 0.0396 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,970.00 0.01117 0.0000 0.0000 0.0000 0.0453 0.0000 0.0000 0.0000
- Formwork m2 207.00 0.01203 0.0000 0.0000 0.0000 0.0488 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 344.90 0.00598 0.0000 0.0000 0.0000 0.0243 0.0000 0.0000 0.0000
- Disposed excavated material m3 153.30 0.00250 0.0000 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 191.60 0.00244 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 87.60 0.00016 0.0000 0.0000 0.0000 0.0006 0.0000 0.0000 0.0000

carried forward 0.16229

brought forward 0.16229 0.0000 0.0000 0.0000

B RC Culvert
- Sub base course 150mm thick m2 87.60 0.00180 0.0000 0.0000 0.0000 0.0073 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 87.60 0.00239 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 52.60 0.02480 0.0000 0.0000 0.0000 0.1006 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 6,307.00 0.03575 0.0000 0.0000 0.0000 0.1450 0.0000 0.0000 0.0000
- Formwork m2 335.80 0.01951 0.0000 0.0000 0.0000 0.0791 0.0000 0.0000 0.0000

G.1.1.3 LANDSCAPE WORK LOT 1.00 0.01296 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 1,178.00 0.00874 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 1,178.00 0.00421 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.1.4 MISCELLANEOUS WORK LOT 1.00 0.02693 0.0000 0.0000 0.0000

A Parking Line (White Paint) m 433.00 0.00567 0.0000 0.0000 0.0000 0.2105 0.0000 0.0000 0.0000
B Repair & Touchup existing Flag Pole lot 1.00 0.01063 0.0000 0.0000 0.0000 0.3947 0.0000 0.0000 0.0000
C Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 0.3947 0.0000 0.0000 0.0000

G.1.2 EXCAVATOR PAINT FACTORY AREA LOT 1.00 0.82498 0.0000 0.0000 0.0000

G.1.2.1 PAVING WORK LOT 1.00 0.38305 0.0000 0.0000 0.0000

A RC Pavement
- Excavation Soil m3 682.65 0.00811 0.0000 0.0000 0.0000 0.0212 0.0000 0.0000 0.0000
- Disposed excavated material m3 682.65 0.01115 0.0000 0.0000 0.0000 0.0291 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 1,517.00 0.00276 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Sub base course 200mm thick m2 1,517.00 0.04085 0.0000 0.0000 0.0000 0.1066 0.0000 0.0000 0.0000
- T=250mm Limestone m2 1,517.00 0.04197 0.0000 0.0000 0.0000 0.1096 0.0000 0.0000 0.0000
- PE Sheet Damp Proof Membrane m2 1,517.00 0.00379 0.0000 0.0000 0.0000 0.0099 0.0000 0.0000 0.0000
- Concrete grade K-250 , T=200mm m3 303.40 0.14307 0.0000 0.0000 0.0000 0.3735 0.0000 0.0000 0.0000
- Wiremesh #M10 ( Single ) m2 1,517.00 0.09572 0.0000 0.0000 0.0000 0.2499 0.0000 0.0000 0.0000
- Formwork m2 79.00 0.00459 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
- Steel Trowel finish m2 1,517.00 0.00481 0.0000 0.0000 0.0000 0.0126 0.0000 0.0000 0.0000
B Construction Joint filled w/ asphalt fill
- Sand Asphlat Fill m 316.00 0.00616 0.0000 0.0000 0.0000 0.0161 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 1,948.00 0.01104 0.0000 0.0000 0.0000 0.0288 0.0000 0.0000 0.0000
- Dowel bar kg 1,164.00 0.00660 0.0000 0.0000 0.0000 0.0172 0.0000 0.0000 0.0000
- Flexible hose m 421.00 0.00091 0.0000 0.0000 0.0000 0.0024 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 17.00 0.00152 0.0000 0.0000 0.0000 0.0040 0.0000 0.0000 0.0000

G.1.2.2 DRAINAGE WORK LOT 1.00 0.42044 0.0000 0.0000 0.0000

A Open Drainage
- Excavation Soil m3 424.00 0.00735 0.0000 0.0000 0.0000 0.0175 0.0000 0.0000 0.0000
- Disposed excavated material m3 190.00 0.00310 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 234.00 0.00298 0.0000 0.0000 0.0000 0.0071 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 180.80 0.00033 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 180.80 0.00372 0.0000 0.0000 0.0000 0.0089 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 180.80 0.00494 0.0000 0.0000 0.0000 0.0118 0.0000 0.0000 0.0000
- River stone m3 156.70 0.04996 0.0000 0.0000 0.0000 0.1188 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 397.70 0.01028 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 14.50 0.00684 0.0000 0.0000 0.0000 0.0163 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,376.00 0.00780 0.0000 0.0000 0.0000 0.0186 0.0000 0.0000 0.0000
- Formwork m2 144.60 0.00840 0.0000 0.0000 0.0000 0.0200 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 1,139.00 0.01975 0.0000 0.0000 0.0000 0.0470 0.0000 0.0000 0.0000
- Disposed excavated material m3 506.00 0.00826 0.0000 0.0000 0.0000 0.0197 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 70
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Back fill part return and compaction m3 633.00 0.00807 0.0000 0.0000 0.0000 0.0192 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 289.20 0.00053 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 289.20 0.00595 0.0000 0.0000 0.0000 0.0142 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 289.20 0.00790 0.0000 0.0000 0.0000 0.0188 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 173.50 0.08182 0.0000 0.0000 0.0000 0.1946 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 20,822.00 0.11803 0.0000 0.0000 0.0000 0.2807 0.0000 0.0000 0.0000
- Formwork m2 1,108.60 0.06441 0.0000 0.0000 0.0000 0.1532 0.0000 0.0000 0.0000

G.1.2.3 LANDSCAPE WORK LOT 1.00 0.00377 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 343.00 0.00255 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 343.00 0.00123 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.2.4 MISCELLANEOUS WORK LOT 1.00 0.01771 0.0000 0.0000 0.0000

A Repair & Touchup existing external work lot 1.00 0.01771 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

G.1.3 ULTRA LARGE COMPONENT FACTORY-2 AREA LOT 1.00 1.70938 0.0000 0.0000 0.0000

G.1.3.1 PAVING WORK LOT 1.00 1.22001 0.0000 0.0000 0.0000

A RC Pavement
- Excavation Soil m3 2,163.60 0.02570 0.0000 0.0000 0.0000 0.0211 0.0000 0.0000 0.0000
- Disposed excavated material m3 2,163.60 0.03533 0.0000 0.0000 0.0000 0.0290 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 4,808.00 0.00876 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Sub base course 200mm thick m2 4,808.00 0.12946 0.0000 0.0000 0.0000 0.1061 0.0000 0.0000 0.0000
- T=250mm Limestone m2 4,808.00 0.13303 0.0000 0.0000 0.0000 0.1090 0.0000 0.0000 0.0000
- PE Sheet Damp Proof Membrane m2 4,808.00 0.01200 0.0000 0.0000 0.0000 0.0098 0.0000 0.0000 0.0000
- Concrete grade K-250 , T=200mm m3 961.60 0.45345 0.0000 0.0000 0.0000 0.3717 0.0000 0.0000 0.0000
- Wiremesh #M10 ( Single ) m2 4,808.00 0.30336 0.0000 0.0000 0.0000 0.2487 0.0000 0.0000 0.0000
- Formwork m2 250.00 0.01453 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000
- Steel Trowel finish m2 4,808.00 0.01525 0.0000 0.0000 0.0000 0.0125 0.0000 0.0000 0.0000
B Construction Joint filled w/ asphalt fill
- Sand Asphlat Fill m 534.00 0.01041 0.0000 0.0000 0.0000 0.0085 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 8,080.00 0.04580 0.0000 0.0000 0.0000 0.0375 0.0000 0.0000 0.0000
- Dowel bar kg 3,721.00 0.02109 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Flexible hose m 715.00 0.00154 0.0000 0.0000 0.0000 0.0013 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 115.00 0.01029 0.0000 0.0000 0.0000 0.0084 0.0000 0.0000 0.0000

G.1.3.2 DRAINAGE WORK LOT 1.00 0.46890 0.0000 0.0000 0.0000

A Open Drainage
- Excavation Soil m3 482.00 0.00836 0.0000 0.0000 0.0000 0.0178 0.0000 0.0000 0.0000
- Disposed excavated material m3 216.00 0.00353 0.0000 0.0000 0.0000 0.0075 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 266.00 0.00339 0.0000 0.0000 0.0000 0.0072 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 205.50 0.00037 0.0000 0.0000 0.0000 0.0008 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 205.50 0.00423 0.0000 0.0000 0.0000 0.0090 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 205.50 0.00562 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000
- River stone m3 178.00 0.05676 0.0000 0.0000 0.0000 0.1210 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 452.00 0.01168 0.0000 0.0000 0.0000 0.0249 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 16.50 0.00778 0.0000 0.0000 0.0000 0.0166 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 1,564.00 0.00887 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
- Formwork m2 165.00 0.00959 0.0000 0.0000 0.0000 0.0204 0.0000 0.0000 0.0000

B RC Culvert
- Excavation Soil m3 1,262.00 0.02189 0.0000 0.0000 0.0000 0.0467 0.0000 0.0000 0.0000
- Disposed excavated material m3 561.00 0.00916 0.0000 0.0000 0.0000 0.0195 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 701.00 0.00894 0.0000 0.0000 0.0000 0.0191 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 320.40 0.00058 0.0000 0.0000 0.0000 0.0012 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 320.40 0.00659 0.0000 0.0000 0.0000 0.0141 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 320.40 0.00876 0.0000 0.0000 0.0000 0.0187 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 192.30 0.09068 0.0000 0.0000 0.0000 0.1934 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 23,069.00 0.13077 0.0000 0.0000 0.0000 0.2789 0.0000 0.0000 0.0000
- Formwork m2 1,228.20 0.07136 0.0000 0.0000 0.0000 0.1522 0.0000 0.0000 0.0000

G.1.3.3 LANDSCAPE WORK LOT 1.00 0.00984 0.0000 0.0000 0.0000

A Turfing ( 100% ) ( Factory Area Only ) m2 895.00 0.00664 0.0000 0.0000 0.0000 0.6748 0.0000 0.0000 0.0000
B Red Soil Filling h-50 m2 895.00 0.00320 0.0000 0.0000 0.0000 0.3252 0.0000 0.0000 0.0000

G.1.3.4 MISCELLANEOUS WORK LOT 1.00 0.01063 0.0000 0.0000 0.0000

A Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

G.1.4 TOUCHUP PAINT BOOTH AREA LOT 1.00 0.19330 0.0000 0.0000 0.0000

G.1.4.1 DRAINAGE WORK LOT 1.00 0.19330 0.0000 0.0000 0.0000

A RC Culvert
- Excavation Soil m3 699.30 0.01213 0.0000 0.0000 0.0000 0.0627 0.0000 0.0000 0.0000
- Disposed excavated material m3 310.80 0.00508 0.0000 0.0000 0.0000 0.0263 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 388.50 0.00495 0.0000 0.0000 0.0000 0.0256 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 177.60 0.00032 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 177.60 0.00366 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 177.60 0.00485 0.0000 0.0000 0.0000 0.0251 0.0000 0.0000 0.0000
- Concrete grade K-250, to Drainage m3 106.60 0.05027 0.0000 0.0000 0.0000 0.2601 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 12,787.00 0.07248 0.0000 0.0000 0.0000 0.3750 0.0000 0.0000 0.0000
- Formwork m2 680.80 0.03956 0.0000 0.0000 0.0000 0.2046 0.0000 0.0000 0.0000

G.1.5 MAIN GATE AND FENCE LOT 1.00 0.33456 0.0000 0.0000 0.0000

G.1.5.1 MAIN GATE

A Automatic Steel Main Gate size. 12.000mm (W) x 2.000mm (H) unit 2.00 0.14586 0.0000 0.0000 0.0000 0.4360 0.0000 0.0000 0.0000
B Foundation to Main Gate unit 2.00 0.05385 0.0000 0.0000 0.0000 0.1610 0.0000 0.0000 0.0000
C Steel Man Door, size : 1.200mm (W) x 2.000mm (H) unit 1.00 0.00461 0.0000 0.0000 0.0000 0.0138 0.0000 0.0000 0.0000
D Steel Grid Fence H = 2.000mm m 22.00 0.01169 0.0000 0.0000 0.0000 0.0349 0.0000 0.0000 0.0000

G.1.5.2 FENCE

RC Wall Fence
A Earth Work
- Excavation Soil m3 33.80 0.00059 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000 0.0000
- Disposed excavated material m3 9.30 0.00015 0.0000 0.0000 0.0000 0.0005 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 24.50 0.00031 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 38.50 0.00007 0.0000 0.0000 0.0000 0.0002 0.0000 0.0000 0.0000
- T=50mm comp. sand bedding m2 38.50 0.00034 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000
B Strauss Pile
- Mob and Demob equipment and transport lot 1.00 0.00248 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
- Drilling Ø200 - 2m nos 50.00 0.00531 0.0000 0.0000 0.0000 0.0159 0.0000 0.0000 0.0000
- Concrete K-250 m3 3.20 0.00151 0.0000 0.0000 0.0000 0.0045 0.0000 0.0000 0.0000
- H.T. Reinforcement kg 684.00 0.00388 0.0000 0.0000 0.0000 0.0116 0.0000 0.0000 0.0000
- Disposal of pre-bored earth nos 50.00 0.00248 0.0000 0.0000 0.0000 0.0074 0.0000 0.0000 0.0000
C Reinforced Concrete Work
- Lean concrete T = 100mm, grade K-150 concrete m2 38.50 0.00105 0.0000 0.0000 0.0000 0.0031 0.0000 0.0000 0.0000
- Concrete grade K-250, to Sloof m3 4.60 0.00217 0.0000 0.0000 0.0000 0.0065 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 71
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Ditto , but to RC Wall m3 21.60 0.01019 0.0000 0.0000 0.0000 0.0304 0.0000 0.0000 0.0000
- Ditto , but to Planter Box m3 3.00 0.00141 0.0000 0.0000 0.0000 0.0042 0.0000 0.0000 0.0000
- HT. Reinforcement to Sloof kg 1,020.00 0.00578 0.0000 0.0000 0.0000 0.0173 0.0000 0.0000 0.0000
- Ditto , but to RC Wall kg 2,784.00 0.01578 0.0000 0.0000 0.0000 0.0472 0.0000 0.0000 0.0000
- Ditto , but to Planter Box kg 478.00 0.00271 0.0000 0.0000 0.0000 0.0081 0.0000 0.0000 0.0000
- Formwork to Sloof m2 61.60 0.00358 0.0000 0.0000 0.0000 0.0107 0.0000 0.0000 0.0000
- Ditto , but to RC Wall m2 287.30 0.01669 0.0000 0.0000 0.0000 0.0499 0.0000 0.0000 0.0000
- Ditto , but to Planter Box m2 39.50 0.00230 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
- Supporting formwork to above m2 326.80 0.00348 0.0000 0.0000 0.0000 0.0104 0.0000 0.0000 0.0000
F Miscellaneous Work
- Textured Spray Paint Fin. m2 458.00 0.01786 0.0000 0.0000 0.0000 0.0534 0.0000 0.0000 0.0000
- Company Logo & Signane nos 2.00 0.00779 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
- Repair & Touchup existing external work lot 1.00 0.01063 0.0000 0.0000 0.0000 0.0318 0.0000 0.0000 0.0000

G.1.6 GUARD HOUSE - 1 LOT 1.00 0.14741 0.0000 0.0000 0.0000

G.1.6.1 STRUCTURE WORK LOT 1.00 0.07973 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.00242 0.0000 0.0000 0.0000

A Manual Excavation to foundation & grade beam m3 29.70 0.00052 0.0000 0.0000 0.0000 0.2127 0.0000 0.0000 0.0000
B Back fill part return and compaction m3 8.60 0.00011 0.0000 0.0000 0.0000 0.0453 0.0000 0.0000 0.0000
C Compacted sub grade m2 77.00 0.00014 0.0000 0.0000 0.0000 0.0579 0.0000 0.0000 0.0000
D Dispose excavated material (out project site) m3 21.10 0.00034 0.0000 0.0000 0.0000 0.1423 0.0000 0.0000 0.0000
E T=50mm comp.sand bedding m2 23.00 0.00020 0.0000 0.0000 0.0000 0.0827 0.0000 0.0000 0.0000
F T=150mm comp. basecourse m2 54.00 0.00111 0.0000 0.0000 0.0000 0.4590 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.02147 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 23.00 0.00063 0.0000 0.0000 0.0000 0.0293 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Ground Beam m3 5.10 0.00240 0.0000 0.0000 0.0000 0.1120 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m3 6.80 0.00321 0.0000 0.0000 0.0000 0.1493 0.0000 0.0000 0.0000
D Ditto , but to Column m3 2.10 0.00099 0.0000 0.0000 0.0000 0.0461 0.0000 0.0000 0.0000
E Ditto , but to to Roof Beam m3 7.10 0.00335 0.0000 0.0000 0.0000 0.1559 0.0000 0.0000 0.0000
F Ditto , but to to Roof Slab m3 6.80 0.00321 0.0000 0.0000 0.0000 0.1493 0.0000 0.0000 0.0000
G Ditto , but to to Parapet m3 4.30 0.00203 0.0000 0.0000 0.0000 0.0944 0.0000 0.0000 0.0000
H Ditto , but to to Canopy m3 10.00 0.00472 0.0000 0.0000 0.0000 0.2196 0.0000 0.0000 0.0000
I Ditto , but to to RC Bench m3 2.00 0.00094 0.0000 0.0000 0.0000 0.0439 0.0000 0.0000 0.0000

IV REINFORCED WORK LOT 1.00 0.02876 0.0000 0.0000 0.0000

A HT. Reinforcement to Ground Beam kg 718.00 0.00407 0.0000 0.0000 0.0000 0.1415 0.0000 0.0000 0.0000
B Ditto , but to Column kg 325.00 0.00184 0.0000 0.0000 0.0000 0.0641 0.0000 0.0000 0.0000
C Ditto , but to to Roof Beam kg 1,097.00 0.00622 0.0000 0.0000 0.0000 0.2162 0.0000 0.0000 0.0000
D Ditto , but to to Roof Slab kg 745.00 0.00422 0.0000 0.0000 0.0000 0.1468 0.0000 0.0000 0.0000
E Ditto , but to to Parapet kg 621.00 0.00352 0.0000 0.0000 0.0000 0.1224 0.0000 0.0000 0.0000
F Ditto , but to to Canopy kg 1,049.00 0.00595 0.0000 0.0000 0.0000 0.2068 0.0000 0.0000 0.0000
G Ditto , but to to RC Bench kg 244.00 0.00138 0.0000 0.0000 0.0000 0.0481 0.0000 0.0000 0.0000
H Wiremesh #M6 to ground slab (1 layer) m2 54.00 0.00156 0.0000 0.0000 0.0000 0.0541 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.02707 0.0000 0.0000 0.0000

A Timber formwork to Ground Beam m2 40.80 0.00237 0.0000 0.0000 0.0000 0.0876 0.0000 0.0000 0.0000
B Ditto , but to Ground Slab m2 5.30 0.00031 0.0000 0.0000 0.0000 0.0114 0.0000 0.0000 0.0000
C Ditto , but to Column m2 32.50 0.00189 0.0000 0.0000 0.0000 0.0697 0.0000 0.0000 0.0000
D Ditto , but to to Roof Beam m2 56.30 0.00359 0.0000 0.0000 0.0000 0.1325 0.0000 0.0000 0.0000
E Ditto , but to to Roof Slab m2 59.30 0.00378 0.0000 0.0000 0.0000 0.1395 0.0000 0.0000 0.0000
F Ditto , but to to Parapet m2 61.80 0.00394 0.0000 0.0000 0.0000 0.1454 0.0000 0.0000 0.0000
G Ditto , but to to Canopy m2 101.50 0.00647 0.0000 0.0000 0.0000 0.2388 0.0000 0.0000 0.0000
H Ditto , but to to RC Bench m2 19.10 0.00122 0.0000 0.0000 0.0000 0.0449 0.0000 0.0000 0.0000
J Supporting formwork m2 330.50 0.00352 0.0000 0.0000 0.0000 0.1302 0.0000 0.0000 0.0000

G.1.6.2 FINISHING WORK LOT 1.00 0.06769 0.0000 0.0000 0.0000

I DOOR and WINDOW WORK LOT 1.00 0.00574 0.0000 0.0000 0.0000

DOORS
A Wooden single swing door (WD-1) unit 2.00 0.00411 0.0000 0.0000 0.0000 0.7159 0.0000 0.0000 0.0000
size : 850mm (W) x 2.100mm (H)

B Hardware and Ironmongery lot 1.00 0.00117 0.0000 0.0000 0.0000 0.2042 0.0000 0.0000 0.0000

C Aluminium Fix Glass Window (AW-1) unit 1.00 0.00046 0.0000 0.0000 0.0000 0.0799 0.0000 0.0000 0.0000
size : 1.250 x 450 mm

II MASONRY WORK LOT 1.00 0.02072 0.0000 0.0000 0.0000

A Common brick wall m2 112.00 0.00741 0.0000 0.0000 0.0000 0.3578 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 1.70 0.00072 0.0000 0.0000 0.0000 0.0346 0.0000 0.0000 0.0000
- HT. Reinforcement kg 269.00 0.00152 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
- Timber formwork m2 22.40 0.00130 0.0000 0.0000 0.0000 0.0628 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 224.00 0.00976 0.0000 0.0000 0.0000 0.4712 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.00785 0.0000 0.0000 0.0000

A Texured spray paint to external wall m2 135.50 0.00529 0.0000 0.0000 0.0000 0.6733 0.0000 0.0000 0.0000
B Emulsion paint to internal wall m2 99.00 0.00120 0.0000 0.0000 0.0000 0.1523 0.0000 0.0000 0.0000
C Emulsion paint to ceiling m2 100.00 0.00121 0.0000 0.0000 0.0000 0.1539 0.0000 0.0000 0.0000
D Syntetic resin oil paint (OP) on door surface m2 8.40 0.00016 0.0000 0.0000 0.0000 0.0205 0.0000 0.0000 0.0000

IV INTERIOR FINISHING WORK LOT 1.00 0.01275 0.0000 0.0000 0.0000

FLOOR FINISHING
A Ceramic tile , 200x200mm w/ bed mortar m2 7.40 0.00059 0.0000 0.0000 0.0000 0.0462 0.0000 0.0000 0.0000
B Ceramic tile , 300x300mm w/ bed mortar m2 46.60 0.00390 0.0000 0.0000 0.0000 0.3055 0.0000 0.0000 0.0000
WALL FINISHING
C Ceramic tile , 200mm x 200mm m2 24.70 0.00201 0.0000 0.0000 0.0000 0.1575 0.0000 0.0000 0.0000
D Ceramic base H=100mm m2 52.10 0.00111 0.0000 0.0000 0.0000 0.0874 0.0000 0.0000 0.0000
CEILING FINISH
E Gypsum Board (Flat) T=9mm w/ LGS Frame m2 46.60 0.00238 0.0000 0.0000 0.0000 0.1864 0.0000 0.0000 0.0000
F Mouisture Gypsum Board (Flat) T=9mm w/ LGS Frame m2 7.40 0.00050 0.0000 0.0000 0.0000 0.0390 0.0000 0.0000 0.0000
G Extra steel chanel to ditto kg 162.00 0.00159 0.0000 0.0000 0.0000 0.1243 0.0000 0.0000 0.0000
H Skim coat to Exposed Ceiling m2 46.00 0.00069 0.0000 0.0000 0.0000 0.0538 0.0000 0.0000 0.0000

V WATERPROOFING WORK LOT 1.00 0.00859 0.0000 0.0000 0.0000

A Waterproofing membrane to roof m2 67.00 0.00356 0.0000 0.0000 0.0000 0.4149 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 54.00 0.00329 0.0000 0.0000 0.0000 0.3836 0.0000 0.0000 0.0000
C Brick protection w/ plastering finish m2 17.00 0.00173 0.0000 0.0000 0.0000 0.2016 0.0000 0.0000 0.0000

VI MISCELLANEOUS WORK LOT 1.00 0.01203 0.0000 0.0000 0.0000

A Lavatory concrete table w/ ceramic tile nos 1.00 0.00113 0.0000 0.0000 0.0000 0.0942 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 72
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
B Pantry concrete table w/ ceramic tile & S/S Sink nos 1.00 0.00248 0.0000 0.0000 0.0000 0.2061 0.0000 0.0000 0.0000
C Toilet partition w/ Door m2 3.70 0.00367 0.0000 0.0000 0.0000 0.3050 0.0000 0.0000 0.0000
D PVC Down Spout Ø 100mm w/ Elbow & Clamp Pipe m 20.00 0.00376 0.0000 0.0000 0.0000 0.3122 0.0000 0.0000 0.0000
E Cast iron roof drain nos 4.00 0.00099 0.0000 0.0000 0.0000 0.0824 0.0000 0.0000 0.0000

G.1.7 GUARD HOUSE - 2 LOT 1.00 0.02012 0.0000 0.0000 0.0000

G.1.7.1 STRUCTURE WORK LOT 1.00 0.01395 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.00024 0.0000 0.0000 0.0000

A Manual Excavation to foundation & grade beam m3 3.60 0.00006 0.0000 0.0000 0.0000 0.2573 0.0000 0.0000 0.0000
B Back fill part return and compaction m3 1.70 0.00002 0.0000 0.0000 0.0000 0.0894 0.0000 0.0000 0.0000
C Compacted sub grade m2 7.60 0.00001 0.0000 0.0000 0.0000 0.0571 0.0000 0.0000 0.0000
D Dispose excavated material (out project site) m3 1.90 0.00003 0.0000 0.0000 0.0000 0.1279 0.0000 0.0000 0.0000
E T=50mm comp.sand bedding m2 3.60 0.00003 0.0000 0.0000 0.0000 0.1291 0.0000 0.0000 0.0000
F T=150mm comp. basecourse m2 4.00 0.00008 0.0000 0.0000 0.0000 0.3393 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.00382 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 3.60 0.00010 0.0000 0.0000 0.0000 0.0257 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Ground Beam m3 0.80 0.00038 0.0000 0.0000 0.0000 0.0987 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m3 0.50 0.00024 0.0000 0.0000 0.0000 0.0617 0.0000 0.0000 0.0000
D Ditto , but to Column m3 1.10 0.00052 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000
E Ditto , but to to Roof Beam m3 0.80 0.00038 0.0000 0.0000 0.0000 0.0987 0.0000 0.0000 0.0000
F Ditto , but to to Roof Slab m3 1.10 0.00052 0.0000 0.0000 0.0000 0.1357 0.0000 0.0000 0.0000
G Ditto , but to to Parapet m3 1.60 0.00075 0.0000 0.0000 0.0000 0.1973 0.0000 0.0000 0.0000
H Ditto , but to to Canopy m3 2.00 0.00094 0.0000 0.0000 0.0000 0.2467 0.0000 0.0000 0.0000
I Ditto , but to to RC Bench m3

IV REINFORCED WORK LOT 1.00 0.00502 0.0000 0.0000 0.0000

A HT. Reinforcement to Ground Beam kg 128.00 0.00073 0.0000 0.0000 0.0000 0.1446 0.0000 0.0000 0.0000
B Ditto , but to Column kg 163.00 0.00092 0.0000 0.0000 0.0000 0.1841 0.0000 0.0000 0.0000
C Ditto , but to to Roof Beam kg 132.00 0.00075 0.0000 0.0000 0.0000 0.1491 0.0000 0.0000 0.0000
D Ditto , but to to Roof Slab kg 98.00 0.00056 0.0000 0.0000 0.0000 0.1107 0.0000 0.0000 0.0000
E Ditto , but to to Parapet kg 163.00 0.00092 0.0000 0.0000 0.0000 0.1841 0.0000 0.0000 0.0000
F Ditto , but to to Canopy kg 181.00 0.00103 0.0000 0.0000 0.0000 0.2044 0.0000 0.0000 0.0000
G Ditto , but to to RC Bench kg 0.00000 -
H Wiremesh #M6 to ground slab (1 layer) m2 4.00 0.00012 0.0000 0.0000 0.0000 0.0230 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.00487 0.0000 0.0000 0.0000

A Timber formwork to Ground Beam m2 6.40 0.00037 0.0000 0.0000 0.0000 0.0764 0.0000 0.0000 0.0000
B Ditto , but to Ground Slab m2 1.00 0.00006 0.0000 0.0000 0.0000 0.0119 0.0000 0.0000 0.0000
C Ditto , but to Column m2 14.60 0.00085 0.0000 0.0000 0.0000 0.1742 0.0000 0.0000 0.0000
D Ditto , but to to Roof Beam m2 6.00 0.00038 0.0000 0.0000 0.0000 0.0785 0.0000 0.0000 0.0000
E Ditto , but to to Roof Slab m2 4.40 0.00028 0.0000 0.0000 0.0000 0.0576 0.0000 0.0000 0.0000
F Ditto , but to to Parapet m2 15.00 0.00096 0.0000 0.0000 0.0000 0.1962 0.0000 0.0000 0.0000
G Ditto , but to to Canopy m2 20.80 0.00133 0.0000 0.0000 0.0000 0.2721 0.0000 0.0000 0.0000
H Ditto , but to to RC Bench m2 0.00000
J Supporting formwork m2 60.80 0.00065 0.0000 0.0000 0.0000 0.1331 0.0000 0.0000 0.0000

G.1.7.2 FINISHING WORK LOT 1.00 0.00616 0.0000 0.0000 0.0000

I DOOR and WINDOW WORK LOT 1.00 0.00000 0.0000 0.0000 0.0000

II MASONRY WORK LOT 1.00 0.00208 0.0000 0.0000 0.0000

A Common brick wall m2 11.00 0.00073 0.0000 0.0000 0.0000 0.3509 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 0.20 0.00008 0.0000 0.0000 0.0000 0.0406 0.0000 0.0000 0.0000
- HT. Reinforcement kg 29.00 0.00016 0.0000 0.0000 0.0000 0.0792 0.0000 0.0000 0.0000
- Timber formwork m2 2.40 0.00014 0.0000 0.0000 0.0000 0.0672 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 22.00 0.00096 0.0000 0.0000 0.0000 0.4621 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.00110 0.0000 0.0000 0.0000

A Texured spray paint to external wall m2 20.30 0.00079 0.0000 0.0000 0.0000 0.7184 0.0000 0.0000 0.0000
B Emulsion paint to internal wall m2 16.70 0.00020 0.0000 0.0000 0.0000 0.1830 0.0000 0.0000 0.0000
C Emulsion paint to ceiling m2 9.00 0.00011 0.0000 0.0000 0.0000 0.0986 0.0000 0.0000 0.0000

IV INTERIOR FINISHING WORK LOT 1.00 0.00089 0.0000 0.0000 0.0000

FLOOR FINISHING
A Ceramic tile , 300x300mm w/ bed mortar m2 4.00 0.00033 0.0000 0.0000 0.0000 0.3763 0.0000 0.0000 0.0000
WALL FINISHING
B Ceramic base H=100mm m2 7.40 0.00016 0.0000 0.0000 0.0000 0.1781 0.0000 0.0000 0.0000
CEILING FINISH
C Gypsum Board (Flat) T=9mm w/ LGS Frame m2 4.00 0.00020 0.0000 0.0000 0.0000 0.2296 0.0000 0.0000 0.0000
D Extra steel chanel to ditto kg 12.00 0.00012 0.0000 0.0000 0.0000 0.1321 0.0000 0.0000 0.0000
E Skim coat to Exposed Ceiling m2 5.00 0.00007 0.0000 0.0000 0.0000 0.0839 0.0000 0.0000 0.0000

V WATERPROOFING WORK LOT 1.00 0.00091 0.0000 0.0000 0.0000

A Waterproofing membrane to roof m2 6.40 0.00034 0.0000 0.0000 0.0000 0.3739 0.0000 0.0000 0.0000
B Protection concrete 60 mm to waterproofing membrane m2 4.00 0.00024 0.0000 0.0000 0.0000 0.2681 0.0000 0.0000 0.0000
C Brick protection w/ plastering finish m2 3.20 0.00033 0.0000 0.0000 0.0000 0.3580 0.0000 0.0000 0.0000

VI MISCELLANEOUS WORK LOT 1.00 0.00119 0.0000 0.0000 0.0000

A PVC Down Spout Ø 100mm w/ Elbow & Clamp Pipe m 5.00 0.00094 0.0000 0.0000 0.0000 0.7911 0.0000 0.0000 0.0000
B Cast iron roof drain nos 1.00 0.00025 0.0000 0.0000 0.0000 0.2089 0.0000 0.0000 0.0000

G.1.8 RC PAVEMENT & DRAINAGE AREA - A LOT 1.00 5.36302 0.0000 0.0011 0.0011

G.1.7.1 PAVING WORK LOT 1.00 5.04700 0.0000 0.0010 0.0010

A RC Pavement
- Excavation Soil m3 8,950.50 0.10630 0.0000 0.1063 0.1063 0.0211 0.0000 0.0000 0.0000
- Disposed excavated material m3 8,950.50 0.14617 0.0000 0.1462 0.1462 0.0290 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 19,890.00 0.03624 0.0000 0.0362 0.0362 0.0072 0.0000 0.0000 0.0000
- Sub base course 200mm thick m2 19,890.00 0.53554 0.0000 0.5355 0.5355 0.1061 0.0000 0.0000 0.0000
- T=250mm Limestone m2 19,890.00 0.55031 0.0000 0.5503 0.5503 0.1090 0.0000 0.0000 0.0000
- PE Sheet Damp Proof Membrane m2 19,890.00 0.04966 0.0000 0.0497 0.0497 0.0098 0.0000 0.0000 0.0000
- Concrete grade K-250 , T=200mm m3 3,978.00 1.87587 0.0000 1.8759 1.8759 0.3717 0.0000 0.0009 0.0009
- Wiremesh #M10 ( Single ) m2 19,890.00 1.25497 0.0000 1.2550 1.2550 0.2487 0.0000 0.0001 0.0001
- Formwork m2 1,034.20 0.06009 0.0000 0.0601 0.0601 0.0119 0.0000 0.0000 0.0000
- Steel Trowel finish m2 19,890.00 0.06308 0.0000 0.0631 0.0631 0.0125 0.0000 0.0000 0.0000
B Construction Joint filled w/ asphalt fill
- Sand Asphlat Fill m 2,209.10 0.04308 0.0000 0.0431 0.0431 0.0085 0.0000 0.0000 0.0000
- Add. Reinforcement bar to edge both side kg 33,426.10 0.18947 0.0000 0.1895 0.1895 0.0375 0.0000 0.0000 0.0000
- Dowel bar kg 15,393.40 0.08726 0.0000 0.0873 0.0873 0.0173 0.0000 0.0000 0.0000
06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 73
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
- Flexible hose m 2,957.90 0.00639 0.0000 0.0064 0.0064 0.0013 0.0000 0.0000 0.0000

C Pavement Concrete Curb m 475.70 0.04257 0.0000 0.0426 0.0426 0.0084 0.0000 0.0000 0.0000

G.1.7.2 DRAINAGE WORK LOT 1.00 0.31602 0.0000 0.0001 0.0001

A Open Drainage
- Excavation Soil m3 1,267.60 0.02198 0.0000 0.0220 0.0220 0.0696 0.0000 0.0000 0.0000
- Disposed excavated material m3 568.00 0.00928 0.0000 0.0093 0.0093 0.0294 0.0000 0.0000 0.0000
- Back fill part return and compaction m3 699.50 0.00892 0.0000 0.0089 0.0089 0.0282 0.0000 0.0000 0.0000
- Pre compacted subgrade m2 540.40 0.00098 0.0000 0.0010 0.0010 0.0031 0.0000 0.0000 0.0000
- Sub base course 150mm thick m2 540.40 0.01112 0.0000 0.0111 0.0111 0.0352 0.0000 0.0000 0.0000
- Lean concrete T = 100mm, grade K-150 concrete m2 540.40 0.01477 0.0000 0.0148 0.0148 0.0467 0.0000 0.0000 0.0000
- River stone m3 468.10 0.14925 0.0000 0.1493 0.1493 0.4723 0.0000 0.0000 0.0000
- Mortar Plestering to above (Siar) m2 1,188.70 0.03072 0.0000 0.0307 0.0307 0.0972 0.0000 0.0000 0.0000
- RC Protection, size : 150 x 200mm m3 43.40 0.02047 0.0000 0.0205 0.0205 0.0648 0.0000 0.0000 0.0000
- HT. Reinforcement to above kg 4,113.10 0.02331 0.0000 0.0233 0.0233 0.0738 0.0000 0.0000 0.0000
- Formwork m2 433.90 0.02521 0.0000 0.0252 0.0252 0.0798 0.0000 0.0000 0.0000

G.2 MECHANICAL WORK LOT 1.00 0.02254 0.0000 0.0000 0.0000 0.0713 0.0000 0.0000 0.0000

G.3 ELECTRICAL WORK LOT 1.00 1.73600 0.0000 0.0000 0.0000 5.4933 0.0000 0.0000 0.0000

H. MOTOR CYCLE PARKING LOT 1.00 2.28928 2.28928 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

H.1 CIVIL WORK LOT 1.00 2.05759 0.0000 0.0000 0.0000

H.1.1 PAVING WORK & DRAINAGE WORK LOT 1.00 0.23619 0.0000 0.0000 0.0000

A Modification External Road & Drainage lot 1.00 0.23619 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

H.1.2 MOTORCYCLE PARKING AREA ( E, F, G & H ) LOT 1.00 0.42140 0.0000 0.0000 0.0000

A Foundation Work
Earth Work
- - Excavation m3 312.80 0.00542 0.0000 0.0000 0.0000 0.0129 0.0000 0.0000 0.0000
- - Backfill m3 0.00 0.00000 -
- - Disposal m3 312.80 0.00511 0.0000 0.0000 0.0000 0.0121 0.0000 0.0000 0.0000
- - Comp. sub grade m2 693.50 0.00126 0.0000 0.0000 0.0000 0.0030 0.0000 0.0000 0.0000
- - Comp. Macadam T = 150mm m2 693.50 0.01427 0.0000 0.0000 0.0000 0.0339 0.0000 0.0000 0.0000
Concrete Work
- Lean concrete T = 50 mm , grade K - 150 concrete m2 693.50 0.01895 0.0000 0.0000 0.0000 0.0450 0.0000 0.0000 0.0000
- Grade K - 250 concrete to Slab m3 173.50 0.08182 0.0000 0.0000 0.0000 0.1942 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal m3 3.50 0.00165 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000
- Timber formwork to Slab m2 105.30 0.00612 0.0000 0.0000 0.0000 0.0145 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal m2 34.10 0.00217 0.0000 0.0000 0.0000 0.0052 0.0000 0.0000 0.0000
- Supporting formwork m2 34.10 0.00036 0.0000 0.0000 0.0000 0.0009 0.0000 0.0000 0.0000
- HT. Reinforcement to Slab kg 5,060.00 0.02868 0.0000 0.0000 0.0000 0.0681 0.0000 0.0000 0.0000
- Ditto , but to Column Pedestal kg 517.50 0.00293 0.0000 0.0000 0.0000 0.0070 0.0000 0.0000 0.0000

B Steel Structure
- Stl Roofing c/w stl. Truss , purlin, sagrod & bracing kg 13,870.20 0.13572 0.0000 0.0000 0.0000 0.3221 0.0000 0.0000 0.0000
- Zinchromate paint 35 µ to steel structure kg 13,870.20 0.01030 0.0000 0.0000 0.0000 0.0244 0.0000 0.0000 0.0000

C Metal Roof
- Roofing Boltless U-527 ( 27mm), Zinc Alume Thk 0,50mm (Tmt) m2 813.00 0.06101 0.0000 0.0000 0.0000 0.1448 0.0000 0.0000 0.0000
- Gable Flashing W=610mm, Zinc Alume Thk 0.50mm (Tmt) m 166.00 0.00934 0.0000 0.0000 0.0000 0.0222 0.0000 0.0000 0.0000
- FRP Gutter, Grey Thk 2.0mm , W=750mm m 166.00 0.02089 0.0000 0.0000 0.0000 0.0496 0.0000 0.0000 0.0000
- Gutter Bracket Sp 3x30mm W=100mm pcs 332.00 0.00889 0.0000 0.0000 0.0000 0.0211 0.0000 0.0000 0.0000
- PVC Pipe AW Grey Dia. 100mm m 78.00 0.00293 0.0000 0.0000 0.0000 0.0069 0.0000 0.0000 0.0000
- PVC Lbow 450 / 900 , Dia. 100mm pcs 62.00 0.00233 0.0000 0.0000 0.0000 0.0055 0.0000 0.0000 0.0000
- Clamp pipe Sp. 3x30mm , Dia. 100mm pcs 93.00 0.00124 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000

H.1.3 MOTORCYCLE PARKING BUILDING ( C & D ) LOT 1.00 1.35208 0.0000 0.0000 0.0000

H.1.3.1 STRUCTURE WORK LOT 1.00 0.99685 0.0000 0.0000 0.0000

I EARTH WORK LOT 1.00 0.04041 0.0000 0.0000 0.0000

A Excavate over site to formation level including cleaning m2 1,043.10 0.00331 0.0000 0.0000 0.0000 0.0819 0.0000 0.0000 0.0000
B site of all debris
C Excavation to ground slab m3 156.40 0.00186 0.0000 0.0000 0.0000 0.0460 0.0000 0.0000 0.0000
D Excavation to pile cap & g.beam m3 170.80 0.00296 0.0000 0.0000 0.0000 0.0733 0.0000 0.0000 0.0000
E Back fill part return and compaction m3 132.00 0.00168 0.0000 0.0000 0.0000 0.0417 0.0000 0.0000 0.0000
F Compacted sub grade m2 1,156.70 0.00211 0.0000 0.0000 0.0000 0.0522 0.0000 0.0000 0.0000
G Dispose excavated material (out project site) m3 195.30 0.00319 0.0000 0.0000 0.0000 0.0789 0.0000 0.0000 0.0000
H T=50mm comp. sand bedding m2 114.10 0.00099 0.0000 0.0000 0.0000 0.0246 0.0000 0.0000 0.0000
I T=150mm comp. basecourse m2 1,053.20 0.02168 0.0000 0.0000 0.0000 0.5364 0.0000 0.0000 0.0000
J Plastic Sheet m2 1,053.20 0.00263 0.0000 0.0000 0.0000 0.0651 0.0000 0.0000 0.0000

II PILING WORK LOT 1.00 0.12653 0.0000 0.0000 0.0000

A Allow for mobilization and demobilization of all unit 1.00 0.00921 0.0000 0.0000 0.0000 0.0728 0.0000 0.0000 0.0000
pilling plant and equipment
B PC Square Pile 250x250 mm , L=20m (Assume) nos 36.00 0.07754 0.0000 0.0000 0.0000 0.6128 0.0000 0.0000 0.0000
C Driving Pile w/ Jacking system m 720.00 0.02808 0.0000 0.0000 0.0000 0.2219 0.0000 0.0000 0.0000
D Welding Joint nos 36.00 0.00230 0.0000 0.0000 0.0000 0.0181 0.0000 0.0000 0.0000
E Cut off excess pile length at required level & expose nos 36.00 0.00089 0.0000 0.0000 0.0000 0.0071 0.0000 0.0000 0.0000
reinforcements incl. all necessary excav. Required
F PDA Test nos 2.00 0.00850 0.0000 0.0000 0.0000 0.0672 0.0000 0.0000 0.0000

III CONCRETE WORK LOT 1.00 0.23536 0.0000 0.0000 0.0000

A Lean concrete T = 50 mm m2 114.10 0.00312 0.0000 0.0000 0.0000 0.0132 0.0000 0.0000 0.0000
B Grade K - 250 concrete to Foundation m3 16.30 0.00769 0.0000 0.0000 0.0000 0.0327 0.0000 0.0000 0.0000
C Ditto , but to Ground Beam m3 15.90 0.00750 0.0000 0.0000 0.0000 0.0319 0.0000 0.0000 0.0000
D Ditto , but to Ground Slab m3 156.40 0.07375 0.0000 0.0000 0.0000 0.3134 0.0000 0.0000 0.0000
E Ditto , but to Column m3 19.80 0.00934 0.0000 0.0000 0.0000 0.0397 0.0000 0.0000 0.0000
F Ditto , but to RC Wall m3 71.90 0.03391 0.0000 0.0000 0.0000 0.1441 0.0000 0.0000 0.0000
G Ditto , but to 2nd Fl Beam m3 51.00 0.02405 0.0000 0.0000 0.0000 0.1022 0.0000 0.0000 0.0000
H Ditto , but to 2nd Fl Slab m3 81.90 0.03862 0.0000 0.0000 0.0000 0.1641 0.0000 0.0000 0.0000
I Ditto , but to Roof Beam m3 35.40 0.01669 0.0000 0.0000 0.0000 0.0709 0.0000 0.0000 0.0000
J Ditto , but to Ramp m3 37.90 0.01787 0.0000 0.0000 0.0000 0.0759 0.0000 0.0000 0.0000
K Ditto , but to Staircase m3 6.00 0.00283 0.0000 0.0000 0.0000 0.0120 0.0000 0.0000 0.0000

IV REINFORCED WORK LOT 1.00 0.29413 0.0000 0.0000 0.0000

A HT. Reinforcement to Foundation kg 2,056.20 0.01166 0.0000 0.0000 0.0000 0.0396 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam kg 1,711.20 0.00970 0.0000 0.0000 0.0000 0.0330 0.0000 0.0000 0.0000
C Ditto , but to Column kg 4,373.50 0.02479 0.0000 0.0000 0.0000 0.0843 0.0000 0.0000 0.0000
D Ditto , but to RC Wall kg 7,736.10 0.04385 0.0000 0.0000 0.0000 0.1491 0.0000 0.0000 0.0000
E Ditto , but to 2nd Fl Beam kg 7,086.30 0.04017 0.0000 0.0000 0.0000 0.1366 0.0000 0.0000 0.0000
F Ditto , but to 2nd Fl Slab kg 8,789.50 0.04982 0.0000 0.0000 0.0000 0.1694 0.0000 0.0000 0.0000
G Ditto , but to Roof Beam kg 3,821.50 0.02166 0.0000 0.0000 0.0000 0.0736 0.0000 0.0000 0.0000
H Ditto , but to Ramp kg 4,462.00 0.02529 0.0000 0.0000 0.0000 0.0860 0.0000 0.0000 0.0000
I Ditto , but to Staircase kg 1,211.00 0.00686 0.0000 0.0000 0.0000 0.0233 0.0000 0.0000 0.0000
J Wiremesh #M6 to ground slab (2 layer) m2 1,043.10 0.06032 0.0000 0.0000 0.0000 0.2051 0.0000 0.0000 0.0000

V FORMWORK LOT 1.00 0.21384 0.0000 0.0000 0.0000


06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 74
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH

A Timber formwork to Foundation m2 67.20 0.00390 0.0000 0.0000 0.0000 0.0183 0.0000 0.0000 0.0000
B Ditto , but to Ground Beam m2 126.70 0.00736 0.0000 0.0000 0.0000 0.0344 0.0000 0.0000 0.0000
C Ditto , but to Ground Slab m2 58.00 0.00337 0.0000 0.0000 0.0000 0.0158 0.0000 0.0000 0.0000
D Ditto , but to Column m2 246.40 0.01570 0.0000 0.0000 0.0000 0.0734 0.0000 0.0000 0.0000
E Ditto , but to RC Wall m2 958.00 0.06103 0.0000 0.0000 0.0000 0.2854 0.0000 0.0000 0.0000
F Ditto , but to 2nd Fl Beam m2 275.40 0.01754 0.0000 0.0000 0.0000 0.0820 0.0000 0.0000 0.0000
G Ditto , but to 2nd Fl Slab m2 676.40 0.04309 0.0000 0.0000 0.0000 0.2015 0.0000 0.0000 0.0000
H Ditto , but to Roof Beam m2 374.30 0.02384 0.0000 0.0000 0.0000 0.1115 0.0000 0.0000 0.0000
I Ditto , but to Ramp m2 123.80 0.00789 0.0000 0.0000 0.0000 0.0369 0.0000 0.0000 0.0000
J Ditto , but to Staircase m2 24.40 0.00155 0.0000 0.0000 0.0000 0.0073 0.0000 0.0000 0.0000
K Supporting formwork m2 2,678.70 0.02856 0.0000 0.0000 0.0000 0.1336 0.0000 0.0000 0.0000

VI STEEL STRUCTURE WORK LOT 1.00 0.06634 0.0000 0.0000 0.0000

Steel trusses & monitor of main building included. purlin, bracing, etc.. Kg 6,302.00 0.06166 0.0000 0.0000 0.0000 0.9295 0.0000 0.0000 0.0000

Finishing paint to steel structure Kg 6,302.00 0.00468 0.0000 0.0000 0.0000 0.0705 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

VII MISCELLANEOUS WORK LOT 1.00 0.02024 0.0000 0.0000 0.0000

Non Shrinkage grouting, size : 420x420x30mm nos 29.00 0.00093 0.0000 0.0000 0.0000 0.0457 0.0000 0.0000 0.0000
Expansion joint to existing slab :
- Sand asphalt fill m 246.40 0.00481 0.0000 0.0000 0.0000 0.2374 0.0000 0.0000 0.0000
- Dowel rebar kg 907.40 0.00514 0.0000 0.0000 0.0000 0.2542 0.0000 0.0000 0.0000
- Add. Rebbar kg 1,538.70 0.00872 0.0000 0.0000 0.0000 0.4310 0.0000 0.0000 0.0000
- Flexible pipe m 327.80 0.00064 0.0000 0.0000 0.0000 0.0317 0.0000 0.0000 0.0000

H.1.3.2 FINISHING WORK LOT 1.00 0.35523 0.0000 0.0000 0.0000

I METAL ROOFING WORK LOT 1.00 0.19542 0.0000 0.0000 0.0000

Roofing Boltless U-650 (100mm), Zinc Alume Thk. 0,5mm (Tct) m2 908.00 0.07782 0.0000 0.0000 0.0000 0.3982 0.0000 0.0000 0.0000
Roof mesh, Galvanized #3x3" m2 908.00 0.00729 0.0000 0.0000 0.0000 0.0373 0.0000 0.0000 0.0000
Aluminium foil single sided m2 908.00 0.00582 0.0000 0.0000 0.0000 0.0298 0.0000 0.0000 0.0000
Glasswool 16 kgs/m3, Thk 25mm m2 908.00 0.00852 0.0000 0.0000 0.0000 0.0436 0.0000 0.0000 0.0000
End Close, Boltless U-650 m 242.00 0.00545 0.0000 0.0000 0.0000 0.0279 0.0000 0.0000 0.0000
Appron Boltless U-650 m 121.00 0.00273 0.0000 0.0000 0.0000 0.0140 0.0000 0.0000 0.0000
Eaves Close Boltless U-650 m 111.00 0.00250 0.0000 0.0000 0.0000 0.0128 0.0000 0.0000 0.0000
Ridge Cover. W=610mm, Zinc. Alume Thk. 0,5mm (Tct) m 61.00 0.00409 0.0000 0.0000 0.0000 0.0209 0.0000 0.0000 0.0000
End Roof Flashing W=610mm, Zinc Alume Thk 0.5mm (Tct) m 76.00 0.00428 0.0000 0.0000 0.0000 0.0219 0.0000 0.0000 0.0000
Gable Flashing. W=610mm, Zinc. Alume Thk. 0,55mm (Tct) m 47.00 0.00265 0.0000 0.0000 0.0000 0.0135 0.0000 0.0000 0.0000
Eaves Flashing W=228mm, Zinc Alume Thk 0.5mm (Tct) m 111.00 0.00369 0.0000 0.0000 0.0000 0.0189 0.0000 0.0000 0.0000
Eaves FRP Gutter , Grey Thk 3.0mm , W=1.200mm m 111.00 0.02498 0.0000 0.0000 0.0000 0.1278 0.0000 0.0000 0.0000
Gutter Bracket SP 3x42 mm, W=1.400mm pcs 226.00 0.00848 0.0000 0.0000 0.0000 0.0434 0.0000 0.0000 0.0000
PVC Pipe AW Grey Dia. 200mm m 162.00 0.02170 0.0000 0.0000 0.0000 0.1110 0.0000 0.0000 0.0000
PVC Lbow 450 / 900 , Dia. 200mm pcs 72.00 0.00964 0.0000 0.0000 0.0000 0.0494 0.0000 0.0000 0.0000
Clamp pipe Sp. 3x42mm , Dia. 200mm pcs 180.00 0.00579 0.0000 0.0000 0.0000 0.0296 0.0000 0.0000 0.0000

II MASONRY WORK LOT 1.00 0.05691 0.0000 0.0000 0.0000

A Common brick wall m2 307.00 0.02032 0.0000 0.0000 0.0000 0.3571 0.0000 0.0000 0.0000
B The following in lintel / stiffener :
- Grade K - 175 concrete m3 4.60 0.00194 0.0000 0.0000 0.0000 0.0341 0.0000 0.0000 0.0000
- HT. Reinforcement kg 760.00 0.00431 0.0000 0.0000 0.0000 0.0757 0.0000 0.0000 0.0000
- Timber formwork m2 61.40 0.00357 0.0000 0.0000 0.0000 0.0627 0.0000 0.0000 0.0000
C Plastering 25mm on common brick walls with float & rendered m2 614.00 0.02677 0.0000 0.0000 0.0000 0.4704 0.0000 0.0000 0.0000
w/ instant mortar

III PAINTING WORK LOT 1.00 0.05528 0.0000 0.0000 0.0000

A Textured paint to external wall m2 560.00 0.02184 0.0000 0.0000 0.0000 0.3951 0.0000 0.0000 0.0000
B Emulsion paint to wall m2 834.00 0.01007 0.0000 0.0000 0.0000 0.1822 0.0000 0.0000 0.0000
C Parking Line (White Paint) m 1,785.00 0.02337 0.0000 0.0000 0.0000 0.4227 0.0000 0.0000 0.0000

IV MISCELLANEOUS WORK LOT 1.00 0.04762 0.0000 0.0000 0.0000

A Steel troweled fin. m2 1,604.00 0.00509 0.0000 0.0000 0.0000 0.1068 0.0000 0.0000 0.0000
B Corner column w/ steel angle H = 1200mm w/ paint fin. nos 131.00 0.01211 0.0000 0.0000 0.0000 0.2543 0.0000 0.0000 0.0000
C Steel Handrail H = 1000mm w/ OP finish m 33.50 0.01306 0.0000 0.0000 0.0000 0.2742 0.0000 0.0000 0.0000
D Groove line to Ramp m2 140.00 0.01736 0.0000 0.0000 0.0000 0.3647 0.0000 0.0000 0.0000

H.1.4 MISCELLANEOUS WORK LOT 1.00 0.04791 0.0000 0.0000 0.0000

A Parking Line (White Paint) m 905.00 0.01185 0.0000 0.0000 0.0000 0.2473 0.0000 0.0000 0.0000
B Weathershield paint to column m2 30.00 0.00064 0.0000 0.0000 0.0000 0.0133 0.0000 0.0000 0.0000
C Repair & Touchup existing external work lot 1.00 0.03543 0.0000 0.0000 0.0000 0.7394 0.0000 0.0000 0.0000

H.2 MECHANICAL WORK LOT 1.00 0.07171 0.0000 0.0000 0.0000 1.4968 0.0000 0.0000 0.0000

H.3 ELECTRICAL WORK LOT 1.00 0.15997 0.0000 0.0000 0.0000 3.3388 0.0000 0.0000 0.0000

I. CRANE WORK LOT 1.00 1.38228 1.38228 0.0000 0.0000 0.0000 1.0000 0.0000 0.0000 0.0000

I.1 TRAINING CENTER & HEAD OFFICE LOT 1.00 0.07294 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 4,592.00 0.04493 0.0000 0.0000 0.0000 0.6160 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 4,592.00 0.00341 0.0000 0.0000 0.0000 0.0467 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Crane Rail, square bar 45 x 45mm m 78.00 0.02183 0.0000 0.0000 0.0000 0.2993 0.0000 0.0000 0.0000

D Installation cost Lot 1.00 0.00276 0.0000 0.0000 0.0000 0.0379 0.0000 0.0000 0.0000

I.2 ULTRA LARGE COMPONENT FACT-2 LOT 1.00 1.01253 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 48,039.60 0.47006 0.0000 0.0000 0.0000 0.4642 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 48,039.60 0.03566 0.0000 0.0000 0.0000 0.0352 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Hoist Crane Rail, square bar 60 x 60mm m 612.00 0.18685 0.0000 0.0000 0.0000 0.1845 0.0000 0.0000 0.0000
D Gantry Crane Rail, square bar 50 x 50mm (upper) m 612.00 0.15865 0.0000 0.0000 0.0000 0.1567 0.0000 0.0000 0.0000
E Gantry Crane Rail, H - 100 x 100 x 6 x 8 (lower) m 612.00 0.09626 0.0000 0.0000 0.0000 0.0951 0.0000 0.0000 0.0000

F Installation cost Lot 1.00 0.06505 0.0000 0.0000 0.0000 0.0642 0.0000 0.0000 0.0000

I.3 EXCAVATOR PAINT FACTORY LOT 1.00 0.29682 0.0000 0.0000 0.0000

A Steel structure of Runway Girder Kg 22,811.00 0.22320 0.0000 0.0000 0.0000 0.7520 0.0000 0.0000 0.0000
B Finishing paint to steel structure Kg 22,811.00 0.01693 0.0000 0.0000 0.0000 0.0570 0.0000 0.0000 0.0000
(synthetic enamel 60 micron)

C Crane Rail, square bar 50 x 50mm m 160.00 0.05102 0.0000 0.0000 0.0000 0.1719 0.0000 0.0000 0.0000

D Installation cost Lot 1.00 0.00567 0.0000 0.0000 0.0000 0.0191 0.0000 0.0000 0.0000

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 75
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520 Minggu ke - 02 ( MAY '2011)

PROGRESS Q'TY PROGRESS WEIGHT


NO. DESCRIPTION Unit Qty. WEIGHT THIS UP TO TOTAL UP TO WEIGHT THIS UP TO TOTAL UP TO
MONTH LAST MONTH THIS MONTH MONTH LAST MONTH THIS MONTH
J. SOIL INVESTIGATION WORK LOT 1.00 0.08557 0.08557 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

1 Mob & Demobilization Tools & Equipment (2 Rigs) lot 1.00 0.01063 0.0000 0.0106 0.0106 0.1242 0.0000 0.0001 0.0001

2 Moving and Setting drilling machine at each location Locs. 6.00 0.00128 0.0000 0.0013 0.0013 0.0149 0.0000 0.0000 0.0000

3 Drilling in soil formantions, 6 location @ 30 m m 180.00 0.03399 0.0000 0.0340 0.0340 0.3972 0.0000 0.0000 0.0000
( Rotary wash boring, incld. Undisturbed Soil
Sampling & SPT )

4 Laboratory Test lot 1.00 0.00886 0.0000 0.0089 0.0089 0.1035 0.0000 0.0001 0.0001

5 Site Supervision and Reporting lot 1.00 0.03082 0.0000 0.0308 0.0308 0.3602 0.0000 0.0010 0.0010

TOTAL ( A ~ J ) 100.00000 100.00000 0.0000 7.2725 7.2725

06/09/2024 file:///conversion/tmp/activity_task_scratch/762509777.xlsx 76
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

NO. WORK ITEM

A. TEMPORARY WORK

B. TEMPORARY ME WORK
B.1
B.1.1
B.1.2

B.2

B.3

C. DEMOLITION WORK
C. STRUCTURE WORK
C.1 WASHING AREA
C.2 MAIN GATE AND BOUNDARY WALL
C.3 GUARD HOUSE
C.4 OFFICE
C.5 CANTEEN
C.6 PARKING & TREE
C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT.
C.8 HEXINDO OFFICE
C.9 TOUCH UP PAINT BOOTH AREA
C.10 STOCK YARD AREA

D. BUILDING WORK

D.1 TRAINING CENTER & HEAD OFFICE


D.1.1
D.1.1.1
D.1.1.2
D.1.1.3
D.1.1.4
D.1.1.5
D.1.1.6
D.1.1.7

D.1.2
D.1.2.1
D.1.2.2
D.1.2.3
D.1.2.4
D.1.2.5
D.1.2.6
D.1.2.7
D.1.2.8

D.2 ULTRA LARGE COMPONENT FACT-2


D.2.1
D.2.1.1
D.2.1.2
D.2.1.3
D.2.1.4
D.2.1.5
D.2.1.6
D.2.1.7

D.2.2
D.2.2.1
D.2.2.2
D.2.2.3
D.2.2.4
D.2.2.5
D.2.2.6
D.2.2.7
D.2.2.8

D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH


D.3.1
D.3.1.1
D.3.1.2
D.3.1.3
D.3.1.4
D.3.1.5
D.3.1.6
D.3.1.7

D.3.2
D.3.2.1
D.3.2.2
D.3.2.3
D.3.2.4
D.3.2.5
D.3.2.6
D.3.2.7
D.3.2.8

D.4 EXCAVATOR PAINT FACTORY


D.4.1
D.4.1.1
D.4.1.2
D.4.1.3
D.4.1.4
D.4.1.5
D.4.1.6
D.4.1.7

D.4.2
D.4.2.1
D.4.2.2
D.4.2.3
D.4.2.4
D.4.2.5
D.4.2.6
D.4.2.7
D.4.2.8

D.5 TOUCHUP PAINT BOOTH


D.5.1
D.5.1.1
D.5.1.2
D.5.1.3
D.5.1.4
D.5.1.5
D.5.1.6
D.5.1.7

D.5.2
D.5.2.1
D.5.2.2
D.5.2.3
D.5.2.4
D.5.2.5
D.5.2.6
D.5.2.7
D.5.2.8

D.6 WASHING AREA


D.6.1
D.6.1.1
D.6.1.2
D.6.1.3
D.6.1.4
D.6.1.5
D.6.1.6
D.6.1.7

E. MECHANICAL WORK

F. ELECTRICAL WORK

G. EXTERNAL WORK

G.1
G.1.1
G.1.1.1
G.1.1.2
G.1.1.3
G.1.1.4

G.1.2
G.1.2.1
G.1.2.2
G.1.2.3
G.1.2.4

G.1.3
G.1.3.1
G.1.3.2
G.1.3.3
G.1.3.4

G.1.4
G.1.4.1

G.1.5

G.1.6
G.1.6.1
I
II
III
IV
V

G.1.6.2
I
II
III
IV
V
VI

G.1.7
G.1.7.1
I
II
III
IV
V

G.1.7.2
I
II
III
IV
V
VI

G.1.8
G.1.7.1
G.1.7.2

G.2

G.3

H. MOTOR CYCLE PARKING

H.1
H.1.1

H.1.2

H.1.3
H.1.3.1
I
II
III
IV
V
VI
VII

H.1.3.2
I
II
III
IV

H.1.4

H.2
H.3

I. CRANE WORK
I.1
I.2
I.3

J. SOIL INVESTIGATION WORK

TOTAL

K. DESIGN FEE

L. SITE EXPENSES

M. OVERHEAD

DISCOUNT

TOTAL
TUNG FACTORY EXPANSION PROJECT
Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

WORK ITEM WEIGHT

TEMPORARY WORK 4.76218

TEMPORARY ME WORK
CIVIL WORKS
CABLE CONECTION WORK 0.09158
RENOVATION EXISTING GENSET ROOM 0.02213

MECHANICAL WORKS 0.26374

ELECTRICAL WORKS 0.61562

DEMOLITION WORK
STRUCTURE WORK
WASHING AREA 0.00875
MAIN GATE AND BOUNDARY WALL 0.00805
GUARD HOUSE 0.00424
OFFICE 0.11102
CANTEEN 0.09257
PARKING & TREE 0.10770
PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. 0.73968
HEXINDO OFFICE 0.02180
TOUCH UP PAINT BOOTH AREA 0.05295
STOCK YARD AREA 0.25679

BUILDING WORK

TRAINING CENTER & HEAD OFFICE


STRUCTURE WORK
EARTH WORK 0.24597
PILING WORK 0.40894
CONCRETE WORK 1.18616
REINFORCED WORK 1.71596
FORM WORK 0.87746
STEEL STRUCTURE WORK 0.49464
MISCELLANEOUS WORK 0.13282

FINISHING WORK
METAL ROOFING & METAL WALL WORK 1.07326
MASONRY WORK 0.58810
TILING WORK 0.37630
DOOR AND WINDOW WORK 0.95350
PAINTING WORK 0.15234
INTERIOR FINISHING WORK 2.04985
WATERPROOFING WORK 0.26793
MISCELLANEOUS WORK 0.64512

ULTRA LARGE COMPONENT FACT-2


STRUCTURE WORK
EARTH WORK 0.33725
PILING WORK 7.78288
CONCRETE WORK 2.23570
REINFORCED WORK 2.72401
FORM WORK 0.60935
STEEL STRUCTURE WORK 4.84123
MISCELLANEOUS WORK 0.08239

FINISHING WORK
METAL ROOFING & METAL WALL WORK 1.78077
MASONRY WORK 0.17348
TILING WORK 0.02202
DOOR AND WINDOW WORK 0.94775
PAINTING WORK 0.41606
INTERIOR FINISHING WORK 0.05144
WATERPROOFING WORK 0.04040
MISCELLANEOUS WORK 0.29942

ULTRA LARGE TOPCOAT PAINTING BOOTH


STRUCTURE WORK
EARTH WORK 0.07503
PILING WORK 0.58263
CONCRETE WORK 0.34177
REINFORCED WORK 0.50742
FORM WORK 0.14620
STEEL STRUCTURE WORK 0.35324
MISCELLANEOUS WORK 0.02273

FINISHING WORK
METAL ROOFING & METAL WALL WORK 0.42084
MASONRY WORK 0.04568
TILING WORK 0.00356
DOOR AND WINDOW WORK 0.33186
PAINTING WORK 0.06056
INTERIOR FINISHING WORK 0.00805
WATERPROOFING WORK 0.00068
MISCELLANEOUS WORK 0.11634

EXCAVATOR PAINT FACTORY


STRUCTURE WORK
EARTH WORK 0.70617
PILING WORK 0.71149
CONCRETE WORK 1.45725
REINFORCED WORK 1.83951
FORM WORK 0.32842
STEEL STRUCTURE WORK 3.53723
MISCELLANEOUS WORK 0.05494

FINISHING WORK
METAL ROOFING & METAL WALL WORK 2.35276
MASONRY WORK 0.51955
TILING WORK 0.01146
DOOR AND WINDOW WORK 0.93405
PAINTING WORK 0.23823
INTERIOR FINISHING WORK 0.04468
WATERPROOFING WORK 0.01696
MISCELLANEOUS WORK 0.78272

TOUCHUP PAINT BOOTH


STRUCTURE WORK
EARTH WORK 0.01521
PILING WORK 0.06592
CONCRETE WORK 0.10945
REINFORCED WORK 0.13468
FORM WORK 0.05795
STEEL STRUCTURE WORK 0.13929
MISCELLANEOUS WORK 0.02380

FINISHING WORK
METAL ROOFING & METAL WALL WORK 0.08387
MASONRY WORK 0.00673
TILING WORK 0.00000
DOOR AND WINDOW WORK 0.02267
PAINTING WORK 0.02494
INTERIOR FINISHING WORK 0.00207
WATERPROOFING WORK 0.00023
MISCELLANEOUS WORK 0.05270

WASHING AREA
STRUCTURE WORK
EARTH WORK 0.00974
PILING WORK 0.00000
CONCRETE WORK 0.02484
REINFORCED WORK 0.02346
FORM WORK 0.01655
STEEL STRUCTURE WORK 0.06485
MISCELLANEOUS WORK 0.12268

MECHANICAL WORK 12.03803

ELECTRICAL WORK 14.64834

EXTERNAL WORK

CIVIL WORK
TRAINING CENTER & HEAD OFFICE AREA
PAVING WORK 0.69379
DRAINAGE WORK 0.24656
LANDSCAPE WORK 0.01296
MISCELLANEOUS WORK 0.02693

EXCAVATOR PAINT FACTORY AREA


PAVING WORK 0.38305
DRAINAGE WORK 0.42044
LANDSCAPE WORK 0.00377
MISCELLANEOUS WORK 0.01771

ULTRA LARGE COMPONENT FACTORY-2 AREA


PAVING WORK 1.22001
DRAINAGE WORK 0.46890
LANDSCAPE WORK 0.00984
MISCELLANEOUS WORK 0.01063

TOUCHUP PAINT BOOTH AREA


DRAINAGE WORK 0.19330

MAIN GATE AND FENCE 0.33456

GUARD HOUSE - 1
STRUCTURE WORK
EARTH WORK 0.00242
PILING WORK 0.00000
CONCRETE WORK 0.02147
REINFORCED WORK 0.02876
FORMWORK 0.02707

FINISHING WORK
DOOR and WINDOW WORK 0.00574
MASONRY WORK 0.02072
PAINTING WORK 0.00785
INTERIOR FINISHING WORK 0.01275
WATERPROOFING WORK 0.00859
MISCELLANEOUS WORK 0.01203

GUARD HOUSE - 2
STRUCTURE WORK
EARTH WORK 0.00024
PILING WORK 0.00000
CONCRETE WORK 0.00382
REINFORCED WORK 0.00502
FORMWORK 0.00487

FINISHING WORK
DOOR and WINDOW WORK 0.00000
MASONRY WORK 0.00208
PAINTING WORK 0.00110
INTERIOR FINISHING WORK 0.00089
WATERPROOFING WORK 0.00091
MISCELLANEOUS WORK 0.00119

RC PAVEMENT & DRAINAGE AREA - A


PAVING WORK 5.04700
DRAINAGE WORK 0.31602

MECHANICAL WORK 0.02254

ELECTRICAL WORK 1.73600

MOTOR CYCLE PARKING

CIVIL WORK
PAVING WORK & DRAINAGE WORK 0.23619

MOTORCYCLE PARKING AREA ( E, F, G & H ) 0.42140

MOTORCYCLE PARKING BUILDING ( C & D )


STRUCTURE WORK
EARTH WORK 0.04041
PILING WORK 0.12653
CONCRETE WORK 0.23536
REINFORCED WORK 0.29413
FORMWORK 0.21384
STEEL STRUCTURE WORK 0.06634
MISCELLANEOUS WORK 0.02024

FINISHING WORK
METAL ROOFING WORK 0.19542
MASONRY WORK 0.05691
PAINTING WORK 0.05528
MISCELLANEOUS WORK 0.04762

MISCELLANEOUS WORK 0.04791

MECHANICAL WORK 0.07171


ELECTRICAL WORK 0.15997

CRANE WORK
TRAINING CENTER & HEAD OFFICE 0.07294
ULTRA LARGE COMPONENT FACT-2 1.01253
EXCAVATOR PAINT FACTORY 0.29682

SOIL INVESTIGATION WORK 0.08557

TOTAL 100.00000

DESIGN FEE 3.41997

SITE EXPENSES 4.99972

OVERHEAD 3.35316

DISCOUNT -7.85110

TOTAL 3.92175

100.00000
Minggu ke - 02 ( MAY '2011)

PROGRESS
UP TO
WEIGHT
THIS WEEK

142.86542% 6.80351

0.62442% 0.00057
0.00000% 0.00000

0.49844% 0.00131

0.47872% 0.00295

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
3.81901% 0.00354
5.59266% 0.00602
0.15241% 0.00113
0.00000% 0.00000
0.00000% 0.00000
23.04549% 0.05918
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00012% 0.00000
2.73615% 0.21295
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

6.26944% 0.00470
42.12889% 0.24545
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.01996% 0.00101
0.01927% 0.00006

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000
0.00000% 0.00000
0.00000% 0.00000

0.00000% 0.00000

228.25040% 7.34238

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000

0.00000% 0.00000
PT. HCMI CIBITUNG FACTORY EXPANSION PROJECT
LOCATION : Jl. Raya Cibitung Km. 48,8 Cibitung , Bekasi 17520

WEIGHT 1 2 3 4 5 6 7 8 9 10 11 12 13 14
NO. DESCRIPTION ( Sub Total ) EVERAGE DURATION March-11 April-11 May-11 June-11 July-11 August-11 September-11 October-11 November-11 December-11 January-12 February-12 March-12 April-12 WEIGHT

2 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

A. TEMPORARY WORK 4.7622 0.1191 40 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.2296 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 4.7622

B. TEMPORARY ME WORK
B.1 CIVIL WORKS
B.1.1 CABLE CONECTION WORK 0.0916 0.0048 19 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0064 0.0064 0.0064 0.0064 0.0064 0.0064 0.0079 0.0079 0.0079 0.0079 0.0024 0.091581248691
B.1.2 RENOVATION EXISTING GENSET ROOM 0.0221 0.0037 6 0.0037 0.0037 0.0037 0.0037 0.0037 0.0037 0.022128248157
0
B.2 MECHANICAL WORKS 0.2637 0.0066 40 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0083 0.0083 0.0083 0.0083 0.0103 0.0103 0.0103 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0123 0.0033 0.0033 0.0033 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.263736542774
0
B.3 ELECTRICAL WORKS 0.6156 0.0154 40 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0077 0.0107 0.0107 0.0107 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0365 0.0077 0.0077 0.0077 0.0051 0.0051 0.0051 0.0051 0.0051 0.0051 0.0051 0.615618235653
0
C. DEMOLITION WORK 0
C. STRUCTURE WORK 0
C.1 WASHING AREA 0.0087 0.0087 1 0.0087 0.008745757948
C.2 MAIN GATE AND BOUNDARY WALL 0.0081 0.0027 3 0.0027 0.0027 0.0027 0.008051371679
C.3 GUARD HOUSE 0.0042 0.0014 3 0.0014 0.0014 0.0014 0.004237915656
C.4 OFFICE 0.1110 0.0278 4 0.0278 0.0278 0.0278 0.0278 0.111015359101
C.5 CANTEEN 0.0926 0.0154 6 0.0051 0.0077 0.0334 0.0334 0.0077 0.0051 0.092565198759
C.6 PARKING & TREE 0.1077 0.0179 6 0.0060 0.0090 0.0389 0.0389 0.0090 0.0060 0.107698500606
C.7 PAINT BOOTH & OTHER AREA AT WEST SIDE OF FACT. 0.7397 0.1849 4 0.1849 0.1849 0.1849 0.1849 0.739683737792
C.8 HEXINDO OFFICE 0.0218 0.0109 2 0.0109 0.0109 0.021802311745
C.9 TOUCH UP PAINT BOOTH AREA 0.0529 0.0265 2 0.0265 0.0265 0.052948538861
C.10 STOCK YARD AREA 0.2568 0.0642 4 0.0642 0.0642 0.0642 0.0642 0.256787618956
0
D. BUILDING WORK 0
D.1 TRAINING CENTER & HEAD OFFICE 0
D.1.1 STRUCTURE WORK 0
D.1.1.1 EARTH WORK 0.2460 0.0820 3 0.0273 0.0410 0.0888 0.0888 0.245965052223
D.1.1.2 PILING WORK 0.4089 0.1363 3 0.0682 0.1082 0.1245 0.1082 0.408936558162
D.1.1.3 CONCRETE WORK 1.1862 0.1318 9 0.0439 0.0439 0.0639 0.0639 0.0639 0.2266 0.2266 0.2266 0.2266 1.186161152544
D.1.1.4 REINFORCED WORK 1.7160 0.1907 9 0.0636 0.0636 0.1036 0.1036 0.1036 0.3195 0.3195 0.3195 0.3195 1.715963569992
D.1.1.5 FORM WORK 0.8775 0.0975 9 0.0325 0.0325 0.0725 0.0725 0.0725 0.1487 0.1487 0.1487 0.1487 0.877462208068
D.1.1.6 STEEL STRUCTURE WORK 0.4946 0.1649 3 0.1649 0.1649 0.1649 0.494638669772
D.1.1.7 MISCELLANEOUS WORK 0.1328 0.0190 7 0.0095 0.0095 0.0261 0.0261 0.0261 0.0261 0.0095 0.13281997197

D.1.2 FINISHING WORK 0


D.1.2.1 METAL ROOFING & METAL WALL WORK 1.0733 0.0767 14 0.0383 0.0383 0.0383 0.0383 0.0980 0.0980 0.0980 0.0980 0.0980 0.0980 0.0980 0.0980 0.0980 0.0383 1.073261199417

Idul Fitri 1431 H


D.1.2.2 MASONRY WORK 0.5881 0.0452 13 0.0226 0.0226 0.0226 0.0226 0.0594 0.0594 0.0594 0.0594 0.0594 0.0594 0.0594 0.0594 0.0226 0.588102434055
D.1.2.3 TILING WORK 0.3763 0.0376 10 0.0188 0.0188 0.0502 0.0502 0.0502 0.0502 0.0502 0.0502 0.0188 0.0188 0.376297407314
D.1.2.4 DOOR AND WINDOW WORK 0.9535 0.1059 9 0.0530 0.1211 0.1211 0.1211 0.1211 0.1211 0.1211 0.1211 0.0530 0.953503895081
D.1.2.5 PAINTING WORK 0.1523 0.0152 10 0.0076 0.0203 0.0203 0.0203 0.0203 0.0203 0.0203 0.0076 0.0076 0.0076 0.152344568536
D.1.2.6 INTERIOR FINISHING WORK 2.0499 0.1708 12 0.0854 0.0854 0.0854 0.2562 0.2562 0.2562 0.2562 0.2562 0.2562 0.0854 0.0854 0.0854 2.049853383971
D.1.2.7 WATERPROOFING WORK 0.2679 0.0298 9 0.0298 0.0298 0.0298 0.0298 0.0298 0.0298 0.0298 0.0298 0.0298 0.26793214743
D.1.2.8 MISCELLANEOUS WORK 0.6451 0.0645 10 0.0323 0.0323 0.0968 0.0968 0.0968 0.0968 0.0968 0.0323 0.0323 0.0323 0.645124186089
0
D.2 ULTRA LARGE COMPONENT FACT-2 0
D.2.1 STRUCTURE WORK 0
D.2.1.1 EARTH WORK 0.3373 0.0843 4 0.0843 0.0843 0.0843 0.0843 0.337250528804
D.2.1.2 PILING WORK 7.7829 1.2971 6 0.4324 0.4324 0.4324 0.4324 0.4324 0.7324 0.8324 2.0281 2.0281 7.782878623913
D.2.1.3 CONCRETE WORK 2.2357 0.1242 18 0.0414 0.0414 0.0414 0.0414 0.0621 0.0621 0.0621 0.0621 0.1955 0.1955 0.1955 0.1955 0.1955 0.1955 0.1955 0.1955 0.1288 0.1288 2.235698169321
D.2.1.4 REINFORCED WORK 2.7240 0.1513 18 0.0504 0.0504 0.0504 0.0504 0.0757 0.0757 0.0757 0.0757 0.2382 0.2382 0.2382 0.2382 0.2382 0.2382 0.2382 0.2382 0.1569 0.1569 2.724006479152
D.2.1.5 FORM WORK 0.6094 0.0339 18 0.0113 0.0113 0.0113 0.0113 0.0169 0.0169 0.0169 0.0169 0.0533 0.0533 0.0533 0.0533 0.0533 0.0533 0.0533 0.0533 0.0351 0.0351 0.609354891747
D.2.1.6 STEEL STRUCTURE WORK 4.8412 0.4401 11 0.2201 0.2201 0.5226 0.5226 0.5226 0.5226 0.5226 0.5226 0.5226 0.5226 0.2201 4.84122896255
D.2.1.7 MISCELLANEOUS WORK 0.0824 0.0206 4 0.0206 0.0206 0.0206 0.0206 0.082394565584
0
D.2.2 FINISHING WORK 0
D.2.2.1 METAL ROOFING & METAL WALL WORK 1.7808 0.2226 8 0.1113 0.2597 0.2597 0.2597 0.2597 0.2597 0.2597 0.1113 1.780772543499
D.2.2.2 MASONRY WORK 0.1735 0.0133 13 0.0067 0.0067 0.0067 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0067 0.0067 0.173483245403
D.2.2.3 TILING WORK 0.0220 0.0015 15 0.0007 0.0007 0.0007 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0007 0.0007 0.0007 0.022023786549
D.2.2.4 DOOR AND WINDOW WORK 0.9477 0.1185 8 0.0711 0.1343 0.1343 0.1343 0.1343 0.1343 0.1343 0.0711 0.947748181954
D.2.2.5 PAINTING WORK 0.4161 0.0416 10 0.0208 0.0555 0.0555 0.0555 0.0555 0.0555 0.0555 0.0208 0.0208 0.0208 0.416061811555
D.2.2.6 INTERIOR FINISHING WORK 0.0514 0.0043 12 0.0021 0.0054 0.0054 0.0054 0.0054 0.0054 0.0054 0.0054 0.0054 0.0021 0.0021 0.0021 0.051442091806
D.2.2.7 WATERPROOFING WORK 0.0404 0.0040 10 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.040404353056
D.2.2.8 MISCELLANEOUS WORK 0.2994 0.0599 5 0.0299 0.1048 0.1048 0.0299 0.0299 0.299415182255
0
D.3 ULTRA LARGE TOPCOAT PAINTING BOOTH 0
D.3.1 STRUCTURE WORK 0
D.3.1.1 EARTH WORK 0.0750 0.0188 4 0.0188 0.0188 0.0188 0.0188 0.075028389173
D.3.1.2 PILING WORK 0.5826 0.1457 4 0.1457 0.1457 0.1457 0.1457 0.582626655094
D.3.1.3 CONCRETE WORK 0.3418 0.0684 5 0.0684 0.0684 0.0684 0.0684 0.0684 0.34176692777
D.3.1.4 REINFORCED WORK 0.5074 0.1015 5 0.1015 0.1015 0.1015 0.1015 0.1015 0.507423474928
D.3.1.5 FORM WORK 0.1462 0.0292 5 0.0292 0.0292 0.0292 0.0292 0.0292 0.146203211225
D.3.1.6 STEEL STRUCTURE WORK 0.3532 0.0706 5 0.0706 0.0706 0.0706 0.0706 0.0706 0.353239936715
D.3.1.7 MISCELLANEOUS WORK 0.0227 0.0057 4 0.0057 0.0057 0.0057 0.0057 0.02273085937
0
D.3.2 FINISHING WORK 0
D.3.2.1 METAL ROOFING & METAL WALL WORK 0.4208 0.1403 3 0.1403 0.1403 0.1403 0.420839108111
D.3.2.2 MASONRY WORK 0.0457 0.0057 8 0.0029 0.0029 0.0086 0.0086 0.0086 0.0086 0.0029 0.0029 0.045678679022
D.3.2.3 TILING WORK 0.0036 0.0005 7 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.003560676477
D.3.2.4 DOOR AND WINDOW WORK 0.3319 0.1659 2 0.1659 0.1659 0.331864473456
D.3.2.5 PAINTING WORK 0.0606 0.0303 2 0.0303 0.0303 0.060555071445
D.3.2.6 INTERIOR FINISHING WORK 0.0080 0.0020 4 0.0020 0.0020 0.0020 0.0020 0.008049077302
D.3.2.7 WATERPROOFING WORK 0.0007 0.0002 4 0.0002 0.0002 0.0002 0.0002 0.000679067933
D.3.2.8 MISCELLANEOUS WORK 0.1163 0.0233 5 0.0233 0.0233 0.0233 0.0233 0.0233 0.116338865699
0
D.4 EXCAVATOR PAINT FACTORY 0
D.4.1 STRUCTURE WORK 0
D.4.1.1 EARTH WORK 0.7062 0.2354 3 0.2354 0.2354 0.2354 0.706170098876
D.4.1.2 PILING WORK 0.7115 0.2372 3 0.2372 0.2372 0.2372 0.71148578435
D.4.1.3 CONCRETE WORK 1.4572 0.1619 9 0.0540 0.0540 0.0540 0.0540 0.0810 0.1310 0.2574 0.2574 0.2574 0.2574 1.457245321022
D.4.1.4 REINFORCED WORK 1.8395 0.2044 9 0.0681 0.0681 0.0681 0.0681 0.1022 0.1522 0.2625 0.2625 0.2625 0.2625 0.2625 1.839509193432
D.4.1.5 FORM WORK 0.3284 0.0365 9 0.0122 0.0122 0.0122 0.0122 0.0182 0.0382 0.0447 0.0447 0.0447 0.0447 0.0447 0.328420992376
D.4.1.6 STEEL STRUCTURE WORK 3.5372 0.3930 9 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 3.53722861059
D.4.1.7 MISCELLANEOUS WORK 0.0549 0.0137 4 0.0137 0.0137 0.0137 0.0137 0.054940934839
0
D.4.2 FINISHING WORK 0
0
D.4.2.1 METAL ROOFING & METAL WALL WORK 2.3528 0.3361 7 0.1681 0.1681 0.5602 0.5602 0.5602 0.1681 0.1681 2.352756524466
D.4.2.2 MASONRY WORK 0.5196 0.0400 13 0.0133 0.0133 0.0133 0.0200 0.0200 0.0933 0.0933 0.0933 0.0933 0.0200 0.0200 0.0133 0.0133 0.519550819779
D.4.2.3 TILING WORK 0.0115 0.0010 12 0.0003 0.0003 0.0005 0.0005 0.0021 0.0021 0.0021 0.0021 0.0005 0.0003 0.0003 0.0003 0.011463008164
D.4.2.4 DOOR AND WINDOW WORK 0.9341 0.2335 4 0.2335 0.2335 0.2335 0.2335 0.934052171959
D.4.2.5 PAINTING WORK 0.2382 0.0397 6 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397 0.238233658326
D.4.2.6 INTERIOR FINISHING WORK 0.0447 0.0056 8 0.0019 0.0028 0.009076 0.009075648 0.009076 0.009076 0.0019 0.0019 0.044680112427
D.4.2.7 WATERPROOFING WORK 0.0170 0.0021 8 0.0007 0.0011 0.0034 0.0034 0.0034 0.0034 0.0011 0.0007 0.016960300278
D.4.2.8 MISCELLANEOUS WORK 0.7827 0.1565 5 0.0783 0.1565 0.1565 0.1565 0.1565 0.0783 0.782722595054

D.5 TOUCHUP PAINT BOOTH 0


D.5.1 STRUCTURE WORK 0
D.5.1.1 EARTH WORK 0.0152 0.0076 2 0.0076 0.0076 0.015211580571
D.5.1.2 PILING WORK 0.0659 0.0659 1 0.0659 0.0659181088
D.5.1.3 CONCRETE WORK 0.1094 0.0365 3 0.0365 0.0365 0.0365 0.109448387745
D.5.1.4 REINFORCED WORK 0.1347 0.0449 3 0.0449 0.0449 0.0449 0.134678072698
D.5.1.5 FORM WORK 0.0579 0.0193 3 0.0193 0.0193 0.0193 0.057948045771
D.5.1.6 STEEL STRUCTURE WORK 0.1393 0.0174 8 0.0058 0.0087 0.0087 0.0247 0.0247 0.0247 0.0247 0.0087 0.0087 0.139289904226
D.5.1.7 MISCELLANEOUS WORK 0.0238 0.0060 4 0.0030 0.0053 0.0053 0.0053 0.0030 0.0020 0.023803034958
0
D.5.2 FINISHING WORK 0
D.5.2.1 METAL ROOFING & METAL WALL WORK 0.0839 0.0140 6 0.0070 0.0210 0.0210 0.0210 0.0070 0.0070 0.0838662056
D.5.2.2 MASONRY WORK 0.0067 0.0008 8 0.0003 0.0004 0.0011 0.0011 0.0011 0.0011 0.0011 0.0004 0.006734413121
D.5.2.3 TILING WORK 0.0000 0.0000 7 0
D.5.2.4 DOOR AND WINDOW WORK 0.0227 0.0057 4 0.0057 0.0057 0.0057 0.0057 0.022673837368
D.5.2.5 PAINTING WORK 0.0249 0.0062 4 0.0062 0.0062 0.0062 0.0062 0.02494061377
D.5.2.6 INTERIOR FINISHING WORK 0.0021 0.0004 5 0.0004 0.0004 0.0004 0.0004 0.0004 0.002072226779
D.5.2.7 WATERPROOFING WORK 0.0002 0.0000 6 0.0000 0.0000 0.0000 0.0001 0.0001 0.0001 0.0000 0.000234161356
D.5.2.8 MISCELLANEOUS WORK 0.0527 0.0105 5 0.0105 0.0105 0.0105 0.0105 0.0105 0.052704525183
0
D.6 WASHING AREA 0
D.6.1 STRUCTURE WORK 0
D.6.1.1 EARTH WORK 0.0097 0.0049 2 0.0049 0.0049 0.009743508015
D.6.1.2 PILING WORK 0.0000 0.0000 3 0
D.6.1.3 CONCRETE WORK 0.0248 0.0041 6 0.0021 0.0052 0.0052 0.0052 0.0052 0.0021 0.024839350793
D.6.1.4 REINFORCED WORK 0.0235 0.0039 6 0.0020 0.0049 0.0049 0.0049 0.0049 0.0020 0.023461753217
D.6.1.5 FORM WORK 0.0166 0.0028 6 0.0014 0.0034 0.0034 0.0034 0.0034 0.0014 0.016551449152
D.6.1.6 STEEL STRUCTURE WORK 0.0648 0.0108 6 0.0054 0.0162 0.0162 0.0162 0.0054 0.0054 0.064847174874
D.6.1.7 MISCELLANEOUS WORK 0.1227 0.0153 8 0.0077 0.0230 0.0230 0.0230 0.0230 0.0077 0.0077 0.0077 0.122679530089
0
E. MECHANICAL WORK 12.0380 0.8025 15 0.4013 0.4013 1.0165 1.0165 1.0165 1.0165 1.0165 1.0165 1.0165 1.0165 1.0165 1.0165 0.4013 0.4013 0.2675 12.03802524961
0
F. ELECTRICAL WORK 14.6483 0.9766 15 0.4883 0.4883 1.2370 1.2370 1.2370 1.2370 1.2370 1.2370 1.2370 1.2370 1.2370 1.2370 0.4883 0.4883 0.3255 14.64834092433
0
G. EXTERNAL WORK 0

G.1 CIVIL WORK 0


0

122
WEIGHT 1 2 3 4 5 6 7 8 9 10 11 12 13 14
NO. DESCRIPTION ( Sub Total ) EVERAGE DURATION March-11 April-11 May-11 June-11 July-11 August-11 September-11 October-11 November-11 December-11 January-12 February-12 March-12 April-12 WEIGHT

2 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
G.1.1 TRAINING CENTER & HEAD OFFICE AREA 0
G.1.1.1 PAVING WORK 0.6938 0.1156 6 0.0578 0.2891 0.2891 0.0578 0.693789176846
G.1.1.2 DRAINAGE WORK 0.2466 0.0616 4 0.0308 0.0925 0.0925 0.0308 0.246555456004
G.1.1.3 LANDSCAPE WORK 0.0130 0.0022 6 0.0011 0.0054 0.0054 0.0011 0.012957423239
G.1.1.4 MISCELLANEOUS WORK 0.0269 0.0067 4 0.0034 0.0101 0.0101 0.0034 0.026925316838
0
G.1.2 EXCAVATOR PAINT FACTORY AREA 0
G.1.2.1 PAVING WORK 0.3830 0.0479 8 0.0239 0.0638 0.0638 0.0638 0.0638 0.0638 0.0239 0.0160 0.383046605667
G.1.2.2 DRAINAGE WORK 0.4204 0.0701 6 0.0350 0.0701 0.0701 0.0701 0.0701 0.0701 0.0350 0.420443382167
G.1.2.3 LANDSCAPE WORK 0.0038 0.0009 4 0.0005 0.0007 0.0007 0.0007 0.0007 0.0005 0.003772832064
G.1.2.4 MISCELLANEOUS WORK 0.0177 0.0044 4 0.0022 0.0033 0.0033 0.0033 0.0033 0.0022 0.017713935444
0
G.1.3 ULTRA LARGE COMPONENT FACTORY-2 AREA 0
G.1.3.1 PAVING WORK 1.2200 0.1743 7 0.0871 0.2469 0.2469 0.2469 0.2469 0.0871 0.0581 1.220008710953
G.1.3.2 DRAINAGE WORK 0.4689 0.0938 5 0.0469 0.0750 0.0750 0.0750 0.0750 0.0750 0.0469 0.468901090863
G.1.3.3 LANDSCAPE WORK 0.0098 0.0012 8 0.0006 0.0014 0.0014 0.0014 0.0014 0.0014 0.0014 0.0006 0.009844561799
G.1.3.4 MISCELLANEOUS WORK 0.0106 0.0027 4 0.0013 0.0027 0.0027 0.0027 0.0013 0.010628361266
0
G.1.4 TOUCHUP PAINT BOOTH AREA 0
G.1.4.1 DRAINAGE WORK 0.1933 0.0483 4 0.0483 0.0483 0.0483 0.0483 0.193297770168
0
G.1.5 MAIN GATE AND FENCE 0.3346 0.0418 8 0.0139 0.0209 0.0662 0.0662 0.0662 0.0662 0.0209 0.0139 0.334555857951
G.1.5.1 MAIN GATE 0
0
G.1.6 GUARD HOUSE - 1 0
0
G.1.6.1 STRUCTURE WORK 0
I EARTH WORK 0.0024 0.0024 1 0.0024 0.00242127566
II PILING WORK 0.0000 0
III CONCRETE WORK 0.0215 0.0054 4 0.0027 0.0081 0.0081 0.0027 0.021471624624
IV REINFORCED WORK 0.0288 0.0072 4 0.0036 0.0108 0.0108 0.0036 0.028758928472
V FORMWORK 0.0271 0.0068 4 0.0034 0.0102 0.0102 0.0034 0.027074019422
0
G.1.6.2 FINISHING WORK 0
I DOOR and WINDOW WORK 0.0057 0.0019 3 0.0019 0.0019 0.0019 0.005740529754
II MASONRY WORK 0.0207 0.0030 7 0.0010 0.0015 0.0042 0.0042 0.0042 0.0042 0.0015 0.020722611951
III PAINTING WORK 0.0078 0.0026 3 0.0026 0.0026 0.0026 0.007849844453
IV INTERIOR FINISHING WORK 0.0128 0.0032 4 0.0016 0.0048 0.0048 0.0016 0.012754343935
V WATERPROOFING WORK 0.0086 0.0021 4 0.0011 0.0025 0.0025 0.0025 0.008588053312
VI MISCELLANEOUS WORK 0.0120 0.0030 4 0.0015 0.0035 0.0035 0.0035 0.01203197977
0
G.1.7 GUARD HOUSE - 2 0
0
G.1.7.1 STRUCTURE WORK 0
I EARTH WORK 0.0002 0.0002 1 0.0002 0.000242657297
II PILING WORK 0.0000 0
III CONCRETE WORK 0.0038 0.0013 3 0.0013 0.0013 0.0013 0.003823726731
IV REINFORCED WORK 0.0050 0.0017 3 0.0017 0.0017 0.0017 0.005018476004
V FORMWORK 0.0049 0.0016 3 0.0016 0.0016 0.0016 0.00486955748
0
0
G.1.7.2 FINISHING WORK 0
I DOOR and WINDOW WORK 0.0000 0.0000 3 0
II MASONRY WORK 0.0021 0.0003 7 0.0001 0.0004 0.0004 0.0004 0.0004 0.0004 0.0001 0.002075438906
III PAINTING WORK 0.0011 0.0004 3 0.0004 0.0004 0.0004 0.001102225171
IV INTERIOR FINISHING WORK 0.0009 0.0002 4 0.0002 0.0002 0.0002 0.0002 0.000888787432
V WATERPROOFING WORK 0.0009 0.0002 4 0.0002 0.0002 0.0002 0.0002 0.000910192614
VI MISCELLANEOUS WORK 0.0012 0.0003 4 0.0003 0.0003 0.0003 0.0003 0.001187002379
0
G.1.8 RC PAVEMENT & DRAINAGE AREA - A 0
G.1.8.1 PAVING WORK 5.0470 0.3154 16 0.1577 0.4101 0.4101 0.4101 0.4101 0.4101 0.1577 0.1577 0.1577 0.4101 0.4101 0.4101 0.4101 0.4101 0.1577 0.1577 5.046998348747
G.1.8.2 DRAINAGE WORK 0.3160 0.0198 16 0.0099 0.0242 0.0242 0.0242 0.0242 0.0242 0.0242 0.0099 0.0099 0.0242 0.0242 0.0242 0.0242 0.0242 0.0099 0.0099 0.316024814093
0
0
G.2 MECHANICAL WORK 0.0225 0.0023 10 0.0008 0.0011 0.0011 0.0021 0.0021 0.0021 0.0021 0.0021 0.0021 0.0021 0.0021 0.0011 0.0011 0.0008 0.022543462804
0
G.3 ELECTRICAL WORK 1.7360 0.1736 10 0.0579 0.0868 0.0868 0.1591 0.1591 0.1591 0.1591 0.1591 0.1591 0.1591 0.1591 0.0868 0.0868 0.0579 1.736004205551
0
H. MOTOR CYCLE PARKING 0
0
H.1 CIVIL WORK 0
0
H.1.1 PAVING WORK & DRAINAGE WORK 0.2362 0.0295 8 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.236185805922
0
H.1.2 MOTORCYCLE PARKING AREA ( E, F, G & H ) 0.4214 0.0176 24 0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0088 0.0088 0.0088 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0295 0.0088 0.0088 0.0088 0.0088 0.421404293996
0
0
H.1.3 MOTORCYCLE PARKING BUILDING ( C & D ) 0
H.1.3.1 STRUCTURE WORK 0
I EARTH WORK 0.0404 0.0202 2 0.0202 0.0202 0.040408186014
II PILING WORK 0.1265 0.0633 2 0.0633 0.0633 0.126531349435
III CONCRETE WORK 0.2354 0.0214 11 0.0071 0.0071 0.0107 0.0315 0.0315 0.0315 0.0315 0.0315 0.0315 0.0107 0.0107 0.235362563425
IV REINFORCED WORK 0.2941 0.0267 11 0.0089 0.0089 0.0134 0.0394 0.0394 0.0394 0.0394 0.0394 0.0394 0.0134 0.0134 0.294132974431
V FORMWORK 0.2138 0.0194 11 0.0065 0.0065 0.0097 0.0286 0.0286 0.0286 0.0286 0.0286 0.0286 0.0097 0.0097 0.213836778022
VI STEEL STRUCTURE WORK 0.0663 0.0133 5 0.0133 0.0133 0.0133 0.0133 0.0133 0.06634202858
VII MISCELLANEOUS WORK 0.0202 0.0051 4 0.0051 0.0051 0.0051 0.0051 0.020238100389
0
H.1.3.2 FINISHING WORK 0
I METAL ROOFING WORK 0.1954 0.0651 3 0.0651 0.0651 0.0651 0.195424049756
II MASONRY WORK 0.0569 0.0063 9 0.0063 0.0063 0.0063 0.0063 0.0063 0.0063 0.0063 0.0063 0.0063 0.056905325927
III PAINTING WORK 0.0553 0.0069 8 0.0069 0.0069 0.0069 0.0069 0.0069 0.0069 0.0069 0.0069 0.05528475389
IV MISCELLANEOUS WORK 0.0476 0.0119 4 0.0119 0.0119 0.0119 0.0119 0.047617791481
0
H.1.4 MISCELLANEOUS WORK 0.0479 0.0120 4 0.0120 0.0120 0.0120 0.0120 0.047913327406
0
H.2 MECHANICAL WORK 0.0717 0.0090 8 0.0090 0.0090 0.0090 0.0090 0.0090 0.0090 0.0090 0.0090 0.071714513367
0
H.3 ELECTRICAL WORK 0.1600 0.0200 8 0.0200 0.0200 0.0200 0.0200 0.0200 0.0200 0.0200 0.0200 0.159974247328
0
I. CRANE WORK 0
I.1 TRAINING CENTER & HEAD OFFICE 0.0729 0.0365 2 0.0365 0.0365 0.072937281025
I.2 ULTRA LARGE COMPONENT FACT-2 1.0125 0.2531 4 0.2531 0.2531 0.2531 0.2531 1.012527713213
I.3 EXCAVATOR PAINT FACTORY 0.2968 0.1484 2 0.1484 0.1484 0.296819156091

J. SOIL INVESTIGATION WORK 0.0856 0.0107 8 0.0107 0.0107 0.0107 0.0107 0.0107 0.0107 0.0107 0.0107 0.085569442669

TOTAL ( A ~ J ) 100.0000 0.0702 0.0702 0.2378 0.5045 0.5179 0.5179 0.5179 0.5821 0.3302 0.7538 0.6418 0.6458 1.0861 1.3459 1.8697 1.7845 2.7294 2.8318 0.7078 1.0240 2.4001 2.4001 2.4320 0.0000 0.0000 3.9525 3.5908 4.9550 5.3230 5.7337 6.1125 6.1573 5.7670 5.9650 5.1312 4.7327 3.7140 2.2945 2.1120 1.6270 0.7700 0.7713 0.7737 0.9167 0.6759 0.5928 0.4880 0.4855 0.4891 0.4945 0.1921 0.1803 0.0000 0.0000 0.0000 0.0000 100.0000

100.0000 0.8828 2.1359 2.3716 6.0862 7.2931 7.2322 12.4983 23.3265 21.5960 9.7474 3.2318 2.2422 1.3560 0.0000

0.0000 0.8828 3.0187 5.3903 11.4765 18.7696 26.0018 38.5001 61.8266 83.4226 93.1700 96.4018 98.6440 100.000 100.000

122
PROJECT : HCMI CIBITUNG EXTENSION
PROGRESS PHOTOGRAPH PROJECT
DATE : May-11

PHOTO VIEW FROM SIDE AREA ULTRA LARGE COMPONENT FACTORY 2

PHOTO VIEW FROM SIDE AREA ULTRA LARGE COMPONENT FACTORY 2


PROJECT : HCMI CIBITUNG EXTENSION
PROGRESS PHOTOGRAPH PROJECT
DATE : May-11

PHOTO VIEW FROM FRONT SIDE AREA HEAD OFFICE

PHOTO VIEW FROM FRONT SIDE AREA EXCAFATOR BUILDING


MONTHLY SAFETY REPORT

PROJECT NAME : Hitachi Construction Machinary Indonesia Project

1. Patrol / Promotional Activities Period : May-11

No. Description Date Performed Comment


1 Safety Engineering System - Provide Risk Assessment before start new job
- On weekly basis - Safety Equipment Inspection
- On weekly basis - Heavy Equipment (Pre-Used Inspection)

2 Safety Inspection System - On weekly basis - Weekly Safety Patrol


- On monthly basis - Subcontractor Site Patrol / Safety Committee Meeting
- On monthly basis - KI-HQ Site Patrol

3 Safety Education System - On daily and weekly basis - Toolbox meeting, Safety talk, Weekly Housekeeping
- On monthly basis - Safety campaign
- Tentative - Safety Induction

4 Safety Enforcement - On daily basis - PPE (Personal, Protective Equipment)


- If found any violation - Violation/ Punishment if not used PPE and unsafe work
- On monthly basis - Safety Award to employees who put in extra effort to make the workplace safe
and free of hazards.

2. Photographs of Patrol / Promotional Activities

Photo : 1

Date Taken : 05,18,2011

Description : Safety Campaign at HCMI project is monthly agenda to informs and educated
to all worker and staff with actual safety issue or base on last incident at
Kajima Indonesia as lesson and learning to prevent incident happen in same
cases

Location : Site Office HCMI Project

Photo : 2

Date Taken : 05.16.2011

Description : Safety Meeting & Patrol is weekly agenda to evaluated last weekly activity and
safety patrol finding as hazard potential, for all sub contractor and all staff

Location : Site Office HCMI Project

Photo : 3

Date Taken : 05,18,2011

Description : Safety tool Box Meeting and Exercise is daily agenda with morning safety
briefing and work planning provide risk assesment,hazard potential, safety
equipment inspection before start working for all kajima daily worker, sub
contractor and staff

Location : Site office HCMI Project

Photo : 4

Date Taken : 05,18,2011

Description : KY Meeting is daily agenda to Anticipatory activity prior to the discussion of


safety, think and understand the team at work (or question and answer his
own) about the "cause harm" that is hidden in the workplace and working
conditions

Location : Warehouse Geotec , Karawang Timur

Photo : 5

Date Taken : 05.06.2011

Description : Premobilization inspection is pre use inspection for all heavy equipment and
make sure all heavy equipmnet is complay with Kajima Indonesia standart as
operator licenced and safety devices is installed corectly
Location : Geotec workShop Karawang Timur Indonesia
PROCUREMENT STATUS

PROJECT NAME : HITACHI CIBITUNG EXTENSION PROJECT


May-11

WORK SUBCONTRACTOR / TARGET


WORK ITEM STATUS
CODE SUPPLIER DATE

3501 TEMPORARY WORK


a. Supply & Delivery Temporary Work PT. SINAR NIAGA DUNIA issued P/O 28-Mar-11
b. Supply & Delivery Portland Cement PT. SINAR NIAGA DUNIA issued P/O 28-Mar-11
c. Labour Cost Temporary Work CV. RAHMAT ABADI JAYA issued P/O 31-Mar-11

3501 DEMOLITION WORK


a. Demolish Canteen, Office, Painth Booth PT. SIBA KARYA UTAMA issued P/O 13-Apr-11
b. Demolish Parking Area & Trees PT. SIBA KARYA UTAMA issued P/O 13-Apr-11
c. Demolish Stock Yard PT. SIBA KARYA UTAMA issued P/O 27-Apr-11

3507 EARTH WORK


a. Earth Work PT. PUTRA BINTANG SEMBADA issued P/O 7-Mar-11

3509 PILING FOUNDATION WORK


a. Supply & Delivery Piling PT. KOMPONINDO BETON JAYA issued P/O 4-Apr-11
b. Supply & Delivery Piling PT. WIJAYA KARYA BETON issued P/O 4-Apr-11
b. Supply & Delivery Piling PT. HUME CONCRETE INDONESIA issued P/O 4-Apr-11
c. Driving PT. GEOTEC KONSTRUKSI UTAMA issued P/O 27-Apr-11

3511 FORM WORK


a. Supply & Delivery Wooden PT. SINAR NIAGA DUNIA issued P/O 30-Mar-11
b. Labour Cost Form Work CV. RAHMAT ABADI JAYA issued P/O 12-May-11

3515 REINFORCING BAR WORK


a. Supply & Delivery Reinforcing Bar Work PT. INTER WORLD STEEL MILLS INDONESIA issued P/O 13-May-11
b. Labour Cost Reinforcing Bar CV. GEMILANG JAYA BAROKAH issued P/O 18-Mar-11

3513 CONCRETE WORK


a. Supply & Delivery Concrete Work PT. ADHIMIX PRECAST INDONESIA issued P/O 27-Apr-11

104 / 122
LIST OF REQUEST FOR INSPECTION (RFI)
PT. HCMI CIBITUNG FACTORY EXTENSION PROJECT

No. Work Item No. Ref

10

11

12

13

14

15

16

17

18
May-08

Date
LIST OF CONTACTOR'S REQUEST FOR APPROVAL (CRA)
PT. HCMI CIBITUNG FACTORY EXTENSION PROJECT

No. Work Item No. Ref Date Date of Return

10

11

12

13

14

15

16
May-08

Comment
LIST OF ARCHITECT'S INSTRUCTION (AI)
PT. HCMI CIBITUNG FACTORY EXTENSION PROJECT May-08

No. Work Item No. Ref Date

10

11

12

13

14

15

16

17

18

19

20

21

22
KI/FORM/FA-SO/09

MAN POWER REPORT


PROJECT: PT. HCMI CIBITUNG FACTORY EXPANSION
DATE
NO DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Japanese Staff 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Local Staff 7 7 8 8 8 8 8 6 9 9 8 9 9 8 8 8 7 8 9 10 8 5 8 8 8 8 8 8 6 8 8
3 Safety Staff 5 5 5 5 5 5 5 3 5 4 4 4 4 3 2 4 4 4 5 5 5 2 5 4 4 5 5 5 3 5 5
4 Safety Man 3 3 3 3 3 3 2 3 3 2 2 2 2 3 3 3 3 3 3 2 3 3 3 2 2 2 2 2 3 2 2
5 Ass. Safety 3 3 3 3 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 2 3 3 3 3 3 3 2 3 3
6 Ass. Superfisor 1 1 1 1 1 1 1 1 - - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Ass. Survey 3 3 2 2 3 3 3 2 3 3 2 2 2 2 3 3 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3
8 Ass. Logistic 1 1 1 1 1 1 1 - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 Ass. ME 3 4 4 4 4 4 4 3 3 3 3 4 4 4 3 4 4 2 4 4 4 4 5 5 5 4 5 5 4 4 4
10 Ass. Adm. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1 1 1 1 1
11 Forman - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
12 Carpenter 13 12 13 13 13 12 13 7 7 7 10 13 13 13 13 12 13 13 13 13 13 7 7 7 6 12 12 12 7 12 12
13 Masonry 23 22 22 21 21 22 22 17 14 14 16 19 19 21 22 20 21 21 21 22 22 15 15 15 16 20 22 20 15 20 20
14 Scafolder - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
15 Digger 5 6 6 6 5 5 5 2 4 5 6 6 4 6 6 6 6 6 5 5 6 3 3 5 6 7 7 7 5 6 6
16 Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
17 Office Boy - - - - - - - - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 1
18 Operator Excafator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Subtotal I 70 70 71 70 69 69 69 48 53 53 57 66 65 68 67 68 68 67 71 72 72 48 57 56 59 70 73 71 53 69 69

1 PT. Taiyosinar Raya Teknik 16 13 16 15 15 15 15 12 12 12 12 19 16 20 14 25 20 20 20 22 22 12 16 17 17 37 17 17 12 17 17


2 PT. Siba Karya Utama 12 12 11 11 11 11 12 6 13 20 24 18 20 20 21 20 20 24 24 24 24 14 24 24 24 24 24 24 20 24 24
3 PT. Geotec Konstruksi Utama 0 17 17 18 18 17 17 0 17 19 19 18 19 0 0 19 19 19 18 21 21 21 29 29 29 29 29 29 19 29 29
4 PT. Lotraco Sukses 0 0 0 0 0 0 0 0 0 0 0 13 13 8 12 8 12 4 5 8 8 8 9 11 12 11 6 6 6 6 6
5 C.V Gemilang Jaya Barokah ( Rebar ) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 4 4 4 4 4 0 3 5 3 3 3 3 3 3 3
6 C.V Rahmat Abadi Jaya ( Temp. Office ) 24 24 23 23 23 23 21 12 20 23 25 24 25 25 12 18 23 23 23 23 23 9 9 9 9 9 9 9 8 8 9
7 Security 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Subtotal II 56 70 71 71 71 70 69 34 66 78 84 96 97 77 63 98 102 98 98 106 106 68 94 99 98 117 92 92 72 91 92


TOTAL 126 140 142 141 140 139 138 82 119 131 141 162 162 145 130 166 170 165 169 178 178 116 151 155 157 187 165 163 125 160 161

Weather C C F F R F F F F F F F F C R R F R F R F F F F F F F F F F F
F C R
KI/FORM/FA-SO/09

May-11

TOTAL

26
245
134
80
84
27
85
29
121
30
-
343
600
-
166
-
7
31

2,008

530
584
585
172
53
548
124

2,596
4,604
4 1 30
MONTHLY PROGRE
PT. HITACHI CONSTRUCTION M
FACTORY EXPANSIO
PERIOD : 01 / MAY / 2011

NO DESCRIPTION

(A) (B)

0
TEMPORARY WORK

TEMPORARY ME WORK

DEMOLITION WORK

BUILDING WORK

TRAINING CENTRE & HEAD OFFICE


2 STRUCTURE WORK
9 FINISHING WORK

ULTRA LARGE COMPONENT FACT-2


### STRUCTURE WORK
### FINISHING WORK

ULTRA LARGE TOPCOAT PAINTING BOOTH


STRUCTURE WORK
FINISHING WORK

EXCAVATOR PAINT FACTORY


STRUCTURE WORK
FINISHING WORK

TOUCHUP PAINT BOOTH


STRUCTURE WORK
FINISHING WORK

WASHING AREA

EXTERNAL WORK

CRANE WORK

SOIL INVESTIGATION WORK

MECHANICAL WORK

ELECTRICAL WORKS
8 12 12 12 12
ONTHLY PROGRESS REPORT
CONSTRUCTION MACHINERY INDONESIA
CTORY EXPANSION PROJECT
IOD : 01 / MAY / 2011 ~ 31 / MAY / 2011
PROGRESS
WEIGHT THIS MONTH UP TO LAST TOTAL UP TO
(%) % Weight MONTH THIS MONTH
(C) (D) (E)=(C)x(D) (F) (G)=(E)+(F)

4.75 - 0.00 0.00

0.99 - 0.00 0.00

1.40 - 0.00 0.00

5.05 - 0.00 0.00


6.09 - 0.00 0.00

18.57 - 0.00 0.00


3.72 - 0.00 0.00

2.02 - 0.00 0.00


0.99 - 0.00 0.00

8.62 - 0.00 0.00


4.89 - 0.00 0.00

0.55 - 0.00 0.00


0.19 - 0.00 0.00

0.26 - 0.00 0.00

11.83 - 0.00 0.00

1.38 - 0.00 0.00

0.09 - 0.00 0.00

12.10 - 0.00 0.00

16.51 - 0.00 0.00


100.00 - - -
12 103

% PROGRESS
CUMMULATIVE
(H)=(G)/(C)x100

-
-

-
-

-
-

-
-

-
-

You might also like