Current Material & Size For Label & Closure Development Time Line Version 2 - 29.9.20
Current Material & Size For Label & Closure Development Time Line Version 2 - 29.9.20
Printed
Project Coordinator : …Wut Yi Win........ Material : ✘ Sticker Paper
Emoboss
✘ Gloss Matt Others: ……........................ Jan
Sr. No Description Responsible Persons Lead Time Date Sign
1 Design Development
□ Concept Lable Drawing submission MKT ???
□ Concept Label Drawing Approval MKT/ Prod / CEO 3 Days
If need to change new machine (or) tooling, follow the (6) and (7)
2 Supplier Selection
□ Selection potential supplier Procurement 7 days Existing
□ Supplier briefing on Label MKT 3 days
□ Request for Quotation Procurement 3 days
□ Negotiation & Supplier selection Procurement 3 days
Depend on Tooling & Machine approval (If not approve, project will be terminate).
3 Development Sample
□ Develop Technical Drawing Procurement 14 days If add new Emboss, we nee
□ Drawing Design approving MKT / Production / QA 3 days do tooling process.
□ Trial Printed Label production Procurement 45 days
□ Printed Label sample Delivery Procurement 14 days
□ Printed Label sample approval MKT 3 days
If printed "not satisfy or fesibility not OK", to restart drawing & sample, time line will be another round.
4 Quality Assurance
□ QA test ( Lab, Line, Load, Travel test ) QA / Production / Logistic 30 days
QA (all tests included with sample in final product form)
If it is new desing or size of Bottle or closure, it will need to align with those developments.
If QA test result "Fail", to restart from commerical mold production, time line will be another round.
Remark : New Supplier development with current closure ✘ 30x35mm 30x44mm 25STD With NRV Without NRV Jan
Sr. No Description Responsible Persons Lead Time Date Sign
1 Design Development
□ Concept closure Drawing submission MKT ???
□ Concept closure Drawing Approval MKT/ Prod / CEO 3 Days
If need to change new machine (or) tooling, follow the (6) and (7)
2 Supplier Selection
□ Selection potential supplier Procurement 7 days Existing
□ Supplier briefing MKT 3 days
□ Request for Quotation Procurement 3 days
□ Negotiation & Supplier selection Procurement 3 days
Depend on Tooling & Machine approval (If not approve, project will be terminate).
3 Development Sample
□ Develop Technical Drawing Procurement 14 days
□ Drawing Design approving MKT / Production / QA 3 days
□ Trial Printed closure production Procurement 35 days
□ Printed closure sample Delivery Procurement 14 days
□ Printed closure sample approval MKT 3 days
If printed "not satisfy or fesibility not OK", to restart drawing & sample, time line will be another round.
4 Quality Assurance
□ QA test ( Lab, Line, Load, Travel test ) QA / Production / Logistic 30 days
QA (all tests included with sample in final product form)
If it is new desing or size of Bottle or label, it will need to align with those developments.
If QA test result "Fail", to restart from commerical mold production, time line will be another round.
After final design finish,
can be adjust with
5 Commercial Ordering supplier.
□ PO for comercial Order Procurement 7 days
□ Comercial closure Ordering Procurement 45 days
□ Commercial closure Production Procurement 5 days
□ Online confirmation at supplier site QA 2 days
□ Preshipment Sample Delivery Procurement 10 days
□ Preshipment Sample test QA 7 days
□ Arranging Shipment Procurement 7 days